Main Office: 256 Khaled Ibn El waleed St.marmistastones.com/files/MARMOTEC.pdf · Main Office: 256...
Transcript of Main Office: 256 Khaled Ibn El waleed St.marmistastones.com/files/MARMOTEC.pdf · Main Office: 256...
Main Office: 256 Khaled Ibn El waleed St.
South of Police Academy, 5th District,
New Cairo,
Egypt.
Tel.: +20 2 386 42 333 - 444
Fax: +20 2 386 42 244
Factory: 6th of October City, CPC
Industrial Park, Sector 111-135
Email: [email protected]
Website: www.marmotec.com.eg
CONTENTS
CONTENTS 1. ABOUT MARMOTEC 1.1 INTRODUCTION 1.2 FINANCIAL CAPACITY 1.3 PRODUCTION CAPACITY AND MACHINES LIST 2. ORGANIZATION 2.1 TECHNICAL CAPACITY 2.1 ORGANIZATION STRUCTURE 3. METHOD OF CONSTRUCTION 3.1 SCOPE 3.2 PURPOSE 3.3 REFERENCES 3.4 MATERIAL 3.5 EQUIPMENT & TOOLS 3.6 PROCEDURES 4. MAJOR PROJECTS LIST
5. ABOUT DETAC (MOTHER COMPANY)
1.1. INTRODUCTION We have the honor of presenting our pre-qualification documents accompanied with some necessary information you may require regarding our Organization. MARMOTEC is a subsidiary company of DETAC Construction Group, which is offers a full service in stone business, providing blocks, slabs, tiles cut -to- size tiles and stones, mosaic and lavatory tops in a high production capacity. MARMOTEC is producing a wide range of stone finishes, polished, honed, unpolished chamfered, believed, antique, rock face tumbled, bush hammered, chiseled, acid and more. MARMOTEC is providing a contractual service for all types of construction; residential building, industrial, hotels, villas, and office buildings. MARMOTEC is keen to have the latest stone cutting, shaping and finishing technologies in its factory. A complete line of automated processing equipment allows us to provide a large volume of slabs, other building products in a short period of time. Our Staff prides themselves on professionalism and expertise in every aspects of, our business, including project design, material specifications, material sourcing, methods of installation, transportation and delivery, and relationship building with our customers and clients. Our factory 15,000 square meters + Storage area of 20,000 square meters, equipped with the latest machinery as block cutters, cutting surfaces finishes, surface treatment, filling, mosaic production line,…….etc.,
ABOUT MARMOTEC
ABOUT MARMOTEC
Item Machine Material Production (M²/day)
1 Gantry crane 35 ton Marble/granite
2 Over head crane 10 ton Marble/granite
3 Over head crane 10 ton Marble/granite
4 Over head crane 10 ton Marble/granite
5 Monofilo(Wire machine) Marble/granite 60
6 Gang saw 80 blade Marble 500
7 Gang saw 80 blade Marble 500
8 Resin line Marble/granite 300
9 Slab Polishing machine 16heads Marble 1000
10 Bridge cut Marble/granite 500
11 Bridge cut Marble/granite 500
12 Bridge cut Marble/granite 500
13 Bridge cut Marble/granite 500
14 Bridge cut Marble/granite 500
15 Block cutter 2200 Marble/granite 150
16 Block cutter 2200 Marble/granite 150
17 Block cutter 2800 Marble/granite 150
18 Block cutter 2800 Marble/granite 150
19 Strip Polishing machine 12heads Granite 600
20 Cross cutting line 11discs Marble/granite 600
21 Water Jet Marble/granite Artistic work
22 Water recycle plant 4000lit/min
1.3. PRODUCTION CAPACITY MARMOTEC factory has a new machines set-up 2013 MACHINES LIST
ABOUT MARMOTEC
2. ORGANIZATION 2.1 TECHNICAL CAPACITIES & LIST OF PERSONEL
GENERAL MANAGER CIVIL ENGINEER PROJECTS MANAGER CIVIL ENGINEER TECHNICAL MANAGER ARCHITECT SITE ENGINEERS 8 Engineers with 5 – 15 years experience TECHNICAL OFFICE 6 Architects and Civil with 5 – 15 years experience MATERIAL ENGINEERS 3 Engineers DESIGN OFFICE 3 Architects SITE SUPERVISORS 12 – 15 Supervisors / Foremen working on different sites MARBLE & TILE FIXERS 95 UNSKILLED LABORERS 40
ABOUT MARMOTEC
GEN
ERA
L M
AN
AG
ER
TECHNICAL MANAGER
Technical Office Head
Technical office Engineers
Draft man
DC.
Q.S. Engineers
QS. Engineers
Design Office Design
Architects
Tender Dep. Head
Tender Engineers
Material Engineers
PROJECTS MANAGER
Project Managers
Project Coordinator
Document Controller
Site Engineers
Site Supervisors
Warehouse
Surveyor
Foreman
QC/QA MANAGER
Q.C. Engineers
Q.C. Inspector
Financial & Sales Manager
Accountants
Cost Controller
Procurement Manager
Procurement Coordinator
Purchasing Specialist
HSE Manager HSE Supervisor HSE Officer
2.2.ORGANIZATION STRUCTURE
METHOD STATEMENT
3. METHOD STATEMENT
3.1. Scope 3.1.1. The scope of this method statement covers the installation of external stone work for wall cladding, mechanical fixing. 3.1.2. MECHANICAL cladding applies for external headings and wall cladding. 3.1.3. Mechanical fixing requirements for external wall cladding will be determined as per the relevant approved shop drawings for each area or section. 3.1.4. Mechanical fixing system load design and analysis. 3.1.5. Flooring tiling and skirting. 3.1.6. Stairs cladding. 3.2. Purpose The purpose of this method statement is to describe all used materials, work procedures, and method of inspection to external stone work wall cladding required or instructed to be mechanically installed. 3.3. References 3.3.1. General specifications, as per the tender package. 3.3.2. IFC drawings. 3.3.3. Approved shop drawings for stone, fixing accessories and relation with other trades. 3.3.4. Coordination minutes of meetings with related treads. 3.4. Material 3.4.1. Marble as per the approved samples by the architect. 3.4.2. Mechanical fixing accessories galvanized steel Z or L – anchors, anchors bolts, pins and plastic tubes (Samples will be submitted later).
METHOD STATEMENT
3. METHOD STATEMENT (Cont’d)
3.5. Equipment & Tools The following equipment and tools shall be deployed in the installation: 3.5.1. Mobile water cutting machine for necessary field cutting or chamfering (as field cutting is only allowed for minor cases, where all edges should be clean and free of defections) 3.5.2. Electric grinders and drilling machines. 3.5.3. Measuring tape, laser meter, level, wires and strings. 3.5.4. Hammer, paddle, brush… (And other necessary hand tools). 3.6. Procedures 3.6.1. Material Submittal / Approval: 3.6.1.1. Submittal is prepared together with a sample board containing all the specified / proposed stone samples that will be used in the execution of works with suitable dimensions or as specified that can give a complete impression for the submitted material. 3.6.1.2. Structural Calculations for fixing accessories shall be prepared according to the panel sizes from the shop drawings draft copy, accordingly submittal is prepared together with a sample board containing all the samples that will be used in the execution of works with actual dimensions. 3.6.2. Shop drawings: 3.6.2.1. The shop drawings shall show the arrangement of fixing accessories (as per approved samples), the tile dimensions, thickness, selections (as per architect), and relationship with other material, details of anchorage, and other installation details. 3.6.2.2. The detail drawings shall show the joint pattern, width, all mechanical fixing accessories including full large scale detail, and grouting material if any. 3.6.2.3. After approval of shop drawings, and fixing accessories samples, cutting lists shall be prepared. The stone as well as the fixing accessories shall be fabricated, packed, and delivered to site in well-protected wooden crates/palettes.
METHOD STATEMENT
3. METHOD STATEMENT (Cont’d)
3.6.4. Site Preparations:
3.6.4.1. Inspected stone works to be stacked and stored safely close to work areas to avoid double handling. 3.6.4.2. Starting points, datum lines and settings to be established and verified by the installer in co-ordination with site surveyor, as per approved shop drawing. Surveyors to identify particularly FFL and site axis. (To be inspected via formal release)
3.6.4.3. All cuts/openings provisions for electro mechanical services will be identified prior to installation.(where a full coordination with all related tread teams is already done)
3.6.4.4. Approved shop drawings and detailed drawings to be available in site for use during installation, for each pertinent location.
3.6.4.5. Formal release, via inspections requests, of all other trades related to the installation works, such as electro-mechanical, plumbing and block works to be secured before starting activity.
3.6.4.6. Concrete walls should be free from any foreign materials (timber, tie wires …etc.). Hollow block walls shall be filled with material (as per architect’s selection) at location where the anchors of the approved section steel chaises will be fixed (if required) and to be firmly adjusted, verticality and locations as per approved shop drawings), to fix the stainless steel anchors on it.
METHOD STATEMENT
3. METHOD STATEMENT (Cont’d)
3.6.5. Execution: Sequence of installation is dependent on site conditions and the progress of other interrelated activities, such as landscaping or roof finishing, for sequence of installation; one of two approaches can be followed, as per site conditions as well as consultant`s recommendation: 3.6.5.1. Proposal-A : wall cladding – flooring – skirting: - These sequence, the wall cladding shall be completed, protected, floorings then
skirting to be installed. - Site surveyor in coordination with the installer shall mark the axes on walls and floors,
establish FFL and level of first row of wall cladding, as per approved shop drawings and method statement.
- First row of tiles will be fixed, using mechanical accessories with one-way-welded pins,
as per approved samples. - Each tile shall be drilled at the upper and lower sides (for supporting anchors in
horizontal joint case. Left and right sides in case of supporting anchor in vertical joint, as per shop drawings) to allow for pins to be inserted. The second row of slabs is supported by 4 anchors: 2 at the lower side for load bearing support, and 2 at the upper side for restraining only.
- The upper part of the pin is fixed by mastic (Polyester mastic as per the architect
approval) while the lower part is inserted in a plastic tube as per approved samples, to secure the compensation of any movement of the building. The above system implies that each tile is individually supported by anchors and the first row of tiles does not carry the load of other rows.
- Once first and second rows are fixed and inspected for alignment and verticality, then,
sand/cement slurry will be poured very carefully to avoid any staining to marble, if necessary.
- Joints will be adjusted by plastic spacers for internal and external cladding and to be temporarily plugged with filler material (in case of back filling for specific height, as per specs) to avoid any spillage between tiles, where joints should be fully consistent.
METHOD STATEMENT
3. METHOD STATEMENT (Cont’d)
3.6.5. Execution (Cont’d) 3.6.5.1. Proposal-A : wall cladding – flooring – skirting (Cont’d) - After setting of slurry backing, temporary filler will be removed and slabs cleaned with
a clean, wet and soft cloth. The slurry backing is made from (4S:1C) with a height of 70 cm from FFL.
- The joints are to be filled with grouting materials on backer rod, (as per approved
material by architect) if any. - Once marble flooring, as per relevant method statement for flooring, is completed and
properly protected plaster shall be made then skirting shall be inserted between wall and floor, and fixed to the concrete backing using mortar applied on the concrete to cover the area of one entire piece of skirting with a trowel and skirting to be firmly fixed.
- Alignment should be checked while works are proceeding. Tolerance shall not exceed
the limits accepted by specifications. - On completion of work, all stone works is to be thoroughly cleaned, as areas should be
protected during construction. - Proper protection shall be applied to the finished product, depending on the traffic
conditions and neighboring activities for each area.
3.6.5.2. Proposal-B: flooring – skirting - wall cladding: - In this sequence, the flooring shall be completed and protected first, as per relevant
method of statement for flooring. Then, skirting shall be supported by the flooring and fixed to wall by mortar or slurry backing, as indicated above.
- The wall cladding shall follow the same sequence mentioned in proposal an above.
METHOD STATEMENT
3. METHOD STATEMENT (Cont’d)
3.6.6. Method of inspection: - The objective is to insure that the stone work is performed in accordance with the
requirements of the contract specifications and approved workshop drawings. - Initial material inspection shall be carried out at the factory prior to shipment to
check coding and marking system for tiles, to minimize the range of color variations to the accepted limit.
- Site inspection is performed by subcontractor’s QC engineer together with the
consultant`s engineer and the installer’s foreman, to check quality requirements. - The setting out of horizontal and vertical lines shall be controlled through the
reference points, axis and starting tiles by installers in coordination with the site surveyor. These criteria shall not exceed the tolerance described in the specifications.
- The safety regulations of the project shall be followed, especially for the scaffolding,
hand tools, heard hats, electricity, fire, accidents, behavior of labors, and so forth.
- Inspection Request form shall be submitted for approval for each area separately. 2.6.7. Plan of Safety: Follow all safety and security systems established by main contractor at the site.
OUR PROJECTS
COMPLETED PROJECTS - EGYPT
Item PROJECT SUPPLY / INSTALL AMOUNT (EGP) DATE CLINTE MAIN CONTRACTOR
1 NARJES VILLAS Supply & Install 43,000,000 2010
Wadi El Nil contracting & real state investment
Wadi El Nil contracting & real state investment
2 AHLI UNITED BANK Supply & Install 7,880,900 2010 Ahli United Bank DETAC
3 CHAMBER of COMMERCE - Office Building - New Cairo
Supply & Install 4,635,100 2010 Chamber of Commerce
DETAC
4 WADI ELNILE HOSPITAL Supply & Install 13,900,000 2010
Wadi El Nil contracting & real state investment
Wadi El Nil contracting & real state investment
5 GENERAL AUTHORITY FOR INVESTMENT BUILDING
Supply & Install 8,171,600 2011 General Authority for Invistment
DETAC
6 EASTERN COMPANY - Office Building - 6th October City
Supply & Install 7,300,000 2012 Eastern Company DETAC
7 RAYA PLAZA Supply & Install 4,500,000 2012 RAYA DETAC
8 DAMAC PARK AVENUE Supply & Install 3,000,000 2013 DAMAC DETAC
9 ALNAEEM OFFICE BUILDINGS Supply & Install 2,600,000 2013 ALNAEEM DETAC
10 MIRAJ MALL Supply & Install 1,606,169 2013 MIRAJ DETAC
11 GOLDEN COAST (Sharm Elshiekh) Supply & Install 1,472,900 2013 GOLDEN COAST DETAC
12 MIVIDA Supply & Install 1,850,000 2013 EMAAR DETAC
13 GEZA SYSTEM Supply & Install 2,250,000 2013 GEZA SYSTEM DETAC
14 Masjed Almoshier Tantawy - New Cairo
Supply & Install 1,500,000 2014 EGYPTIAN ARMY ARAB CONTRACTORS
15 UPTOWN CAIRO - Village G Supply & Install 2,200,000 2014 EMAAR ALLAM SONS
16 NEW CAIRO MALL Supply & Install 1,820,000 2014 Cairo Housing RWAD
17 SAKAN Residential Building Supply & Install 1,800,000 2014 Cairo Housing CAIRO HOUSING
18 UPTOWN CAIRO - Village K Supply & Install 680,000 2014 EMAAR ALLAM SONS
19 Miscellaneous Projects Supply & Install 46,000,000 PRIVATE VILLAS
PROJECTS IN PROGRESS - EGYPT
Item PROJECT SUPPLY / INSTALL AMOUNT
(EGP) DATE CLINTE MAIN CONTRACTOR
1 Cairo International Airport - Terminal 2 (Marmotec & HAZ Egypt JV)
Supply & Install 80,000,000 In Progress Cairo Airports LIMAK INSAT
2 ETISALAT MISR Headquarters at Smart Village (Marmotec & HAZ Egypt JV)
Supply & Install 12,000,000 In Progress ETISALAT MISR DETAC
3 Porto New Cairo Supply & Install 16,500,000 In Progress AMER GROUP DETAC
4 Headquarters of the Administrative Prosecution
Supply & Install 5,800,000 In Progress Administrative Prosecution
DETAC
5 Miscellaneous Projects Supply & Install 4,500,000 PRIVATE VILLAS
OUR PROJECTS
GIZA SYSTEM – OFFICE BUILDING
- INTERNAL FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - COUNTERS
OUR PROJECTS
AHLI UNITED BANK – NEW CAIRO
- INTERNAL FLOORING - INTERNAL WATER-JET FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - VANITY COUNTERTOPS
OUR PROJECTS
AHLI UNITED BANK – NEW CAIRO
- INTERNAL FLOORING - INTERNAL WATER-JET FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - VANITY COUNTERTOPS
OUR PROJECTS
AMWAL – OFFICE BUILDING
- INTERNAL FLOORING - INTERNAL WATER-JET FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - INTERNAL CLADDING (MECHANICAL FIXING)
OUR PROJECTS
EASTERN COMPANY – OFFICE BUILDING
- INTERNAL FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - VANITY COUNTERTOPS
OUR PROJECTS
ALFUTTAIM VILLAS
- INTERNAL FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - VANITY COUNTERTOPS & SHOWER TRAY
OUR PROJECTS
ALNAEEM – OFFICE BUILDING
- INTERNAL FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - COUNTERS
OUR PROJECTS
GENERAL AUTHORITY FOR INVESTMENT BUILDING
- INTERNAL FLOORING - INTERNAL WATER-JET FLOORING - INTERNAL STAIRS - EXTERNAL FLOORING - EXTERNAL CLADDING (MECHANICAL FIXING) - INTERNAL CLADDING - VANITY COUNTERTOPS
OUR PROJECTS
Miscellaneous Projects
40 WEST
OUR PROJECTS
Miscellaneous Projects
40 WEST
OUR PROJECTS
Miscellaneous Projects
40 WEST
OUR PROJECTS
Miscellaneous Projects
40 WEST
OUR PROJECTS
Miscellaneous Projects
THE POLYGON - office space
OUR PROJECTS
Miscellaneous Projects
PRIVATE VILLA
OUR PROJECTS
Miscellaneous Projects
PRIVATE VILLA
OUR PROJECTS
Miscellaneous Projects
PRIVATE VILLA
ABOUT DETAC MOTHER COMPANY
• Name of the company: Dar for Construction and Trading (DETAC) • Address: KM 28 - Cairo Alex. Road, Abu Rawash, Giza – EGYPT • Telephone: +20 2 3539 2701/2/3/4 • Fax: +20 2 3539 2700 • Website: www.detac.com.eg • Registration Statues: First category out of 7 categories available in Egypt (Construction,
Finishes & MEP) • Number of employees: 3,100 including 350 engineers • Field of Experience: - General contracting and construction - Manufacture and supplier as per DETAC Group list of companies: 1- DeMix Ready mix concrete 2- DeWood Wooden fire rated doors and products 3- DeTarget Applicator – Insulation and concrete repair works 4- MarmoTEC Marble and Granite products 5- AluRal Aluminum and curtain walling industry 6- ProGlass Architectural glass and glazing products 7- B&B Cement block factory 8- CSS A specialist company in the field of post tension technique 9- DeSteel Light steel products 10- DeFM Facility management services company • Projects: DETAC has completed many industrial, residential, administrative, educational
and healthcare projects for many prestigious clients designed / supervised by the most reputable multinational and local consulting firms.
• Annual Turnover: 1.4 B EGP (DETAC Group) – 700 M EGP (DETAC Construction) • Certifications: DETAC certified as ISO 9001:2008, 140001:2004, OHSAS 18001:2007
DETAC Group (Mother Company) – General Information