Community Meeting November 19, 2019 Los Angeles Street Civic Building Update civiccenterprojects.lacity.org

Transcript of Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines....

Page 1: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Community Meeting November 19, 2019

Los Angeles Street Civic Building Update

civiccenterprojects.lacity.org

Page 2: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Agenda

Civic Building Project Overview ― 00

Civic Building ― 01

Civic Building Urban Design Vision and Guidelines ― 02

Next Steps ― 03

2

Page 3: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building and Civic Center DistrictCivic Building Project

KEY

District Boundary

Existing Metro Stations

Future Metro Stations

City Hall

00 300 600 ft.

Scale: 1” = 300’0”

N

Broa

dway

Hill

St

Spring St

Main StLo

s Ange

les St

Judg

e Joh

n Ai

so S

t

San

Pedr

o St

Temple St

Aliso St

101 FWY

1st St

2nd St

Onizuka S

t

Civic Center/Grand Park

Go for Broke Memorial

Civic Building Site

LAPD

Future FAB Park

Grand Park

CalTrans

The Geffen Contemporary at MOCA

Japanese American National Museum

Future Stop

OverviewCIVIC CENTER MASTER PLAN (CCMP)

Master Development Plan Study (completed) as applied to the Civic Building Project

Civic Center District Urban Design Vision and Guidelines as applied to the Civic Building Project

Urban Design Vision and Guidelines EIR (process to

begin by early 2020)

Civic Building Project Civic Building EIR (completed)

Parker Center Demolition (near completion)

Civic Building Programming and

Performance Criteria (in progress)

Civic Building Public Private Partnership (P3)

Procurement (in progress)

3

Page 4: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building Project

Civic Building Overview

PHASE 1 PASEO CONCEPT PLAN

3

2

1

1st Street

Aliso Street

Temple Street

2nd Street

Sprin

g St

reet

Main

Stre

et

Los

Ange

les

Stre

et

Judg

e Jo

hn A

iso S

treet

P

Building Program

Office space for approximately 3,000 employees

Basement parking

Conference center

Childcare center

Street-level commercial space

Public displays of Parker Center site history as well as

building history

Community center (2,000 - 3,000 sq.ft.)

Project Delivery

To be delivered through a Public Private Partnership (P3)

Civic Building Site Study

• Los Angeles Street Space

• LASCB Paseo

• Square at Judge John Aiso Street

1

2

3

4

Page 5: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building Project

Civic Building Urban Design Vision and Guidelines • Implement the Council

direction and certified EIR

– Land use

– 24/7 activatoin

– Key plan concepts

•Coordinate with other City agencies

•Engage community and stakeholders

•Shape a vision for the physical environment

•Develop and test guidelines

5

Page 6: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Process Overview

• Inter-departmental meetings

(City family)

•Community advisory council,

downtown neighborhoods

•City-wide community meetings

•Little Tokyo stakeholder meetings

•Develop and test guidelines

Key Stakeholder and

Community Priorities

•Connect to downtown neighborhoods

•Make comfortable, interesting,

safe streets and sidewalks

•Celebrate and preserve

City Hall’s prominence

•Bridge to Little Tokyo and

acknowledge history

Civic Building Project

Community and Stakeholder Process

6

Page 7: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Temporary Street Closures

Curb Cuts

Street Trees and Landscape

CrosswalksFlex Zones Surface MaterialsFurnishings

Mobility Lanes

Ground-Floor Frontages

Curb-Side Drop-Offs

Safety Features

Civic Building Project

Public Realm Design

7

Page 8: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Design and ArchitectureCivic Building Project

•Encourage architectural diversity

•Height and massing

relative to City Hall

•Create civic streetscapes with

engaging ground floors

•Encourage sustainable design

•Showcase demonstration projects

•Support Sustainable City pLAn

and Resilient LA

8

Page 9: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building Project

Public Private Partnership/DBFOM

•A Public/Private Partnership (P3) is a project delivery

approach whereby a government entity (City of LA)

engages a consortium of private sector companies

organized into a single entity (Proposer or Developer)

to take various risks implementing a project

•The Civic Building will use a Design-Build-Finance-

Operate-Maintain (DBFOM) form of P3.

9

Page 10: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

•Municipal Facilites

Committee (early 2020)

•Board of Public Works (early 2020)

•Request for Proposals

released (spring 2020)

•Additional community

engagement during the design

and construction process

Next StepsCivic Building Project

10

Page 11: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Center Master Development Plan InitiatedCity Council Motion Introduced Jan 2017

LASCB Environmental Impact ReportAdopted Mar 2017

Civic Center Master Development Plan GuidelinesDeveloper 2018 - 2019

Parker Center DemolitionStarted September 2018Expected Completion Early 2020

LASCB Request for QualificationsReleasedApr 2019

LASCB Announcement of RecommendedShort-Listed RespondentsAug 2019 LASCB

Community Update MeetingNov 19, 2019

LASCB Preferred Proposer Selection Anticipated Early 2021

Additional Community MeetingsOnce Preferred Proposer is Selected2021-2024

2018 2019 2020

LASCB Request for Proposals ReleasedAnticipated Spring 2020

2021 2024

COMMUNITY MEETINGS(CAC, LTCC, BIDS, ETC.)

FUTURE COMMUNITYENGAGEMENT OPPORTUNITIES

Next StepsCivic Building Project

11

Page 12: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building Project

Project Website

civiccenterprojects.lacity.org

12

Page 13: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Civic Building Project

Project One-Page Overview

13

Page 14: Los Angeles Street Civic Building Update · Civic Center Master Development Plan Guidelines. Developer 2018 - 2019. Parker Center Demolition Started September 2018 Expected Completion

Thank you.