Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Transcript of Madhya Pradesh Power Generating Co. Ltd, Jabalpur
I Capacity Charges or Fixed Charges of SSTPP Stage-I, Khandwa
FY14 FY 16
Unit # 1 Unit # 2 (Unit # 1 & 2)
W.E.F. 01.04.2014
to 31.03.2015
W.E.F. COD of Unit
# 2 28.12.2014 to
31.03.2015
W.E.F. 01.04.2015
to 31.03.2016
1 Return on Equity 104.37 107.46 101.79 209.25 210.80
2 Depreciation 168.48 173.31 180.55 353.86 372.88
3 Interest & Finance Charges 340.60 355.72 364.65 720.37 708.68
4 O&M Expenses 77.70 83.88 83.88 167.76 181.08
5 Intt. On Working Capital 59.32 73.27 95.70 168.96 151.27
6 Secondary Oil Expenses 23.36 19.36 19.36 38.72 22.88
7 Annual Fixed Charges 773.83 812.99 845.94 1658.93 1647.58
8 No. of days in operation 59 365 94 366
9 Proportionate Fixed Charges. 125.08 812.99 217.86 1030.85 1647.58
10 Non Tariff Income -17.33 -9.00 -2.32 -11.32 -26.39
11 Net Fixed Charges 107.75 803.99 215.54 1019.53 1621.19
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Summary Sheet
FORM TPS-1
Total
Petitioner
(Rs. in Crores)
Thermal
Particulars
FY 15
W.E.F. COD of Unit
# 1 (01.02.2014 to
31.03.2014)
F - 1
Plant Characteristics
Unit(s)/ Block(s)/Parameters Unit-I Unit-II
Installed Capacity (MW) 600 600
Schedule COD as per Investment Approval 6/11/2012 10/11/2012
Actual COD/Date of Taken Over (as applicable) 2/1/2014 12/28/2014
Pit Head or Non Pit Head Non Pit Head Non Pit Head
Name of the Boiler Manufacture BHEL BHEL
Name of Turbine Generator Manufacture BHEL BHEL
Main Steams Pressure at Turbine inlet (kg/Cm2) abs
1 170 170
Main Steam Temperature at Turbine inlet(oC)
1 537 537
Reheat Steam Pressure at Turbine inlet (kg/Cm2)1 40.4 40.4
Reheat Steam Temperature at Turbine inlet (oC)
1 537 537
Main Steam flow at Turbine inlet under MCR condition (tons/hr)2 1799.7 1799.7
Main Steam flow at Turbine inlet under VWO condition (tons/hr)2 1908.5 1908.5
Unit Gross electrical output under MCR/Rated condition (MW)2 600 600
Unit Gross electrical output under VWO condition (MW)2 630.256 630.256
*Guaranteed Design Gross Turbine Cycle Heat Rate (kCal/kWh)3 1945 1945
Conditions on which design turbine cycle heat rate guaranteed 0% MU 100% TMCR 0% MU 100% TMCR
% MCR 100% TMCR 100% TMCR
% Makeup Water Consumption 3% 3%
Design Capacity of Make up Water System 60 m³/hr 60 m³/hr
Design Capacity of Inlet Cooling System (CW+ACW) 69474 69474
Design Cooling Water Temperature (oC) 33 33
Back Pressure (ata) 0.1047 0.1047
Steam flow at super heater outlet under BMCR condition (tonns/hr) 1975 1975
Steam Pressure at super heater outlet under BMCR condition (kg/Cm2) 178 178
Steam Temperature at super heater outlet under BMCR condition (oC) 540 540
Steam Temperature at Reheater outlet under BMCR condition (oC) 540 540
Design/Guaranteed Boiler Efficiency (%)4 87.35 87.35
Design Fuel with and without Blending of domestic/imported coal coal 3500 Kcal/kg coal 3500 Kcal/kg
Type of Cooling Tower Splash Fill Splash Fill
Type of Cooling System5 Close cycle (NDCT) Close cycle (NDCT)
Type of Boiler Feed Pump6 MD+TD MD+TD
Fuel Details
-Primary Fuel Coal Coal
-Secondary Fuel Oil Oil
-Alternate Fuel
Special Features/Site Specific Features7 Intake water system Intake water system
Special Technological Features
Environmental Regulation related features8 ESP, Zero Discharge ESP, Zero Discharge
Any other special features
M.P. Power Generating Co. Ltd.
Form TPS-2
Name of the Petitioner: M.P. POWER GENERATING CO. LTD., JABALPUR
Name of the Generating Station: 2x600 MW SHREE SINGAJI THERMAL POWER PROJECT KHANDWA
Petitioner
* Subject to PG Test.
F-2
ThermalTPS-3
Control Period
FY 14 to FY 16
(1) (2)
Rate of Return on Equity 15.50%
Effective Tax Rate
Target Availability 85.0%
Auxiliary Energy Consumption 6.00%
Gross Station Heat Rate 2384.25
Specific Fuel Oil Consumption 1.00
Cost of Coal/Lignite for WC(in Months) 2
Cost of Main Secondary Fuel Oil for WC(in Months) 2
Fuel Cost for WC(in Months) 2
Liquid Fuel Stock for WC(in Months) 2
O & M expenses (FY-14) 12.95 Lakh/MW
O & M expenses (FY-15) 13.98 Lakh/MW
O & M expenses (FY-16) 15.09 Lakh/MW
Maintenance Spares for WC 20.0%
Recievables for WC(in Months) 2
Base Rate of SBI + 3.50% 13.5% / 13.5% / 13.35%
(Petitioner)
Particulars
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Name of the Generating Station: 2x600 MW SHREE SINGAJI THERMAL POWER PROJECT KHANDWA
Normative parameters considered for tariff computations
F-3
PART-I
Form No:
TPS-5A
NAME OF THE GENERATING COMPANY
NAME OF THE POWER STATION
Board of Director/Agency approving the Capital cost estimates
Date of approval of the Capital cost estimates Letter No.F5-15/13 dtd.23.01.15
Approved Present Day
Cost (Rs.7820 Cr.)
Completed Cost as on
Scheduled Date of Station
CoD (28.12.14)
Price level of approved estimates 01/2014 01/2014
Foreign exchange rate considered for the capital cost estimates N/A N/A
Foreign component, if any (In Million US $ or the relevant Currency) 0.00 0.00
Domestic Component (Rs. Cr.) 6346.95 5833.06
Capital cost excluding IDC, FC, FERV & Hedging Cost 6346.95 5833.06
Foreign Component, if any (In Million US $ or the relevant Currency) 0.00 0.00
Domestic Component (Rs. Cr.) 1473.05 1593.10
Total IDC, FC, FERV & Hedging Cost 1473.05 1593.10
Rate of taxes & duties considered
Foreign Component, if any (In Million US $ or the relevant Currency) 0.00 0.00
Domestic Component 7820.00 7426.16
Capital cost Including IDC &FC (Say) 7820.00 7426.16
Schedule of Commissioning Scheduled Actual
COD of Unit-I 11-Jun-12 1-Feb-14
CoD of Unit-II 11-Oct-12 28-Dec-14
COD of last Unit/ Block 11-Oct-12 28-Dec-14
(Petitioner)
Government of Madhya Pradesh
Capital Cost excluding IDC & FC
IDC, FC FERV & Hedging Cost
Capital cost Including IDC, FC FERV & Hedging Cost
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Abstract of Capital Cost for the New Projects
( Amount Rs. in Crores)
M.P. POWER GENERATING CO. LTD., JABALPUR
(2X600 MW) SHREE SINGAJI THERMAL POWER
PROJECT, KHANDWA
F-4
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
1. Cost of Land & Site Development
1.1Land Cost including Rehabilitation & Resettlement
(R&R)117.50 56.82 56.82 113.63 56.82 56.82 113.63
1.2Preliminary Investigation & Site development and
enabling works
Included in
Overheads
1.3 Environment Improvement MeasuresIncluded in
various heads0.00 0.00 0.00 0.00 0.00 0.00
Total Land & Site Development 117.50 56.82 56.82 113.63 56.82 56.82 113.63
2. Main Power Block
2.1 Steam Generator Island excluding T&D
2.2 Turbine Generator Island incl. CW/RW system
2.3 MPB- C& I
2.4Price Variation towords extention of zero date including
T&D- Supply
2.5 Exchange Rate / CD Variation
2.6 Total MPB Supply of Plant & Equipment (Incl. cst.) 2230.11 1133.03 1069.84 2202.87 1133.57 1070.79 2204.36
3. BOP Mechanical & Electrical
3.1 BOP Mechanical
3.1.1 External water supply system
3.1.2 CW system equipments
Included in Total Included in Total
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Included in Total Included in Total
F-5
Part-I TPS Form No.5B
1 2 3
1. Cost of Land & Site Development
1.1Land Cost including Rehabilitation & Resettlement
(R&R)117.50
1.2Preliminary Investigation & Site development and
enabling works
Included in
Overheads
1.3 Environment Improvement MeasuresIncluded in
various heads
Total Land & Site Development 117.50
2. Main Power Block
2.1 Steam Generator Island excluding T&D
2.2 Turbine Generator Island incl. CW/RW system
2.3 MPB- C& I
2.4Price Variation towords extention of zero date including
T&D- Supply
2.5 Exchange Rate / CD Variation
2.6 Total MPB Supply of Plant & Equipment (Incl. cst.) 2230.11
3. BOP Mechanical & Electrical
3.1 BOP Mechanical
3.1.1 External water supply system
3.1.2 CW system equipments
Included in Total
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Included in Total
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
56.93 56.93 113.86 56.93 56.93 113.86
0.00 0.00 0.00 0.00 0.00 0.00
56.93 56.93 113.86 56.93 56.93 113.86
1134.14 1077.32 2211.46 1134.14 1077.32 2211.46
Included in Total
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
Included in Total
F-6
Part-I TPS Form No.5B
1 2 3
1. Cost of Land & Site Development
1.1Land Cost including Rehabilitation & Resettlement
(R&R)117.50
1.2Preliminary Investigation & Site development and
enabling works
Included in
Overheads
1.3 Environment Improvement MeasuresIncluded in
various heads
Total Land & Site Development 117.50
2. Main Power Block
2.1 Steam Generator Island excluding T&D
2.2 Turbine Generator Island incl. CW/RW system
2.3 MPB- C& I
2.4Price Variation towords extention of zero date including
T&D- Supply
2.5 Exchange Rate / CD Variation
2.6 Total MPB Supply of Plant & Equipment (Incl. cst.) 2230.11
3. BOP Mechanical & Electrical
3.1 BOP Mechanical
3.1.1 External water supply system
3.1.2 CW system equipments
Included in Total
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Included in Total
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
3.64 0.34 0.34 0.68 57.27 57.27 114.54
0.00
0.00 0.00
3.64 0.34 0.34 0.68 57.27 57.27 114.54
18.65 0.65 0.89 1.55 1134.79 1078.21 2213.01
Included in
Total
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
F-7
Part-I TPS Form No.5B
1 2 3
1. Cost of Land & Site Development
1.1Land Cost including Rehabilitation & Resettlement
(R&R)117.50
1.2Preliminary Investigation & Site development and
enabling works
Included in
Overheads
1.3 Environment Improvement MeasuresIncluded in
various heads
Total Land & Site Development 117.50
2. Main Power Block
2.1 Steam Generator Island excluding T&D
2.2 Turbine Generator Island incl. CW/RW system
2.3 MPB- C& I
2.4Price Variation towords extention of zero date including
T&D- Supply
2.5 Exchange Rate / CD Variation
2.6 Total MPB Supply of Plant & Equipment (Incl. cst.) 2230.11
3. BOP Mechanical & Electrical
3.1 BOP Mechanical
3.1.1 External water supply system
3.1.2 CW system equipments
Included in Total
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Included in Total
Liabilties as
on 31.03.16
23
2.96
2.96
17.10
F-8
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.1.3 Water System(WTP,DM,ETP,STP,CW Chlorination)
3.1.4 Fuel Oil unloading & Storage system
3.1.5 Ash Handling System
3.1.6 Coal Handling System
3.1.7 Fire Protection & Detection System
3.1.8 Compressed Air System
3.1.9 Air Condition & Ventilation System (HVAC)
3.1.10 Chimney
3.1.11 LP Piping
3.1.12 Raw Water Intake System
3.1.13Natural Draft Cooling Towers (including Mechanical &
Electrical)
3.1.14 Misc. Pumps
3.1.15 Misc. Hoists & Cranes,Elevators etc.
3.1.16 Hydrogen Gen. Plant
3.1.17 Workshop Equipments & Misc.
3.1.18 Chemical Lab Equipments
Total BOP Mechanical
3.2 BOP Electrical
Included in Total Included in Total
F-9
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.1.3 Water System(WTP,DM,ETP,STP,CW Chlorination)
3.1.4 Fuel Oil unloading & Storage system
3.1.5 Ash Handling System
3.1.6 Coal Handling System
3.1.7 Fire Protection & Detection System
3.1.8 Compressed Air System
3.1.9 Air Condition & Ventilation System (HVAC)
3.1.10 Chimney
3.1.11 LP Piping
3.1.12 Raw Water Intake System
3.1.13Natural Draft Cooling Towers (including Mechanical &
Electrical)
3.1.14 Misc. Pumps
3.1.15 Misc. Hoists & Cranes,Elevators etc.
3.1.16 Hydrogen Gen. Plant
3.1.17 Workshop Equipments & Misc.
3.1.18 Chemical Lab Equipments
Total BOP Mechanical
3.2 BOP Electrical
Included in Total
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
Included in Total
F-10
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.1.3 Water System(WTP,DM,ETP,STP,CW Chlorination)
3.1.4 Fuel Oil unloading & Storage system
3.1.5 Ash Handling System
3.1.6 Coal Handling System
3.1.7 Fire Protection & Detection System
3.1.8 Compressed Air System
3.1.9 Air Condition & Ventilation System (HVAC)
3.1.10 Chimney
3.1.11 LP Piping
3.1.12 Raw Water Intake System
3.1.13Natural Draft Cooling Towers (including Mechanical &
Electrical)
3.1.14 Misc. Pumps
3.1.15 Misc. Hoists & Cranes,Elevators etc.
3.1.16 Hydrogen Gen. Plant
3.1.17 Workshop Equipments & Misc.
3.1.18 Chemical Lab Equipments
Total BOP Mechanical
3.2 BOP Electrical
Included in Total
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
F-11
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.1.3 Water System(WTP,DM,ETP,STP,CW Chlorination)
3.1.4 Fuel Oil unloading & Storage system
3.1.5 Ash Handling System
3.1.6 Coal Handling System
3.1.7 Fire Protection & Detection System
3.1.8 Compressed Air System
3.1.9 Air Condition & Ventilation System (HVAC)
3.1.10 Chimney
3.1.11 LP Piping
3.1.12 Raw Water Intake System
3.1.13Natural Draft Cooling Towers (including Mechanical &
Electrical)
3.1.14 Misc. Pumps
3.1.15 Misc. Hoists & Cranes,Elevators etc.
3.1.16 Hydrogen Gen. Plant
3.1.17 Workshop Equipments & Misc.
3.1.18 Chemical Lab Equipments
Total BOP Mechanical
3.2 BOP Electrical
Included in Total
Liabilties as
on 31.03.16
23
F-12
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.2.1 Switchyard+Electrical +Control & Instrumentation
3.3 C & I Package
3.4 Total BOP Mechanical, Electrical,C&I 780.10 376.51 376.51 753.02 376.74 376.74 753.47
4. Total Plant & Equipment excluding taxes & Duties 3010.21 1509.54 1446.35 2955.89 1510.31 1447.53 2957.83
5. Taxes and Duties
5.1 MPB: Taxes and Duties Included in 2.6
5.2 BoP: Taxes and Duties Included in 3.4
5.3 Custom Duty (not applicable as Mega status)
5.4 Other Taxes & Duties (Entry Tax)Included in 10
(overheads)
5.5 Other Taxes & Duties (Labour welfare cess)Incl. in Civil and
E&TC heads
Total Taxes & Duties 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Plant & Equipment including taxes & duties 3010.21 1509.54 1446.35 2955.89 1510.31 1447.53 2957.83
6. Initial spares
6.1 MPB: Mandatory Spares (Incl. taxes & duties) 102.92 24.69 24.69 49.39 24.69 24.69 49.39
6.2 BoP: Mandatory Spares (Incl. taxes & duties) 31.00 4.53 0.00 4.53 4.53 0.00 4.53
6.3 Additional Spares 60.31 0.00 0.00 0.00 0.00 0.00 0.00
Included in Total Included in Total
F-13
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.2.1 Switchyard+Electrical +Control & Instrumentation
3.3 C & I Package
3.4 Total BOP Mechanical, Electrical,C&I 780.10
4. Total Plant & Equipment excluding taxes & Duties 3010.21
5. Taxes and Duties
5.1 MPB: Taxes and Duties Included in 2.6
5.2 BoP: Taxes and Duties Included in 3.4
5.3 Custom Duty (not applicable as Mega status)
5.4 Other Taxes & Duties (Entry Tax)Included in 10
(overheads)
5.5 Other Taxes & Duties (Labour welfare cess)Incl. in Civil and
E&TC heads
Total Taxes & Duties 0.00
Total Plant & Equipment including taxes & duties 3010.21
6. Initial spares
6.1 MPB: Mandatory Spares (Incl. taxes & duties) 102.92
6.2 BoP: Mandatory Spares (Incl. taxes & duties) 31.00
6.3 Additional Spares 60.31
Included in Total
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
384.83 384.83 769.65 384.83 384.83 769.65
1518.97 1462.15 2981.11 1518.97 1462.15 2981.11
0.00 0.00 0.00 0.00 0.00 0.00
1518.97 1462.15 2981.11 1518.97 1462.15 2981.11
32.61 32.61 65.22 32.61 32.61 65.22
6.17 1.64 7.81 6.17 1.64 7.81
0.00 0.00 0.00 0.00 0.00 0.00
Included in Total
F-14
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.2.1 Switchyard+Electrical +Control & Instrumentation
3.3 C & I Package
3.4 Total BOP Mechanical, Electrical,C&I 780.10
4. Total Plant & Equipment excluding taxes & Duties 3010.21
5. Taxes and Duties
5.1 MPB: Taxes and Duties Included in 2.6
5.2 BoP: Taxes and Duties Included in 3.4
5.3 Custom Duty (not applicable as Mega status)
5.4 Other Taxes & Duties (Entry Tax)Included in 10
(overheads)
5.5 Other Taxes & Duties (Labour welfare cess)Incl. in Civil and
E&TC heads
Total Taxes & Duties 0.00
Total Plant & Equipment including taxes & duties 3010.21
6. Initial spares
6.1 MPB: Mandatory Spares (Incl. taxes & duties) 102.92
6.2 BoP: Mandatory Spares (Incl. taxes & duties) 31.00
6.3 Additional Spares 60.31
Included in Total
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
10.45 5.10 5.10 10.20 389.93 389.93 779.85
29.10 5.75 5.99 11.75 1524.72 1468.14 2992.86
0.00 0.00 0.00 0.00 0.00 0.00 0.00
29.10 5.75 5.99 11.75 1524.72 1468.14 2992.86
37.70 5.21 5.21 10.41 37.82 37.82 75.63
23.19 6.52 6.52 13.05 12.69 8.16 20.86
60.31 0.00 0.00 0.00 0.00 0.00 0.00
F-15
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.2.1 Switchyard+Electrical +Control & Instrumentation
3.3 C & I Package
3.4 Total BOP Mechanical, Electrical,C&I 780.10
4. Total Plant & Equipment excluding taxes & Duties 3010.21
5. Taxes and Duties
5.1 MPB: Taxes and Duties Included in 2.6
5.2 BoP: Taxes and Duties Included in 3.4
5.3 Custom Duty (not applicable as Mega status)
5.4 Other Taxes & Duties (Entry Tax)Included in 10
(overheads)
5.5 Other Taxes & Duties (Labour welfare cess)Incl. in Civil and
E&TC heads
Total Taxes & Duties 0.00
Total Plant & Equipment including taxes & duties 3010.21
6. Initial spares
6.1 MPB: Mandatory Spares (Incl. taxes & duties) 102.92
6.2 BoP: Mandatory Spares (Incl. taxes & duties) 31.00
6.3 Additional Spares 60.31
Included in Total
Liabilties as
on 31.03.16
23
0.25
17.35
0.00
0.00
0.00
17.35
0.00
27.29
10.14
60.31
F-16
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Total Spares 194.23 29.22 24.69 53.92 29.22 24.69 53.92
BOP PV
PVC on Supply (Incl. Service Tax) 121.67 49.42 49.42 98.84 50.38 50.38 100.75
PVC on E&TC (Incl. Service Tax) 18.26 6.33 6.33 12.66 6.48 6.48 12.97
PVC on Civil (Incl. Service Tax) Included in 8.2
7. PVC Incl. Service Tax (Supply,E&TC,Civil) 139.92 55.75 55.75 111.50 56.86 56.86 113.72
8. Civil Works
8.1 MPB:
8.1.1 Estimated Base value + Service Tax 406.71 202.39 169.54 371.93 203.53 171.06 374.59
8.2 BoP (Incl. Service Tax + PV) 824.78 376.49 376.49 752.98 385.23 385.23 770.46
8.2.1 CW system
8.2.2 Cooling Towers
8.2.3 DM water Plant
8.2.4 Clarification plant
8.2.5 Chlorination plant
8.2.6 Fuel Handiling & Storage system
8.2.7 Coal Handling Plant
8.2.8 Ash Handling System Included in Sr.
No. 8.2Included in Sr. No. 8.2
F-17
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Total Spares 194.23
BOP PV
PVC on Supply (Incl. Service Tax) 121.67
PVC on E&TC (Incl. Service Tax) 18.26
PVC on Civil (Incl. Service Tax) Included in 8.2
7. PVC Incl. Service Tax (Supply,E&TC,Civil) 139.92
8. Civil Works
8.1 MPB:
8.1.1 Estimated Base value + Service Tax 406.71
8.2 BoP (Incl. Service Tax + PV) 824.78
8.2.1 CW system
8.2.2 Cooling Towers
8.2.3 DM water Plant
8.2.4 Clarification plant
8.2.5 Chlorination plant
8.2.6 Fuel Handiling & Storage system
8.2.7 Coal Handling Plant
8.2.8 Ash Handling System Included in Sr.
No. 8.2
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
38.78 34.25 73.03 38.78 34.25 73.03
51.40 51.40 102.80 51.40 51.40 102.80
8.08 8.08 16.17 8.17 8.17 16.34
59.48 59.48 118.97 59.57 59.57 119.14
218.74 179.03 397.77 218.74 179.03 397.77
397.66 397.66 795.31 397.65 397.65 795.31
Included in Sr. No. 8.2
F-18
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Total Spares 194.23
BOP PV
PVC on Supply (Incl. Service Tax) 121.67
PVC on E&TC (Incl. Service Tax) 18.26
PVC on Civil (Incl. Service Tax) Included in 8.2
7. PVC Incl. Service Tax (Supply,E&TC,Civil) 139.92
8. Civil Works
8.1 MPB:
8.1.1 Estimated Base value + Service Tax 406.71
8.2 BoP (Incl. Service Tax + PV) 824.78
8.2.1 CW system
8.2.2 Cooling Towers
8.2.3 DM water Plant
8.2.4 Clarification plant
8.2.5 Chlorination plant
8.2.6 Fuel Handiling & Storage system
8.2.7 Coal Handling Plant
8.2.8 Ash Handling System Included in Sr.
No. 8.2
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
121.20 11.73 11.73 23.46 50.51 45.98 96.49
18.87 0.00 0.00 0.00 51.40 51.40 102.80
1.92 1.28 1.28 2.56 9.45 9.45 18.90
20.78 1.28 1.28 2.56 60.85 60.85 121.70
8.94 7.94 4.01 11.95 226.68 183.04 409.72
29.47 10.15 10.15 20.31 407.81 407.81 815.61
Included in Sr. No. 8.2
F-19
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
Total Spares 194.23
BOP PV
PVC on Supply (Incl. Service Tax) 121.67
PVC on E&TC (Incl. Service Tax) 18.26
PVC on Civil (Incl. Service Tax) Included in 8.2
7. PVC Incl. Service Tax (Supply,E&TC,Civil) 139.92
8. Civil Works
8.1 MPB:
8.1.1 Estimated Base value + Service Tax 406.71
8.2 BoP (Incl. Service Tax + PV) 824.78
8.2.1 CW system
8.2.2 Cooling Towers
8.2.3 DM water Plant
8.2.4 Clarification plant
8.2.5 Chlorination plant
8.2.6 Fuel Handiling & Storage system
8.2.7 Coal Handling Plant
8.2.8 Ash Handling System Included in Sr.
No. 8.2
Liabilties as
on 31.03.16
23
97.74
0.00
18.87
-0.65
18.22
0.00
0.00
-3.01
9.17
0.00
0.00
0.00
0.00
0.00
0.00
0.00
F-20
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
8.2.9 Ash disposal area development
8.2.10 Fire fighting System
8.2.11 Temp. construction & enabling works
8.2.12 Road & Drainage
8.2.13 Chimney
8.2.14 ETP
8.2.15 Switchyard
8.3 Rail Transportation System 288.33 81.06 81.06 162.12 82.44 82.44 164.87
8.4 GCW-I (incl. T&D) 193.50 94.24 94.24 188.48 94.24 94.24 188.48
8.5 GCW-II (incl. T&D) 112.00 17.18 17.18 34.35 24.69 24.69 49.38
8.6 GCW-III (incl. T&D) Town Ship & Colony 177.42 66.42 66.42 132.83 73.81 73.81 147.62
Total Civil works along with Railway siding 2002.74 837.77 804.92 1642.69 863.94 831.47 1695.40
9. Construction & Pre commissioning Expenses
9.1.1 MPB: Erection Testing and commissioning (Incl. taxes) 345.86 163.03 113.05 276.08 166.0400 127.1100 293.15
9.1.2MPB: Freight charges
(Incl. service tax)64.40 29.70 27.64 57.34 29.74 27.67 57.41
9.1 MPB: Erection Testing and commissioning incl Freight
charges410.26 192.73 140.69 333.42 195.78 154.78 350.56
9.2.1 BoP: Erection Testing and commissioning 82.54 32.60 32.60 65.20 34.74 34.74 69.47
9.2.2 BoP Special Test 14.70 1.00 1.00 2.00 1.00 1.00 2.00
Included in Sr.
No. 8.2Included in Sr. No. 8.2
F-21
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
8.2.9 Ash disposal area development
8.2.10 Fire fighting System
8.2.11 Temp. construction & enabling works
8.2.12 Road & Drainage
8.2.13 Chimney
8.2.14 ETP
8.2.15 Switchyard
8.3 Rail Transportation System 288.33
8.4 GCW-I (incl. T&D) 193.50
8.5 GCW-II (incl. T&D) 112.00
8.6 GCW-III (incl. T&D) Town Ship & Colony 177.42
Total Civil works along with Railway siding 2002.74
9. Construction & Pre commissioning Expenses
9.1.1 MPB: Erection Testing and commissioning (Incl. taxes) 345.86
9.1.2MPB: Freight charges
(Incl. service tax)64.40
9.1 MPB: Erection Testing and commissioning incl Freight
charges410.26
9.2.1 BoP: Erection Testing and commissioning 82.54
9.2.2 BoP Special Test 14.70
Included in Sr.
No. 8.2
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
85.34 85.34 170.68 96.14 96.14 192.29
94.24 94.24 188.48 94.24 94.24 188.48
25.82 25.82 51.65 41.40 41.40 82.80
82.39 82.39 164.78 82.39 82.39 164.78
904.19 864.48 1768.67 930.56 890.86 1821.42
169.53 164.62 334.15 169.53 166.79 336.32
29.83 27.76 57.59 29.83 27.76 57.59
199.36 192.38 391.74 199.36 194.55 393.91
41.05 41.05 82.10 41.65 41.65 83.30
1.00 1.00 2.00 1.00 1.00 2.00
Included in Sr. No. 8.2
F-22
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
8.2.9 Ash disposal area development
8.2.10 Fire fighting System
8.2.11 Temp. construction & enabling works
8.2.12 Road & Drainage
8.2.13 Chimney
8.2.14 ETP
8.2.15 Switchyard
8.3 Rail Transportation System 288.33
8.4 GCW-I (incl. T&D) 193.50
8.5 GCW-II (incl. T&D) 112.00
8.6 GCW-III (incl. T&D) Town Ship & Colony 177.42
Total Civil works along with Railway siding 2002.74
9. Construction & Pre commissioning Expenses
9.1.1 MPB: Erection Testing and commissioning (Incl. taxes) 345.86
9.1.2MPB: Freight charges
(Incl. service tax)64.40
9.1 MPB: Erection Testing and commissioning incl Freight
charges410.26
9.2.1 BoP: Erection Testing and commissioning 82.54
9.2.2 BoP Special Test 14.70
Included in Sr.
No. 8.2
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
96.04 2.92 2.92 5.84 99.07 99.07 198.13
5.02 0.00 0.00 0.00 94.24 94.24 188.48
29.20 0.72 0.72 1.43 42.12 42.12 84.23
12.64 0.00 0.00 0.00 82.39 82.39 164.78
181.32 21.74 17.80 39.53 952.30 908.66 1860.96
9.54 1.25 3.75 5.00 170.78 170.54 341.32
6.81 0.12 0.00 0.12 29.95 27.76 57.71
16.35 1.37 3.75 5.12 200.73 198.30 399.03
-0.76 1.11 1.11 2.22 42.76 42.76 85.51
12.70 0.00 0.00 0.00 1.00 1.00 2.00
Included in Sr. No. 8.2
F-23
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
8.2.9 Ash disposal area development
8.2.10 Fire fighting System
8.2.11 Temp. construction & enabling works
8.2.12 Road & Drainage
8.2.13 Chimney
8.2.14 ETP
8.2.15 Switchyard
8.3 Rail Transportation System 288.33
8.4 GCW-I (incl. T&D) 193.50
8.5 GCW-II (incl. T&D) 112.00
8.6 GCW-III (incl. T&D) Town Ship & Colony 177.42
Total Civil works along with Railway siding 2002.74
9. Construction & Pre commissioning Expenses
9.1.1 MPB: Erection Testing and commissioning (Incl. taxes) 345.86
9.1.2MPB: Freight charges
(Incl. service tax)64.40
9.1 MPB: Erection Testing and commissioning incl Freight
charges410.26
9.2.1 BoP: Erection Testing and commissioning 82.54
9.2.2 BoP Special Test 14.70
Included in Sr.
No. 8.2
Liabilties as
on 31.03.16
23
0.00
0.00
0.00
0.00
0.00
0.00
0.00
90.20
5.02
27.77
12.64
141.78
0.00
4.54
6.69
11.23
-2.97
12.70
F-24
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
9.2.3 BoP: Freight charges 24.46 11.08 11.08 22.17 11.08 11.08 22.17
9.2 BoP: Erection Testing and commissioning incl Freight
charges121.70 44.68 44.68 89.36 46.82 46.82 93.63
9.3 Operator's Training
9.4 Site supervision
9.5 Construction Insurance
9.6 Tools & Plant
9.7 Start up fuel 190.78 97.08 0.00 97.08 97.08 0.00 97.08
9.8 Construction power (Inside plant) 5.30 2.63 2.63 5.27 2.63 2.63 5.27
Total Construction & Pre Commissioning Expenses 728.04 337.13 188.01 525.13 342.31 204.23 546.54
10. Overheads
10.1
Railway Project Management Consultancy,Project
Monitoring Consultancy & TPI ( including service tax and
other claims)
15.00
10.2 Establishment & admin. And other works,Audit &
Accounts60.00
10.3 Contingency 40.00
10.4Preliminary Investigation & Site development and
enabling works 0.71
10.5 Water Charges Payable to WRD 2.50
10.6 Construction Power Incl. T&D (outside plant) 9.70
31.88 3.88 35.76 35.87 34.49 70.36
Inclusive in Sr.
No. 9.1 & 9.2
F-25
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
9.2.3 BoP: Freight charges 24.46
9.2 BoP: Erection Testing and commissioning incl Freight
charges121.70
9.3 Operator's Training
9.4 Site supervision
9.5 Construction Insurance
9.6 Tools & Plant
9.7 Start up fuel 190.78
9.8 Construction power (Inside plant) 5.30
Total Construction & Pre Commissioning Expenses 728.04
10. Overheads
10.1
Railway Project Management Consultancy,Project
Monitoring Consultancy & TPI ( including service tax and
other claims)
15.00
10.2 Establishment & admin. And other works,Audit &
Accounts60.00
10.3 Contingency 40.00
10.4Preliminary Investigation & Site development and
enabling works 0.71
10.5 Water Charges Payable to WRD 2.50
10.6 Construction Power Incl. T&D (outside plant) 9.70
Inclusive in Sr.
No. 9.1 & 9.2
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
11.78 11.78 23.56 11.78 11.78 23.56
53.83 53.83 107.66 54.43 54.43 108.85
97.08 83.90 180.98 97.08 83.90 180.98
2.63 2.63 5.27 2.63 2.63 5.27
352.90 332.74 685.64 353.50 335.51 689.01
34.53 48.74 83.27 34.53 48.74 83.27
F-26
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
9.2.3 BoP: Freight charges 24.46
9.2 BoP: Erection Testing and commissioning incl Freight
charges121.70
9.3 Operator's Training
9.4 Site supervision
9.5 Construction Insurance
9.6 Tools & Plant
9.7 Start up fuel 190.78
9.8 Construction power (Inside plant) 5.30
Total Construction & Pre Commissioning Expenses 728.04
10. Overheads
10.1
Railway Project Management Consultancy,Project
Monitoring Consultancy & TPI ( including service tax and
other claims)
15.00
10.2 Establishment & admin. And other works,Audit &
Accounts60.00
10.3 Contingency 40.00
10.4Preliminary Investigation & Site development and
enabling works 0.71
10.5 Water Charges Payable to WRD 2.50
10.6 Construction Power Incl. T&D (outside plant) 9.70
Inclusive in Sr.
No. 9.1 & 9.2
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
0.90 0.00 0.00 0.00 11.78 11.78 23.56
12.85 1.11 1.11 2.22 55.53 55.53 111.07
9.80 0.00 -0.04 -0.04 97.08 83.86 180.94
0.03 -0.137 0.067 -0.07 2.50 2.70 5.20
39.03 2.34 4.89 7.23 355.84 340.39 696.24
37.68 56.53 94.2144.64 3.14 7.79 10.94
F-27
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
9.2.3 BoP: Freight charges 24.46
9.2 BoP: Erection Testing and commissioning incl Freight
charges121.70
9.3 Operator's Training
9.4 Site supervision
9.5 Construction Insurance
9.6 Tools & Plant
9.7 Start up fuel 190.78
9.8 Construction power (Inside plant) 5.30
Total Construction & Pre Commissioning Expenses 728.04
10. Overheads
10.1
Railway Project Management Consultancy,Project
Monitoring Consultancy & TPI ( including service tax and
other claims)
15.00
10.2 Establishment & admin. And other works,Audit &
Accounts60.00
10.3 Contingency 40.00
10.4Preliminary Investigation & Site development and
enabling works 0.71
10.5 Water Charges Payable to WRD 2.50
10.6 Construction Power Incl. T&D (outside plant) 9.70
Inclusive in Sr.
No. 9.1 & 9.2
Liabilties as
on 31.03.16
23
0.90
10.63
0.00
0.00
0.00
9.84
0.10
31.80
0.00
33.70
F-28
Part-I TPS Form No.5B
Unit I Unit II Total Unit I Unit II Total
1 2 3 4 5 6=4+5 7 8 9=7+8
Total Expenditure upto 31/01/2014
( COD of Unit I )
Total Expenditure Up to
31st Mar. 2014
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.5 Entry Tax 26.40 12.79 12.79 25.58 13.10 13.10 26.20
Non Plant Assets incl. in 10.3 0.00 0.00 0.00 0.00 0.00 0.00
Total Overheads 154.31 44.67 16.66 61.33 48.97 47.59 96.56
11. Capital cost excluding IDC & FC 6346.95 2870.90 2593.20 5464.10 2908.42 2669.19 5577.60
12. IDC, FC, FERV & Hedging Cost
12.1 Interest During Construction (IDC) 1473.05 659.19 622.30 1281.49 659.19 674.43 1333.62
12.2 Financing Charges (FC)Incl. in Sr No.
12.1
12.3 Foreign Exchange Rate Variation (FERV)
inclusive in
respective
contracts
12.4 Hedging Cost 0.00 0.00 0.00 0.00
Total of IDC, FC, FERV & Hedging Cost 1473.05 659.19 622.30 1281.49 659.19 674.43 1333.62
Capital cost including IDC, FC, FERV & Hedging
Cost7820.00 3530.08 3215.50 6745.58 3567.61 3343.62 6911.22
F-29
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.5 Entry Tax 26.40
Non Plant Assets incl. in 10.3
Total Overheads 154.31
11. Capital cost excluding IDC & FC 6346.95
12. IDC, FC, FERV & Hedging Cost
12.1 Interest During Construction (IDC) 1473.05
12.2 Financing Charges (FC)Incl. in Sr No.
12.1
12.3 Foreign Exchange Rate Variation (FERV)
inclusive in
respective
contracts
12.4 Hedging Cost 0.00
Total of IDC, FC, FERV & Hedging Cost 1473.05
Capital cost including IDC, FC, FERV & Hedging
Cost7820.00
Unit I Unit II Total Unit I Unit II Total
10 11 12=10+11 13 14 15=13+14
Total Expenditure Up to
28th Dec. 2014 (Stn. COD)
Total Expenditure Up to
31st March 2015
3.57 4.94 8.51 3.57 4.94 8.51
0.00 0.00 0.00 0.00 0.00 0.00
38.11 53.68 91.78 38.11 53.68 91.78
2969.36 2863.71 5833.06 2996.42 2892.94 5889.35
659.19 933.91 1593.10 659.19 933.91 1593.10
0.00 0.00 0.00
659.19 933.91 1593.10 659.19 933.91 1593.10
3628.55 3797.62 7426.17 3655.61 3826.85 7482.46
F-30
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.5 Entry Tax 26.40
Non Plant Assets incl. in 10.3
Total Overheads 154.31
11. Capital cost excluding IDC & FC 6346.95
12. IDC, FC, FERV & Hedging Cost
12.1 Interest During Construction (IDC) 1473.05
12.2 Financing Charges (FC)Incl. in Sr No.
12.1
12.3 Foreign Exchange Rate Variation (FERV)
inclusive in
respective
contracts
12.4 Hedging Cost 0.00
Total of IDC, FC, FERV & Hedging Cost 1473.05
Capital cost including IDC, FC, FERV & Hedging
Cost7820.00
Unit I Unit II Total Unit I Unit II Total
16= 3-15 17 18 19=17+18 20 21 22=20+21
Liabilties /
provisions
w.r.t App.Cost
Estimated Expenditure
during
FY- 2015-16
Total Expenditure Up to
31st March 2016
17.89 0.96 0.29 1.25 4.54 5.22 9.76
0.00 0.00 0.00 0.00 0.85 0.13 0.98
62.53 4.11 8.08 12.19 43.07 61.89 104.96
457.60 47.29 50.11 97.40 3044.57 2943.18 5987.74
-120.05 0.00 0.00 0.00 659.19 933.91 1593.10
0.00 0.00 0.00 0.00 0.00 0.00 0.00
-120.05 0.00 0.00 0.00 659.19 933.91 1593.10
337.54 47.29 50.11 97.40 3703.76 3877.09 7580.85
(Petitioner)
F-31
Part-I TPS Form No.5B
1 2 3
NAME OF THE POWER STATION: SSTPP Stage-1 (2x600MW)
BREAK-UP OF CAPITAL COST FOR COAL/LIGNITE BASED PROJECTS
NAME OF THE GENERATING COMPANY: MPPGCL
in Rs.Crores
Break Down Revised CostSN
3.5 Entry Tax 26.40
Non Plant Assets incl. in 10.3
Total Overheads 154.31
11. Capital cost excluding IDC & FC 6346.95
12. IDC, FC, FERV & Hedging Cost
12.1 Interest During Construction (IDC) 1473.05
12.2 Financing Charges (FC)Incl. in Sr No.
12.1
12.3 Foreign Exchange Rate Variation (FERV)
inclusive in
respective
contracts
12.4 Hedging Cost 0.00
Total of IDC, FC, FERV & Hedging Cost 1473.05
Capital cost including IDC, FC, FERV & Hedging
Cost7820.00
Liabilties as
on 31.03.16
23
33.70
359.21
0
-120.05
0.00
-120.05
239.15
(Petitioner)
F-32
PART-I Form No: TPS-5C
1 2 3 4 5 6
1 Name/No. of Construction /Supply /Service Package
2 Scope of works 1 (In line with head of cost break ups as
applicable)
Supply Erection Civil Supply Erection Civil
3 Whether awarded through ICB/DCB/Departmentally/Deposit
WorkICB ICB ICB ICB ICB ICB
4 No. of bids received
5 Date of Award 12.12.2008 12.12.2008 12.12.2008 26.10.09 26.10.09 26.10.09
6 Date of Start of work 22.12.2009 18.09.2010 10.02.2010 18.06.10 10.01.11 14.03.10
7 Date of Completion of work Main Plant Supply
almost completed.
Mandatory spares
supply under
progress.
Steam Generator
and Turbine
Erection completed.
HVAC System and
Boiler Lift work
under progress.
All Major work
completed. Minor
pending civil works
under progress.
All BOP Supply
completed.
Mandatory spares
supply under
progress.
All Major BOP
Erection work
completed by July-
14.
Punch points
liquidation under
progress.
All BOP Civil
Erection work
completed by
June'14.
8 Value of award 2 including taxes and duties (Rs. Cr.)
2333.03 410.26 406.71 932.77 125.26 824.78
9 Firm or With escalation in prices FIRM FIRM FIRM
10 Actual capital expenditure till COD of unit 2 dtd.28.12.14
includind Taxes & Duties ( Rs. Cr.)2276.68 391.74 397.77 880.26 121.83 795.31
11 Taxes & Duties and IEDCIncl. in 10 Incl. in 10 Incl. in 10 Incl. in 10 Incl. in 10 Incl. in 10
(10) + (11) 2276.68 391.74 397.77 880.26 121.83 795.31
12 IDC, FC, FERV & Hedging cost (Projected upto Station CoD)
13 Sub total (10+11+12)
14 Current status as on 31-03-2016 2288.64 399.03 409.72 903.51 127.98 815.61
1593.10
BREAK-UP OF CONSTRUCTION/ SUPPLY/ SERVICE
PACKAGESPART-I Form No: TPS-5C
NAME OF THE POWER STATION: SSTPP Stage-1(2x600MW)
6527.66
NAME OF THE GENERATING COMPANY:MPPGCL
Main Power Block Balance of Plant Package
2 3
With PV
Particulars
F-33
PART-I Form No: TPS-5C
1 Name/No. of Construction /Supply /Service Package
2 Scope of works 1 (In line with head of cost break ups as
applicable)
3 Whether awarded through ICB/DCB/Departmentally/Deposit
Work
4 No. of bids received
5 Date of Award
6 Date of Start of work
7 Date of Completion of work
8 Value of award 2 including taxes and duties (Rs. Cr.)
9 Firm or With escalation in prices
10 Actual capital expenditure till COD of unit 2 dtd.28.12.14
includind Taxes & Duties ( Rs. Cr.)
11 Taxes & Duties and IEDC
(10) + (11)
12 IDC, FC, FERV & Hedging cost (Projected upto Station CoD)
13 Sub total (10+11+12)
14 Current status as on 31-03-2016
BREAK-UP OF CONSTRUCTION/ SUPPLY/ SERVICE
PACKAGES
NAME OF THE POWER STATION: SSTPP Stage-1(2x600MW)
NAME OF THE GENERATING COMPANY:MPPGCL
Particulars 7 8 9 10 11 12
S&T work from
Bir station to
Inplant
S&T work from
Surgaon Banjari to
Bir station
OHE work from Bir
station to Inplant
OHE work from
Surgaon Banjari
to Bir station
Consultancy
Services to explore
take off point
avoiding engine
reversal
Project
Management
Consultancy for
S&T work from Bir
station to Inplant
DCB Deposit Work Deposit Work Deposit Work DCB DCB
3 -- -- -- 1 1
01.07.13 06.11.12 07.12.11 08.06.12 12.03.10 27.02.12
01.08.13 07.05.13 26.03.12 01.03.13 12.03.10 21.03.12
System
commissioned on
29.06.16. Minor
pending works
under progress.
System
commissioned on
09.02.16. Minor
pending works
under progress.
OHE System Lines
charged by Railways
up to wagaon trippler
on 24.06.14 and
complete yard
charged on 04.03.15
OHE System
charged by
Railways on
04.02.16 September/11 Under Progress
6.35 13.57 11.02 17.68 1.87 0.82
FIRM FIRM FIRM FIRM FIRM FIRM
0.00 13.57 11.02 17.68 1.87 0.35
Incl. in 10 Incl. in 10 Incl. in 10 Incl. in 10 Incl. in 10 Extra
0.00 13.57 11.02 17.68 1.87 0.35
0.00 13.57 11.02 17.68 1.87 0.35
Private Railway siding
1593.10
6527.66
Private Railway siding
F-34
PART-I Form No: TPS-5C
1 Name/No. of Construction /Supply /Service Package
2 Scope of works 1 (In line with head of cost break ups as
applicable)
3 Whether awarded through ICB/DCB/Departmentally/Deposit
Work
4 No. of bids received
5 Date of Award
6 Date of Start of work
7 Date of Completion of work
8 Value of award 2 including taxes and duties (Rs. Cr.)
9 Firm or With escalation in prices
10 Actual capital expenditure till COD of unit 2 dtd.28.12.14
includind Taxes & Duties ( Rs. Cr.)
11 Taxes & Duties and IEDC
(10) + (11)
12 IDC, FC, FERV & Hedging cost (Projected upto Station CoD)
13 Sub total (10+11+12)
14 Current status as on 31-03-2016
BREAK-UP OF CONSTRUCTION/ SUPPLY/ SERVICE
PACKAGES
NAME OF THE POWER STATION: SSTPP Stage-1(2x600MW)
NAME OF THE GENERATING COMPANY:MPPGCL
Particulars 13 14 15 16 17 18
Consultancy services
for obtaining
Environmental
Clearance
Consultancy Services
for Study of Rail
Transportation
system
Project Consultancy
Services
Permanent
Construction
Power Supply
arrangement
Deposit work for
providing 10 MVA
Construction Power
supply
Project
Monitoring
Services
Preparation of
Comprehensive EIA
study report and
assistance for obtaining
Environmental
clearance from MoEF
Preparation of DPR
and Tender
documents for
installation of Private
Railway Siding
Assistance for selection
of EPC/ Non-EPC
Contractors and
providing technical
support during
construction
Construction of
Permanent
Construction
Power Supply
system
Laying of 33 kV line
from Chhegaon-
Makhan to SSTPP site
for providing
uninterupted Power
supply to the project
Monitoring
Progress of
Design,Engg.,Sup
ply,E&TC of the
project
DCB DCB DCB DCB Deposit Work DCB
3 3 3 3 -- 7
21.11.2005 20.10.2006 28.04.2006. 24.09.2009 30.01.2008 24.06.2010
30.11.2005 20.11.2006 09.05.2006 26.10.2009 25.03.2008 25.09.2010
10.09.2008 28.02.2013 under progress 28.10.2015 31.08.2013 03.05.2015
0.13 excluding service
tax0.14 2.87 5.30 9.79 10.48
FIRM ‘FIRM’ FIRM FIRM FIRM FIRM
0.13 0.14 2.73 5.27 9.79 8.09
0.015 0.31 Incl. in 10 Incl. in 10 Incl. in 10
0.14 0.14 3.04 5.27 9.79 8.09
0.14 0.14 3.08 5.20 9.79 8.92
1593.10
6527.66
F-35
PART-I
Form No: TPS-5D
2X600 MW
2
Greenfield
S. No. Variables (Design Operating Range) Values
1 Coal Quality - Calorific Value 3500 Kcal/KG
2 Ash Content 44%
3 Moisture Content 12.00%
4 Boiler Efficiency 87.35%
5 Suspended Particulate Matter 295 microgram/m3
6 Ash Utilization 100% within 5 years
7 Boiler Configuration Controlled circulation with rifled tubing, radiant
reheat, dry bottom, top supported
8 Turbine Heat Rate 1945
9 CW Temperature 33°C
10 Water Source Indira Sagar Reserviour
11 Distance of Water Source 7 KM
12 Clarifier HRSCC
13 Mode of Unloading Oil Through unloading pumps
14 Coal Unholding Mechanism manual unloading at track hopper , mechanized
unloading through Wagon Trippler
15 Type of Fly Ash Disposal and Distance Wet and Dry mode
16 Type of Bottom Ash Disposal and Distance Wet mode, 4-5 Km
17 Type of Soil Black cotton soil
18 Foundation Type (Chimney) RCC
19 Water Table pH-7.1, Turbidity (NTU) -8.0
20 Seismic and Wind Zone Stable Peninsular shield of India (Horst block)/ 8.7
Kmph (moderate)
21 Condensate Cooling Method NDCT
22 Desalination/ RO Plant NIL
23 Evacuation Voltage Level 220 KV/ 400 KV
24 Type of Coal (Domestic / Imported) (Domestic)
Values
U#1- 11-06-12 U#2- 11-10-12
Document Attached as Appendix-1
3.5 Cr. for every 0.1% shortfall of Boiler Efficiency.
/ 1.5 Lakh for every KW shortfall in Gross power
output)
MPB- Firm/ BoP- Escalation
India
Yes/ No
No
No
Yes
No
65 Km / 150 Km.
(Petitioner)
MGR
Railway Siding
Unloading Equipment at Jetty
Rolling Stock/ Locomotive
Length of Transmission Line till Tie Point (in km)
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
DETAILS OF VARIABLES, PARAMETERS,
OPTIONAL PACKAGE etc. FOR NEW
PROJECT
Name of the Petitioner: Mp P Power Generating Company Ltd
Name of the Generating Station: SSTPP Stage-1(2x600 MW)
Desalianation Plant/ RO Plant
Unit Size
Number of Units
Greenfield/ Extension
Parameter/ Variables
Completion Schedule
Terms of Payment
Performance Guarantee Liability
Basis of Price (Firm/ Escalation-Linked)
Equipment Supplier (Country of Origin)
Optional Packages
F-36
1 2 4
Loan No.20701001 Rs. Crs Rs. Crs
Equity
Foreign
Domestic Rs. Crs Rs. Crs
Debt : Equity Ratio 80 20 81 19
1521.20 1350.00
( Petitioner)
Date of Commerical Operation of the Station : 28-12-14
Financial Package as Approved Financial Package as on CoD of station
6238.00 5700.66
3 5
Currency and Amount3
Currency and Amount3
Particulars
Project cost as on COD : Rs.7820 Crs.
Name of the Petitioner: MP Power Generating Company Ltd. Jabalpur
Name of the Generating Station: 2x600 MW Shree Singaji Thermal Power Project, Khandwa
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Form No: TPS-6FINANCIAL PACKAGE UPTO CoD
F-37
Name of the Petitioner: MP Power Generating Company Ltd. Jabalpur
Name of the Generating Station: SSTPP Stage-1(2x600MW)
Particulars Loan No.10701001 Remark
1 2 4
Source of Loan1 PFC
Currency2 Rs.
Amount of Loan sanctioned 6238.00
Amount of Gross Loan drawn upto Stn. COD 28.12.2014 5700.66
Interest Type Floating
Fixed Interest Rate (%), if applicable 11.25 to 13
Base Rate, if Floating Interest7
Margin, if Floating Interest
Are there any Caps/ Floor No
If above is yes, specify caps/ floor
Moratorium Period
Moratorium effective from 15.07.2016
Repayment Period 15 years
Repayment effective from -
Repayment Frequency Quarterly
Repayment Instalment 60
Base Exchange Rate --
Are foreign currency loan hedged --
If above is yes, specify details
Petitioner
DETAILS OF PROJECT SPECIFIC LOANS
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Form No: TPS-7
F-38
SSTPP Stage-I
FY14 FY 16
Unit # 1 Unit # 2 (Unit # 1 & 2)
W.E.F.
01.04.2014 to
31.03.2015
W.E.F. COD of
Unit # 2
28.12.2014 to
31.03.2015
W.E.F.
01.04.2015 to
31.03.2016
1 Opening Gross Block 3152.10 3448.51 3621.49 7069.99 7206.71
2 Asset Additions 296.41 111.52 41.51 153.03 227.85
3 Deletions/Adjustment 0.00 -16.31 0.00 -16.31 59.11
4 Closing Gross Block 3448.51 3543.72 3662.99 7206.71 7493.66
5 Average Gross Block 3300.31 3496.11 3642.24 7138.35 7350.19
6 Wtd. Avg. Rate of depreciation 5.10% 5.07%
7 Amount of Depreciation for the year 168.48 173.31 180.55 353.86 372.88
8 Days in operation 59 365 94 366
9 Depreciation for days in operation 27.23 173.31 46.50 219.81 372.88
Wtg. Av. Rate of
Depreciation
(%)
1 FY 2013-14 5.10%
2 FY 2014-15 4.96%
3 FY 2015- 16 5.07%
.
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Form No: TPS-12
in Rs. Crores
Statement of Depreciation (Thermal) FY-14 to FY 16
(Petitioner)
Particulars FY 15
W.E.F. COD of
Unit # 1
(01.02.2014 to
31.03.2014)
Total
4.96%
Finacial Year
F-39
Rs.Crores
Sl. no. Particulars 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16
1 2 3 4 5 6 7 8 9 10
1 Gross loan - Opening 0.00 103.00 467.39 1345.31 2878.75 4026.37 5204.45 5930.03
2Cumulative repayments of Loans upto
previous year0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Net loan - Opening 0.00 103.00 467.39 1345.31 2878.75 4026.37 5204.45 5930.03
4 Add: Drawal(s) during the Year 103.00 364.39 877.92 1533.43 1147.62 1178.09 725.58 123.42
5Less: Repayment (s) of Loans during the
year0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Net loan - Closing 103.00 467.39 1345.31 2878.75 4026.37 5204.45 5930.03 6053.45
7 Interest on loan 190.69 1750.70 8741.16 24414.10 45965.17 60359.28 72829.53 76464.63
8 Weighted average Rate of Interest 12.75 12.46 11.56 12.24 12.76 12.96 12.97 12.75
(Petitioner)
Calculation of Weighted Average Rate of Interest (%) on Actual Loans (SSTPP Stage-I)
Thermal
FORM TPS-13
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
Loan-1 , 2 & 3 (Loan No. 20701001)
F-40
FORM TPS-13A
FY14 FY 16
Unit # 1 Unit # 2 (Unit # 1 & 2)
W.E.F.
01.04.2014 to
31.03.2015
W.E.F. COD
of Unit # 2
28.12.2014 to
31.03.2015
W.E.F.
01.04.2015 to
31.03.2016
1 Normative loan - Opening 2608.34 2647.89 2777.43 5425.32 5682.99
2 Add: Drawal(s) during the Year 66.79 362.79 114.69 477.47 123.42
3Less: Repayment (s) of Normative Loans
during the year(depreciation)27.23 173.31 46.50 219.81 372.88
4 Net Normative loan – Closing 2647.89 2837.37 2845.62 5682.99 5433.52
5 Average Normative Loan 2628.11 2742.63 2811.52 5554.15 5558.26
6Weighted Avg. Rate of Interest on Actual
Loans12.96% 12.75%
7 Interest on Normative Loan for the year 340.60 355.72 364.65 720.37 708.68
8 Days in operation 59 365 94 366
9Interest on Normative Loan, for the
period of operation during the Year 55.06 355.72 93.91 449.63 708.68
Thermal
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
12.97%
(Petitioner)
Interest on Normative Loan FY 14 to FY 16 (SSTPP Stage-1)
In Rs. Crores
Particulars
FY 15
W.E.F. CoD of
Unit # 1
(01.02.2014 to
31.03.2014)
Total
F-41
1 FY 14 142.26 3.89 15.54 271.23 6.48 439.40 13.50% 59.32
2 FY 15 460.55 6.45 33.55 737.04 13.98 1251.57 13.50% 168.96
3 FY 16 401.70 3.81 36.22 676.30 15.09 1133.11 13.35% 151.27
(Petitioner)
Form No: TPS-13BCalculation of Interest on Working Capital - (FY 14 to FY 16) for SSTPP Stage-1
Madhya Pradesh Power Generating Co. Ltd, Jabalpur
O&M expense
1 month
Total Working
Capital
in Rs. Crores
Rate of
Interest
Interest on WC
in Rs. Crores
per annumSl
NoFinancial Year
Coal Cost
2 Months
Oil Cost
2 months
Maintenance
Spare
20% of O&M
expenses
Receivable
2 months
F-42
M.P. POWER GENERATING CO. LTD.
Name of Power Station: Shree Singaji TPP (2X600 MW), Stage-I, IN KHANDWA DIST., MP
Date of Commercial Operation Unit #1:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 103.00
Draw down amount of Unit-1 (as
on CoD of Unit-1)
Draw down amount of Unit-2 (as
on CoD of Unit-1)
IDC/Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.91
Financing charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total (IDC+Financing Charges) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.91
IDC of Unit-1
(as on CoD of Unit-1)
IDC of Unit-2
(as on CoD of Unit-1)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn 0.00 10.24 0.00 29.76 0.00 0.00 0.00 95.19 0.00 0.00 0.00 64.61
Equity drawls of Unit-1 (as on
CoD of Unit-1)
Equity drawls of Unit-2 (as on
CoD of Unit-1)
0.00 10.24 0.00 29.76 0.00 0.00 0.00 95.19 0.00 0.00 0.00 64.61Total equity deployed
Note The IDC, Loan & Equity Drawls has been proportionately apportioned based on the ratio of
work completion of Unit-1&2 as on date of CoD of Unit-1.
1
Particulars
Form-14(A)
01.02.2014
Year 2006-07 2007-08 2008-09
F-43
M.P. POWER GENERATING CO. LTD.
Name of Power Station:
Date of Commercial Operation Unit #1:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount
Draw down amount of Unit-1 (as
on CoD of Unit-1)
Draw down amount of Unit-2 (as
on CoD of Unit-1)
IDC/Interest
Financing charges
Total (IDC+Financing Charges)
IDC of Unit-1
(as on CoD of Unit-1)
IDC of Unit-2
(as on CoD of Unit-1)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn
Equity drawls of Unit-1 (as on
CoD of Unit-1)
Equity drawls of Unit-2 (as on
CoD of Unit-1)
Total equity deployed
1
Particulars
Year
0.51 0.49
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
0.00 0.00 52.78 311.61 81.52 65.38 298.69 432.33 183.11 498.81 294.22 557.29
3.27 3.31 3.62 7.30 14.48 16.75 22.56 33.63 39.26 54.52 68.11 82.25
0.00 0.00 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.27 3.31 3.64 7.32 14.48 16.75 22.56 33.63 39.26 54.52 68.11 82.25
0.00 18.67 0.00 37.33 59.51 0.00 59.51 130.02 26.00 38.00 76.10 102.33
0.00 18.67 0.00 37.33 59.51 0.00 59.51 130.02 26.00 38.00 76.10 102.33
Form-14(A)
2009-10 2010-11 2011-12
F-44
M.P. POWER GENERATING CO. LTD.
Name of Power Station:
Date of Commercial Operation Unit #1:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount
Draw down amount of Unit-1 (as
on CoD of Unit-1)
Draw down amount of Unit-2 (as
on CoD of Unit-1)
IDC/Interest
Financing charges
Total (IDC+Financing Charges)
IDC of Unit-1
(as on CoD of Unit-1)
IDC of Unit-2
(as on CoD of Unit-1)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn
Equity drawls of Unit-1 (as on
CoD of Unit-1)
Equity drawls of Unit-2 (as on
CoD of Unit-1)
Total equity deployed
1
Particulars
Year
Q1 Q2 Q3 Q4 Q1 Q2 Q3
Q4
upto 31
Jan
289.79 342.66 270.41 244.76 227.43 320.09 290.95 206.04 5070.88 13357.149
2608.34
2462.54
99.82 110.80 120.97 128.07 135.80 147.37 157.17 30.44 1281.40
0.00 0.00 0.00 0.00 0.01 0.01 0.00 0.00 0.05
99.82 110.80 120.97 128.07 135.81 147.38 157.17 30.44 1281.45
659.15
622.30
75.00 75.00 21.41 191.59 0.00 60.00 100.00 0.00 1270.27
653.40
616.87
75.00 75.00 21.41 191.59 0.00 60.00 100.00 0.00 1270.27
Febto march 14
Petitioner
Form-14(A)
2012-13 2013-14 Total (Up to
CoD)
01.02.2014
F-45
M.P. POWER GENERATING CO. LTD.
Name of Power Station: Shree Singaji TPP (2X600 MW), Stage-I, IN KHANDWA DIST., MP
Date of Commercial Operation Unit # 2:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 103.00
Draw down amount of Unit-1
(as on CoD of Unit-2)
Draw down amount of Unit-2
(as on CoD of Unit-2)
IDC/Interest 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.91
Financing charges 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total (IDC+Financing Charges) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.91
IDC of Unit-1
(as on CoD of Unit-2)
IDC of Unit-2
(as on CoD of Unit-2)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn 0.00 10.24 0.00 29.76 0.00 0.00 0.00 95.19 0.00 0.00 0.00 64.61
Equity drawls of Unit-1 (as on
CoD of Unit-2)
Equity drawls of Unit-2 (as on
CoD of Unit-2)
0.00 10.24 0.00 29.76 0.00 0.00 0.00 95.19 0.00 0.00 0.00 64.61Total equity deployed
Note The IDC, Loan & Equity Drawls has been proportionately apportioned based
on the ratio of work completion of Unit-1&2 as on date of CoD of Unit-1.
1
Particulars
Form-14(B)
28.12.2014
Year 2006-07 2007-08 2008-09
F-46
M.P. POWER GENERATING CO. LTD.
Name of Power Station:
Date of Commercial Operation Unit # 2:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount
Draw down amount of Unit-1
(as on CoD of Unit-2)
Draw down amount of Unit-2
(as on CoD of Unit-2)
IDC/Interest
Financing charges
Total (IDC+Financing Charges)
IDC of Unit-1
(as on CoD of Unit-2)
IDC of Unit-2
(as on CoD of Unit-2)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn
Equity drawls of Unit-1 (as on
CoD of Unit-2)
Equity drawls of Unit-2 (as on
CoD of Unit-2)
Total equity deployed
1
Particulars
Year
0.51 0.49
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
0.00 0.00 52.78 311.61 81.52 65.38 298.69 432.33 183.11 498.81 294.22 557.29
3.27 3.31 3.62 7.30 14.48 16.75 22.56 33.63 39.26 54.52 68.11 82.25
0.00 0.00 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.27 3.31 3.64 7.32 14.48 16.75 22.56 33.63 39.26 54.52 68.11 82.25
0.00 18.67 0.00 37.33 59.51 0.00 59.51 130.02 26.00 38.00 76.10 102.33
0.00 18.67 0.00 37.33 59.51 0.00 59.51 130.02 26.00 38.00 76.10 102.33
2011-12
Form-14(B)
2009-10 2010-11
F-47
M.P. POWER GENERATING CO. LTD.
Name of Power Station:
Date of Commercial Operation Unit # 2:
Draw Down Schedule for Calculation of IDC & Financing Charges (in Rs. Crores)
Indian Loan 1
(PFC Loan No. 20701001)
Draw down amount
Draw down amount of Unit-1
(as on CoD of Unit-2)
Draw down amount of Unit-2
(as on CoD of Unit-2)
IDC/Interest
Financing charges
Total (IDC+Financing Charges)
IDC of Unit-1
(as on CoD of Unit-2)
IDC of Unit-2
(as on CoD of Unit-2)
2 Equity
2 Foreign equity drawn
2 Indian equity drawn
Equity drawls of Unit-1 (as on
CoD of Unit-2)
Equity drawls of Unit-2 (as on
CoD of Unit-2)
Total equity deployed
1
Particulars
Year
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
289.79 342.66 270.41 244.76 227.43 320.09 290.95 339.62 260.84 193.63 41.74 - 5700.66
2923.23
2777.43
99.82 110.80 120.97 128.07 135.80 147.37 157.17 30.44 64.50 85.14 89.13 72.81 1592.97
0.00 0.00 0.00 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.05
99.82 110.80 120.97 128.07 135.81 147.38 157.17 30.44 64.50 85.14 89.13 72.81 1593.03
659.147
933.880
75.00 75.00 21.41 191.59 0.00 60.00 100.00 79.73 0.00 0.00 0.00 0.00 1350.00
693.26
656.74
75.00 75.00 21.41 191.59 0.00 60.00 100.00 79.73 0.00 0.00 0.00 0.00 1350.00
Petitioner
2012-13 2013-14 2014-15 Total (Up
to COD)
28.02.14
Form-14(B)
F-48