Map of Power Plants in Iowa that Will Reduce Emissions Due to Settlement

1
Acronyms MW Megawatts NOX Nitrogen Oxides SO2 Sulphur Dioxide CD Consent Decree Unit: SUTHERLAND 1 & 3 Location: 3001 East Main St., Marshalltown, IA 50158 Capacity: 38 MW (S1); 82 MW (S3) Years built: 38 MW (1955), 82 MW (1961) Projected NOX Reductions: 599 tons/year Projected SO2 Reductions: 4,600 tons/year Refuel Date: Natural gas upon entry of CD Retire/Repower Date: 6/1/2019 Unit: OTTUMWA 1 Location: 20775 Power Plant Rd., Ottumwa, IA 52501 Capacity: 726 MW Year built: 1981 Projected NOX Reductions: 1,514 tons/year Projected SO2 Reductions: 10,933 tons/year Controls/Requirements: - Dry flue gas desulfurization device (DFGD): 30 operating days after 12/31/2015 - Selective Catalytic Reduction (SCR): 30 operating days after 12/31/2019 - Baghouse: 30 operating days after 12/31/2015 Interstate Power Interstate Power & Light Clean Air & Light Clean Air Act Settlement Act Settlement LANSING 4 OTTUMWA 1 ML KAPP 2 PRAIRIE CREEK 1, 2, 3 & 4 BURLINGTON 1 DUBUQUE 1, 5, & 6 SUTHERLAND 1 & 3 USGS The National Map: National Boundaries Dataset, National Elevation Dataset, Geographic Names Information System, National Hydrography Dataset, National Land Cover Database, National Structures Dataset, and National Transportation Dataset; U.S. Census Bureau - TIGER/Line; HERE Road Data NOTE: The Environmental Protection Agency does not guarantee the accuracy, completeness, or timeliness of the information shown, and shall not be liable for any injury or loss resulting from reliance upon the information shown. HM 7/15/2015 ´ 0 200 100 Miles IOWA Unit: LANSING 4 Location: 2320 Power Plant Dr., Lansing, IA 52151 Capacity: 275 MW Years built: 15 MW (1948), 12 MW (1949), 38 MW (1957), 275 MW (1977) Projected NOX Reductions: 288 tons/year Projected SO2 Reductions: 4,795 tons/year Controls/Requirements: - Dry flue gas desulfurization device (DFGD): 30 operating days after 12/31/2016 - Selective Catalytic Reduction (SCR): 12/31/2015 - Baghouse: 30 operating days after 12/31/2016 Unit: DUBUQUE 1, 5, & 6 Location: 920 Kerper Blvd., Dubuque, IA 52004 Capacity: 38 MW (D1); 29 MW (D5); 15 MW (D6) Years built: 15 MW (1929), 28.7 MW (1952), 37.5 MW (1959) Projected NOX Reductions: 461 tons/year Projected SO2 Reductions: 661 tons/year Refuel Date: Natural gas upon entry of CD Retire/Repower Date: 6/1/2019 Unit: ML KAPP 2 Location: 2001 Beaver Channel Pkwy., Clinton, IA 52732 Capacity: 219 MW Year built: 1967 Projected NOX Reductions: 32 tons/year Projected SO2 Reductions: 3,575 tons/year Retire/Refuel Date: 6/1/2015 Unit: BURLINGTON 1 Location: 4282 Sullivan Slough Rd., Burlington, IA 52601 Capacity: 212 MW Year built: 1968 Projected NOX Reductions: 140 tons/year Projected SO2 Reductions: 4,254 tons/year Retire/Refuel Date: 12/31/2021 Unit: PRAIRIE CREEK 1 , 2, 3 & 4 Location: 3300 C St. Southwest, Cedar Rapids, IA 52404 Capacity: 245 mmBTU/hr (PC1); 304 mmBTU/hr (PC2); 50 MW (PC3); 149 NW (PC4) Years built: 23 MW (1951), 50 MW (1958), 149 MW (1967), 23 MW (1997) Projected NOX Reductions: Units 1 & 2 = 0 tons/year; Units 3 & 4 = 950 tons/year Projected SO2 Reductions: Units 1 & 2 = 924 tons/year; Units 3 & 4 = 2,797 tons/year Retire/Refuel Date: Units 1, 2 & 3 on 12/31/2025; Unit 4 on 6/1/2018

description

Map of power plants within Iowa that will reduce emissions as a result of the settlement reached between Interstate Power and Light, a subsidiary of Alliant Energy, and EPA. Iowa will see reductions of sulfur dioxide (SO2) emissions by 32,500 tons per year and nitrogen oxide (NOx) emissions by 3,800 tons per year.

Transcript of Map of Power Plants in Iowa that Will Reduce Emissions Due to Settlement

AcronymsMW MegawattsNOX Nitrogen OxidesSO2 Sulphur DioxideCD Consent Decree

Unit: SUTHERLAND 1 & 3Location: 3001 East Main St., Marshalltown, IA 50158Capacity: 38 MW (S1); 82 MW (S3)

Years built: 38 MW (1955), 82 MW (1961)Projected NOX Reductions: 599 tons/yearProjected SO2 Reductions: 4,600 tons/year

Refuel Date: Natural gas upon entry of CDRetire/Repower Date: 6/1/2019

Unit: OTTUMWA 1Location: 20775 Power Plant Rd., Ottumwa, IA 52501Capacity: 726 MW

Year built: 1981Projected NOX Reductions: 1,514 tons/yearProjected SO2 Reductions: 10,933 tons/year

Controls/Requirements: - Dry flue gas desulfurization device (DFGD): 30 operating days after 12/31/2015 - Selective Catalytic Reduction (SCR): 30 operating days after 12/31/2019 - Baghouse: 30 operating days after 12/31/2015

Interstate PowerInterstate Power& Light Clean Air& Light Clean AirAct SettlementAct Settlement

LANSING 4

OTTUMWA 1

ML KAPP 2PRAIRIE CREEK 1, 2, 3 & 4

BURLINGTON 1

DUBUQUE 1, 5, & 6

SUTHERLAND 1 & 3

USGS The National Map: National Boundaries Dataset, National Elevation Dataset, Geographic Names InformationSystem, National Hydrography Dataset, National Land Cover Database, National Structures Dataset, and NationalTransportation Dataset; U.S. Census Bureau - TIGER/Line; HERE Road Data

NOTE: The Environmental ProtectionAgency does not guarantee the

accuracy, completeness, or timeliness of the information

shown, and shall not be liable for any injury or loss resulting from

reliance upon the information shown.HM 7/15/2015´ 0 200100Miles

IOWA

Unit: LANSING 4Location: 2320 Power Plant Dr., Lansing, IA 52151Capacity: 275 MW

Years built: 15 MW (1948), 12 MW (1949), 38 MW (1957), 275 MW (1977)Projected NOX Reductions: 288 tons/yearProjected SO2 Reductions: 4,795 tons/year

Controls/Requirements: - Dry flue gas desulfurization device (DFGD): 30 operating days after 12/31/2016 - Selective Catalytic Reduction (SCR): 12/31/2015 - Baghouse: 30 operating days after 12/31/2016

Unit: DUBUQUE 1, 5, & 6Location: 920 Kerper Blvd., Dubuque, IA 52004Capacity: 38 MW (D1); 29 MW (D5); 15 MW (D6)

Years built: 15 MW (1929), 28.7 MW (1952), 37.5 MW (1959)Projected NOX Reductions: 461 tons/yearProjected SO2 Reductions: 661 tons/year

Refuel Date: Natural gas upon entry of CDRetire/Repower Date: 6/1/2019

Unit: ML KAPP 2Location: 2001 Beaver Channel Pkwy., Clinton, IA 52732Capacity: 219 MW

Year built: 1967Projected NOX Reductions: 32 tons/yearProjected SO2 Reductions: 3,575 tons/year

Retire/Refuel Date: 6/1/2015

Unit: BURLINGTON 1Location: 4282 Sullivan Slough Rd., Burlington, IA 52601Capacity: 212 MW

Year built: 1968Projected NOX Reductions: 140 tons/yearProjected SO2 Reductions: 4,254 tons/year

Retire/Refuel Date: 12/31/2021

Unit: PRAIRIE CREEK 1 , 2, 3 & 4Location: 3300 C St. Southwest, Cedar Rapids, IA 52404Capacity: 245 mmBTU/hr (PC1); 304 mmBTU/hr (PC2); 50 MW (PC3); 149 NW (PC4)

Years built: 23 MW (1951), 50 MW (1958), 149 MW (1967), 23 MW (1997)Projected NOX Reductions: Units 1 & 2 = 0 tons/year; Units 3 & 4 = 950 tons/yearProjected SO2 Reductions: Units 1 & 2 = 924 tons/year; Units 3 & 4 = 2,797 tons/year

Retire/Refuel Date: Units 1, 2 & 3 on 12/31/2025; Unit 4 on 6/1/2018