Management and Reuse of Construction Wastes
Transcript of Management and Reuse of Construction Wastes
Management and Reuse of Construction Wastes
Professor C.S. Poon
Dept of Civil and Structural EngineeringThe Hong Kong Polytechnic University
15
C&D Waste Generation
• Inert C&D materials (mainly sand, bricks and concrete) both suitable for land reclamation and land formation works, are disposed of at public filling areas.
• Non inert portion (bamboo, plastics, glass, wood, paper, vegetation and other organic materials) ends up at municipal solid waste landfills.
2
6
Salvageable Scraps –Reuse/Recycling
C&D Waste
C&D Waste Management in Hong Kong
Non-inert Portion -Landfills
Inert Portion – Public fills Mixed waste – Sorting facility
3
Construction Waste (source EPD)(2008)
5%
86%
10%
Sorting Facilities2,080 tpd
Public Fill Reception Facilities18,680 tpd
Landfills1,020 tpd
Total: 21,780 tpd
Figures may not add up to total due to rounding-off
93% 7%
Non-inert
68% 25%
Soft Hard
20% 5%
Recyclable Non-recyclable
Inert
Construction Waste(Approx. 15.4 M tonnes in Year 2009) (source CEDD)
88
C&D Materials Management Facilities Locations
30
The Problem
Hong Kong will soon be running out of both landfill space and public filling areas.
According to Government sources :
• Landfills will be filled up soon.
• Limited reclamation projects. Temporary fill banks will be full soon.
11
12
Delivery of Reclamation Material to Mainland
13
Designated Reclamation Site in Mainland
台山廣海灣華僑投資開發試驗區
香港特別行政區
20km
香港特別行政區
14
Construction Waste Disposal Charging Scheme
• Implemented on 1 Dec 2005
Government waste disposal facilities
Type of construction waste acceptedCharge per
tonne
Public fill reception facilitiesConsisting entirely of inert construction waste
$27
Sorting facilitiesContaining more than 50% by
weight of inert construction waste
$100
LandfillsContaining not more than 50% by
weight of inert construction waste
$125
Outlying Islands Transfer Facilities
Containing any percentage ofinert construction waste
$125
5
What can we do with the problems?
1. Avoid waste generation
2. Minimize waste generation
3. Reuse/Recycle the material
4. Proper disposal of waste
AVOID
MINIMISE
REUSE/RECYCLE
DISPOSAL
24
Form work Finish work Concrete
work
Masonry
work
Material
handling
Scaffolding
work
Hoarding
Ranking of Major Waste Producing Processeson Building Sites
Source : HK PolyU
25
Damaged during
laying
19%
Cutting Waste
39%
Damaged during
storage
11%
Over Order
15%
Damaged during
transportation
16%
Figure 6 Major Causes of Waste for Brick/Block (Source: Hong Kong PolyU [ 6 ] )
26
Over order
11%
Others
7%Cutting waste
40%
Damaged during
storage
29%
Change of design
13%
Figure 8 Major Causes of Waste for Tiles (Source: Hong Kong PolyU [ 6 ] )
Source : HK PolyU
27
Major Causes of Waste for Cement/Plaster
Improper storage
11%
Lost while
applying
19%
Left over of
mixed materials
59%
Others
11%
Source : HK PolyU
28
Percentage wastage of various trades
Trade Material Percentage wastage
Public Private
Concrete Concrete 3-5% 4-5%
Formwork Timber broad - 100%
Reinforcement Steel bars 3-5% 1-8%
Masonry Brick and block
3% 4-8%
Dry Wall Fine aggregate 3% -
Wall screeding Ready-mix cement
7% 4-20%
Floor screeding Ready-mix cement
1% 4-20%
Wall plastering Plaster 3% 4-20%
Source : HK PolyU
29
Ceiling plastering
Plaster 3% 4-20%
Wall tiling Tiles 8% 4-10%
Floor tiling Tiles 6% 4-10%
Installation of bathroom fitting
Sanitary fitting 6% 1-5%
Installation of kitchen joinery
Kitchen joinery 1% 1-5%
Percentage wastage of various trades
Source : HK PolyU
34
Design to Minimize Construction Waste
Waste arising from construction can be reduced by:
• Dimensional coordination and standardization
• Minimizing temporary works
• Avoiding late design modifications
• Detailing and simple design
35
Dimensional Coordination and Standardization
36
Minimizing Temporary Works
• In Hong Kong, most of the waste arising from temporary works is due to the use of timber formworks
37
Minimizing Temporary Works
Alternatives to be considered:
•system formworks (metal or aluminum formworks) that can be reused and/or recycled
•Prefabricated elements (facades, slabs, staircases, etc)
38
Minimizing Temporary Works
Other reusable alternatives to be considered:
• Metal temporary work• Metal platform work• Reusable safety system• Metal scaffolding or mixed
bamboo and metal scaffolding• Metal hoarding
39
0.21
0.56
0.76
1.11
1.31
1.33
0 0.2 0.4 0.6 0.8 1 1.2 1.4
Waste reduction
Labor dependence
Developers requirement
Familiarity with the construction tecnology
Construction cost
Construction time
Fac
tors
Index
Construction Method Selection
41
On-site Construction Methods
Most waste producing work process
0
0
0
0
0.35
0.46
0.77
1.09
0 0.2 0.4 0.6 0.8 1 1.2
Hoarding
Masonry work
Concrete work
Scaffolding
Materials handling
Finish work
Packaging & protection
Formwork
Bu
ildin
g w
ork
co
mp
on
ents
index
43
On-site Low Waste Building Technologies
Formworks:
• Large panel formwork.
• Steel, aluminum and plastic forms.
• Composite steel decking.
• Pecaform.
44
Off-site: Precast and Prefabrication
• Off-site construction can reduce waste generation on-site, as waste is generated at a plant and easier to be managed and sorted.
• The use of prefabricated elements is highly applicable to high-rise construction in Hong Kong.
• Prefabrication requires experience, knowledge and also early planning and decisions at the design stage.
45
Off-site: Precast and Prefabrication
46
Modular Construction
•Modular construction approach has been demonstrated for high-rise buildings in Hong Kong by the Integer project.
Prof. C.S. PoonDept of Civil and Structural EngineeringThe Hong Kong Polytechnic UniversityTel : (852) 2766-6024Email : [email protected]
Thank You