LOTO Pre-Outage Activity Guidelines

13
LOTO Pre-outage Activity Guidelines

description

LOTO Preoutages

Transcript of LOTO Pre-Outage Activity Guidelines

  • LOTO Pre-outage Activity Guidelines

  • 2 Footer appears here

    Date appears here

    The objective of the Lock Out Tag Out (LOTO) checklist is to provide a tool to identify and then secure the various energy sources related to a gas or steam turbines.

    This should be used by the customer as a guide and may not include all energy sources. Therefore, this should be verified using the Piping Instrumentation Diagram (P&ID), Electrical System Schematics, walking down the local configuration and any other tools to ensure the equipment has been identified that will be de-energized.

    The checklist is intended to engage the end-customer and verify the completeness of their LOTO process during pre-outage. It will also be used during the verification walk down of the LOTO process prior to commencement of works along with TAB M of the OneGE Plan

    LOTO CHECKLIST OBJECTIVES

  • 3 Footer appears here

    Date appears here

    Pre-outage Activities / Timeline

    Pre-planning Period

    Outage Execution

    Outage Start

    2 Months Prior 3-Month

    Pre-outage meeting

    7 days

    prior

    TCM / CPM

    sends the LOTO

    Checklist to

    customer

    Customer Identifies the

    system Idenfitication numbers& Secondary

    Control

    (Grounds, breaker,

    etc.)

    "Appendix K"

    filled by SM /

    CPM / TCM GE Lead FE or

    TCM review the

    " LOTO

    checklist "

    7 days

    prior

    GE Lead FE /

    TCM / CPM /

    Customer

    "system

    walkdown" to

    identify the

    additional

    LOTO point

    Customer provides

    "LOTO Checklist to

    GE" and feedback

    session held

    During

    System LOTO

    GE Lead Fe / TA &

    Customer use the

    last revision of

    "LOTO cheklist"

    and

    fills "TAB M"

    GE TCM / CPM

    release the

    last revision of

    "LOTO

    checklist"

    7 days

    prior 1 Month Pre-outage

    meeting

  • 4 Footer appears here

    Date appears here

    WHEN : 7 days prior to 3- month Pre-outage Meeting

    WHO : TCM / CPM

    WHAT: TCM / CPM sends the LOTO Checklist to customer

    HOW:

    Chose proper LOTO checklist.V2 as per the scope

    Consult with LTA

    If the scope does not MI, HGP or CI, chose proper one which covers the lines needs to be isolated.

    Pre-outage Activities

    Just Version 2

    has this detail !

  • 5 Footer appears here

    Date appears here

    WHEN : Until 3- month Pre-outage Meeting

    WHO : Customer

    WHAT: Customer Identifies the system Idenfitication numbers & Secondary Control (Grounds, breaker, etc.)

    HOW:

    By drawings or customer lists

    If system Idenfitication numbers is not available, note the location of the respected isolation point

    Pre-outage Activities

  • 6 Footer appears here

    Date appears here

    WHEN : 3- Month Pre-outage Meeting

    WHO : TCM / CPM / SM

    WHAT :

    a) Customer provides "LOTO Checklist to GE" and feedback session held.

    b) Fill the "Appendix K"

    HOW :

    Review the "LOTO Checklist" which customer added system Idenfitication numbers & Secondary Control"

    Appendix K includes generic information of customer LOTO

    Pre-outage Activities

  • 7 Footer appears here

    Date appears here

    WHEN : 7 days prior to 1 month Pre-outage Meeting

    WHO : TCM / Lead FE

    WHAT : GE Lead FE or TCM review the " LOTO checklist "

    HOW :

    Does any other line needs to be isolated for this scope? (as per experience & knowledge)

    Additional controls needed?

    Review !

    Pre-outage Activities

  • 8 Footer appears here

    Date appears here

    WHEN : 1 month Pre-outage Meeting

    WHO : GE Lead FE / TCM / CPM / Customer

    WHAT : GE Lead FE / TCM / CPM / Customer "system walkdown" to identify the additional LOTO point point

    HOW :

    Physical system walkdown.

    Verify last "LOTO checklist" reviewed by Lead FE,

    Be open for constructive discussion with customer.

    Pre-outage Activities

  • 9 Footer appears here

    Date appears here

    WHEN : 7 Days Before Outage Start

    WHO : CPM / TCM

    WHAT : GE CPM / TCM release the last revision of "LOTO checklist"

    HOW :

    Share with customer, GE SM, Lead FE

    Lead FE shares it with shift TA.

    Pre-outage Activities

  • 10 Footer appears here

    Date appears here

    WHEN : Outage day during LOTO Walkdown

    WHO : Shift FE, Safety Specialist, Customer

    WHAT : During System LOTO GE TA & Customer use the last revision of "LOTO cheklist" and fill "TAB M"

    HOW : Perform LOTO Walk down, place GE LOTO locks on

    identified points or Customer LOTO Box (depend on the GE aggreed Customer system)

    Ensure that all the lines isolated properly and Lock&Tag applied.

    Record the key numbers vs isolated lines.

    Fill Tab M - Lock Out/Tag Out Clearance Control Proof of Isolation Agreement ( as per OneGE EHS Plan requirement)

    Outage Activities

  • GT & ST LOTO Checklists V2

  • 12 Footer appears here

    Date appears here

    GAS TURBINE Checklist

    CI HGPI MI GENERATOR

    STEAM TURBINE Checklist

    Minor Major Valves GENERATOR

    GT & ST LOTO Checklist V2

    Just Version 2

    has this detail !