Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

15
Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting

description

3 Purpose of the Document 1

Transcript of Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

Page 1: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

Madrid15th June 2009

OS Agreement to Reserve Capacity10th IG meeting

Page 2: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

2

Index

1. Purpose of the Document

2. Main principles

3. Compatibility with Spanish Regulations

Page 3: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

3

Purpose of the Document

1

Page 4: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

4

Purpose of the Document The Agreement to Reserve Capacity is a document whereby the Shipper

agrees to subscribe to a capacity in the future

The future capacity being not built yet, it is not possible in France to sign a standard Transmission Contract at the time of capacity allocation

The Agreement covers the period:

From the signature shortly after the allocation

Up to the signature of the transmission contract

The Agreement is required to ensure the rational of the investment project

As any project, investment in gas transmission capacity requires a solid business case

Long term commitments to pay for a sufficient share of the capacity act as a “proof of concept”

Furthermore, commitments need to be backed by some financial guarantees

Page 5: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

5

Main principles2

Page 6: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

6

Scope One Agreement shall correspond to one Transmission Contract to be

executed

Contract for each product and each TSO

The commitment to pay for the Capacity must state clearly

the Capacity Product

What happens in case the Capacity Product undergoes substantial changes, for example following a change in the Contractual Structure

Page 7: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

7

Obligations of the TSO / the Shipper Once the conditions detailed in the next slide have been met, the TSO

undertakes to develop the capacity:

Delivery on time, matching the adjacent network capacity delivery

Information by the TSO to the Shipper on the progress

Prior notification of actual availability

The Shipper

Undertakes to sign a Transmission Contract with the TSO 30 to 90 days before the capacity becomes available

Should the Shipper fail to sign the Transmission Contract, the Shipper commits to pay any booked capacity that is not possible to re-sell to the market during the booking duration

Page 8: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

8

Implementation of the Contract The Agreement comes into effect under the following conditions,

Administrative Authorization

Approval by Regulatory Authorities Investment program

WACC corresponding to the development of new infrastructures

Board Approval

Final investment decision by the adjacent TSO

Financial guarantee is in place

Each condition must be met before a given deadline: after each deadline is passed, the Shipper gets more visibility on the progress of the decision-making process

Page 9: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

9

Availability of the Capacity The case of delay in the availability of capacity must be addressed

How would the Shipper capacity be affected?

Liability of the TSO

The case of early availability of the capacity must be addressed too

Allocation of the early capacity shall be non discriminatory

Priority to capacity holder?

Page 10: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

10

Financial Guarantee The Financial Guarantee should be in place shortly after the signature of

the Agreement

Type of Guarantee

Determination of the amount covered

Exemption of Guarantee

Duration of the Guarantee

The change of control of the Shipper and/or the assignment of the capacity to another shipper have to be addressed in the agreement too

Page 11: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

11

Compatibility with Spanish Regulations

.

3

Page 12: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

12

Necessity of the Agreement to Reserve Capacity In Spain the proposed “OS Agreement to Reserve Capacity” is not required

to proceed with the investment.

There is, however, a need to obtain before the capacity allocation the commitment from the shipper to book the capacity allocated at the OS. This can be done through the Request Letter to be submitted by shippers alongside the Request Forms.

TSOs are working on the development of an appropriate Request Letter, which will be part of the documentation of the OS.

Page 13: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

13

Necessity of the Agreement to Reserve Capacity In Spain it is possible to sign a standard Transmission Contract at the time of

capacity allocation, with some appendices/addenda to reflect that the obligation of the TSO is subject to the adoption of FIDs by all TSOs involved.

Most of the issues dealt with in the OS Agreement to Reserve Capacity are included in the standard Transmission Contract in Spain, or could be easily adapted through ad hoc addenda/appendices. If required, other additional guarantees could be reflected in the Information Memorandum: e.g. general information obligations between TSOs and shippers.

This option is not unusual in the Spanish system, where the standard contract can be adapted through additional appendices/addenda to reflect particular circumstances, as long as the additional appendices/addenda are not in conflict with the regulatory framework.

Spanish TSOs are working on a proposal of the adapted standard Transmission Contract to be included in the OS documentation, alongside a non-binding English version. The standard transmission contract in Enagás system is available at:

http://www.enagas.es/cs/Satellite?blobcol=urldata&blobheader=application%2Fpdf&blobkey=id&blobtable=MungoBlobs&blobwhere=1146242597955&ssbinary=true

Page 14: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

14

Compatibility with Spanish Regulations If the OS Agreement to Reserve Capacity was required in Spain, its

compatibility would have to be evaluated:

Financial guarantees and Ship-or-Pay obligations should be in line with the obligations already established in the Spanish regulatory framework.

The responsibility by TSOs in case of delays is generally established in general regulations, not in the transmission contract.

Page 15: Madrid 15 th June 2009 OS Agreement to Reserve Capacity 10 th IG meeting.

Thank you for your attention!