Machine Shop Practices

download Machine Shop Practices

of 104

Transcript of Machine Shop Practices

  • 8/11/2019 Machine Shop Practices

    1/104

    SB

    MACHINE SHOP

    PRACTICES

  • 8/11/2019 Machine Shop Practices

    2/104

    SB

    IN CASE OF DOUBT

    GET CLARIFICATIONS

    NEVER ASSUME

  • 8/11/2019 Machine Shop Practices

    3/104

    SB

    PRE-PLANNING 1. STUDY SCOPE

    ORDER FOR SCOPE OF OPERATIONS TECHNOLOGICAL PROCESS

    DRAWINGS QUALITY PLAN REQUIREMENTS

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVERASSUME

  • 8/11/2019 Machine Shop Practices

    4/104

    SB

    PRE-PLANNING 2. STUDY DOCUMENTS

    WHAT IS THE MATERIAL ? IS CORRECT MATERIAL SUPPLIED ?

    IDENTIFICATIONS ATTESTATIONS (IF REQUIRED)EVIDENCE OF COMPLETION OF ALL

    PREVIOUS OPERATIONS(FABRICATIONS , HEAT TREATMENTETC) GET CLARIFICATIONS IN CASE OF DOUBTS NEVER

    ASSUME

  • 8/11/2019 Machine Shop Practices

    5/104

    SB

    PRE-PLANNING 3. PLAN PRODUCTION PROCESS

    WHAT ARE YOUR F ACI L I TI ES ? ARE THEY IN LINE WITH TECH

    PROCESS ? MODIFY YOUR PROCESS TO SUIT YOURFA C I L I T I E S IF POSSIBLE

    IDENTIFY THE ATTESTATIONSTRANSFER POINTS(IF REQUIRED)

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVER ASSUME

  • 8/11/2019 Machine Shop Practices

    6/104

    SB

    PRE-PLANNING 4. PLAN SPECIAL REQUIREMENTS

    IDENTIFY AND LIST THE REQUIREMENTSOF

    JIGS FIXTURES SPECIAL TOOLS

    GAUGES SPECIAL INSTRUMENTS etc

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVER ASSUME

  • 8/11/2019 Machine Shop Practices

    7/104SB

    PRE-PLANNING 5. PLAN INSPECTION RE-STUDY THE DRAWING AND PROCESS

    IN DETAIL

    FORMAT THE I N-PROCESS I NSPECTI ON DOCUMENT (DIR) BASED ON THEDIMENSIONS AT EACH STAGE OF THEMANUFACURING SEQUENCE .

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVER

    ASSUME

  • 8/11/2019 Machine Shop Practices

    8/104SB

    INPROCESS INSPECTION REPORTPage 1 of 3

    VENDOR CODE : Record No. Date :

    Product and Project Pulvrisers / Record No

    Work Order No Part no & Name JOURNAL HEAD

    Drawing No 061000001690208 Identification

    SRV/FGDC No

    SNO DESCRIPTION DETAILS SIGN OF INSP

    1 NDT Results

    2 Hydrostatic Test Results

    3 Other Tests (if any)

    Actual ValuesSNO Characteristics as per Drg/Specificn

    1 2 3 4

    IDENTIFICATIONSRemarks

    1 353-0.1/-0.3 (SEC AA

    (2)

    2 DEPTH 133 TOT HT 724

    4 495.25 -0.05 (SEC AA)

    (2)

    5 CONC TAPER BORE 0.13

  • 8/11/2019 Machine Shop Practices

    9/104SB

    PRE-PLANNING 5. PLAN INSPECTION

    IDENTIFY THE MEASURING INSTRUMENTSTO BE USED FOR EACH DIMENSION

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVERASSUME

  • 8/11/2019 Machine Shop Practices

    10/104SB

    PRE-PLANNING 6. CRITICAL DIMENSIONS

    CLEARLY IDENTIFY CRITICALDIMENSIONS ON THE INSP DOCUMENT.

    IDENTIFY AND MARK INSPECTIONCHECK POINTS AND AGENCY ON THEDOCUMENT ( INTERNAL/ BHEL/ 3rd

    PARTY) BASED ON QUALITY PLAN / TECHPROCESS

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVERASSUME

    INPROCESS INSPECTION REPORT

  • 8/11/2019 Machine Shop Practices

    11/104SB

    INPROCESS INSPECTION REPORTPage 1 of 3

    VENDOR CODE : Record No. Date :

    Product and Project Pulvrisers / Record No

    Work Order No Part no & Name JOURNAL HEAD

    Drawing No 061000001690208 Identification

    SRV/FGDC No

    SNO DESCRIPTION DETAILS SIGN OF INSP

    1 NDT Results

    2 Hydrostatic Test Results

    3 Other Tests (if any)

    Actual ValuesSNO Characteristics as per Drg/Specificn

    1 2 3 4

    IDENTIFICATIONSRemarks

    1 353-0.1/-0.3 (SEC AA MICR

    (2)

    2 DEPTH 13 DEP GG

    3 TOT HT 724 VERN.

    4 495.25 -0.05 (SEC AA) MICR

    (2)

    5 CONC TAPER BORE 0.13

    6 PERP FACE : A 0.08

    BHEL ON M/C

  • 8/11/2019 Machine Shop Practices

    12/104

    SB

    PRE-PLANNING 7. GEOMETRICAL TOLERANCES

    IDENTIFY ALL THE GEOMETRICALTOLERANCES ON THE DRAWING. (eg

    etc IDENTIFY THE REFERENCE DIMENSION

    FOR THESE TOLERANCES

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVER

    ASSUME

  • 8/11/2019 Machine Shop Practices

    13/104

    SB

    PRE-PLANNING 8. PLANNING FOR GEOM. TOLS

    FORMALISE THE GEOMETRICALTOLERANCES

    HOW TO IN-BUILT IN THE PROCESS

    HOW TO INSPECT

    INSPECTION ON MACHINE / OFF MACHINE

    GET CLARIFICATIONS IN CASE OF DOUBTS NEVERASSUME

  • 8/11/2019 Machine Shop Practices

    14/104

    SB

    EXECUTION 9. DISCUSSION

    DISCUSS WITH THE OPERATOR(S) INDETAIL ABOUT ALL THE EARLIER

    STAGESMANUFACTURING PROCESS

    INSPECT HOLD POINTS

    RECORDING FORMAT

    ATTESTATION REQUIREMENTS etc

    MODIFY THE EARLIER STEPS IF NECESSARY.

  • 8/11/2019 Machine Shop Practices

    15/104

    SB

    EXECUTION 10. JOB MARKINGMARK THE JOB FOR MACHINING ALLOWANCES

    START WITH REFERENCE DIMENSION ASBASE.

    CHECK FOR ALLOWANCES ON ALL OTHERDIMENSIONS WITH RESP TO REF DIMENSION.

    RE-DISTRIBUTE FOR EQUAL ALLOWANCE ONALL MACHINED SURFACES.

  • 8/11/2019 Machine Shop Practices

    16/104

    SB

    EXECUTION 10. JOB MARKINGENSURE THAT

    WALL THICK-NESSES.

    FLANGE THICK-NESSES. CRITICAL BUT UN-MACHINED SURFACES

    ARE MAINTAINED.

  • 8/11/2019 Machine Shop Practices

    17/104

    SB

    EXAMPLEA SEGMENTAL COMPONENT HAS 90DEGREE SPAN.

  • 8/11/2019 Machine Shop Practices

    18/104

    SB

    FOUR SUCH SEGMENTS ARE ASSEMBLEDTOGETHER TO MAKE A RING.

    - THE PARTING PLANES ARE MILLED, - PARTING PLANE HOLES ARE DRILLED ,- FOUR HALVES ARE JOINED FOR FINAL

    BORING.

  • 8/11/2019 Machine Shop Practices

    19/104

    SB

  • 8/11/2019 Machine Shop Practices

    20/104

    SB

    AT THE TIME OF BORING, IT WAS FOUNDTHAT ONE SEGMENT IS NOT MATCHING

    WITH OTHER THREE : THERE IS NOMACHINING ALLOWANCE ON OUTSIDEDIAMETER

  • 8/11/2019 Machine Shop Practices

    21/104

    SB

    IF THE PROBLEM IS ANALYSED IT CANBE EASILY SEEN THAT THE COMPONENTCOULD HAVE BEEN SALVAGED HAD ITBEEN MARKED EARLIER BY TAKING THECENTER OF THE DIAMETERS ASREFERENCE

  • 8/11/2019 Machine Shop Practices

    22/104

    SB

    THE COMPONENT SHOULD HAVE BEEN MARKEDWITH REFERENCE TO THE DIAMETERS AND THEMACHINING ALLOWANCES ON THE FLANGESSHOULD HAVE BEEN FIXED BASED ON THIS

  • 8/11/2019 Machine Shop Practices

    23/104

  • 8/11/2019 Machine Shop Practices

    24/104

    SB

    JOB SETTINGPROVIDE SUPPORTS/SHIMS BELOW EACH

    CLAMP.NECESSARY CARE SHOULD BE TAKEN

    WHILE CLAMPING SUCH THAT THE JOB

    STRESS DUE TO CLAMPING IS MINIMUM .IN CASE COOLANT IS USED DURING

    MACHINING CHECK THE COOLANT TO

    BE USED FOR THE MATERIAL.ENSURE THE COOLANT CONDITION

  • 8/11/2019 Machine Shop Practices

    25/104

    SB

    EXECUTION 12. MACHININGFIRST ROUGH MACHINE THE MAIN

    REFERENCE SURFACE.ALL OTHER PARAMETERS RELATED TO

    THIS PLANE MUST WITH REFERENCE TOTHIS PLANE.

    ROUGH MACHINE ALL OTHER SURFACESWITH RESPECT TO THIS PLANE

    PREFERABLE ALLOWANCE AT THISSTAGE IS APPROXIMATELY 3mm.

  • 8/11/2019 Machine Shop Practices

    26/104

    SB

    EXECUTION 12.1. ROUGH MACHININGNECESSARY CARE MUST BE TAKEN

    WHILE ROUGH MACHINING TO :

    A) AVOID OVER-LOADING THE MACHINE B) AVOID OVER STRESSING THE JOB: THIS

    MAY GIVE RESULT IN BURNING/

    DISTORTION. C) LEAVE SUFFICIENT ALLOWANCE FOR

    FINISH MACHINING

  • 8/11/2019 Machine Shop Practices

    27/104

    SB

    MACHINING STRESSESANY MACHINING CREATES

    MACHINING STRESSES IN THE JOB

    MORE DEPTH OF CUT / FEED / SPEED

    MEANS MORE STRESS THESE MACHINING STRESS DISTORT

    THE JOB OVER TIME : WHICH MAY

    TAKE FROM A FEW HOURS TOMONTHS OR MAY BE YEARS

  • 8/11/2019 Machine Shop Practices

    28/104

    SB

    MACHINING STRESSESTHE BEST WAY TO REMOVE THESE

    STRESSES IS TO STRESS RELIEVEAFTER ROUGH MACHINING

    THIS IS MANDATORY FOR CRITICALCOMPONENTS

    HOWEVER A FEW PRE-CAUTIONS

    MAY KEEP THESE STRESSES WITHINMANAGEABLE LIMITS FOR MOST OFTHE JOBS

  • 8/11/2019 Machine Shop Practices

    29/104

    SB

    MACHINING STRESSESA) ENSURE THAT THE JOB IS NOT

    DISTORTED DURING CLAMPINGB) DO NOT TAKE HEAVY CUT DURING

    ROUGH MACHINING

    C) COMPLETE THE ROUGH M/Cng ANDALLOW THE JOB TO REST BY REMOVINGTHE CLAMPS, AND ALLOWING THE JOBTO STAND FOR A FEW HOURS.

    D) A PRACTICAL WAY TO DO THIS WILLBE TO ROUGH MACHINE ALL THE JOBSAND THEN ONE BY ONE FINISH MACHINE

  • 8/11/2019 Machine Shop Practices

    30/104

    SB

    12.2 FINISH MACHINING1. ASSESS

    THE CONDITION OF THE MACHINE. THE ACCURACY IT CAN ACHIEVE

    THIS HELPS IN SCHEDULING (PLANNING

    THE JOB FOR A MACHINE)

    2. SELECT THE RIGHT TOOL FOR THE

    MATERIAL OF THE COMPONENT

  • 8/11/2019 Machine Shop Practices

    31/104

    SB

    FINISH MACHINING3. ASSESS THE FEED/ SPEED/ DEPTH OF

    CUT PARAMETERS FOR THE MATERIALTO GET THE REQUIRED FINISH. THISCAN BE FOUND DURING ROUGHINSTAGE BY TAKING A TRIAL FINISHINGCUT WITH FINISHING TOOL IF NO DATAIS AVAILABLE.

    KEEP A RECORD OF M/C ACCURACIESALL PARAMETERS etc. THIS WILL

    HELP YOU IN FUTURE JOBS.

  • 8/11/2019 Machine Shop Practices

    32/104

    SB

    FINISH MACHINING1. START BY MACHINING THE REFERENCE

    PLANE FIRST2. ALL THE REFERENCE M/C SURFACES

    REQUIRED TO ACHIEVE GEOMETRICAL

    TOLERANCES MUST BE MACHINED WITHREFERENCE TO THIS SURFACE3. ADHERE TO THE DECIDED SEQUENCE

    OF OPERATIONS.

  • 8/11/2019 Machine Shop Practices

    33/104

    SB

    FINISH MACHINING4. DO NOT CARRY OUT MEASUREMENTS

    WHEN JOB IS HOT OR STRESSED. ALLOWTHE JOB TO COOL DOWN. ENSURE THATTHE JOBS, CLAMPS, ETC ARE NOT OVERSTRESSING THE COMPONENT(EXTREMELY CRITICAL FOR THINWALLED COMPONENTS )

  • 8/11/2019 Machine Shop Practices

    34/104

    SB

    UNDERSTANDING GEOMETRICAL TOLERANCES

  • 8/11/2019 Machine Shop Practices

    35/104

    SB

    O.O2 A

  • 8/11/2019 Machine Shop Practices

    36/104

    SB

    O.O2 A

    TOLERANCE VALUE

    TOLERANCE CHARACTERISTIC DATUM

  • 8/11/2019 Machine Shop Practices

    37/104

    TOLERANCE OF FORM

  • 8/11/2019 Machine Shop Practices

    38/104

    SB

    TOLERANCE OF FORM

    FEATURE CHARACTERISTIC

    SYMBOL ASME Y14.5M

    Ref.

    STRAIGHTNESS 4.4.1

    FLATNESS 6.4.2

    CIRCULARITY (ROUNDNESS )

    6.4.3

    CYLINDRICTY 6.4.4

    TOLERANCE OF PROFILE

  • 8/11/2019 Machine Shop Practices

    39/104

    SB

    TOLERANCE OF PROFILE

    FEATURE CHARACTERISTIC SYMBOLASMEY14.5M Ref.

    PROFILE OF LINE

    6.5.2(b)

    PROFILE OF SURFACE 6.5.2(a)

    TOLERANCE OF ORIENTATION

  • 8/11/2019 Machine Shop Practices

    40/104

    SB

    TOLERANCE OF ORIENTATION

    FEATURE CHARACTERISTIC SYMBOLASMEY14.5M Ref.

    ANGULARITY 6.6.2

    PERPENDICULARITY

    6.6.4

    PARALLEISM // 6.6.3

    TOLERANCE OF LOCATION

  • 8/11/2019 Machine Shop Practices

    41/104

    SB

    TOLERANCE OF LOCATION

    FEATURE CHARACTERISTIC SYMBOL

    ASME

    Y14.5M Ref.

    POSITION 5.2

    CONCENTRICTY 5.11.3

    SYMMETRY 5.13

    TOLERANCE OF RUN OUT

  • 8/11/2019 Machine Shop Practices

    42/104

    SB

    TOLERANCE OF RUN-OUT

    FEATURE CHARACTERISTIC SYMBOLASME Y14.5M Ref.

    CIRCULAR RUNOUT 6.7.1.2.1

    TOTAL RUNOUT 6.7.1.2.2

  • 8/11/2019 Machine Shop Practices

    43/104

    SB

    SPECIAL MACHINING

    ACTIVITIES

    1. REFERENCE CUT

  • 8/11/2019 Machine Shop Practices

    44/104

    SB

    REFERENCE MACHINING

    IF THE JOB IS TO BE MACHINED FROMMORE THAN ONE SIDE , (ie JOB TO BEUNCLAMPED AND RE-CLAMPED AT ADIFFERENT POSITION), eg MACHININGON VERTICAL BORING ON 2 FACES

  • 8/11/2019 Machine Shop Practices

    45/104

    SB

    REFERENCE : VERTICAL BORING

    IT IS NECESSARY TO HAVE A FACE ASWELL AS MINIMUM ONE SETTINGDIAMETER (IDEAL 2 DIAS) REFERENCE

    FOR RE-ALIGNMENT PURPOSE.FOR VERTICAL BORING OPERATIONS,

    REFERENCE DIMENSIONS MAY BE

    A) SEATING FACE ON BEDB) REFERENCE DIAMETER FOR DIALLINGC) REFERENCE FACE FOR DIALLING

  • 8/11/2019 Machine Shop Practices

    46/104

    SB

    REFERENCE : VERTICAL BORING

    REFERENCE VERTICAL BORING

  • 8/11/2019 Machine Shop Practices

    47/104

    SB

    REFERENCE : VERTICAL BORING(PREFERABLE)

  • 8/11/2019 Machine Shop Practices

    48/104

    SB

    REFERENCE : CENTER LATHES

    FOR CENTER LATHES ALMOST ALWAYSTHE SETTING IS BY TWO SETTINGDIAMETER REFERENCE FOR RE-ALIGNMENT PURPOSE.

  • 8/11/2019 Machine Shop Practices

    49/104

    SB

    REFERENCE MACHINING

    FOR HORIZONTAL BORING OPERATIONS,THE NUMBER OF FACTORS AND HENCENUMBER OF REFERENCE AXIS BECOMESMUCH HIGHER

    A JOB LOOSENED AND RE-TIGHETENEDCAN BE DISTURBED IN 3 AXIS (X,Y & Z)

  • 8/11/2019 Machine Shop Practices

    50/104

    SB

    REF MACHINING : HORIZ BORING

    CONSIDER A PIPE UNDER MACHINING.THIS CAN BE RE-CLAMPED DISTURBED IN 3

    AXIS AS SHOWN.

  • 8/11/2019 Machine Shop Practices

    51/104

    SB

    IN ADDITION IT CAN BE DISTURBED IN ATLEAST TWO ANGLES .

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    52/104

    SB

    TO COMPLICATE THE MATTER FURTHER,THE MACHINE POSITION ITSELF CAN BEDISTURBED WITH REFERENCE TO JOB.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    53/104

    SB

    ANOTHER PROBLEM USUALLY FACEDWITH HORIZONTAL BORING IS THESPINDLE SAG AS IT IS MOVED OUT.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    54/104

    SB

    ONE MAY END UP WITH THE SHAPE OF ASTRAIGHT BORE AS SHOWN.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    55/104

    SB

    ONE OF THE WAY TO OVERCOME THIS SAGIS BY BED MOVEMENT.

    THE SPINDLE IS KEPT STATIONARY THEMACHINE BED IS MOVED FORWARD/BACKWARD.( PROVIDED TABLE FEEDFACILITY IS AVAILABLE IN THE M/C)

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    56/104

    SB

    HOWEVER IT IS NECESSARY THAT FORTHIS PURPOSE, THE MOVEMENT AXIS OFTHE BED MUST BE EXACTLY PARALLELTO THE MACHINE AXIS

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    57/104

    SB

    OTHER WISE THE SHAPE OF THE BORESMAY BE AS SHOWN

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    58/104

    SB

    TO OVERCOME THIS THE REFERENCE

    MACHINING IS CARRIED OUT.ALL THE ERRORS WHETHER BECAUSE OF

    POSITIONING OR ANGLE CAN BE

    DIVIDED INTO 5 GROUPS

    REF MACHINING : HORIZ BORING

    REF MACHINING HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    59/104

    SB

    A) X AXIS POSITION

    B) Y AXIS POSITIONC) Z AXIS POSITION

    D) ANGLE IN Y-Z PLANE

    E) ANGLE IN X-Z PLANE

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    60/104

    SB

    IF THE JOB IS SET IN 2 PERPENDICULAR DIRECTION AND THE X, Y AND ZPOSITIONS ARE FIXED WITH RESPECT TOANY FIXED PLANES, THE JOB AFTERDISTURBANCE (DUE TO JOB ROTATION,JOB RESETTING) ETC CAN BE SET BACKTO ORIGINAL POSITION.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    61/104

    SB

    THE ONLY CARE TO BE TAKEN

    HERE IS THAT THE ANGLESETTING (BY DIALLING) MUST BEDONE IN THE SAME WAY AS THE

    ACTUAL MACHINING :

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    62/104

    SB

    A) IF ACTUAL MACHINING IS BY TABLE

    MOVEMENT : SETTING DIALLING MUSTBE BY TABLE MOVEMENT .

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    63/104

    SB

    B) IF ACTUAL MACHINING IS BY SPINDLE

    MOVEMENT : SETTING DIALLING MUSTBE BY SPINDLE MOVEMENT.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    64/104

    SB

    C) IF ACTUAL MACHINING IS BY RAM

    MOVEMENT : SETTING DIALLING MUSTBE BY RAM MOVEMENT.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    65/104

    SB

    THE POSITIONAL REFERENCE SHOULDBE TAKEN FROM AN UN-DISTURBEDPOINT.

    THUS IF A BED IS ROTATED, THEHEIGHT FROM BED WILL NOT GIVEPOSITIONAL ACCURACY UNLESS THEGEOMETRIC ACCURACY OF THE BEDIS KNOWN AND ADJUSTED.

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    66/104

    SB

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    67/104

    SB

    THE MOST PREFERRED WAY MAY BETO TAKE A CUT ON THE JOB ITSELFIF POSSIBLE

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    68/104

    SB

    DIAL THIS SURFACE AS DISCUSSEDEARLIER ( BED MOVEMENT / RAMMOVEMENT /SPINDLE MOVEMENT )

    REF MACHINING : HORIZ BORING

  • 8/11/2019 Machine Shop Practices

    69/104

    IN SECOND SETTING AGAIN DIAL THE

  • 8/11/2019 Machine Shop Practices

    70/104

    SB

    IN SECOND SETTING AGAIN DIAL THEREFERENCE FACE MACHINE THE

    FEATURE SO THAT THE SAMEDIMENSION X IS ACHIEVED ( AFTERCORRECTING FOR THE

    DIMENSIONAL DIFFERENCES Y1 &Y2)

    X

    IN SECOND SETTING AGAIN DIAL THE

  • 8/11/2019 Machine Shop Practices

    71/104

    SB

    IN SECOND SETTING AGAIN DIAL THEREFERENCE FACE

    MACHINE THE FEATURE SO THAT THE

  • 8/11/2019 Machine Shop Practices

    72/104

    SB

    MACHINE THE FEATURE SO THAT THESAME DIMENSION X IS ACHIEVED (

    AFTER CORRECTING FOR THEDIMENSIONAL DIFFERENCES Y1 &Y2)

    X X

    Y1

    Y2

    IF THIS REFERENCE CUT IS TAKEN IN

  • 8/11/2019 Machine Shop Practices

    73/104

    SB

    IF THIS REFERENCE CUT IS TAKEN INTWO PERPENDICULAR AXES, THEN

    BY DIALING THESE TWO AXIS ANDMAINTAINING THE DIMENSIONS X,POSITIONAL AND ANGULAR

    POSITIONS ON 2 AXIS CAN BEENSURED INDEPENDENT OF THEMACHINE.

  • 8/11/2019 Machine Shop Practices

    74/104

    SB

  • 8/11/2019 Machine Shop Practices

    75/104

  • 8/11/2019 Machine Shop Practices

    76/104

    SB

    SPECIAL MACHINING

    ACTIVITIES

    2. BLUE MATCHING

    BLUE MATCHING

  • 8/11/2019 Machine Shop Practices

    77/104

    SB

    BLUE MATCHINGIN CASE ANY PARTING PLANE BLUE

    MATCHING IS REQUIRED, IT IS TOBE DONE BY FINISH MACHININGTHE CORERSPONDING SURFACESIMMEDIATELY AFTER ROUGHMACHINING.

    FOR BLUE MATCHING TWO MATINGSURFACES, FIRST BLUE MATCHBOTH INDIVIDUALLY WITH A

    MASTER LEVEL BED

  • 8/11/2019 Machine Shop Practices

    78/104

    SB

    BLUE MATCHING

  • 8/11/2019 Machine Shop Practices

    79/104

    SB

    BLUE MATCHINGENSURE THE CONDITION OF THE

    LEVEL BED BEFORE STARTING THEOPERATION.

    BLUE MUST BE APPLIED ON THE BEDBY A ROLLER, AND A VERY SMALLQUANTITY OF BLUE MUST BESPREAD EVENLY

    ALTERNATELY A CLEAN CLOTH MAYBE USED TO SPREAD THE BLUE.

    BLUE MATCHING

  • 8/11/2019 Machine Shop Practices

    80/104

    SB

    BLUE MATCHINGAFTER BOTH THE SURFACES ARE

    INDIVIDUALLY MATCHED, MATCHTHE SURFACES WITH EACH OTHER.

    APPLY MINIMUM QUANTITY OF BLUEON ONE SURFACE

    MOVEMENT OF ONE SURFACE

    AGAINST SECOND MUST BELIMITED TO APPROXIMATELY 10-15mm ONLY.

  • 8/11/2019 Machine Shop Practices

    81/104

    SB

    BLUE MATCHING

  • 8/11/2019 Machine Shop Practices

    82/104

    SB

    BLUE MATCHINGCHECK THE GAP BETWEEN

    SURFACES WITH A FEELER 0.02 TO0.03 mm THICK.

    REMOVE THE COMPONENTS ANDINSPECT BOTH THE SURFACES.

    IN THE CLEAN SURFACE OBSERVE

    BLUE MARK,IN THE BLUE SURFACE OBSERVE

    FOR ANY SHINE/ SCRATCH

    BLUE MATCHING

  • 8/11/2019 Machine Shop Practices

    83/104

    SB

    BLUE MATCHINGCONTINUE BLUE MATCHING BY SCRAPING

    TILL A) % CONTACT IS AS PER REQUIREMENT B) FEELER DOES NOT ENTER THE SURFACE

    IN FREE CONDITION (WITHOUT BOLT)C) NO ABNORMAL SCRATCH MARKS ON

    SURFACES

    D) THE AREAS WITHOUT BLUE ARESCATTERED AND DO NOT CREATE ALEAKAGE PATH ACROSS

  • 8/11/2019 Machine Shop Practices

    84/104

    SB

  • 8/11/2019 Machine Shop Practices

    85/104

    SB

    SPECIAL MACHININGACTIVITIES

    3. MACHINING HALF DIAMETERS

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    86/104

    SB

    HALF DIA MACHININGVERY OFTEN COMPONENTS ARE

    MACHINED IN 2 HALVES.EACH OF THE HALF SEGMENT OF

    HAS TO HAVE HALF OF THE BORE

    ie THE BORE AXIS SHOULD PASSTHROUGH THE PARTING PLANE

  • 8/11/2019 Machine Shop Practices

    87/104

    SB

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    88/104

    SB

    HALF DIA MACHININGTHERE MAY BE SEVERAL METHODS

    AVAILABLE TO MEET THIS TYPE OFREQUIREMENTS.

    HALF DIA MACHINING VERT BORING

  • 8/11/2019 Machine Shop Practices

    89/104

    SB

    HALF DIA MACHINING VERT BORING

    MOST CRUDE METHOD IS TO DIAL

    THE PARTING PLANE.

    THE ALIGNMENT CHECK IS VISUALAND ACCURACY IS LOW

    HALF DIA MACHINING VERT BORING

  • 8/11/2019 Machine Shop Practices

    90/104

    SB

    SECOND METHOD IS TO MACHINE

    HALF BORE IN ONE OF THE HALVES.

    MEASURE DIMENSIONS X & YCALCULATE HALF BORE OFFSET AS

    = Y - X/2 ON VERTICAL BORING WHILEDIALING GET THIS VALUE.

    X

    Y

    HALF DIA MACHINING VERT BORING

  • 8/11/2019 Machine Shop Practices

    91/104

    SB

    FOR EXAMPLE, IF

    X= 300.00 Y = 150.20Y - X/2 = 150.20 - 300/2 = 0.20

    X

    Y

    HALF DIA MACHINING VERT BORING

  • 8/11/2019 Machine Shop Practices

    92/104

    SB

    FOR EXAMPLE, IF

    X= 300.00 Y = 150.20Y - X/2 = 150.20 - 300/2 = 0.20

    0 0+0.20

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    93/104

    SB

    HALF DIA MACHININGADJUST THE JOB ON TABLE TILL

    THIS DIAL READING PATTERN ISACHIEVED.

  • 8/11/2019 Machine Shop Practices

    94/104

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    95/104

    SB

    HALF DIA MACHININGSET THE JOB APPROXIMATELY (BY

    TRACING THE PARTING PLANE ASPER METHOD-1)

    MEASURE THE DIAMETER ANDDIMENSION Y

    D

    Y

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    96/104

    SB

    IF THE DIMENSION

    Y = X - D/2THE SETTING IS OK

    ELSE ADJUST THE JOB TILL THEVALUE IS ACHIEVED

    D

    YX

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    97/104

    SB

    IF THE CENTERING IS TO BE DONE

    ON 2 DIRECTIONS, 2 REFERENCECUTS AS SHOWN MAY BE TAKEN

    X

    Y

    R

    P

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    98/104

    SB

    X-R

    P/2+Y-R

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    99/104

    SB

    FOR SETTING OF THE JOB, ALONG

    WITH THIS REFERENCE CUT,ANOTHER SETTING IS REQUIRED TOENSURE VERTICALLITY OF THEPARTING PLANE.

    THE USUAL PRACTICE IS TO HAVETHE REFERENCE CUTTHROUGHOUT THE LENGTH FORDIALLING.

  • 8/11/2019 Machine Shop Practices

    100/104

    SB

    OR

  • 8/11/2019 Machine Shop Practices

    101/104

    SB

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    102/104

    SB

    THIS IS THE MOST PREFERABLE

    METHOD OF JOB SETTING SINCEA) THE HALF DIA SETTING CAN BE

    MOST ACCURATELY DONE

    B) THE SETTING AND THE RESULTCAN BE CROSS CHECKED EVEN

    AFTER UN-LOADING FROMMACHINE.

    HALF DIA MACHINING

  • 8/11/2019 Machine Shop Practices

    103/104

    SB

    THIS IS METHOD CAN BE APPLIED

    EVEN ON HORIZONTAL BORINGOPERATION

  • 8/11/2019 Machine Shop Practices

    104/104