Maintaining Efficiency using Your Building Controls and ...€¦ · Maintaining Efficiency using...
Transcript of Maintaining Efficiency using Your Building Controls and ...€¦ · Maintaining Efficiency using...
Rhode Island Convention Center • Providence, Rhode Island
Maintaining Efficiency using Your Building Controls and Automation
Session: Building Controls and Automation
Carl E. Lundstrom, PE, CCP Dewberry Design Builders Inc.
August 10, 2016
Energy Exchange: Federal Sustainability for the Next Decade
Summary
Using your building control and automation systems for:
• Managing your energy use
• Using your controls system to commission
• Operating your controls systems for persistence
2
Energy Exchange: Federal Sustainability for the Next Decade
Terminology – Per DoD Lingo
• UMCS = Utility Monitoring and Control System
– aka: BAS, EMCS, UCS, FMS, EMACS, EMUCS, etc.
• FCS = Field Control System
– BCS = Building Control System
– UCS = Utility Control System
• FPOC = Field Point of Connection
• Facility-Related Control System
– DoD “facilities” are more than just buildings
• M&C = Monitoring and Control (Front End stuff)
Energy Exchange: Federal Sustainability for the Next Decade
2 Types of FCS – Per DoD Lingo
• Building Control System (BCS) – Controls for building electrical and mechanical
systems, typically HVAC and lighting – Generally uses Direct Digital Control (DDC) Hardware – Generally does NOT include its own local front end
• Utility Control System (UCS) – For utility systems such as an electrical substation,
sanitary sewer lift station, water pump station, etc. – A UCS may include its own local front-end
• A single building may have both a BCS and UCS – May even share components between them – such as
the FPOC
Energy Exchange: Federal Sustainability for the Next Decade
DoD Requirements for a Complete, Working UMCS
• Control Functionality to Control Mechanical Equipment – Sequences in UFGS 23 09 93
– Instrumentation and control devices in UFGS 23 09 13
– Controllers for sequences, supervisory control, interface to front end in UFGS 23 09 23.01 (LonWorks) or UFGS 23 09 23.02 (BACnet)
– Other (submittals, PVT, training, etc.) in UFGS 23 09 00
• User Interface – Primary front end in UFGS 25 10 10
– Local Display Panels in buildings in UFGS 23 09 23.XX
Energy Exchange: Federal Sustainability for the Next Decade
Building control and automation systems are fundamental for a strong energy management program at a building, site or agency.
• Day-to-day controls operation
• Meter data management
• Support commissioning to maintain highly efficient buildings
6
Energy Managers & Building Automation Systems
Rhode Island Convention Center • Providence, Rhode Island
Managing Your Energy
Energy Exchange: Federal Sustainability for the Next Decade
Building automation systems can support facility energy management from meter data.
A successful metering program will incorporate:
– Appropriate and accurate data in a timely manner
– Provide analysis of meter information
– Data and analysis provided to user in a format that leads to action
– Operate continuously on a daily, weekly, monthly, and annual basis
8
Meter data management
Energy Exchange: Federal Sustainability for the Next Decade
Successful program - start with a metering plan – Program objectives – what are the goals, objectives, and risk
– Identify current and future metering needs for all energy and water utilities
– Recovery procedures when meter stops, deemed out of calibration, data lost, or considered questionable
– Obtain and maintain management and stakeholder support
– Identify key program milestones and assign roles and responsibilities
– Detail the training and retraining requirements for meter and data analysis
– On-going metering program monitoring
9
Meter data management
Energy Exchange: Federal Sustainability for the Next Decade
Overall metering objectives: – Ultimate goal – reduce utility use and costs
– Bill allocation throughout the entire facility
– Manage utility loads to minimize costs
• Example, electrical - time-based rates
– Identify system-specific operational efficiency opportunities
– Identify equipment malfunction or impending malfunction in critical use facilities – such as hospitals
– Retro-commissioning (RCx) & on-going commissioning (OCx)
– Special metering consideration
• Data centers
• On-site generation
10
Metering Objectives
Energy Exchange: Federal Sustainability for the Next Decade
• Meter programs are not “set-them and forget-them”
• Staffing resources needed to operate the metering system, when in place, are critical to a successful program
• Cybersecurity requirements – IT staff participate early in development of system
• RMF: Risk Management Framework: An approach to Cybersecurity to reduce risk while taking into account cost vs benefit (NIST SP 800-37)
11
Meter data management
Energy Exchange: Federal Sustainability for the Next Decade
Metering Hierarchy - Maximize your metering value – minimize your metering costs
• Starts at Whole Building Meter
– Diagnostic in identifying trends and variances
• Next finer level – Electrical Panel/Sub-Panel or mechanical system
– Lighting, plug, or motor loads
• Moving down – Circuit-level monitoring
– Specific load of interest
• Final level – End-use equipment (chiller, boiler, motor)
12
Meter data management
Energy Exchange: Federal Sustainability for the Next Decade 13
Meter Location Selection
Whole Building Meter
Circuit Level Meter
Panel Level Meters
End-use Level Meters
Energy Exchange: Federal Sustainability for the Next Decade 14
Water, Air, Gas, Electric, Steam Meters
• Electric
– Energy management
– Power Quality
• Gas
• Water
• Air
• Steam
Metering program Water, Air, Gas, Electric, Steam (WAGES)
Energy Exchange: Federal Sustainability for the Next Decade 15
Energy Information Systems
• First element for consideration – output information
• Volume of data and time to process
• Graphical output
– Daily Profile
– Day overlay
– Calendar/Month of consumption
Analytical Outputs
• Benchmarking
• Aggregation
• Data mining (data slice/drill down)
• Normalization
– Building area
– Number of occupants
– Cooling or heating degree days
Energy Exchange: Federal Sustainability for the Next Decade 16
Energy Information Systems
• Reimbursable billing
• Validation/Planning – shadow meter
• Efficiency Opportunity Identification
• On-going commissioning
• Power Quality Application
• Measurement and Verification
• Benchmarking
• Active alarm notification
• Utilities Interaction
– Demand limiting
– Time of use pricing
– Real time pricing
– Load aggregation
– Power factor
– Demand response
Energy Exchange: Federal Sustainability for the Next Decade 17
Meter Profiling
High demand
Demand response Extended usage on weekends
Rhode Island Convention Center • Providence, Rhode Island
Using Your Controls System to Commission
Energy Exchange: Federal Sustainability for the Next Decade
• New building commissioning
• Existing building commissioning
– Re-commissioning
– Retro-commissioning
19
Controls & Commissioning
Energy Exchange: Federal Sustainability for the Next Decade
Commissioning of building controls for a new building project is probably the most fundamental systems every project should include: Owner Project Requirements Design review of controls Submittal review of controls Is the instrumentation correctly
mounted, tested, calibrated, and operational
Safety interlocks Integration of data transfer Functional testing of complex
control sequences Incorporate data trending and
analytics to support commissioning and future operations
20
New Building Commissioning
Energy Exchange: Federal Sustainability for the Next Decade
Commissioning supports final close-out with
Training
O&M Documentation
As-builts
Systems Manual
GIS & BIM
DoD – get final “Point Schedule”
21
New Building Commissioning
Energy Exchange: Federal Sustainability for the Next Decade
Existing building commissioning of controls can provide significant savings for an energy management program. Any building system will degrade and need attention to maintain their low energy utilization. Incorporate re-commissioning or retro-commissioning into site or agency energy plans
22
Existing Building Commissioning
Energy Exchange: Federal Sustainability for the Next Decade 23
Existing Building Commissioning
Source: http://www.calmac.org/publications/SCE_RCx_Pre-Calc_Report-03-31-10.pdf
Energy Exchange: Federal Sustainability for the Next Decade
Existing Building Cx Phases
Planning Phase Establish Goals, Owner Needs &
EBCx Plan
Investigation
Phase
Implementation
Phase
Turnover
Phase
Persistence
Phase
Evaluate Current System Performance with Owner
Needs & Identify Improvements
Establish Smooth Transition and Hand Over to O&M
Staff
Implement Recommended Improvements and Verify
Performance
Ensure Continuous System Performance
Improvement
-As defined by BCA “Best Practices”
Energy Exchange: Federal Sustainability for the Next Decade 25
Wall of shame
“Economizer” “Secured” damper
Rhode Island Convention Center • Providence, Rhode Island
Operating your control systems for persistence
Energy Exchange: Federal Sustainability for the Next Decade 27
Maintaining Building Performance
Energy Exchange: Federal Sustainability for the Next Decade
Energy managers should strongly considering adding on-going commissioning with their building control systems to maintain (and improve) their building performance.
28
Persistence
Stage 1
Building data
Stage 2
Analyze and notify
Stage 3
O&M Action
Energy Exchange: Federal Sustainability for the Next Decade 29
Stage 1 - Transfer of Building Data
$
• Web Services
• Open Protocols
• RDBMS
• Automated Export
$$
• Proprietary Drivers
• Integration – Existing Hardware
$$$
• Full Integration, New Hardware
Energy Exchange: Federal Sustainability for the Next Decade 30
Stage 2 - Analyze and Notify
Analytics: Tests for Conditions Engineer Review
&
Energy Exchange: Federal Sustainability for the Next Decade
• Prioritization of projects
• O&M Actions
• Verification
• Ongoing Diagnostics
31
Stage 3 - O&M Action
Energy Exchange: Federal Sustainability for the Next Decade
• Building control and automation systems are fundamental for a strong energy management program at a building, site or agency.
• Building automation systems can support facility energy management from meter data.
• Anticipate requirements for cyber-security and IT support requirements early in the project
• Energy managers should incorporate automation systems into an on-going commissioning program to have good persistence of their facility energy usage.
32
Summary
Energy Exchange: Federal Sustainability for the Next Decade
Risk Management Framework - Cybersecurity
• NIST SP 800-37: Guide for Applying the Risk Management Framework to Federal Information Systems
• NIST SP 800-39: Managing Information System Risk • NIST SP 800-53: Security and Privacy Controls for Federal
Information Systems and Organizations • NIST SP 800-82: Guide to Industrial Control Systems (ICS) Security • DoD Instruction 8510.01: Risk Management Framework (RMF) for
DoD Information Technology (IT) • Committee on National Security Systems Instruction (CNSSI) 1253:
Security Categorization and Control Selection for National Security Systems
• https://rmfks.osd.mil • UFC 4-010-06: Cybersecurity of Facility-Related Control Systems • Upcoming UFGS for Cybersecurity for UMCS
Energy Exchange: Federal Sustainability for the Next Decade
DoD Spec/Criteria Overview
UFGS 25 10 10: Utility Monitoring & Control System (UMCS) Front End and Integration UFGS 23 09 00: Instrumentation and Control for HVAC UFGS 23 09 23.01: LonWorks DDC for HVAC & Other Local Controls UFGS 23 09 23.02: BACnet DDC for HVAC & Other Local Controls UFGS 23 09 13: Instrumentation and Control Devices for HVAC UFGS 23 09 93: Sequences of Operation for HVAC Control UFGS 25 08 10: UMCS Testing UFC 3-410-02: DDC for HVAC & Other Local Controls UFC 3-470-01: Utility Monitoring & Control System (UMCS) Front End and Integration UFC 4-010-06: Cybersecurity of Facility-Related Control Systems UFGS ?? ?? ??: Cybersecurity of Facility-Related Control Systems Specifications and Criteria in red font are draft, under development, or under revision
Energy Exchange: Federal Sustainability for the Next Decade 35
Building Controls and Automation
Carl E. Lundstrom, PE, CCP Associate Vice President Dewberry 2836 Brandywine Road, Suite 100 Atlanta, GA 30341-4015 770.329.3625 [email protected] www.dewberry.com