FAUZ Engineering PRIMAVERA PROJECT PLANNER Engro Rice Project REPORT DATE 19JUL10 RUN NO. 129 RESOURCE LOADING REPORT START DATE 10JUL10 FIN DATE 10SEP10* 22:13 DATA DATE 10JUL10 PAGE NO. 1 RL-09 Manpower Report PEAK USAGE FOR WEEK 5JUL 12JUL 19JUL 26JUL 2AUG 9AUG 16AUG 23AUG 30AUG 6SEP RESOURCE RESOURCE DESCRIPTION 2010 2010 2010 2010 2010 2010 2010 2010 2010 2010 FAB Fabricator 2 4 7 6 14 15 6 FITTER Fitter 4 7 14 12 29 30 12 HELPER Helper 3 5 6 13 21 27 26 18 RIGGER Rigger 3 4 5 10 13 17 18 6 T-WELDER Tack Welder 1 1 2 3 1 6 7 2 WELDER Welder 3 4 6 13 10 14 12 REPORT PEAK 6 17 23 42 65 89 90 56

description

Manpower Deployment Table

Transcript of Manpower Deployment Table

Page 1: Manpower Deployment Table

FAUZ Engineering PRIMAVERA PROJECT PLANNER Engro Rice Project REPORT DATE 19JUL10 RUN NO. 129 RESOURCE LOADING REPORT START DATE 10JUL10 FIN DATE 10SEP10* 22:13 DATA DATE 10JUL10 PAGE NO. 1 RL-09 Manpower Report PEAK USAGE FOR WEEK 5JUL 12JUL 19JUL 26JUL 2AUG 9AUG 16AUG 23AUG 30AUG 6SEPRESOURCE RESOURCE DESCRIPTION 2010 2010 2010 2010 2010 2010 2010 2010 2010 2010

FAB Fabricator 2 4 7 6 14 15 6FITTER Fitter 4 7 14 12 29 30 12HELPER Helper 3 5 6 13 21 27 26 18RIGGER Rigger 3 4 5 10 13 17 18 6T-WELDER Tack Welder 1 1 2 3 1 6 7 2WELDER Welder 3 4 6 13 10 14 12 REPORT PEAK 6 17 23 42 65 89 90 56