Mamma Affidavit to correct rating and regularisation of period
-
Upload
chandira-thangavel -
Category
Documents
-
view
146 -
download
2
Transcript of Mamma Affidavit to correct rating and regularisation of period
BEFORE THE HON’BLE HIGH COURT OF JUDICATURE AT CHENNAI
(Under Art226 of Indian Constitutional Law)
M.P.No:1/15
In
W.P.No: /15
1) P.Chandira,M.E(M.B.A)(B.G.L)
W/o R.Thangavel,
E-77, Anna Road,Block-27, Neyveli-3
2) R.Thangavel,M.E.,
The Chief Manager,TPS-I,
NLC,Neyveli- 3 -------------Petitioner/Petitioner
Verses
1) The Chairman cum Managing Director,NLC,Neyveli
2) The Chief Vigilance officer, NLC,Neyveli
3) The Director(HR), NLC,Neyveli.
4)The Central Public Information officer,NLC, Neyveli.
5)Balasubramanian,the enquiry officer,NLC.Neyveli.
6)The Chief General Manager,Mine-I, NLC,Neyveli.
7)A.R.Ramachandran,the enquiry officer,NLC,Neyveli
8)Thiru.Paramasivam,the former CGM,TPS-I.Neyveli.
9)Thiru.Sureshbabu,the G.M,TPS-I,Neyveli. ----------Respondents/Respondents.
AFFIDAVIT FILED BY THE 1 st PETITIONERS ON HER BEHALF AND ON BEHALF OF THE 2 ND PETITIONER.
1. I, the 1st petitioner Mrs.P.Chandira aged about 47 years is working as
an Assistant Engineer(H) Nabard and Rural Roads, Panruti and the wife of the 2nd
petitioner, Er.R.Thangavel,is aged about 56 years, Chief Manager Neyveli Lignite
Corporation, First Thermal Power Station, Neyveli residing at E-77,Anna Road,
Block-27, Neyvei-3 is sincerely and solemnly state as follows:
2. The 2nd petitioner humbly pray that this Hon’ble High Court may please
to permit the 1st petitioner his power of Attorney and wife Mrs.P.Chandira to
represent this case on behalf of the 2nd petitioner as she knows the facts and
circumstances of the case very well and represented the cases on behalf of the
second petitioner in W.P.No:17124/08, Writ.ReviewNo:103/08, Writ Appeal
SRNo: 15515/09, Writ Appeal in WANo: 282/09, Writ Appeal Review No: 37/09
and the 2nd review Petition. The copy of the Notary attested Power Attorney is
submitted before this Hon’ble High Court. As the 1st petitioner is the witness to
state Vigilance and NLC management witness against Er.Ananthakrishnan and
Thiru.Natarajan 2nd petitioner is victimised.
3. The 2nd petitioner studied Bachelor of Engineering Degree in Mechanical in
Coimbatore Institute of Technology, Coimbatore in the year of 1981 and Master of
Engineering, Design in Government College of Technology, Coimbatore in the
year of 1983. The 2nd Petitioner worked as Lecturer in Coimbatore Institute of
Technolgy, Coimbatore. The 2nd petitioner joined his duty as Graduate Engineer
Trainees on 15/11/1983 in esteemed Neyveli Lignite Corporation. The 2nd
petitioner was promoted as Assistant Executive Engineer on 01.06.1985, Executive
Engineer on 01.09.1989 and Deputy Superintendent (Scale), Senior Executive
Engineer on 01.09.1993. The 2nd petitioner availed Lien Service, Foreign Service
(Lien) in abroad in the period of 19.09.2001 to 30.10.2003 after relieving from the
Neyveli Lignite Corporation on 18.09.2001. The 2nd petitioner rejoined his duty
back to Neyveli Lignite Corporation on 31.10.2003.
4. The 2nd petitioner was promoted as Deputy Chief Engineer E5 with
effect from 01.09.1997 by paper movement before the Departmental Promotion
Committee for his four years of his service completion as Senior Executive
Engineer, the Deputy Superintendent (Scale) 01.09.1993 to 30.08.1996. The 2nd
petitioner was promoted as Additional Chief Manager Scale E6 on 01.07.2005 and
subsequently on Additional Chief Manager, M-1 Grade/E6 on 01.07.2006.
5. In the mean time the petitioners purchased a land to construct an
apartment under PPA rules and regulation in the year of 2008 jointly with some
other Neyveli Lignite Corporation employees on 13.03.08 through Natarajan, the
Chief Technician, Neyveli Lignite Corporation, Neyveli. Thiru.Ananthakrishnan is
also the one of the purchaser in Pondy. Thiru.Natarajan, the Chief Technician and
Thiru.Ananthakrishnan is doing real estate business from 2008. In the mean the 1st
petitioner was posted to Rajasthan Barshingsar Project on 02.04.08 by Neyveli
Lignite Corporation Proceeding. The petitioners submitted several representations
to the Neyveli Lignite Corporation Chairman-Cum-Managing Director of Neyveli
Lignite Corporation and all the Directors of Neyveli Lignite Corporation to permit
to continue the 2nd petitioner to do his duty at Tamilnadu until FIRNo: 10/03 filed
by the Vigilance Anti-Corruption Department is pending as the 1st petitioner is
witness to Tamilnadu State Vigilance Department subsequent orders in
W.P.No:26463/01 Dated: 04.03.02, 14.03.02, 23.04.03 and 24.06.03.
6. When the 2nd petitioner were went to his native for her mother’s death six
month ceremonial function at his native he was deemed to be relieved on 14.04.08
without serving the Transfer order. The 2nd petitioner submitted a representation on
18.04.08 to the Director (Power) and the Chairman-Cum-Managing Director of
Neyveli Lignite Corporation to permit to continue his duty at Neyveli. Further the
petitioners planned to purchase an apartment at Chennai Valasarawakkam on
14.05.08 through Thiru.Natarajan. The Director (Power) permitted the 1st
petitioner to continue the duty up to 14.07.08 in his proceeding on 22.05.08.
7. The 1st petitioner filed a defamation case in C.C.No:314/02 on 08.10.02
before the Judicial Magistrate Court-II, Chidambaram against a)
Thiru.Tamilselvan, the former Divisional Engineer (H) (Regular) Cuddalore b)
Thiru.Ponnselvan, the former Assistant Divisional Engineer (H) (Regular)
Chidambaram c) Thiru.Haribabu, the former Junior Engineer (H), Nabard and
Rural Roads, KattumannarKovil. Subsequently the 1st petitioner filed 91CRPC
before the Judicial Magistrate Court-II, Chidambaram on 29.01.2003 and is still
pending and hence the transfer OP No: 4787/14 is filed before the Judicial
Magistrate Court-II, Chidambaram to the District Munisiff Cum Judicial
Magistrate Court, Neyveli.
8. The 2nd petitioner filed a W.P.No:17124/08 on behalf of the 1st
petitioner before this Hon’ble High Court on 14.07.08 with M.P.No:1/08 to
dispense the transfer order and to stay the transfer order in M.P.No:2/08 against a)
The Director (Power) NLC, Neyveli b) The DGM (P&A) NLC, Neyveli c) The
General Manager, Thermal Power Station-I, Neyveli d) The DGM (P&A) Welfare,
NLC, Neyveli e) The Chief Manager (P&A) Neyveli. The Hon’ble High Court
granted an interim stay in M.P.No:2/08 in W.P.No:17124/08 on 05.08.08.
Subsequently the 1st petitioner was permitted to continue duty at First Thermal
Power Station, Neyveli on 08.08.08. In order to prove the malafide act of
respondents in M.P.No:2/08 in W.P.No:17124/08 ,the 2nd petitioner filed
M.P.No:4/08 in individual capacity and to extend the stay in M.P.No:5/08 before
the Hon’ble High Court on 13.08.08. During the hearing on 18.08.08 the Hon’ble
High Court permitted the implead petition in M.P.No:4/08 and added the six to
tenth respondents in individual capacity and extended the stay petition in
M.P.No:5/08 until further orders.
9. The 2nd respondent DGM (P&A) filed counter in M.P.No:3/08 on
behalf of the 1 to 5 respondents in official capacities in W.P.No:17124/08. The
respondents in individual capacity has not filed counter in W.P.No:17124/08.
During the hearing on 01.09.08 the Hon’ble High Court dismissed the
W.P.No:17124/08 with the direction to the 2nd respondent DGM (P&A) to consider
the grievances in accordance with law. The 2nd petitioner was forcefully relieved
on 05.09.2008 by the Neyveli Lignite Corporation. The 2nd petitioner filed Writ
Review No: 103/08 with M.P.No:1/08 on 06.09.08. The Hon’ble High Court
issued notice to the ten respondents to file counter in M.P.No:1/08. The proof of
the Private notice also filed before the Hon’ble High Court High Court. During the
hearing on 18.09.08 the case is argued without counter by the one to ten
respondents and the case is adjourned for judgements. The Hon’ble Court passed
an order in Writ Review No: 103/08 without any order in M.P.No:1/08 without the
knowledge of the petitioners on 24.09.08. In the mean time the petitioners arranged
for an advocate N.R.R.Natarajan from Mrs.Nalini Chidambaram madam office.
The advocate issued contempt notice to the NLC management Chairman-Cum-
Managing Director of Neyveli Lignite Corporation, to the Directors and DGM,
(P&A) of Neyveli Lignite Corporation. Further the 1st petitioner filed a Writ
Petition against the 1st respondent herein the Chairman-Cum-Managing Director of
Neyveli on 14.05.2009 and the 2nd petitioner filed contempt petition which is
numbered as Cont.Pet.No:483/09 on 01.06.09. Even though the 1st petitioner filed
Writ Petition on 14.05.09 and 2b petition on 27.05.09 to add the 2nd petitioner in
the single writ petition, the Writ Petition was numbered in the 2nd petitioner name
only in W.P.No:11001/09 to call for the records on the file of
CORP/P&A/EE/0502/2008 Dated: 15.09.08 on the file of CGM (P&A) and all
further proceedings initiated by the Neyveli Lignite Corporation.
10. In the mean time the 1 st respondent has not conducted DPC in the year
of 2009. In the mean time the Project head, Rajasthan has issued a illegal charge
memo to the second petitioner. Even though the 1st respondent permitted the 2nd
petitioner to attend DPC in the year 2010, because of the illegal charge memo
created by the Project head the second petitioner was not promoted as Chief
Manager. Even though the 1st respondent permitted the 2nd petitioner to attend DPC
in the year 2011, because of the illegal charge memo created by the Project head
the 2nd petitioner was not promoted as Chief Manager. The 1st petitioner submitted
complaints on 27.05.2012 to the 2nd respondent herein against
Thiru.Ananthakrishnan and Thiru.Natarajan .The 2nd respondent directed the Chief
Manager Thiru.Sivashanmugham to conduct the preliminary enquiry on
14.05.2012 .The 1st petitioner submitted seventeen pages of documents along with
three pages of written statement. The 2nd petitioner was promoted as Chief
Manager Scale E6A on 01.07.2012 and subsequently on Chief Manager, M-2
Grade/E6A on 01.07.2013.
11. The 1st petitioner filed a Writ Petition before this Hon’ble High Court
on 07.10.2012 with twelve orders 1)FI.R.No:10/03 filed by the Vigilance and Anti-
Corruption Department, Cuddalore 2) The order of the Hon’ble High Court in
W.P.No:17124/08 Dated: 01.09.08 3) The order of the Hon’ble High Court in
Writ.Review.No:103/08 Dated: 24.09.08 4) The Secretary,Highways and Minor
Ports Department Lr Dated:13.10.08 5) The order of the Hon’ble High Court in
W.A.No:282/09 Dated: 18.03.09 6) The order of the Hon’ble High Court in Writ
Appeal Review.No:37/09 Dated: 30.04.09 7) The 2b Petition in SRNo:41218
Dated:27.05.09 8)The substituted order of the Hon’ble High Court in
W.P.No:17124/08 Dated: 02.07.09 9) The substituted order of the Hon’ble High
Court in W.P.No:17124/08 Dated: 07.08.09 10) To set aside the order of the CJM
Court,Cuddalore order: dated:01.12.09 11) The order of the Hon’ble High Court in
W.P.No:11001/09 Dated: 13.02.09 12) The order of the Hon’ble High Court in
Crl.O.P.No:22241/11 Dated: 11.11.11.The 1st petitioner filed a Writ Petition in
W.P.No:11001/09 against the CMD,NLC,Neyveli which is numbered in the second
petitioner by the Registrar(Judicial) with the influence of the Principle
Secretary,Highways and Minor Ports Department,Secretariat,Chennai-9, the Chief
Judicial Magistrate Court,Cuddalore and the Inspector of Police,V&AC,Cuddalore
and caused undue harassment to the petitioners. Hence the petitioners filed this
Writ Petition on 07.10.2012 to regularise the period of the petitioner and her
husband with damaged remedy and relief and thus render justice.
12. In the reasons stated the first petitioner humbly prayed on 07.10.2012
that this Hon’ble High Court may please to direct the CMD,NLC,Neyveli which is
numbered in the second petitioner by the Registrar(Judicial) with the influence of
the Principle Secretary,Highways and Minor Ports Department,Secretariat,
Chennai-9, the Chief Judicial Magistrate Court,Cuddalore and the Inspector of
Police,V&AC,Cuddalore to file their report before this Hon’ble High Court based
upon the above case bundles and the representations submitted to them within the
stipulated period of time until disposal of the writ petition on 07.10.12 and thus
render justice.
13. In the reasons stated the first petitioner humbly prayed on 07.10.2012
that this Hon’ble High Court may please to issue the Writ of Certiorari or any other
Writ calling for the records on the file of respondents in 1)FI.R.No:10/03 filed by
the Vigilance and Anti-Corruption Department, Cuddalore 2) The order of the
Hon’ble High Court in W.P.No:17124/08 Dated: 01.09.08 3) The order of the
Hon’ble High Court in Writ.Review.No:103/08 Dated: 24.09.08 4) The
Secretary,Highways and Minor Ports Department Lr Dated:13.10.08 5) The order
of the Hon’ble High Court in W.A.No:282/09 Dated: 18.03.09 6) The order of the
Hon’ble High Court in Writ Appeal Review.No:37/09 Dated: 30.04.09 7) The 2b
Petition in SRNo:41218 Dated:27.05.09 8)The substituted order of the Hon’ble
High Court in W.P.No:17124/08 Dated: 02.07.09 9) The substituted order of the
Hon’ble High Court in W.P.No:17124/08 Dated: 07.08.09 10) To set aside the
order of the third respondent dated:01.12.09 11) The order of the Hon’ble High
Court in W.P.No:11001/09 Dated: 13.02.09 12) The order of the Hon’ble High
Court in Crl.O.P.No:22241/11 Dated: 11.11.11 and consequently quash the illegal
proceedings of respondents on public interest to prevent the misuse of Government
funds and to regulate the period from the date of transfer order issued to the second
petitioner to the date of his joining duty as duty period and promote him as Deputy
General Manager and regularization of Period 08.06.09 to 25.10.09 as duty to the
first petitioner and promote the petitioner as Assistant Divisional Engineer and the
compensation to the petitioners as this Hon’ble High Court may deem fit and
proper in the circumstances of the case and thus render justice.
14. The 1st respondent arranged for the departmental enquiry against
Thiru.Ananthakrishnan and Thiru.Natarajan in the month of January- 2014. When
the first petitioner had a plan to attend enquiry against Thiru.Ananthakrishnan at
Rajasthan Barshingsar Project with the second petitioner, an accident happened at
First Thermal Power station on 20.05.2014 which is registered as FIRNo:59/14 by
the Inspector of Police, Thermal Power Station,Neyveli on the file of District
Munisiff Cum Judicial Magistrate Court,Neyveli and subsequently the first
petitioner was threatened on 24.05.2014 and falsely implicated in C.C.No:41/14
before the Judicial Magistrate Court-II,Panruti which was transferred to the District
Munisiff Cum Judicial Magistrate Court,Neyveli. The 2nd petitioner submitted
twenty three pages of documents by fax to the departmental internal enquiry
officer, Rajasthan Barshingsar Project against Thiru.Ananthakrishnan. The 2nd
petitioner submitted nineteen documents to the departmental external enquiry
officer,A.R.Ramachandran against Thiru.Natarajan which is conducted in
Tamilnadu.
GROUNDS.
15) The 1st petitioner submitted complaints dated: 27.05.2012 to the
second respondents to take necessary action against Thiru.Ananthakrishnan and
Thiru.Natarajan. The second respondent had taken necessary steps to conduct an
enquiry through the 1st respondent department against Thiru.Ananthakrishnan
through departmental internal enquiry officer and an enquiry against
Thiru.Natarajan against through external enquiry officer Thiru.A.R.Ramachandran.
The respondents failed to serve the details of the action taken by them based upon
the complaints submitted by the petitioner to them is in violation of Principles of
Natural Justice and against law. Even though the 1st petitioner requested the details
the presenting officer advised to get the details under Right to Information
Act2005. The 1st petitioner submitted an application under Right to Information
Act 2005 to the Central Public Information officer, Neyveli Lignite Corporation.
As the Central Public Information has not provided the details an appeal has been
submitted to the Appellate Authority, Right to Information Act2005.As the
Appellate authority also has not submitted the details the 2nd Appeal submitted
before the Central Information Commissioner to get the details and the respondents
are causing undue harassment to the petitioners in different ways.
16) The Hon’ble High Court passed an order in W.P.No:17124/08 on
01.09.08 and substituted on 02.07.09 and 07.08.09. The period between 01.09.08
to 07.08.09 is stay existing period.
17) The petitioner filed M.P.No:1/08 in Writ Review No:103/08 on
06.09.08.The Hon’ble High Court issued notice to the respondents in
M.P.No:1/08.The Hon’ble High Court has not passed any orders in M.P.No:1/08 in
Writ Review No:103/08.
18) The 1st petitioner humbly submits that the Postal department receipt
despatched from NLC management on 12.03.09 through the post office in vide
serial No:A687 to the 2nd petitioner, in vide serial No:688,to the District
Collector,Cuddalore and in vide serial No:689,to the Secretary, Highways/Govt of
Tamilnadu Highways Department,Secretariat,Chennai-9.
19) The 1st petitioner humbly submits that the Central Public Information
officer Letter No: PRD/CPIO/0062/2008-6 Dated: 08.07.2008. As per the terms
and conditions of appointment and promotion orders of the employees, they are
liable to be transferred to any branch/Department/subsidiaries/undertaking of the
Corporation situated anywhere in India. There is a need of experienced and
dedicated executives at the Project site for coordinating and executing various
activities for smooth implementation of the Project. Barshingsar Project at
Rajasthan is an upcoming and Prestigious, Mining-Cum-Power Project of NLC and
several senior and experienced executives have been transferred so as to
commence the project of NLC and several senior and experienced executives have
been transferred so as to commence this project as envisaged as per schedule.
Transfer is administrative decision and Prerogative of the Management and
transfer orders are issued deployment of employees who well experienced and
trained, so as to get best results for the Organisation. The 2nd petitioner as per the
direction of the Hon’ble High Court joined his duty on 19.08.09 and submitted a
representation to the 1st respondent to regularise the litigation period as duty and
promote the 2nd petitioner as Deputy General Manager and performed his duty for
the period of two years at Rajasthan Barshingsar Project.
20) The 1st petitioner humbly prayed on 07.10.2012 that this Hon’ble High
Court may please to direct the CMD,NLC,Neyveli which is numbered in the
second petitioner by the Registrar(Judicial) with the influence of the Principle
Secretary,Highways and Minor Ports Department,Secretariat,Chennai-9, the Chief
Judicial Magistrate Court,Cuddalore and the Inspector of Police,V&AC,Cuddalore
to file their report before this Hon’ble High Court based upon the above case
bundles and the representations submitted to them within the stipulated period of
time until disposal of the writ petition on 07.10.12 and thus render justice.
21) The 1st petitioner humbly prayed on 07.10.2012 that this Hon’ble High
Court may please to issue the Writ of Certiorari or any other Writ calling for the
records on the file of respondents in 1)FI.R.No:10/03 filed by the Vigilance and
Anti-Corruption Department, Cuddalore 2) The order of the Hon’ble High Court in
W.P.No:17124/08 Dated: 01.09.08 3) The order of the Hon’ble High Court in
Writ.Review.No:103/08 Dated: 24.09.08 4) The Secretary,Highways and Minor
Ports Department Lr Dated:13.10.08 5) The order of the Hon’ble High Court in
W.A.No:282/09 Dated: 18.03.09 6) The order of the Hon’ble High Court in Writ
Appeal Review.No:37/09 Dated: 30.04.09 7) The 2b Petition in SRNo:41218
Dated:27.05.09 8)The substituted order of the Hon’ble High Court in
W.P.No:17124/08 Dated: 02.07.09 9) The substituted order of the Hon’ble High
Court in W.P.No:17124/08 Dated: 07.08.09 10) To set aside the order of the third
respondent dated:01.12.09 11) The order of the Hon’ble High Court in
W.P.No:11001/09 Dated: 13.02.09 12) The order of the Hon’ble High Court in
Crl.O.P.No:22241/11 Dated: 11.11.11 and consequently quash the illegal
proceedings of respondents on public interest to prevent the misuse of Government
funds and to regulate the period from the date of transfer order issued to the second
petitioner to the date of his joining duty as duty period and promote him as Deputy
General Manager and regularization of Period 08.06.09 to 25.10.09 as duty to the
1st petitioner and promote the petitioner as Assistant Divisional Engineer and the
compensation to the petitioners as this Hon’ble High Court may deem fit and
proper in the circumstances of the case and thus render justice.
22). The 1st petitioner submitted to amend the prayer petition before this
Hon’ble High Court,Chennai to set-aside the order passed by the Hon’ble High
Court on 30.03.2012 to direct the State represented by the Secretary,Highways and
Minor Ports Department,Secretariat,Chennai to recover the loss to Government
money from the Partners of Sridevi Enterprises, Contractor,Chennai and from
Thiru.Haribabu,the Junior Engineer,Highways,Nabard Section,KattumannarKovil
and consequently if the Hon’ble High Court may please to direct the
CMD,NLC,Neyveli to regulate the period as duty and promote him as Deputy
General Manager and to pass a policy to not to transfer an employee whose spouse
are working in Tamilnadu the State represented by the Secretary,Highways and
Minor Ports Department,Secretariat,Chennai to grant the monetary benefits to the
1st petitioner as Assistant Divisional Engineer with effect from 17.06.2002 on
which loss to government money is proved in W.P.No:26463/01 and consider
Meritorious Promotion as Divisional Engineer and thus render justice. The copy of
the Petition,affidavit and typed submitted before this Hon’ble High Court. As the
first petitioner seeking legal justice from the year of 2001,the 2nd petitioner are
victimised by the respondents with influence of so many people mentioned in
Crl.O.P.No:6002/15 before this Hon’ble High Court on 06.03.2015. The 1st
respondent in Crl.O.P.No:6002/15 is the Director,Vigilance and Anti-Corruption
Department,Neyveli and the eighth respondent the Inspector of Police, Vigilance
and Anti-Corruption Department,Cuddalore only filed counter on 30.03.2015 out
of fourteen respondents.
23) The 3rd respondent recently implemented the rating of NLC employees
through Bell Curve. The 2nd petitioner is even though done his work out standing,
the DGM awarded as “Very Good” rating and the CGM award the rating as
“Good”. The respondents are keeping the rating of NLC employees in a
confidential manner. The aggrieved about the rating the 2nd petitioner submitted an
appeal through proper channel. The respondents without hearing the 2nd petitioner
and without serving the copies of the rating of DGM and CGM reduced the rating
of the 2nd petitioner on the wreck vengeance as the 1st petitioner submitted
compliants against Thiru.Ananthakrihnan and Thiru.Natarajan to the 2nd
respondent on 27.05.2012 violating the “Principles of Natural Justice.”. The
respondents inordinately delayed to take action from 27.05.2012 against
Thiru.Ananthakrishnan and Thiru.Natarajan reduced the rating of outstanding
employee who has attended duty more than others 256 days during review period
2013-14 against the minimum eligibility days of 220 days for Performance Related
Pay without availed medical leave and Earn leave and sincerely done his service
for the Corporation. Instead of maintaining transparency in administration and
keeping the rating of an employee in confidential manner affects the right of the
employees in the Corporation which creates the misuse of power in the
Corporation. The respondents failed to act in accordance with law and caused
undue harassment to the both the petitioners and only due to wreck vengeance on
seeking legal remedy through this Hon’ble High Court,Chennai. The respondents
failed to consider the representations of the both the petitioner and violated the
“Principles of Natural Justice”in turn Art14 and 16 of our Indian Constitutional
Law and inordinately delayed in Displinary Proceedings of Er.Ananthakrihnan
and Thiru.Natarajan and against the 2nd petitioner and caused undue harassment to
both the petitioners.
24) The departmental enquiry officer closed the enquiry stating that the no
charges proved against the second petitioner and it is not necessary to call for the
records from the department.The petitioners submit the copy of the enquiry
proceedings by the 2nd petitioner in presence of the presenting officer, CM,
Personnel,Neyveli Lignite Corporation,Barshingsar Project,Neyveli.The ninth
respondent inordinately delayed to take necessary steps in passing final orders in
the Disciplinary Proceedings against the 2nd petitioner.The eight respondent
wrongly reduced the rating of the 2nd petitioner as “Good”instead of maintain the
rating of DGM as very good or to fix as “Outstanding.” Even though the 2nd
petitioner clearly explained about the reasons for reducing the rating the ninth
respondent refused to take necessary steps in accordance with law and their acts
are tainted with malafide. An incident happened in the first thermal power station
on 20.05.14 and the first thermal power police has registered case in
F.I.R.No:59/14.The eighth respondent is awarding the rating of the second
petitioner based upon the report of the Deputy General Manager for the period of
2013-14,1st of April2013 to March-31of 2014 and reduced the rating of the 2nd
petitioner as “good”as he has not reported to the police station without knowing the
facts and circumstances and without hearing the 2nd petitioner. The eighth
respondent reduced the rating for the incident of May2014. The eighth respondent
is the factory manager he has to report the factory accident to the police station and
to the District Munisiff and Judicial Magistrate Court, Neyveli. The eighth
respondent instead of acting in accordance with company personnel manual he
forced all to report to the police station. The statement of the eighth respondent
about the factory accident creates so much of confusion about the accident. Three
peoples lost their life in the accident.Hence the department has initiated
departmental disciplinary proceedings against some officials after conducting five
member committee enquiry report. When the 2nd petitioner was in a position to
attend enquiry against Thiru.Ananthakrishnan at Rajasthan and against
Thiru.Natarajan at Tamilnadu.The 2nd petitioner planned to go with the 1st
petitioner to attend enquiry at Rajasthan. Subsequently the 1st petitioner was falsely
implicated in C.C.No:41/14 before the Judicial Magistrate Court-II,Panruti and
threatened by the Inspector of Police,Pudhupet on 24.05.2014. Mrs.Radhika,the
S.P,Cuddalore District failed to take action against Thiru.Ananthakrishnan and
against Thiru.Natarajan even though the matter was published in the paper.
25) The petitioners humbly prayed that this Hon’ble Court may please to
direct the respondents to must have fixed the Annual Performance rating of the
second petitioner for the year 2013-14 as “out standing ”instead of “good”which
was erroneously awarded by the eight respondent and the ninth respondent also not
rectified in the Appeal.
26) The petitioner humbly prayed that this Hon’ble Court may please to
note that the respondent must have fixed the seniority of the Engineers based upon
their date of Joining at Rajasthan Barshingsar Project as the public information
stated that the outstanding candidates are posted for Rajasthan Barshingsar Project.
The petitioners humbly prayed that this Hon’ble High Court may please to direct
the details of the action taken by the nine respondents based of the representations
of the petitioners from 16.04.08 to till date as the respondents refused to permit to
peruse the records and the fourth respondent failed to provide under Right to
Information act2005 and thus render Justice.
27) In the above circumstance the petitioners humbly prayed that this
Hon’ble High Court may please to direct the respondents to keep one post vacant
in Deputy General Manager for which the 2nd petitioner must have promoted with
effect from 18.08.09 the date of joining at Barshingsar Project,Rajasthan until
disposal of this writ petition and thus render Justice.
28) In the above circumstances the petitioners humbly prayed that this
Hon’ble Court may please to issue a writ of certiorari calling for the records of the
nine respondents to promote the second petitioner as the Deputy General Manager
from 19.08.09 as he joined his duty at Barshingsar Project, Rajasthan as directed in
W.A.No:282/09 and regularize the period as duty from the date of transfer order
02.04.08 to 18.08.09 and consequently quash
1) the Disciplinary Proceedings No: 7596/NLC/ BP/P&A/Disp/08 Dated: 11.11.08
against the 2nd petitioner
2) the Annual Performance rating of the 2nd petitioner for the period 2013-14 as
“good” which is erroneously awarded by the eighth respondent instead of “out
standing”
with the adequate compensation to the both the petitioner for the
loss, not tolerable mental agony,threatening,undue harassment suffered due to the
acts of the nine respondents deem fit and proper in the facts and circumstances of
the case with consequential benefits and thus render justice.
Sincerely and solemnly as sworn 1st Petitioner Party-in-Person
On 22.02.2015 at Chennai 2nd Petitioner through his wife&Power