Management of Ageing London UG Tunnels___new Techno to Old Bds
-
Upload
alanjalil9365 -
Category
Documents
-
view
214 -
download
0
Transcript of Management of Ageing London UG Tunnels___new Techno to Old Bds
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
1/63
Management of ageingLondon Underground tunnels:
-Applying new technologies to old problems
Peter Wright
Tube Lines
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
2/63
Who are Tube Lines?
Infrastructure consortium responsible for the
Jubilee, Northern and Piccadilly Lines.
PPP Contract over 30 years to improve
London's Underground system.
Required to improve knowledge and
understanding of deep tube tunnels, which
were in an uncertain condition (grey).
In practice over 200km of tunnels and shafts
have to be structurally assessed.
Also required to make grey assets safe
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
3/63
Typical conditions
in deep tubes
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
4/63
City and South LondonRailway
First cast iron tube railway completed in 1889 From King William Street to Stockwell
Completed in 4 miles in 4 years
Compressed air working, Greathead shield, JH Greathead was the
engineer
Original concept cable-hauled but changed toelectric power
Not a single life lost
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
5/63
The Greathead Shield
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
6/63
Compressed Air Working
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
7/63
The Padded Cells
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
8/63
Northern Line
Tunnel expansionin
1920s
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
9/63
11ft 8.25 CI Lining
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
10/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
11/63
A closer look ata tunnel length..
Stn Stn
Distorted rings
Cross passage opening,
cross passage
Cracked segments
Ventilation opening
Pump sump
Disused station Shield chamber Cross tunnelVarying separation,
but normally less
than 1 diameter
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
12/63
Generic studies
Investigate on a global basis, rather thanasset specific, wherever possible
Apply results of these studies
Examples:- Lining circularity
- Cast iron lining thickness & strength
- Geotechnical parameters
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
13/63
20. Databases
and other
software
21. Exemplar
Assessments
22. Guidance
on Overall
AssessmentProcedure
Future
Amendments
to LULStandards
3. M/N
interaction
diagramsfor CI and
calculation
of safety
factors
4.Investigation
of Failure
Mechanisms
5. Soil
Parameters
and their
variation
16. CI
deterioration
mechanisms
and
degradation
model
10. Concrete
Tunnel Lining
durability and
residual life
assessments
15. Defects
model for CI
rings14. Defects
model for
Concrete rings
2. In situ stress
measurement
in CI and
Concrete
11. FE model
of CI joints
17. Study of
Historical
Construction
methods
18. Study of
Bomb
locations
19. Adoption
of suitable FE
and other
software
13. Grey CI
transverse
stress
research
1.Development
of In situ stress
measurement
techniques in CIand Concrete
12. Investigation
of non-
destructive
testing methods
6. Study of
Radar and
other
geophysical
methods
K & P Projects Concept
JNP tunnel assessment manual & toolkit
8. Supplementary
investigations
7. Critical
Situations
and
Parameter
Sensitivity
9. Adatptation of
Totaline or expert
system for
assessment
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
14/63
Inspection/Assessment
Options
Factors Affecting
Failure Behaviour
Failure
Behaviour
So What?
How will
the FailureHappen?
What are the
Engineering Factors
that Influence Failure?
What Tools are
(or could be)
Available?
How Good?Mature?
Linkage?
Significance?Confidence?
Development
Consequence
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
15/63
Expanded
Bolted
Existing Damage
Manufacturing Quality
Visual Immediate
Complete
CollapseMaterial Quality
Significance?
Build Quality
Water
Acid ity
Voids Outside Tunnel
External Contamination
Outside Party Works
Internal Environment
Component Degradation
Other Structure Proximity
EMC/Electrical Discharge
Openings
Partial
Collapse
Distortion
Safety
Related
Impact
Survey (Depth/Circularity)
Radar
Ultrasonics
Core Sampling
Electro-Magnetic
In Situ Stress Analysis
Desk Top Study
Confidence?
Inspection/Assessment
Options
Factors Affecting
Failure Behaviour
Failure
Behaviour
Consequence
100030050620
100030050
620
1000
30050620
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
16/63
Tunnel Analysis & Design
1. Elastic ContinuumMethod
Morgan, Muir Wood,Curtis, Peck, Arends etc
We use TOTALINE
program (Curtis full
bond).
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
17/63
Geotechnical FE
Long term
deformed mesh
LH tunnel
constructed
first
Initial, long term
squat = -1mm, 6mmGround loss at
excavation = 1.93%first tunnel, 1.69%
second tunnel
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
18/63
Stresses along
tunnel axis range
from
54MPa in tension
to41 MPa in compression
3Dstructural
FE
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
19/63
Looking at invert,with LH segment
removed
3D structural FE
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
20/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
21/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
22/63
Coring and ultrasonics ingrey cast iron
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
23/63
Position of Coring & Ultasonic Inspection Results
NORTHBOUND RUNNING TUNNEL: Position of cores relative to each other (in all cases):
R1930 R1940 R3260
23.12 23.33 21.91 22.94 24.30 23.00
27.45 27.60 22.57 24.05 26.00 24.77
27.05 27.45 23.80 23.58 27.70 27.80
R3241 NORTHBOUND SOUTHBOUND
Average measured thickness of core:
R1930 22.88 mm
19.10 20.20 R1940 20.10 mm
20.20 20.75 R3260 25.08 mm
21.77 24.60 R3241 20.38 mm
DIRECTION
OF RUNNING
DIRECTION
OF RUNNING
Typical coring andultrasonic readings
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
24/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
25/63
Grey cast iron strengthtesting
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
26/63
Grey cast iron strength
testing
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
27/63
Grey cast iron strength testing
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
28/63
CPT and soil testing
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
29/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
30/63
CPT and soil testing
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
31/63
CPT and soil testing
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
32/63
Circularity measurement
Best-fit Perfect Circle
Circularity Survey Data
Deformation exaggerated x 10
Estimated Centre
Typical circularity
measurement,showing approx
1% squat
Circularity carried
out using Leica
3000 track trolley
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
33/63
-2.0
-1.0
0.0
1.0
2.0
860
900
940
980
1020
1060
1100
1140
1180
1220
1260
1300
1340
1380
1420
1460
1500
1540
1580
1620
1660
1700
1740
1780
1820
1860
1900
1940
1980
2020
2060
2100
2140
Northbound Ring Number
%ooc(squat+ve
-2.0
-1.0
0.0
1.0
2.0
1280
1320
1360
1400
1440
1480
1520
1560
1600
1640
1680
1720
1760
1800
1840
1880
1920
1960
2000
2040
2080
2120
2160
2200
2240
2280
2320
2360
2400
2440
2480
2520
2560
Southbound Ring Number
Circularity measurement
Typical longitudinal plot showing tunnel
deformations between Golders Green and
Hampstead
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
34/63
Direct Stress Measurement
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
35/63
ACSM - StressProbe
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
36/63
Basics of Stressprobe
Stress in a material causes changes in magnetic
domain behaviour The altered domain distribution causes changes
in the permeability of the material
Stressprobe measures the changes inpermeability using an induced magnetic field andpickup coils
Often a demag cycle is needed to removemagnetic hysteresis
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
37/63
ACSM - StressProbe
Stress
across CIpan
(N/mm2)
Hoop Load
adjacent toOpening
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
38/63
Summary of AssessmentWork Tunnel assessment work now nearly complete
Tube Lines Tunnels team have used a combinationof in house and external expertise to carry out
Analysis
Investigation
Inspection Assessment
Reporting
Classification
Risk Assessment and Remediation Inspection
Further Analysis
Monitoring and Survey
Strengthening
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
39/63
Openings in Tunnels
Support by lintel and bolts
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
40/63
Covent Garden
BOLTS SHEARED
SEGMENT PUSHING FORWARD BY 30mm
FRACTURE NOTE TO LINTEL
LINTEL COMPRESSING & DISTORTING
GENERAL VIEW
LINTEL ENDS
COMPRESSED &
DISTORTED
30mm PUSH INWARD TO
SEGMENT & BOLTS ARE
SHEARED.
SEGMENTS FRACTURED
FRACTURE TO EDGE OF
SEGMENT
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
41/63
EustonPhotographs
GENERAL VIEW
MANY BOLTS MISSINGAROUND THE OPENING
LINTEL COMPRESSEDAND DISTORTED
BRAKE DUST BUILD UP
HAS FALLEN OF APOTENTIAL REASON MAY
BE LINTEL MOVEMENT
APPARENT SHEAR
MISS-ALIGNEDSEGMENTS
LINTEL BUCKLING
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
42/63
Acid attack
at
Old Street
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
43/63
Acid attack at Old Street
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
44/63
Cracked Lining
atOld Street
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
45/63
Acid attack
at
Bond St?
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
46/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
47/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
48/63
Outside Party Developments
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
49/63
Expanded ConcreteLiningsSignificant face spalling of segments
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
50/63
BOTDR Monitoring
Photo No. 4-
5
Protection of
the Cable
Fibre Optics Strain Measurement
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
51/63
Fibre Optics Strain Measurement
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
52/63
Average strain over 1m every 5cmRange ~5-10km
Resolution 30 (0.003%)Low cost sensors - optical fibre
5 - 25 minutes per measurement
Can link or switch between fibres
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
53/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
54/63
Monitoring of existing ThamesLink tunnel
Tunnelling obliquely under Victorian masonry tunnel
Existing tunnel loaded by canal basin retaining wall
Directly below Midlands Main Line (MML)
MML
above
Existing
ThamesLin
k tunnel
Canal basin
New tunnelReproduced from Ordnance Survey of Northern Ireland mapping with the
permission of the Director and Chief Executive, Crown Copyright.
3.6m
6.5m
8.5m
Thameslink Tunnel at KingThameslink Tunnel at Kings Crosss Cross
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
55/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
56/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
57/63
Underground M3Aims of the project
Develop
Micro-detection - computer vision Micro-monitoring - MEMS sensors (Micro-electro-
mechanical systems)
Micro-communication Wireless communication
and power harvesting Data analysis and expert systems
Industry Application System Safety, adaptation and field application
Business Plan and Integration
http://www-civ.eng.cam.ac.uk/underground/index.html
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
58/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
59/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
60/63
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
61/63
Tube Lines Role AssociatePartner
Attend quarterly meetings
Advice and guidance from an industry point of
view
Facilitate visits and pilot studies in our tunnels
Benefit from developments made by the
project
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
62/63
Concluding Remarks
Increasing demand (Why?) for sensor
systems to monitor civil infrastructure? For
what purpose? To monitor structures with reduced/indeterminate assessed safety
factors, and, in connection with an Emergency PreparednessSystem, to prevent vehicles entering the danger area in the event
of failure.
To monitor structures where new construction works affect existing
infrastructure, and in connection... Ditto
As part of a temporary works system to control and reduce theeffects of construction movements
To better understand the behaviour of structures to improve
assessment accuracy.
-
7/30/2019 Management of Ageing London UG Tunnels___new Techno to Old Bds
63/63