MAcc Supply Chain

download MAcc Supply Chain

of 27

Transcript of MAcc Supply Chain

  • 7/31/2019 MAcc Supply Chain

    1/27

    Supply Chain Management

    Macc. Business Core

  • 7/31/2019 MAcc Supply Chain

    2/27

    Forecast Demand

    Produce to forecast

    Ship

    Ship

    Buffer betweenproduction anddemand variation

    Ship

    Ship

    Change requirement

    Change due date Forecast error

    Produce to forecast Produce to order with lead time

    Supplier

    Factory

    Warehouse

    SellingEntity

    Customer

    Distributor

    Typical Supply Chain

  • 7/31/2019 MAcc Supply Chain

    3/27

    SUPPLIER FACTORY WAREHOUSE SELLINGENTITY

    CUSTOMER

    RATE-BASED PLANNING

    Distributor

    Lean Enterprise

  • 7/31/2019 MAcc Supply Chain

    4/27

    Objective of Rate-Based

    Management Balance demand variation against

    production, supply, and transportation

    responsiveness

    Create product flow across the supply chain

    by producing and moving the product at a

    steady rate at all stages in the supply chain.

  • 7/31/2019 MAcc Supply Chain

    5/27

    Benefits of Improved Forecasts for

    the Supply Chain

    Supply Planning Reduced Safety Stock Requirements

    Stability of Plan (week to week, month to month)

    Procurement Reduced material costs due to elimination of short-term

    fluctuations

    Reduces impact of long lead time items

    Manufacturing Plant efficiencies

    Reduces lost output due to last minute schedule changes

    Logistics Cost of expedited transportation/deployment

  • 7/31/2019 MAcc Supply Chain

    6/27

    Rate-Based vs. ConventionalRate-Based Planning and

    ExecutionConventional Planning and

    Execution

    1. Capacity accommodatesdemand variation

    Inventory accommodates demandvariation

    2. Forecast used for planning Forecast used for execution(build ahead)

    3. Rates are established for end

    items and component parts.Build to rate.

    No rates are established for end

    items or parts. Build tomanufacturing orders

    4. Rates are broadcastthroughout supply chain

    Orders used to communicaterequirements sequentiallythroughout the supply chain

    5. Demand variation is critical todetermining capacity bounds

    Demand variation unknown

    6. Flexible capacity boundariesare planned as a function of leadtime

    Flexible capacity boundaries arenot established

  • 7/31/2019 MAcc Supply Chain

    7/27

    Issues to be Addressed

    How to level schedules in the face of variation in

    product demand

    How to balance demand variation with production,supply, and transportation resources.

    How to communicate production requirements to

    all key suppliers and transportation providers so

    that all parties operate assets efficiently.

  • 7/31/2019 MAcc Supply Chain

    8/27

    How to Reduce Demand

    Variation Reduce Promotional Activity

    Reduce Set Up Times

    Produce in Small Lots

    Postponement Strategies

    Variation Aggregation

  • 7/31/2019 MAcc Supply Chain

    9/27

    Demand Variation Analysis

    The demand pattern for Neon, Inc. flashlights is basically level (non-seasonal)

    with only a 5% annual growth rate.

    1. Demand variation as seen by distributor/dealer.

    Actual Demand Data (Last 26 Weeks) by Channel

    Model Average Std. Deviation

    Distributor #1

    Green 20.52 1.94

    Yellow 10.65 3.64

    Red 15.10 1.62

    Dealer Network #2Green 15.63 1.82

    Yellow 5.99 3.42

    Red 9.85 1.50

    Distributor #3

    Green 15.84 1.62

    Yellow 5.64 3.85

    Red 5.00 1.75

  • 7/31/2019 MAcc Supply Chain

    10/27

    Standard Deviation

    Standard Deviation (): a measure of the magnitude of variation around an

    average value.

    Xi individual measurements of a population of measurements

    (e.g., weekly demand data).

    =

    X = average value for a population of measurements.

    standard

    deviation=

    (Xi - X)

    n

    n

    i =1

    2

    X

    5

    46

    3

    4

    22

    X22

    5= = 4.4

    standard

    deviation=

    (5-4.4)2 + (4-4.4)2 + (6-4.4)2 + (3-4.4)2 + (4-4.4)2

    5

    0.36 + 0.16 + 2.56 + 1.96 + 0.16

    5= 1.04= = 1.02

  • 7/31/2019 MAcc Supply Chain

    11/27

    Standard Deviation (Cont.)If we assume the following:

    1. Weekly demand data is stable over time (in control).

    2. Weekly demand data forms a normal distribution.

    X

    1

    68.26%

    2

    95.44%

    3

    99.73%

  • 7/31/2019 MAcc Supply Chain

    12/27

    Combining Demand Across Customers, Products and

    Locations

    In developing an inventory strategy it is necessary tounderstand variation of demand and of combined demands.

    For example:

    How much end item safety stock is required asprotection against variation in demand? How muchcould the inventory be reduced if components wereinventoried instead?

    How much flex capacity would be needed to achievemake-to -order capability?

    How much could the inventory be reduced byincreasing commonality of components.

    What would be the impact of moving the inventorystored at regional distribution centers to the factorywarehouse?

  • 7/31/2019 MAcc Supply Chain

    13/27

    Demand Variation Analysis2. Demand variation as seen at the factory warehouse.

    Red 29.95 28.8%

    Yellow 22.28 21.3% 6.31 28.42 56.85 85.27

    Green 51.99 49.9% 3.11 5.98 11.96 17.95

    Model Average % Mix Std. Dev. 1 Std Dev 2 Std Dev 3 Std Dev

    Actual Demand Variation by Model

    (Last 10 Weeks)

    Variation as a Percent of

    Demand

    NOTE: Average Green Model = Dist. #1 + Dealer Network #2 + Dist. #3

    = 20.52 + 15.63 + 15.84 = 51.99

    STD Deviation Green Model = (Std Dev #1)2 + (Std Dev #2)2 + (Std Dev #3)2

    = (1.94) 2 + (1.62) 2 + (1.82) 2 = 3.11* Complete the above table

    for the red model.

  • 7/31/2019 MAcc Supply Chain

    14/27

    Demand Variation

    We will use this information to:

    Construct planning bills of materials.

    Support demand funneling strategies.

    Support safety stock strategies.

  • 7/31/2019 MAcc Supply Chain

    15/27

    Example Implications

    The range of variation in demand for each of 100 individual items might be 50%, while the range of variation for the aggregate demand might be 5%.The former would determine inventory requirements in a make to stockenvironment. The later would determine inventory requirements in a configure

    to order environment. Variation of demand common components, as a percentage of the average

    demand, much smaller than the variation for individual end items.

    The demand for an item at one warehouse location has a standard deviation of3. At a second warehouse the same item has a standard deviation of 4. If thedemand for the two warehouse were combined the standard deviation would

    be . Thus in the first case the safety stock required for three standarddeviation protection would be 3*3+3*4= 21. In the second case therequired safety stock is reduced to 3*5=15.

    The demand for end items varies 100%. Thus in a make to inventoryenvironment a high level of safety stock is required. The aggregate demandmay vary only 10%, indicative of the amount of flex capacity needed in amake to order environment.

    54322

  • 7/31/2019 MAcc Supply Chain

    16/27

  • 7/31/2019 MAcc Supply Chain

    17/27

    Learning about Demand

    Variation In order to establish rates, it is necessary to

    know the underlying demand for various

    commodities and products.

    The orders you receive may not reflect

    actual underlying demand. Why?

  • 7/31/2019 MAcc Supply Chain

    18/27

    DEMAND PLANNING &

    PRODUCT TYPES

    BTS

    PlanningLevel

    PlanningLevel

    Components

    End Items

    Components

    CTO

    Components

    Modules

    End Items

  • 7/31/2019 MAcc Supply Chain

    19/27

    PRODUCT TYPES

    PRODUCT TYPE DEFINITION EXAMPLE

    Build-to-Stock

    (BTS)

    Built prior to demand

    with a standard bill of

    material.

    Diet Coke

    Build-to-Order

    (BTO)

    Built to demand

    requirements withstandard Bill of Material.

    Executive Jet

    Configure-to-Order

    (CTO)

    Built to demand with

    standard modules or

    components. Higher

    product variation than

    BTO.

    Desk-top Computer

    Engineer to Order

    (ETO)

    Built from drawings.

    Unique end products.

    Custom valve to a

    space station

  • 7/31/2019 MAcc Supply Chain

    20/27

    Rate Based SchedulingWeekly Schedule Flexibility

    Full Schedule

    MPS

    Wk1 Wk2 Wk3

    vs.

    Plan

    Wk1 Wk2 Wk3

    CTO

    Specials

    BTO

    CTO BTO

    ETOETO ETO

    Hold

    for BTOsCTO

    Specials Ds

    At-Once

    Wk4

    New

    Orders

    New

    New

  • 7/31/2019 MAcc Supply Chain

    21/27

    Customer Demand Profile

    Lead Time

    At-Once Order

    < lead-time

    Dema

    nd

    Order outside

    of lead-time

    BTS-FG Kanban

    BTO/CTO

    BTO

    ETO

  • 7/31/2019 MAcc Supply Chain

    22/27

  • 7/31/2019 MAcc Supply Chain

    23/27

    Product Response Profiles-

    Different Perspectives

    Product Response

    Profile

    | | | | |0 1 2 3 4 . . . . wks

    | | | | |0 1 2 3 4 . . . . wks

    InfiniteFlexibility

    Market

    | | | | | |0 1 2 3 4 5 . . . . wks

    No Changes -Level Load

    Plant

    | | | | | | |0 1 2 3 4 5 6 . . . . wks

    Some MoreFlexibleThan OthersSupplier ?

  • 7/31/2019 MAcc Supply Chain

    24/27

    Supply Response Profiles

    A firms flexibility is limited by supplier capabilities.

    The objective is to increase flexibility.

    RAMP UP... .

    RAMP DOWN....

    Time

    QUANTITY

    TODAY FUTURE

    Each supplier will have its own

    response profile. The responseprofile is NOT only leadtime. It is

    the ability to flex up or down for

    subsequent periods into the future.

    The objective is to drive the

    suppliers to achieve response

    profiles that allow us to meet ourcustomers' demands/needs.

    Suppliers can achieve the desired

    response profile either by stocking

    material or having flexible internal

    capacities.

  • 7/31/2019 MAcc Supply Chain

    25/27

  • 7/31/2019 MAcc Supply Chain

    26/27

    ConventionalSpecific Tail

    NumberI-C

    Sheet MetalShop

    Composites

    Parts

    Ocean

    48-WeekCycle

    Parts committed totail numbers

    months before use

    SaltTreat

    ASEA

    HPM

    StretchForm

    MRP

    MRP

    MRP

    MRP

    MRP

    MRP

    Schedule

    MR

    MaterialsRelease

    MetalBond

    S

    MR

    PI-H

    I-G

    I-F

    I-F I-F I-F I-F

    I-E I-E I-E I-E

    I-E

    I-D

    I-C

    I-CI-D

    MR

    MRP

    Missing!

    48-WkSchedule

    S

    S

    I-B Wings

    I-E I-D

    LEAN Fi l A blTakt

  • 7/31/2019 MAcc Supply Chain

    27/27

    LEAN

    Schedule

    Final Assembly

    Salt

    Treat

    ASEA

    HPM

    Stretch

    Form

    Press Area

    Supermarket

    Thru - Kanban

    Kanban

    Board

    Flat Pattern Parts

    SheetStock

    Wings

    TaktNose Middle Tail

    MetalBondWing

    Cell