Major Open-Pit Copper Mines Move Underground--- Some of the World Largest Open Pit Copper Mine
-
Upload
bekuggsbeku -
Category
Documents
-
view
25 -
download
2
description
Transcript of Major Open-Pit Copper Mines Move Underground--- Some of the World Largest Open Pit Copper Mine
Major Open-Pit Copper Mines Move Underground
Major Open-Pit Copper Mines Move Underground
Some of the world’s largest open-pit copper mining operations are heading underground with
ambitious block cave production plans By Steve Fiscor, Editor-in-Chief
Steel liners installed at the feed head of a grinding mill. (Photo courtesy of ME Elecmetal) The natural progression for an open-pit mine in a rich orebody that extends at depth is to eventually convert to some
form of underground mining to extract the ore. During the near term, two open-pit mining icons will do just that.
The world’s largest copper and gold mine, Freeport McMoRan Copper & Gold’s Grasberg mine in Papua,
Indonesia, will reach its open-pit limits and head underground in 2016. Similarly, Codelco’s Chuquicamata mine,
one of the largest open-pit copper mines in Chile will do the same in 2018.
While this natural order of progression is nothing new to metal miners, the size and scope of what is being planned
today is breaking new ground. South Africa’s Palabora Mining was probably the most recent large copper miner to
transition from open-pit to block cave. It was and remains a learning experience for the mine engineers and today
they are quite proud of what they have achieved: a block cave operation that produces at an average rate of 30,000
metric tons per day (mt/d). Freeport and Codelco are considering 160,000 mt/d and 140,000 mt/d respectively.
What further complicates the situation is that Grasberg and Chuqui are located in remote regions with limited access
to resources. The existing workforce will have to be retrained to bring these operations online quickly. It also means
that the engineers will have to get it right the first time. The advantage they have is that both Freeport and Codelco
have experience with block cave mining.
While six to eight years seems like a long time, replenishing these large sources for copper ore has serious
implications for the parent companies and world markets. Codelco is in the midst of preparing a feasibility study of
the engineering design work to properly plan the conversion process. Freeport’s Grasberg block cave development is
underway and detailed design work is ongoing. They will rely on this advanced level of mining engineering to
successfully launch the new underground era for copper mining worldwide.
Palabora Mining Set the Precedent During the early 1990s, Palabora Mining embarked on a similar series of feasibility studies to convert its open-pit
copper mine in the Limpopo Province to an underground mine. In 1996, it announced it would proceed with the
development of an underground block cave mine with a production rate of 30,000 mt/d.
Palabora Mining’s engineering design work set a precedent for converting from open-pit to underground design; no
other block cave mine has been put into as competent an orebody, according to the mine owners. The block height
of the cave is also testing previous limits at 450 m in the center increasing up to 700 m on the periphery.
The construction and development of the underground mine was completed in October 2004, but the Palabora
Mining underground project could not be considered a success until it finally averaged 30,000 mt/d for a month.
This occurred for the first time in May 2005, giving Palabora’s block cave one of the fastest ramp-ups to full
production in history.
The production footprint measures 650-m long and 200-m wide and consists of 20 production cross-cuts and 320
drawpoints. With the orebody’s coarse fragmentation, a high degree of secondary breaking activities is required to
free hang-ups and reduce oversize chunks to keep ore flowing through the drawpoints.
The mine’s fleet of LHDs tip 3,000 buckets per day into four jaw crushers on the northern side of the mine. Ore is
reduced to less than 220 mm and fed onto a high capacity conveyor system up to the shaft complex for hoisting to
surface.
During 2009, the mine averaged more than 31,600 mt/d. More than 11.5 million mt were hoisted last year, a slight
decrease over 2008 tonnages. The decrease was due to a failure on a winder drum. The ore grade averaged 0.67%
copper.
Today, the performance from the cave continues to improve. Increased mobile equipment availability and a general
awareness on the possible impact of the open-pit waste have compelled the underground team to focus closely on
proper draw control principles. Other improvements include the use of two LHDs in one crosscut and a continued
use of oversize reduction philosophy where a rock breaker and a loader operate in the same production crosscut
simultaneously to improve productivity.
Figure 1—Chuquicamata Underground will begin block cave mining below the pit in 2018. Chuquicamata Subterránea After more than 100 years of production, Codelco’s Chuquicamata, one of the greatest open-pit copper mines, which
is located in northern Chile, will deplete its surface minable reserves and move to underground production by 2018.
This is a significant milestone for one of the world’s largest copper producers. Yielding 450,000 mt of copper in
concentrate annually, Chuqui represents more than one-fourth of Codelco’s total copper production. From that
perspective, it’s easy to understand why Codelco has been working diligently to make the transformation to the next
phase, Chuquicamata Subterránea (underground) as smooth as possible. After nine years of preliminary work,
Codelco has reached the fourth stage of a six-stage (17-year) timeline to bring this mine into production in 2018 and
to go on to achieve full production of 140,000 mt/d by 2025.
The Chuqui Underground project (Chuqui UG) will offer Codelco at least 50 years of copper production. More than
1.7 billion mt of reserves with an average grade of 0.7% copper will be extracted from the underground mine.
Copper production in concentrate is expected to total 320,000 mt/y. To mine the ore, Codelco will retrain the Chuqui
workforce to transition from open-pit mining to underground mining. Around $2 billion will be invested in the
project to mine the first ore.
Codelco has decided to pursue a block cave approach. Among other objectives, Codelco also expects Chuquicamata
underground production costs to come in between the lowest and second-lowest quartiles among world copper
producers.
“We are now starting the basic engineering stage,” said Sergio Olavarria, engineering director, Chuquicmata
Subterránea mine project, Codelco. “We plan to have the infrastructure design work completed by the end of the
year. In 2011, construction will begin on what will be one of the largest, safest and most efficient underground
mines in the world.”
At 140,000 mt/d, the annual extraction rate will be 65 million mt. Chuqui UG will require two shafts between 11-
and 12-m in diameter for development extraction and ventilation. The orebody will be mined in four 215-m lifts
during a 42-year mine life. The first lift, Level 1, will begin at an elevation of 1,840 m. The cave will consist of
production blocks as large as 36,000 m2. Four years before the first level is depleted, they will begin to prepare the
next level. Final production is in approximately 2060. At that point the mine will reach a total depth of nearly 790
m.
During the caving process, they plan to pre-condition the current area of mining using a hydro-fracturing technique.
“We will break the rock mass before the caving process begins,” Olavarria said. “We will use water for hydro
fracturing and other holes for explosives. We think this approach will work well for the geology, which is similar to
that of Palabora.” In addition to guiding the cave and managing dilution, Olavarria explained, it might also reduce
the potential for air blasts.
The mine would use 30 6.9-m3 LHDs to move ore from as many as 12 production crosscuts to an orepass feeding a
crusher installation. The engineers are not committing to remote operation yet. They are looking at their experience
at El Teniente, before they commit to any type of automation. Crushed ore would travel by belt haulage to an
underground storage silo, which meters ore onto a main conveyor belt. The ramp for the main belt is 7-km long,
which conveys ore to the surface. “The current plan for the main belt is three flights with two transfer stations, but
we are also studying the possibility of using one transfer stage,” Olavarria said. “Because the conveyor would move
material more than 1,000 m vertically up a 15% slope, it would consume 60 megawatts— making it one of the
highest powerconsuming conveyors.”
Chuqui UG will employ 3,000 to 3,500 miners. The training approach for miners will consist of 80% field training
and 20% classroom. Codelco expects the entire training process for both new workers and converting existing
workers from the openpit to take about three years to complete.
Block Caving at Freeport Indonesia When the Grasberg open-pit mine reaches final production, Freeport Indonesia plans to have the skill and
infrastructure in place to launch the Grasberg block cave mine and ramp production up to 160,000 mt/d. The mine is
under development and scheduled for production in 2016.
Underground mining is nothing new to Freeport Indonesia. For more than 30 years, it has mined ore from the East
Ertsberg Skarn System (EESS) by block caving methods through a systematic set of lifts. The total remaining EESS
reserves are more than 775 million mt, which will yield 11 billion lb of payable copper and 13 million oz of payable
gold.
The Gunung Bijih Timor (GBT) mines first worked the deposit from 1980-1994 and during that period the mines,
which were initially designed for 5,000 mt/d, peaked at 30,000 mt/d. From1994- 2003, the Intermediate Ore Zone
(IOZ) mine worked the next lift and similarly its design capacity of 10,000 mt/d exceeded initial plan and peaked at
19,000 mt/d. The IOZ mine encountered and had to learn how to cope with wet muck, a combination of water and
fines that resulted in occasional large flows of mud in the production areas. Wet muck is a safety hazard, is difficult
to handle and results in less productive mining. To overcome this challenge, the IOZ mine introduced teleremote
mining with LHDs.
Today, the Deep Ore Zone (DOZ) mine works the current lift. Considered one of the largest caving mines in the
world, it was originally designed at 25,000 mt/d. As additional ore was discovered at the DOZ the planned
production rate underwent a series of expansions from 25,000 mt/d to a final sustained production of 80,000 mt/d,
which was achieved in February 2010. Freeport plans to sustain a production level of more than 80,000 mt/d through
at least 2015. The DOZ mine has already produced 112 million mt since it opened in 2003 and it will produce an
additional 282 million mt through 2020.
The DOZ mine, currently working at the 3,125 m level, inherited the wet muck conditions from the IOZ mine. In
fact, of the 490 active drawpoints, 20% are classified as wet. The DOZ mine has also improved underground
construction standards. One initiative in the DOZ is the use of an engineered, boltable linter set in the drawpoints,
which requires less concrete.
Figure 2—The GBC mine would share common infrastructure with the DMLZ mine, namely the adits and
the conveyor network. Mining the DMLZ Ore Body The DMLZ will be the deepest and highest stress block cave mine in the Ertsberg District to date. The reserve is
located below the DOZ mine, between the 3,125- and 2,590-m elevations. Development operations commenced in
November 2008, with the start of a rail spur leading from the AB Adits, and in January 2009 with a conveyor and
service decline access (Figure 2).
Production plans revolve around a block cave mining approach, similar in many respects to current operations at the
DOZ mine.
A departure from the DOZ operation is the main inclined conveyors (~15%) planned to transport production ore up
to the mill area. The DOZ mine, being located at the mill elevation, required relatively short, flat conveyors to
transfer ore from the crushers to surface stockpiles. The DMLZ will use twin gyratory crushers fed by trucks
operating above on the haulage level. Ore will be transported to the surface over a series of 1,829-mm conveyor
belts totaling approximately 4 km in length. This conveyor system raises the ore 550 m vertically from the crusher
discharge up to an existing conveyor near the surface.
The DMLZ ore body measures roughly 1,300-m long (oriented southeast to northwest) and is between 350- and
500-m wide. There are 43 production panel drifts planned. Panel length between the first and last drawpoints varies
from 72 m at the southeast end of the level to 474 m, with an average of 372 m.
Orepasses are installed along the panel drifts at a maximum spacing of 170 m. Aside from the 12 panels short
enough to require only a single orepass and the eastern two panels that share an orepass, the remaining 30 panels
require two orepasses, for a total of 72 orepasses in the current design.
The DMLZ ore body will be mined using an advance undercut method similar to the DOZ mine. Drawbells are
drilled and blasted from the drawpoint drifts into caved material previously blasted above on the undercut level.
Drawbells are blasted in one shot using programmable detonators. The undercut blast forms the major pillar apex;
the drawbell blast forms the minor pillar apex (Figure 3).
Figure 3—Undercutting and drawbelling methods at the proposed DMLZ mine. Undercutting will lead drawbelling by a minimum of 15 m horizontally. It will typically advance beyond this
minimum point, but as a general rule should not lead drawbelling by more than three months. Exceeding this
maximum, according to Freeport Indonesia, creates an elevated risk of blasted undercut material re-compacting and
taking weight.
Caving operations will commence in the higher-grade east section of the mineable footprint, moving in a series of
three blocks to the west. Draw columns along the north side of the mine tend to be shorter in height, averaging
approximately 245-m height of draw (HoD). The majority of the production activity will occur in the southern half
of the mine where HoDs reach 526 m.
Manpower for the DMLZ is forecast to peak at 2,550 during the 2009–2021 preproduction and production ramp-up
years, with a range of 1,950 to 2,400 for the full production period. The first drawbell ton is schedule for January
2015 with peak production achieved during 2020.
The Grasberg Transition Freeport Indonesia is using what it has learned from planning and operating the DOZ and planning the DMLZ to
design and build the Grasberg block cave (GBC) mine that is planned to produce 160,000 mt/d. The GBC mine has
reserves of 1 billion mt with an average grade of 1.03% copper and 0.81 g/mt gold. At a cutoff grade of 0.60%
copper equivalent, the deposit would yield 23 billion lb of copper and 26 million oz of gold.
The GBC mine design comprises a total of 2,400 drawpoints covering an area of 700,000 m2. The drawbells will be
30- x 20-m.
The mine will use an extensive rail haulage network with 40-mt electric trolley locomotives to haul ore. Five to six
trains will have 20 to 24 20-m3-cars. The trains will haul ore to three pockets feeding individual gyratory crushing
stations. Inclined conveyors will transport ore to the surface.
Figure 4—A shift to underground block cave production will help the company maintain 240,000 mt/d. Similar to the DOZ mine, caving would consist of an advanced undercutting system. The average column height
would be greater than 450 m. Caving would be initiated in 2016. The maximum drawbell opening rate would be
eight drawbells per month.
Workers will pass through a security checkpoint at the Ridge Camp rail yard, the area just outside the AB Adits. The
area would also have a materials handling facility, waste muck handling facility, rolling stock maintenance depot, a
mine rescue station and concrete batch plants.
Currently, mine engineers are developing geotechnical and drifting designs. The underground batch plant will be
designed, procured and constructed during 2010 and 2011. Basic engineering for the ore flow system will be
completed along with the underground electrical distribution system design. Detailed design engineering for the
service shaft is also in progress.
The GBC mine plans to initiate service shaft excavation by early 2011. The mine also plans to complete an inter-
level ramp and the first portion of the mine ventilation system in 2010.
During 2011 and 2012, the GBC AB terminal will be constructed with the rail installed to it, along with underground
support infrastructure. By 2012, rail installation should be completed with train service to the GBC mine from
surface. The mine will also commission the service shaft in 2013 and begin development on the undercut, extraction
and rail haulage levels.
The crushing plant will be operational by 2014, along with the initial feed conveyor and main conveying system.
The rail haulage system and main shop come online in 2015. By the end of 2015, the required development on the
extraction and undercut levels will be completed to initiate caving.
Caving will begin in 2016 and the GBC mine will reach full production in 2022. The GBC mine will be the flagship
for the district during the new “underground era.” What the company is learning in the DOZ today at 80,000 mt/d is
critical to achieving the goals for tomorrow’s GBC mine.
References 1. Casten, T., Brannon, C., and Thomas, L., “A Review of the Caving Mines at PT Freeport Indonesia’s East
Ertsberg Skarn System,” SME Annual Meeting, Feb. 28- March 3, 2010, Phoenix, Arizona, USA.
2. Duckworth, I., Casten T., and Rakidjan, “An Overview of the Proposed DMLZ Mine,” SME Annual Meeting, Feb.
28- March 3, 2010, Phoenix, Arizona, USA.
3. Brannon, C., Vergara, P., and Baker, R., “Grasberg Block Cave Mine: Design Considerations to Achieve
160,000 tpb,” SME Annual Meeting, Feb. 28-March 3, 2010, Phoenix, Arizona, USA.
Petra Diamonds Plc 11 Apr 11
Finsch opens the road to producing 3m carats pa
Petra Diamonds Plc has acquired, from De Beers the Finsch Mine in South Africa. The Finsch
mine is the second biggest producing diamond mine in South Africa. The acquisition more than
doubles annual carat production, while adding to the in-ground resource. The acquisition is a
major step toward achieving the target of producing five million carats per annum. The following
figure shows the location of the Finsch mine, together with Petra’s other South African assets.
The acquisition price was R1,425 million (approximately £131 million). The Finsch mine is
considered to be one of the world’s major diamond mines, producing around two million carats
of diamonds per annum. Petra will hold a 74% interest in the mine with the remaining 26% held
by the Black Economic Empowerment (BEE) partners Sedibeng Mining, Namoise Mining and
the Petra Employee Share Trust. Petra will free carry the 26% held by the BEE partners.
The purchase price was paid in cash, with Petra successfully placing 136.7 million shares at 150
pence per share, raising £205 million. The majority of the raising was used to fund the Finsch
purchase of approximately £131 million, with £24.6 million paid to the South African
Department of Mineral Resources for the environmental guarantee and for working capital
requirements at Finsch.
A further £35 million raised was used for internal working capital requirements, accelerate
certain capital expenditure programmes and settle some or all of the deferred Cullinan
consideration owing to Al Rajhi.
The Finsch purchase is subject to conditions including certain South African Government
approvals, approval by the current BEE partners in the Finsch mine, Board approvals by the
current owners and various other approvals and waivers from involved parties. The conditions
appear to be similar to those regularly attaching to the sale of a major mining asset.
Concerning the conditions, we hold an opinion that Petra would not have entered into the
transaction, should it believe these conditions were We cannot not comment
The acquisition includes a major resource of 48.1 million carats, including 26.6 million carats in
reserves and 4.7 million carats as tailings. The mine site is state-of-the-art with a shaft capacity
of 4.6 million tonnes and a plant capacity of 7.2 million tonnes. On site is an 800 plus housing
unit estate in a well established town environment.
The Finsch mine is an underground operation currently producing around two million carats of
diamonds from a deep pipe. The following figure shows a schematic of the Finsch mine’s
diamond pipe.
Over the past four years the pipe has produced a number of large special diamonds with an
average of 27 stones over 50 carats recovered per annum. Some of the better quality diamonds
recovered include a 204.7 carat diamond (in 2003), 109.9 carat (2007) and 101.7 carat diamond
(2010). The recovery of a significant number of large high quality diamonds can
substantially increase the total value of production in any one year.
The mine operates on a block cave mining format. Operating in a block cave format delivers
high volume and low costs. The following figure shows the concept of a block cave underground
mining operation.
The Finsch mine’s unit cash cost per tonne is R15, which compares very favourably with the
R30 for the company’s Cullinan mine which operates in the same block cave format. The
company will benefit from acquiring Finsch as it will be able to bench mark Cullinan and
also the Kimberley underground (block and cave mining format) which is yet to become a
producer.
Diamond production for Finsch is forecast to grow over the course of the next five years. The
following table shows the forecast production of carats carat. The production references refer to
the blocks in the figure Finsch – Underground schematic appearing earlier in this review.
With the acquisition of Finsch, diamond production for 2011 will approach two million carats.
While for 2012, including a full year of production from Finsch will surpass three million carats.
Petra holds a right to mine on site at Finsch until 2038. The following figure shows forecast
diamond production and revenue out to 2019.
We hold the opinion that the acquisition of the Finsch mine will be both earnings and
cashflow accretive and value adding going forward. The opportunity to lift diamond
production to the five million carats by 2019 appears to be readily achievable from the
company’s now expanded production base. The acquisition lifts the total diamond resource of the
company to 309 million carats.
We consider management does have a very good track record in acquiring diamond operations
having successfully acquired Koffiefontein (in 2007), Cullinan (2008), Williamson (2008) and
the Kimberley underground (2010).
After finding solid support at the 142p support region, Petra Diamonds managed to surge higher.
The recent break above the 50 day moving average indicates short term momentum to favour the
upside. We would expect a retest of the January high of 189p in the near term.
The weekly chart signifies an important breakout from the 2007 highs of 167p. This is suggestive
that the broader term uptrend to remain intact. Once the 189 resistance level is cleared, we would
expect a new leg higher to unfold.
We consider the opportunities available to the company to grow diamond production
organically are further enhanced with the Finsch purchase. We consider this aspect of
Petra’s operation is the key to delivering future shareholder value.
Petra is a superior exposure to diamonds and the company will be firmly held within the
Portfolio.
Interstate Technical Group on Abandoned Underground Mines
Fourth Biennial Abandoned Underground Mine Workshop
Figures: Underground Mining and Its Surface Effects
Paper
Figure 1. Schematic developments of mine effects.
Figure 2. Longwall coal face ripper. The overlying strata are of varying thickness and rock types
(photo courtesy of David Young).
Figure 3. Folded coal and other sedimentary strata, Smokey River Coal Mine, Alberta (photo
courtesy of Dave Young).
Figure 4. Longwall mining method and ground reaction [Brady and Brown, 1985].
Figure 5. Rock mass behavior above and behind longwall mining face support [Whittaker and
Reddish, 1989].
Figure 6. Drawing shows bending and breaking of strata above a mined longwall panel.
[Kolebaevna, 1968] in Peng (1992).
Figure 7. Longwall mining subsidence effect.
Figure 8. Generic ground and rock mass movements associated with longwall mining [Whittaker
and Reddish, 1989].
Figure 9. Subsidence from longwall mining in terms of width and depth of working [Orchard,
1956-57], in Whittaker and Reddish (1989).
Figure 10. Surface subsidence profiles for dipping seams [Whittaker and Reddish, 1989].
Figure 11. Location of arching over longwall mining [Whittaker and Reddish, 1989].
Figure 12. Subcritical, critical and supercritical subsidence surface effects [Whittaker and
Reddish, 1989].
Figure 13. Subsidence surface profile with multiple seam situation [Whittaker and Reddish,
1989].
Figure 14. Subsidence factor versus mining depth in the Appalachian coalfield [Peng, 1992].
Figure 15. Mathematical form of longwall mining subsidence profile [Brady and Brown, 1985].