Page 1 of 12 MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014 SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-No T A T A T A T A T A T 1 TG-1 & PH-1 Civil SPCL 80 51 80 51 80 52 80 45 80 80 2 TG-2 & PH-2 Civil SPCL 100 68 100 71 100 72 100 85 100 100 3 Control Building Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 4 Guard Pond Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 5 Fire Station Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 6 ESP-1 & 2 Civil SPCL 15 35 15 30 15 20 15 22 15 15 7 ESP Control Building-2 Civil SPCL 25 15 25 15 25 18 25 0 25 0 25 8 Lube Oil Building Civil SPCL 20 14 20 12 20 12 20 7 20 20 9 Boiler-1 & 2 Civil SPCL 50 40 50 35 50 60 50 55 50 50 10 Structural SPCL 0 0 0 5 0 5 0 4 0 0 11 TG #2 Structural SPCL 50 33 50 33 50 34 50 23 50 50 12 TG#1 Painting Structural SPCL 10 0 10 0 10 0 10 0 10 0 10 13 TG#2 Painting Structural SPCL 30 5 30 5 30 5 30 0 30 0 30 14 Fabrication U#1 Fabrication SPCL 0 0 0 0 0 0 0 0 0 0 0 15 Fabrication U#2 Fabrication SPCL 0 0 0 0 0 0 0 0 0 0 0 16 ID Fan Unit #1 & 2 Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 17 Mill Bunker # 1 & 2 Civil SPCL 30 26 30 26 30 38 30 41 30 30 18 Service Building Civil SPCL 100 45 100 42 100 45 100 42 100 100 19 Canteen Building Civil SPCL 15 12 15 8 15 11 15 10 15 15 20 Workshop Building Civil SPCL 30 18 30 24 30 25 30 27 30 30 21 Overhead Tank Civil SPCL 15 0 15 0 15 0 15 0 15 0 15 22 Storage Shed Civil/Ern SPCL 40 12 40 8 40 15 40 16 40 40 23 Cable Rack & Trench Civil/|Ern SPCL 15 0 15 0 15 0 15 12 15 15 24 Civil SPCL 100 65 100 70 100 55 100 60 100 100 25 Drain & Road Civil SPCL 50 22 50 22 50 22 50 22 50 50 26 Siemens SwitchYard Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 27 Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 SPCL 795 461 795 457 795 489 795 471 795 0 795 Night Shift Civil SPCL 0 0 0 0 0 28 BOILER-1 ERECTION BHEL/PCP 150 101 100 93 100 85 100 89 100 100 Night Shift BHEL/PCP 0 0 0 0 0 29 ERECTION BHEL/UBEL 300 278 300 262 300 255 300 252 300 300 30 POWER CYCLE PIPING-1 ERECTION BHEL/B&R 0 0 0 0 0 0 0 0 0 0 0 31 LINING & INSULATION -1 ERECTION BHEL/B&R 100 40 100 42 100 40 100 41 100 100 B & R 100 40 100 42 100 40 100 41 100 0 100 Night Shift B & R 0 0 0 0 0 32 LINING & INSULATION -2 ERECTION BHEL/PowerMech 500 425 500 435 500 488 500 509 500 500 33 POWER CYCLE PIPING-2 ERECTION BHEL/PowerMech 450 390 450 390 450 385 450 383 450 450 PowerMech 950 815 950 825 950 873 950 892 950 0 950 Night Shift PowerMech 25 25 30 35 34 BTG-Electrical Erection BHEL/Vasavi 120 93 120 87 120 83 120 97 120 120 35 BTG-C&I BHEL/Auto Trical 15 8 15 9 15 8 15 9 15 15 36 BTG-C&I 110 120 130 120 130 121 130 118 130 130 37 PHB Cladding Erection Lloyd Insulation 20 8 20 8 20 11 20 11 20 20 38 TURBINE-1 ERECTION BHEL/UBEL 10 8 10 7 10 6 10 5 10 10 39 TURBINE-2 ERECTION BHEL/EEPL 200 118 150 120 150 115 150 117 150 150 UBEL 310 286 310 269 310 261 310 257 310 0 310 Night Shift UBEL 40 ESP-1 & Ducting ERECTION BHEL/Golden Edge 30 15 30 12 30 16 30 15 30 30 Night Shift BHEL/Golden Edge 0 0 0 0 0 41 ESP-2 & Ducting ERECTION BHEL/Rukmani 200 122 200 165 200 148 200 151 200 200 Night Shift Rukmani 35 32 32 32 42 Mill Bunker-2 Omega 120 91 120 93 120 96 120 93 120 120 Omega 120 91 120 93 120 96 120 93 120 0 120 Night Shift Omega 0 0 0 0 0 TG #1 & Control Building Misc (Store, Batching plant, QC,survey, steel yard,etc) Air Compressor Building BOILER-2 Erection U#01 Erection U#02 BHEL/ Powertronics Fabrication / Erection

description

h

Transcript of Manpower Report 29.11.2014

Page 1: Manpower Report 29.11.2014

Page 1 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

1 TG-1 & PH-1 Civil SPCL 80 51 80 51 80 52 80 45 80 80

2 TG-2 & PH-2 Civil SPCL 100 68 100 71 100 72 100 85 100 100

3 Control Building Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 0

4 Guard Pond Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0

5 Fire Station Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0

6 ESP-1 & 2 Civil SPCL 15 35 15 30 15 20 15 22 15 15

7 ESP Control Building-2 Civil SPCL 25 15 25 15 25 18 25 0 25 0 25 0

8 Lube Oil Building Civil SPCL 20 14 20 12 20 12 20 7 20 20

9 Boiler-1 & 2 Civil SPCL 50 40 50 35 50 60 50 55 50 50

10 TG #1 & Control Building Structural SPCL 0 0 0 5 0 5 0 4 0 0

11 TG #2 Structural SPCL 50 33 50 33 50 34 50 23 50 50

12 TG#1 Painting Structural SPCL 10 0 10 0 10 0 10 0 10 0 10 0

13 TG#2 Painting Structural SPCL 30 5 30 5 30 5 30 0 30 0 30 0

14 Fabrication U#1 Fabrication SPCL 0 0 0 0 0 0 0 0 0 0 0 0

15 Fabrication U#2 Fabrication SPCL 0 0 0 0 0 0 0 0 0 0 0 0

16 ID Fan Unit #1 & 2 Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0

17 Mill Bunker # 1 & 2 Civil SPCL 30 26 30 26 30 38 30 41 30 30

18 Service Building Civil SPCL 100 45 100 42 100 45 100 42 100 100

19 Canteen Building Civil SPCL 15 12 15 8 15 11 15 10 15 15

20 Workshop Building Civil SPCL 30 18 30 24 30 25 30 27 30 30

21 Overhead Tank Civil SPCL 15 0 15 0 15 0 15 0 15 0 15 0

22 Storage Shed Civil/Ern SPCL 40 12 40 8 40 15 40 16 40 40

23 Cable Rack & Trench Civil/|Ern SPCL 15 0 15 0 15 0 15 12 15 15

24 Civil SPCL 100 65 100 70 100 55 100 60 100 100

25 Drain & Road Civil SPCL 50 22 50 22 50 22 50 22 50 50

26 Siemens SwitchYard Civil SPCL 0 0 0 0 0 0 0 0 0 0 0 0

27 Air Compressor Building Civil SPCL 10 0 10 0 10 0 10 0 10 0 10 0

SPCL 795 461 795 457 795 489 795 471 795 0 795 0

Night Shift Civil SPCL 0 0 0 0 0 0

28 BOILER-1 ERECTION BHEL/PCP 150 101 100 93 100 85 100 89 100 100

Night Shift BHEL/PCP 0 0 0 0 0 0

29 ERECTION BHEL/UBEL 300 278 300 262 300 255 300 252 300 300

30 POWER CYCLE PIPING-1 ERECTION BHEL/B&R 0 0 0 0 0 0 0 0 0 0 0 0

31 LINING & INSULATION -1 ERECTION BHEL/B&R 100 40 100 42 100 40 100 41 100 100

B & R 100 40 100 42 100 40 100 41 100 0 100 0

Night Shift B & R 0 0 0 0 0 0

32 LINING & INSULATION -2 ERECTION BHEL/PowerMech 500 425 500 435 500 488 500 509 500 500

33 POWER CYCLE PIPING-2 ERECTION BHEL/PowerMech 450 390 450 390 450 385 450 383 450 450

PowerMech 950 815 950 825 950 873 950 892 950 0 950 0

Night Shift PowerMech 25 25 30 35

34 BTG-Electrical Erection BHEL/Vasavi 120 93 120 87 120 83 120 97 120 120

35 BTG-C&I Erection U#01 BHEL/Auto Trical 15 8 15 9 15 8 15 9 15 15

36 BTG-C&I Erection U#02 110 120 130 120 130 121 130 118 130 130

37 PHB Cladding Erection Lloyd Insulation 20 8 20 8 20 11 20 11 20 20

38 TURBINE-1 ERECTION BHEL/UBEL 10 8 10 7 10 6 10 5 10 10

39 TURBINE-2 ERECTION BHEL/EEPL 200 118 150 120 150 115 150 117 150 150

UBEL 310 286 310 269 310 261 310 257 310 0 310 0

Night Shift UBEL

40 ESP-1 & Ducting ERECTION BHEL/Golden Edge 30 15 30 12 30 16 30 15 30 30

Night Shift 0 0 0 0 0 0

41 ESP-2 & Ducting ERECTION BHEL/Rukmani 200 122 200 165 200 148 200 151 200 200

Night Shift Rukmani 35 32 32 32

42 Mill Bunker-2 Omega 120 91 120 93 120 96 120 93 120 120

Omega 120 91 120 93 120 96 120 93 120 0 120 0

Night Shift Omega 0 0 0 0 0 0

Misc (Store, Batching plant,QC,survey, steel yard,etc)

BOILER-2

BHEL/Powertronics

BHEL/Golden Edge

Fabrication/ Erection

Page 2: Manpower Report 29.11.2014

Page 2 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

43 ESP Control Room & ID fan Civil Gammon 0 0 0 0 0 0 0 0 0 0 0 0

Page 3: Manpower Report 29.11.2014

Page 3 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

44 ChimneyCIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION Gammon 0 0 0 0 0 0 0 0 0 0 0 0

45CIVIL Gammon 0 5 0 5 0 0 0 5 0 0

Fab/Ern Gammon 0 0 0 0 0 0 0 0 0 0 0 0

46 Water treatment plant CIVIL Gammon 10 10 10 10 10 10 10 12 10 10

47 CIVIL Gammon 0 8 0 8 0 8 0 7 0 0

48 Air Washer Building CIVIL Gammon 25 16 25 15 25 16 25 20 25 25

49 Fuel Oil Pump House CIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0

50 Raw Water Pump House CIVIL Gammon 15 0 15 0 15 0 15 0 15 0 15 0

51 CW PipingCIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION Gammon 0 0 0 0 0 0 0 0 0 0 0 0

52 TOWNSHIP CIVIL Gammon 600 455 600 458 600 455 600 421 600 600

53 Transformer yard Civil Gammon 60 12 60 20 60 15 60 15 60 60

54 Transformer yard-Drain Civil Gammon 0 3 0 5 0 5 0 4 0 0

55 Civil Gammon 0 0 0 0 0 0 0 0 0 0 0 0

56 Misc Gammon 80 58 80 55 80 55 80 58 80 80

GAMMON 820 581 820 590 820 578 820 556 820 0 820 0

Night Shift Civil GAMMON 25 25 25 25

57 TRANSMISSION LINECIVIL GAMMON 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION GAMMON 0 0 0 0 0 0 0 0 0 0 0 0

GAMMON-TR LINE 0 0 0 0 0 0 0 0 0 0 0 0

58CIVIL SIEMENS 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION SIEMENS 0 0 0 0 0 0 0 0 0 0 0 0

59 E BOPCIVIL SIEMENS 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION SIEMENS 70 45 70 45 70 36 70 41 70 70

60 PLANT ILLUMINATION ERECTION JITPL Agency 0 0 0 0 0 0 0 0 0 0 0 0

SIEMENS 70 45 70 45 70 36 70 41 70 0 70 0

Night Shift SIEMENS

61 LP PIPING ERECTION 20 12 20 12 20 7 20 10 20 20

62 ERECTION NEW FIRE ENGG. 100 128 150 124 150 120 150 120 150 150

63 DG Building CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

64 Mill Bunker-1 CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

Erection KSSIIPL 20 8 20 8 20 8 20 8 20 20

65 Duct Support & ID fan CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

66 ESP control room-2 CIVIL KSSIIPL(JITPL) 100 20 100 22 100 24 100 24 100 100

67 PA, FD fan foundation CIVIL KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

68 Structural Erection-TG-2 ERECTION KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

69 Structural Fabrication Fabrication KSSIIPL 0 0 0 0 0 0 0 0 0 0 0 0

70 Misc KSSIIPL 10 0 10 0 10 0 10 0 10 0 10 0

KSSIIPL 130 28 130 30 130 32 130 32 130 0 130 0

Night Shift KSSIIPL 0 0 0 0 0 0

71 COOLING TOWER-1CIVIL PCTL 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION PCTL 0 0 0 0 0 0 0 0 0 0 0 0

72 COOLING TOWER-2CIVIL PCTL 30 32 30 23 30 24 30 15 30 30

ERECTION PCTL 0 0 0 0 0 0 0 0 0 0 0 0

PCTL 30 32 30 23 30 24 30 15 30 0 30 0

Night Shift PCTL

73CIVIL TECPRO 50 0 50 0 50 15 50 28 50 50

ERECTION TECPRO 210 15 210 15 210 40 210 145 210 210

74CIVIL TECPRO 20 0 20 0 20 7 20 12 20 20

ERECTION TECPRO 0 0 0 0 0 0 0 0 0 0 0 0

TECPRO 280 15 280 15 280 62 280 185 280 0 280 0

CW Pump House & SG Bldg

CW Side Stream Filtration Unit & Chlorination Building

River Water PH,channel & forebay & Cofferdam

Misc (Store, batching plant,QC,survey etc)

Bays at Angul pooling station with metering yard

Zeromm/Other Agency

FIRE PROTECTION SYSTEM

Infrastructure & Misc (Store, batching plant,QC,survey ,steel yard etc)

CHP

MINE CONVEYOR SYSTEM

Page 4: Manpower Report 29.11.2014

Page 4 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

Night Shift Tecpro

Page 5: Manpower Report 29.11.2014

Page 5 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

75 C W PUMPs ERECTION KBL 12 7 12 7 12 7 12 7 12 12

76 River Water Piping RAUNAQ 0 0 0 0 0 0 0 0 0 0 0 0

77 Raw Water Pump house ERECTION RAUNAQ 0 0 0 0 0 0 0 0 0 0 0 0

78 River Water Pump House ERECTION RAUNAQ 0 0 0 0 0 0 0 0 0 0 0 0

79 CW makeup line ERECTION RAUNAQ 0 0 0 0 0 0 0 0 0 0 0 0

RAUNAQ 0 0 0 0 0 0 0 0 0 0 0 0

80 CIVIL SAMARPITA 0 0 0 0 0 0 0 0 0 0 0 0

81 ERECTION IEL 60 55 60 57 60 56 60 71 60 60

82 FLY ASH SYSTEMCIVIL MACAWBER 10 3 10 0 10 0 10 0 10 0 10 0

ERECTION MACAWBER 50 53 50 55 50 48 50 47 50 50

83

CIVIL BSBK 10 3 10 5 10 8 10 8 10 10

ERECTION BSBK 50 43 50 44 50 42 50 44 50 50

Refractory ERECTION BSBK 0 0 0 0 0 0 0 0 0 0 0 0

MBPL/BSBK 120 102 120 104 120 98 120 99 120 0 120 0

Night Shift MBPL/BSBK

84 ERECTION ATLAS COPCO 0 0 0 0 0 0 0 0 0 0 0 0

85 FUEL OIL SYSTEM ERECTION 0 0 0 0 0 0 0 0 0 0 0 0

86 ERECTION 0 0 0 0 0 0 0 0 0 0 0 0

87 ERECTION 40 29 40 26 40 26 40 32 40 40

88 EOT CRANE 105/15 T-2ND ERECTION WMI 0 0 0 0 0 0 0 0 0 0 0 0

89 EOT CRANE -30 T ERECTION SAFEX 0 0 0 0 0 0 0 0 0 0 0 0

90CIVIL Gammon 10 10 10 10 10 10 10 10 10 10

ERECTION Airox Nigen 10 2 10 2 10 2 10 2 10 10

91CIVIL Gammon 0 0 0 0 0 0 0 0 0 0 0 0

ERECTION Ion Exchange 10 0 10 0 10 0 10 0 10 0 10 0

92 ERECTION CHEMTROL 0 0 0 0 0 0 0 0 0 0 0 0

93 COLTCS ERECTION GEA-BGR 10 0 10 4 10 4 10 4 10 10

94 WORKSHOP EQUIP.-I ERECTION HMT 0 0 0 0 0 0 0 0 0 0 0 0

95 ERECTION BATLIBOI 0 0 0 0 0 0 0 0 0 0 0 0

96 WORKSHOP EQUIP.-III ERECTION PATHAK 0 0 0 0 0 0 0 0 0 0 0 0

97 Raw Water Reservoir Civil Sinhotia 15 0 15 0 15 0 15 6 15 15

98 Roads

Civil Nanda 30 21 30 22 30 21 30 20 30 30

Civil RK Associates 25 55 25 48 25 52 25 55 25 25

Civil Pradhan 0 0 0 0 0 0 0 0 0 0 0 0

Civil Monalisha 25 23 25 24 25 24 25 25 25 25

99 Civil Monalisha 60 31 60 34 60 35 60 36 60 60

100 Peripheral Drainage-IICivil R K Associates 50 22 50 23 50 34 50 31 50 50

Civil Essem Constn 0 0 0 0 0 0 0 0 0 0 0 0

101 Internal Drains

Civil R K Associates 45 10 45 12 45 14 45 28 45 45

Civil Gammon 20 4 20 4 20 4 20 4 20 20

Civil Sinhotia 50 25 50 28 50 29 50 36 50 50

Civil Essem Constn 0 0 0 0 0 0 0 0 0 0 0 0

102 Ash Dyke` Civil Sinhotia 15 4 15 4 15 4 15 4 15 15

95 32 95 35 95 48 95 59 95 0 95 0

60 31 60 34 60 35 60 36 60 0 60 0

0 0 0 0 0 0 0 0 0 0 0 0

Sinhotia 80 29 80 32 80 33 80 46 80 0 80 0

Night Shift(Sinhotia) Sinhotia 0 0 0 0 0 0

103 Civil Swheta Constn 15 0 15 0 15 0 15 0 15 0 15 0

CIVIL/ERECTION

Haul Road-River Water System

WATER TREATMENT PLANT

BOTTOM ASH HANDLING SYSTEM

COMPRESSED AIR SYSTEM

THERMOSYSTEMS

POTABLE WATER SYSTEM

THERMOSYSTEMS

AIR CONDITIONING SYSTEM

STERLING & WILSON

HYDROGEN GENERATION PLANT

SEWAGE TREATMENT PLANT

Ambient Air Quality Monitoring System

WORKSHOP EQUIP.-II (BATLIBOI)

Peripheral Drainage-I + Internal drain

R K Associates( Drain)

Monalisha(Drains)

Essem Constn(Drains)

Overhead Tank(Plant Area)

DC130
CIVIL20: includes supply manpower 20 nos
Page 6: Manpower Report 29.11.2014

Page 6 of 6

MANPOWER DEPLOYMENT STATUS OF 2X600 MW, JITPL, ANGUL, ODISHA Nov-2014

SL NO PACKAGE DISCIPLINE AGENCY 24-Nov-14 25-Nov-14 26-Nov-14 27-Nov-14 28-Nov-14 29-Nov-14

T A T A T A T A T A T A

104 EOT CRANE ERECTION Electromech 5 0 5 0 5 0 5 0 5 0 5 0

TOTAL 5167 3505 5137 3534 5137 3611 5137 3776 5137 0 5137 0

Night Shift (Total) 85 82 87 92 0 0

Note:(1)Manpower targets revised from 5167 to 5137 wef 25-Nov-14 based on balance quantum of work.(2)Agency wise manpower includes night shift manpower also. Total manpower in nightshift as on 28.11.2014 - heads.(3) Manpower of O & M services & House keeping is excluded.