Luis Medeiros Romão Dirk Vandeplassche SCK CEN

23
Luis Medeiros Romão Dirk Vandeplassche SCKCEN Roadmap towards the MYRRHA Accelerator Construction MYRRHA Accelerator 1 st International Design Review – Brussels, 12 – 13 November 2012 Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 1

description

Roadmap towards the MYRRHA Accelerator Construction. Luis Medeiros Romão Dirk Vandeplassche SCK  CEN. MYRRHA Accelerator 1 st International Design Review – Brussels, 12 – 13 November 2012. Agenda. Context Scope Time frame Reactor’s roadmap General needs R&D Roadmap - PowerPoint PPT Presentation

Transcript of Luis Medeiros Romão Dirk Vandeplassche SCK CEN

Page 1: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Luis Medeiros RomãoDirk Vandeplassche

SCKCEN

Roadmap towards theMYRRHA Accelerator Construction

MYRRHA Accelerator 1st International Design Review – Brussels, 12 – 13 November 2012

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 1

Page 2: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Agenda

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 2

• Context• Scope• Time frame• Reactor’s roadmap• General needs• R&D Roadmap• Road to construction• Concluding thoughts

Page 3: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Context

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 3

• SCKCEN:• promoting ADS• but…without accelerator tradition• and…in a nuclear reactor environment

• Belgium:• supporting ADS• without accelerator development tradition in the research

environment

Page 4: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Scope, in a nutshell

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 4

• Superconducting Proton Linac (coupled to sub-critical reactor): 600MeV 4mA CW MTBF > 250h

• Full power beam-dump (2.4MW)• ISOL@MYRRHA beam deviation system (optional)

Page 5: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

What do we want to build ?

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 5

Page 6: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Injectors Building

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 6

Acc. Element #

Ion Source 2

LEBT 2

4-rod RFQ 2

RT-CH cavities 4

SC-CH cavities 8

Magnets 21

Re-bunchers (spoke cav.)

4

Other Elements #

RF amplifiers 14

Power supplies N

Other electronics N

Clean room 1

Mechanical workshop

1

RF workshop 1

Office space

Page 7: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Linac Tunnel & RF Gallery

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 7

Acc. Elements #Spoke cryomodules 24

Elliptical cryomodules Section 1

17

Elliptical cryomodules Section 2

15

Magnets 114

RF Gallery Elements #RF Amplifiers 142Power supplies NOther electronics N

Page 8: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

HEBT

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 8

Acc. Elements #Magnets 41

ISOL@MYRRHA deviation 1FP beam-dump 1

Page 9: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Ancillary & Distributed Systems

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 9

SystemsElectrical power 13MW

Cooling 10MWHVACVacuumCryogenics 2K

/5MWDiagnostics NControl System EPICSMPSPPS

Page 10: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

MYRRHA’s Time Line

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 10

2010-2014- R&D- Front EndEngineeringDesign

2019On site

assembly

2016-2018Construction ofcomponents &civil engineering

2015 Tendering &

Procurement

2020-2022 Commissioning

2023Progressivestart-up

2024-Full

exploitation

FEED(Front End Engineering

Design)

Minimisetechnological

risks

Securethe licensing

Secure a sound

management and

investment structure

PDPpreliminary dismantling

plan

PSARpreliminary

safety assesment

EIARenvironmental

impact assesment

CentralProjectTeam

OwnerEngineering

Team

OwnerConsortium

Group

Page 11: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

MYRRHA in 2024

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 11

ReactorSubcritical or Critical modes65 to 100 MWth

Accelerator(600 MeV - 4 mA proton)

FastNeutronSource

Spallation Source

Lead-Bismuthcoolant

MultipurposeFlexible

IrradiationFacility

Page 12: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Reactor’s roadmap

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 12

Design & Experiments•SCK•CEN•European FP projects•Other scientific collaborations (ex: Von Karman Institute)

Component and Integration Engineering •SCK•CEN (specific reactor core components)•FEED Engineer - Industrial Consortium

Building & Manufacturing•MYRRHA Consortium (incl. SCK•CEN)•Industrial partners•Including accelerator infrastructures

Page 13: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Reactor’s roadmap

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 13

Installation• MYRRHA Consortium (incl. SCK•CEN)• Industrial partners

Commissioning • MYRRHA Consortium (incl. SCK•CEN)• Industrial partners

Operations • MYRRHA Consortium (incl. SCK•CEN)

Page 14: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Accelerator Postulate

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 14

The accelerator is a unique engine with first of a kind performances that can be acquired by the MYRRHA Consortium from an external scientific – industrial collaboration, the Accelerator Consortium.

Page 15: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

General Needs

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 15

Page 16: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Present Accelerator Roadmap

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 16

Design & Prototyping•European FP projects•SCK•CEN•Other scientific collaborations (ex: CNRS, Ganil, …)

Component and Integration Engineering •Accelerator Consortium – Scientific & Industrial Collaboration•SCK•CEN

Manufacturing •Accelerator Consortium•SCK•CEN

Page 17: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

R&D Roadmap

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 17

17

today

RFQ@UCLPhase 1

Cryomodule prototypes

end 2014

INJ@UCLPhase 2RT-CH RAFI

FP8

• engineering• construction• test

end 2016

end 2018

SC-CH spoke

INJ@UCLPhase 3SC-CH

ellipticProd

Prod

elliptic

MAXFP7

Prod

Page 18: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

2014 Recruitement plan

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 18

2011 2012 2013 20140

1

2

3

4

5

6

7

8

Cryogenics Engineer

Technician 2

Technician 1

Control System Engineer

RF Engineer

System Engineer

Licensing Officer

Program Manager

Head of ADT

Page 19: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

2015

todayBu

ildin

g la

yout

Road to construction

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 19

2017

2019

Elec

tricit

y

Cool

ing

Vent

ilatio

n

Cryo

geni

cs

RF g

alle

ry

Acce

lera

tor

Integration Integration

Manufacturing and Installation

Global Integration

2020

Page 20: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Present Accelerator Scenario

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 20

Installation• MYRRHA Accelerator Consortium (incl.

SCK•CEN)• Industrial partners

Commissioning• MYRRHA Accelerator Consortium (incl.

SCK•CEN)• Industrial partners

Operations • MYRRHA Consortium (incl. SCK•CEN)

Page 21: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Concluding thoughts

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 21

• MLA can be considered as an engine– 2 choices: Make or Buy– SCK’s present position: Buy is the choice really open ?

• Is this model viable ? – Other similar projects follow a different path– Strong internal involvement in every phase– European project is in preparation in order to analyse

this scenario

Page 22: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

Concluding thoughts

Luis Medeiros Romão, MLA 1st International Design Review, Brussels, 12-13 November, 2012 22

• Longer term issues:– Operations– Maintenance– Reengineering– Configuration management

Can the MYRRHA Consortium live without the Accelerator Consortium after delivery ?

Page 23: Luis Medeiros Romão Dirk Vandeplassche SCK  CEN

23

Thank-you!