M-3 Surface Water Control Structure Rehabilitation

7
M-3 Surface Water Control Structure Rehabilitatio n M-3 existing structure ist rendering of finished M-3 structure

description

M-3 Surface Water Control Structure Rehabilitation. M-3 existing structure. Artist rendering of finished M-3 structure. Established Priorities. M-3 Location; Birchview Place. 2014 Approved Budget. Revenue M-3 Weir Budget$467,500 Land Budget Transfer $16,000 - PowerPoint PPT Presentation

Transcript of M-3 Surface Water Control Structure Rehabilitation

Page 1: M-3 Surface Water Control Structure Rehabilitation

M-3 Surface Water Control Structure

Rehabilitation

M-3 existing structure

Artist rendering of finished M-3 structure

Page 2: M-3 Surface Water Control Structure Rehabilitation

Established Priorities

Page 3: M-3 Surface Water Control Structure Rehabilitation

M-3 Location; Birchview Place

Page 4: M-3 Surface Water Control Structure Rehabilitation

2014 Approved Budget

Page 5: M-3 Surface Water Control Structure Rehabilitation

RevenueM-3 Weir Budget $467,500Land Budget Transfer $16,000Revised Budget $483,500

ExpensesCline M-3 Bid $439,325Water Main Relocation $18,4805.5% Contingency $25,695

$483,500

Page 6: M-3 Surface Water Control Structure Rehabilitation

Notice to proceed FebruarySubstantial completion May - June (90 days)Final completion June - July (30 days)

Page 7: M-3 Surface Water Control Structure Rehabilitation

Artists rendering of M-3 Finished Project

Recently completed R-1 (Royal Palms Parkway and Belle Terre Boulevard) Project