DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED 1 MAJOR PROJECTS EXECUTED S/N YEAR PROJECT DESCRIPTION LOCATION CLIENT 1 1996 CONSTRUCTION OF LANDING JETTY ABARA, BURUTU LOCAL GOVT. DELTA STATE OMPADEC / SAMSON ENE ENT. 2 1996 CONSTRUCTION OF LANDING JETTY ORUGBO, WARRI SOUTH LGA. DELTA STATE. OMPADEC / ROBENS NIG. LTD. 3 1997 BUMPER PILE SUPPORT FOR CONCRETE BARGE. OLERO CREEK, WARRI NORT LGA. DELTA STATE. DAEWOO/ CHEVRON 4 1998 JETTY PILE DRIVING WORK MOSHESHE JETTY, WARRI C.G.G. LTD. 5 1998 CONSTRUCTION OF MARKET STORE AGGE, DELTA STATE SPDC WEST 6 1999 FLOWSTATION EXTENSION FOUNDATION- PILING & FABRICATION WORKS FOR TANK INSTALLATION. OPUAMA FLOWSTATION SPDC / SOIMI / LEE ENGINEERING 7 1999 HELIPAD CONSTRUCTION OTUMARA FLOWSTATION SPDC / RANC 8 1999 400-M LONG SHORE PROTECTION (STEEL SHEET PILING). OGBOTOBO ESPRO FLOWSTATION BAYELSA SPDC / RAYCON 9 2000 CONSTRUCTION OF PILE FOUNDATION FOR 104M SELF SUPPORTING TELECOM TOWER OPUAMA FLOWSTATION SPDC / WESTERN BELL ENG. LTD.

Transcript of MAJOR PROJECTS EXECUTED - doriginternational.com

Page 1: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

1

MAJOR PROJECTS EXECUTED

S/N YEAR PROJECT DESCRIPTION LOCATION CLIENT

1 1996 CONSTRUCTION OF

LANDING JETTY

ABARA, BURUTU LOCAL

GOVT. DELTA STATE

OMPADEC / SAMSON

ENE ENT.

2 1996 CONSTRUCTION OF

LANDING JETTY

ORUGBO, WARRI SOUTH

LGA. DELTA STATE.

OMPADEC / ROBENS

NIG. LTD.

3 1997

BUMPER PILE SUPPORT

FOR CONCRETE BARGE.

OLERO CREEK, WARRI NORT

LGA. DELTA STATE.

DAEWOO/

CHEVRON

4 1998 JETTY PILE DRIVING

WORK

MOSHESHE JETTY, WARRI C.G.G. LTD.

5 1998 CONSTRUCTION OF

MARKET STORE

AGGE, DELTA STATE SPDC WEST

6 1999 FLOWSTATION

EXTENSION

FOUNDATION- PILING &

FABRICATION WORKS

FOR TANK

INSTALLATION.

OPUAMA FLOWSTATION SPDC / SOIMI / LEE

ENGINEERING

7 1999 HELIPAD CONSTRUCTION

OTUMARA FLOWSTATION SPDC / RANC

8 1999 400-M LONG SHORE

PROTECTION (STEEL

SHEET PILING).

OGBOTOBO ESPRO

FLOWSTATION BAYELSA

SPDC / RAYCON

9 2000 CONSTRUCTION OF PILE

FOUNDATION FOR 104M

SELF SUPPORTING

TELECOM TOWER

OPUAMA FLOWSTATION SPDC / WESTERN

BELL ENG. LTD.

Page 2: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

2

10 2000 OVERHEAD WATER &

DIESEL TANKS

FOUNDATION WORKS.

TUNU FLOWSTATION

SPDC / DEE-DAMOR

11 2000 BOSKEL FLARE

FOUNDATION PILING.

OPUKUSHI FLOW. SPDC / NESTOI

12 2001 CONSTRUCTION OF

PILED FOUNDATION FOR

104M 3-ST TELECOM

TOWER.

ESCRAVOS FLOWSTATION

OGIDIGBEN.

SPDC / WESTERN

BELL ENG. LTD.

13 2001 CONSTRUCTION OF

PILED FOUNDATION FOR

80.0M FOUR-LEGGED

SELF-SUPPORTTING

TELECOM / MICROWAVE

TOWER.

ALAKIRI GAS PLANT. SPDC/ WESTERN

BELL ENG. LTD.

14 2001 CONSTRUCTION OF

PILED FOUNDATION FOR

100.0M SELF-

SUPPORTTING TELECOM

& MICROWAVE TOWER.

NEMBE 1 CREEK

FLOWSTATION.

SPDC / WESTERN

BELL ENG. LTD.

15 2001 STEEL CASE PILES FOR

FOUNDATION AND

INSTALLATION OF

MANIFOLD PLATFORM.

BATAN. SPDC / DAEWOO

16 2001 CONSTRUCTION OF

PILED FOUNDATION

OLOMU BRIDGE

(ABUTMENTS).

OKPARE OLOMU DELTA STATE GOVT.

/ SKYGRADE

Page 3: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

3

17 2001 UQCC ACCESS RAOD

RESURFACING AND

DRAINAGE

UGHELLI SPDC WEST

18 2002 PILED FOUNDATION FOR

ERIEMU 10 & EVWRENI

2/7 BRIDGES.

ERIEMU & EVWRENI SPDC/ HI-TECH

CONT. LTD.

19

2002 TUNU FLOW STATION

DEVELOPMENT PHASE 3

(PILED FOUNDATION OF

PUMP HOUSE, FLARE

WALKWAY, SEPARATOR

BANK 3, SURGE VESSEL,

FLARE LINE, INLET

MANIFOLD)

TUNU FLOW STATION SPDC / NATONY LTD

20 2002 PILED FOUNDATION

CONSTRUCTION FOR THE

INSTALLATION OF

TURBINE GENERATORS

FOR RURAL

ELECTRIFICATION.

OPUKUSHI FLOW STATION SPDC / VICKLEY

21 2002 STEEL CASING PILED

FOUNDATION FOR THE

INSTALLATION OF

FLARELINE PIPE

SUPPORT FOR TUNU

TRAIN 3 FLOWSTATION

DEVELOPMENTS.

TUNU FLOW STATION SPDC / JACKNEL

Page 4: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

4

22 2002 STEEL CASE PILING AND

CONSTRUCTION OF

CONCRETE LANDING

JETTIES IN TWO (2)

LOCATIONS

DELEKETA & OBAGHORO

COMMUNITIES.

NDDC DELTA STATE

23 2002 PRECAST CONCRETE

PILING FOR NEPA

TOWERS ACROSS

BOMADI RIVER.

BOMADI DELTA STATE GOVT.

/ ASYTON LTD.

24 2002 610MM DIA. STEEL CASE

MOORING PILES FOR GAS

PROCESSING PLANT

(CONCRETE BARGE) AND

FLARE LINE SUPPORT

AND 508mm DIAMETER

STEEL CASE PILED

FOUNDATION AND

INSTALLATION OF

MANIFOLD PLATFORM.

OTUMARA GAS PROCESSING

PLANT.

SPDC WEST / IGPS

LTD.

25 2002 STEEL CASE PILING AND

CONSTRUCTION OF

CONCRETE LANDING

JETTIES IN TWO (2)

LOCATIONS.

ORI-OKE & UGBONLA IN

ONDO STATE.

NDDC

26 2002 12” DIAMETER STEEL

CASE PILES FOR

MANIFOLD PLATFORM &

INFILLED WITH

REINFORCED CONCRETE.

OTUMARA FLOW STATION SPDC WEST

Page 5: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

5

27 2002 14” AND 12” DIAMETER

STEEL CASE PILING &

INFILLING WITH

REINFORCED CONCRETE

FOR OTUMARA

FLOWSTATION TRAIN III

de-BOTTLE NECKING.

OTUMARA FLOWSTATION SPDC WEST /

NESTOIL LTD.

28 2002 400 X 400mm SQ. PRECAST

CONCRETE JETTY PILES.

IGBEGUNGUN IN ESCRAVOS

DELTA STATE.

CHEVRON / DAGMAR

LTD

29 2003 400 X 400mm SQ. PRECAST

CONCRETE JETTY PILES.

BUGUMA IN RIVERS STATE CHEVRON / DAGMAR

LTD

30 2003 155M LONG STEEL SHEET

PILE RETAINING WALL

AT UNWANA-AFIKPO

EBONYI STATE.

UNWANA SAND BEACH.

UNITED NATIONS

/FG OF NIG. MAK

&MAK LTD

31 2003 472Nos. OF 300mm X

300mm SQ. AND 100Nos.

OF 400 X 400 SQ. PRECAST

CONCRETE PILES.

NORTH BANK FORCADOS/

YOKRI INTERGATED EPIC

PROJECT.

SPDC /HMS

32 2003 250Nos. 360 X 360MM

SQUARE PRECAST

CONCRETE PILES.

NLNG BONNY ISLAND. TSKJ / FOUGEROLLE

33 2003 KING’S PALACE

FLOATING JETTY

MOORING CASE PILING &

JETTY INSTALLATIONS.

(NLNG) BONNY ISLAND. TSKJ

34 2003 TSKJ FLOATING JETTY

MOORING CASE PILING &

JETTY INSTALLATION.

(NLNG) BONNY ISLAND. TSKJ

Page 6: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

6

35 2003 ESCRAVOS - OGIDIGBEN

ROAD RESURFACING

ESCRAVOS BEACH SPDC WEST

36 2004 IGBUKU BRIDGE 53M

SHEET PILED WALL

CONSTRUCTION

IGBUKU – ASHAKA BRIDGE SETRACO NIG. /

DELTA STATE GOVT.

37 2004 PILING OF 300MM SQR.

275NOS. PRE-CAST PILES

FORCADOS-YOKRI

INTERGRATED EPIC

PROJECTS FYIP AT CCP

AREA.

SPDC/DGY

38 2004 PILING OF 300MM SQR.

275NOS. PRE-CAST PILES

AT YOKRI FLOW

STATION EXTENSION

FORCADOS-YOKRI

INTERGRATED EPIC

PROJECT FYIP YOKRI F/S.

SPDC/ HMS/ NATONY

39 2004 PILING OF 300MM SQR.

AND 400MM SQR. PRE-

CAST CONCRETE PILES

FOR THE EXTENSION OF

NORTH-BANK

FLOWSTATION

FORCADOS-YOKRI

INTERGRATED

PROJECT.NORTH BANK F/S

EXTENTION

SPDC / HMS / ALCON

ENG.

40 2004 4 NOS. FOUR - LEGGED

TOWERS FOUNDATION

FOR WARRI TOWNSHIP

STADIUM FLOODLIGHT.

WARRI TOWNSHIP

STADIUM

DELTA STATE GOVT.

/ INCOME ELECTRIX

LTD.

41 2004 ODIDI GASLINK PIPELINE

CONSTRUCTION 400X400

PRECAST CONCRETE

PILING AND LOAD TEST

NORTH-BANK YOKRI SPDC / B+B

Page 7: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

7

42 2004 UTOROGU GAS PLANT

ACCESS ROAD

RESURFACING

OTUJEREMI SPDC WEST

43 2005 ONYOMA COMMUNITY

REINFORCED CONCRETE

LANDING JETTY

EKREMO LGC BAYELSA BAYELSA STATE

GOVT.

44 2005 AGORO COMMUNITY

REINFORCED CONCRETE

LANDING JETTY

AGORO BAYELSA NDDC

45

46

47

2005

2005

2005

IDI-OGBA COMMUNITY

CONCRETE LANDING

JETTY AND REINFORCED

CONCRETE

RETAINING WALL

OGULAGHA/ YOBEBE

ROAD REFURBISMENT

INCLUDING PERIMETER

DRAINAGE ILOWO

COMMUNITY HOSPITAL

CONCRETE LANDING

JETTY AND

REINFORCED

CONCRETE

RETAINING WALL.

IDI-OGBA, ONDO

STATE

OGULAGHA

ILOWO, ONDO STATE

NDDC

SPDC WEST

NDDC

48 2006 AKASSA SHORE

PROTECTION, PRE-CAST

CONCRETE SHEET PILE

WALL

AKASSA-BRASS BAYELSA

STATE

NDDC / WILLIAMS

LYLODS

Page 8: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

8

49 2006 UGBUWANGUE

CONCRETE LANDING

JETTY

UGBUWANGUE DELTA STATE GOVT.

50 2006 CONCRETE LANDING

JETTY DRIVING OF

FOUNDATION PILES

SWALI, YENAGOA NIG. INLAND WATER

WAYS

51 2006 AYAMA COMMUNITY

CONCRETE LANDING

JETTY

AYAMA, BAYELSA STATE UTILITIES, BAYELSA

STATE GOVT

52 2006 CONCRETE LANDING

JETTY DRIVING OF

FOUNDATION PILES

SWALI, YENAGOA NIG. INLAND WATER

WAYS

53 2006 AGGE COMMUNITY

CONCRETE LANDING

JETTY

AGGE

BAYELSA STATE

UTILITIES, BAYELSA

STATE GOVT

54 2006 IKIBIRI COMMUNITY

CONCRETE JETTY

IKIBIRI

BAYELSA STATE

UTILITIES, BAYELSA

STATE GOVT

55 2006 POLAKRO COMMUNITY

CONCRETE JETTY

POLAKRO

BAYELSA STATE

UTILITIES, BAYELSA

STATE GOVT

56 2006 ANGALABIRI

COMMUNITY CONCRETE

JETTY

ANGALABIRI BAYELSA

STATE

UTILITIES, BAYELSA

STATE GOVT

57 2006 RIVERINE

ELECTRIFICATION

PROJECT: ELECTRIC

TOWERS PILED

FOUNDATION

INSTALLATION

DELTA STATE GOVERNMENT OKWAGBE –

OKIRIKA RIVER

CROSSING &

OPHORIGBALA –

OBETEBE

Page 9: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

9

58 2007 ETELEBOU GAS TURBINE

PLANT PROJECT PILED

FOUNDATION WORKS.

ETELEBOU IN BAYELSA

STATE

BAYELSA STATE

GOVERNMENT &

ASEN POWER

ENGINEERING COY

RUSSIA

59 2007 PILED FOUNDATION FOR

FORCADOS (OGULAGHA)

COMMUNITY LANDING

JETTY

OGULAGHA COMMUNITY SPDC/ BENTOKON

LTD.

60 2007 SHORE LINE

PROTECTION WORKS

WITH STEEL SHEET PILE

WALL

NESTOIL YARD PORT

HARCOURT RIVERS STATE.

NESTOIL NIG LTD.

61 2008 COMMUNITY CONCRETE

LANDING JETTY

BILABIRI 1 COMMUNITY SPDC (WEST)

62 2008 COMMUNITY CONCRETE

LANDING JETTY

BILABIRI 2 COMMUNITY SPDC (WEST)

63 2008 COMMUNITY CONCRETE

LANDING JETTY

BISANGBENE COMMUNITY SPDC (WEST)

64 2008

COMMUNITY CONCRETE

LANDING JETTY

LETUGBENE COMMUNITY SPDC (WEST)

65 2008 COMMUNITY CONCRETE

LANDING JETTY

AMATU 2 COMMUNITY SPDC (WEST)

66 2008

OPOROMA COMMUNITY

CONCRETE LANDING

JETTY

OPOROMA COMMUNITY

BAYELSA STATE

UTILITIES BOARD,

BAYELSA STATE

GOVT.

67 2008 LETUGBENE COMMUNITY

CONCRETE LANDING

JETTY

LETUGBENE COMMUNITY

BAYELSA STATE

UTILITIES BOARD,

BAYELSA STATE

GOVT.

Page 10: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

10

68 2008 ANCHOR MOORING PILES ESCRAVOS CHEVRON / GREDOR

NIG. LTD.

69 2008 OPOLO FOOT BRIDGE

PILING WORKS

OPOLO-YENAGOA BAYELSA

STATE

BENTOKON NIG. LTD.

70 2008 NIGER-DELTA

UNIVERSITY,

WILBERFORCE ISLAND

LIBRARY COMPLEX PILED

FOUNDATION WORKS.

AMASOMA, BAYELSA STATE SPDC/ FIRST MARINE

& ENG. SERV. LTD.

71 2008 LOADING JETTY/RAMP

CONSTRUCTION,

SHORELINE PROTECTION

& DRILLING LOCATION

CELLAR SLAB

PREPARATION

K-2 MARGINAL FIELD

BUGUMA, RIVERS STATE

DEL-SIGMA ENG.

LTD.

72 2009 UMUTU MARGINAL

FIELD PILING WORKS

WITH CLOSE-ENDED

STEEL CASE PILES AT

CELLAR SLAB.

UMUTU MARGINAL FIELD,

DELTA STATE

PLATFORM

PETROLEUM LTD.

73 2009 SEVER/SKIMMER PIT

CONSTRUCTION

INCLUDING BORROW PIT

RENULVATION AND

SURFACE DRESSING

UMUSADEGE OIL & GAS

FIELD, KWALE. DELTA

STATE

MID-WESTERN OIL &

GAS PLC.

74 2009 ODEH-ITSHEKIRI

CONCRETE LANDING

JETTY.

BIG WARRI, DELTA STATE DELTA STATE GOVT.

75 2010 LOCATION

PREPARATION PILING

WORK INCLUDING

AWA OGUTA L.G.A

IMO STATE

ADDAX PETROLEUM/

MOTAK

INVESTMENT NIG.

Page 11: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

11

CELLAR SLAB PIT

CONSTRUCTION

LTD

76 2010 CONSTRUCTION OF

CONCRETE JETTY AT

OGBOTOGBO

COMMUNITY

OGBOTOGBO BAYELSA

STATE

BAYELSA STATE

GOVT.

77 2010 CONSTRUCTION OF

LANDING CONCRETE

JETTY

NDOROBAYELSA STATE BAYELSA STATE

78 2010 CONSTRUCTION OF

TELECOM TOWER 56M

INCLUDING THE PILED

FOUNDATION AND

ERECTION

ALAKIRI FLB SPDC

79 2011 AMATU SHORE

PROTECTION

WORKS (REINFORCED

CONCRETE PILES)

AMATU SPDC

80 2011 OPUAMA SHORE

PROTECTION WORKS

OPUAMA IRPC-CHEVRON

81 2011 CONSTRUCTION OF

OGBOTOBO JETTY

OGBOTOBO

BAYELSA STATE

SPDC

82 2012 UTOROGU DOMGAS-NAG

2(PILING WORKS)

UTOROGU

DELTA STATE

MAKON/SPDC

83 2012 AGBADA DOMGAS-NAG 2

(PILING WORKS)

PORT HARCORT RIVERS

STATE

MAKON/SPDC

Page 12: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

12

84 2012 SHORE LINE

PROTECTION WORK AT

AMADIAMA

RIVER STATE NDM

86 2013 CONSTRUCTION OF

AMADIAMA CONCRETE

JETTY / SHORE LINE

PROTECTION WORK

DELTA STATE MINISTRY OF NIGER

DELTA

87 2013 CONSTRUCTION OF

LANDING JETTY

AWAITING HOUSE AT

OMADINO

DELTA STATE NDDC

88 2014 ENEKA WASTE

MANAGEMENT UPGRADE

– EXCAVATION OF CELL

2&3

RIVERS STATE SPDC

89 2014 CALL OFF CONTRACT

FOR PILES & MAT

FOUNDATION WORKS –

SEPLAT

AMUKPE FLOW STATION

SAPELE, DELTA STATE

SEPLAT

90 2014 2 BUFFER TANK AND 4

PILE HEADER

(CONSTRUCTION & PILE

FOUNDATION WORKS)

AMUKPE FLOW STATION

SAPELE, DELTA STATE

SEPLAT

91 2014 MANIFOLD AND RISER

FABRICATION, P ILE

DRIVING & REINFORCED

CONCRETE OF PILES FOR

OML 42 RE-ENTRY

PROJECT

ODIDI 2 EGWA 2 NESTOIL PLC / NPDC

Page 13: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

13

92 2015 CONSTRUCTION AND

INSTALLATION OF

FLOATING JETTY,

WALKWAY AND

DOLPHINS FOR ORIENT

PETROLEUM

RESOURCES REFINERY

JETTY

NSUGBE / UMUERI

NATONY LTD /

SPDC

93 2015 CONSTRUCTION AND

INSTALLATION OF 277

NUMBERS OF BORED

PILE INCLUDING THE

FOUNDATIONS UP TO

GROUND FLOOR SLAB

ESCRAVOS

JOLOMI ENGR.

LTD./CHEVRON

94 2016 PILING SERVICES FOR

KEREMOR PIPELINES

AND BARGING WORKS

ODIDI NESTOIL

LIMITED

95 2017 CONSTRUCTION OF

ONE MOORING

DOLPHIN, TWO BREAST

DOLPHINS, REPAIR OF

HYDRANT LINE AND

CROCODILE PILES

WARRI REFINERY

PETRO-CHEMICAL

COMPANY (WRPC) JETTY

SEPLAT

96 2017 CFA PILING AND

CONCRETE WORKS IN

ODIDI & JONES CREEK

ODIDI & JONES CREEK NESTOIL LIMITED

Page 14: MAJOR PROJECTS EXECUTED - doriginternational.com

DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

14

LIST OF MAJOR PROJECTS EXECUTED BY DORIG TECHNICAL SERVICES INTERNATIONAL LIMITED

97 2017 CONSTRUCTION OF

OGIJO HEALTH CENTRE

OGUN STATE

SNEPCO

98

2018

PROVISION OF

PROCUREMENT AND

INSTALLATION OF

MOORING PILLARS FOR

KEREMOR BARGING OF

OML 42 RE-ENTRY

PROJECT

KEREMOR

NESTOIL LIMITED

99

2019

CONSTRUCTION OF

GBETIOKUN JETTY AND

MOORING FACILITIES

KOKO

BENIN RIVER

ELCREST E & P

NIGERIA LIMITED

100 2020 CONSTRUCTION AND

INSTALLATION OF

GASLIFT COMPRESSOR

SHELTER

UMUSADEGE KWALE

DELTA STATE

MIDWESTERN OIL

AND GAS CO. LTD