LOTO Pre-outage Activity Guidelines
-
2 Footer appears here
Date appears here
The objective of the Lock Out Tag Out (LOTO) checklist is to provide a tool to identify and then secure the various energy sources related to a gas or steam turbines.
This should be used by the customer as a guide and may not include all energy sources. Therefore, this should be verified using the Piping Instrumentation Diagram (P&ID), Electrical System Schematics, walking down the local configuration and any other tools to ensure the equipment has been identified that will be de-energized.
The checklist is intended to engage the end-customer and verify the completeness of their LOTO process during pre-outage. It will also be used during the verification walk down of the LOTO process prior to commencement of works along with TAB M of the OneGE Plan
LOTO CHECKLIST OBJECTIVES
-
3 Footer appears here
Date appears here
Pre-outage Activities / Timeline
Pre-planning Period
Outage Execution
Outage Start
2 Months Prior 3-Month
Pre-outage meeting
7 days
prior
TCM / CPM
sends the LOTO
Checklist to
customer
Customer Identifies the
system Idenfitication numbers& Secondary
Control
(Grounds, breaker,
etc.)
"Appendix K"
filled by SM /
CPM / TCM GE Lead FE or
TCM review the
" LOTO
checklist "
7 days
prior
GE Lead FE /
TCM / CPM /
Customer
"system
walkdown" to
identify the
additional
LOTO point
Customer provides
"LOTO Checklist to
GE" and feedback
session held
During
System LOTO
GE Lead Fe / TA &
Customer use the
last revision of
"LOTO cheklist"
and
fills "TAB M"
GE TCM / CPM
release the
last revision of
"LOTO
checklist"
7 days
prior 1 Month Pre-outage
meeting
-
4 Footer appears here
Date appears here
WHEN : 7 days prior to 3- month Pre-outage Meeting
WHO : TCM / CPM
WHAT: TCM / CPM sends the LOTO Checklist to customer
HOW:
Chose proper LOTO checklist.V2 as per the scope
Consult with LTA
If the scope does not MI, HGP or CI, chose proper one which covers the lines needs to be isolated.
Pre-outage Activities
Just Version 2
has this detail !
-
5 Footer appears here
Date appears here
WHEN : Until 3- month Pre-outage Meeting
WHO : Customer
WHAT: Customer Identifies the system Idenfitication numbers & Secondary Control (Grounds, breaker, etc.)
HOW:
By drawings or customer lists
If system Idenfitication numbers is not available, note the location of the respected isolation point
Pre-outage Activities
-
6 Footer appears here
Date appears here
WHEN : 3- Month Pre-outage Meeting
WHO : TCM / CPM / SM
WHAT :
a) Customer provides "LOTO Checklist to GE" and feedback session held.
b) Fill the "Appendix K"
HOW :
Review the "LOTO Checklist" which customer added system Idenfitication numbers & Secondary Control"
Appendix K includes generic information of customer LOTO
Pre-outage Activities
-
7 Footer appears here
Date appears here
WHEN : 7 days prior to 1 month Pre-outage Meeting
WHO : TCM / Lead FE
WHAT : GE Lead FE or TCM review the " LOTO checklist "
HOW :
Does any other line needs to be isolated for this scope? (as per experience & knowledge)
Additional controls needed?
Review !
Pre-outage Activities
-
8 Footer appears here
Date appears here
WHEN : 1 month Pre-outage Meeting
WHO : GE Lead FE / TCM / CPM / Customer
WHAT : GE Lead FE / TCM / CPM / Customer "system walkdown" to identify the additional LOTO point point
HOW :
Physical system walkdown.
Verify last "LOTO checklist" reviewed by Lead FE,
Be open for constructive discussion with customer.
Pre-outage Activities
-
9 Footer appears here
Date appears here
WHEN : 7 Days Before Outage Start
WHO : CPM / TCM
WHAT : GE CPM / TCM release the last revision of "LOTO checklist"
HOW :
Share with customer, GE SM, Lead FE
Lead FE shares it with shift TA.
Pre-outage Activities
-
10 Footer appears here
Date appears here
WHEN : Outage day during LOTO Walkdown
WHO : Shift FE, Safety Specialist, Customer
WHAT : During System LOTO GE TA & Customer use the last revision of "LOTO cheklist" and fill "TAB M"
HOW : Perform LOTO Walk down, place GE LOTO locks on
identified points or Customer LOTO Box (depend on the GE aggreed Customer system)
Ensure that all the lines isolated properly and Lock&Tag applied.
Record the key numbers vs isolated lines.
Fill Tab M - Lock Out/Tag Out Clearance Control Proof of Isolation Agreement ( as per OneGE EHS Plan requirement)
Outage Activities
-
GT & ST LOTO Checklists V2
-
12 Footer appears here
Date appears here
GAS TURBINE Checklist
CI HGPI MI GENERATOR
STEAM TURBINE Checklist
Minor Major Valves GENERATOR
GT & ST LOTO Checklist V2
Just Version 2
has this detail !
-
Questions