Long Term Planning Example
description
Transcript of Long Term Planning Example
Generated by Jive on 2015-04-14+02:001
Long term planning execution - step by step
Long term planning is being used to simulate the future demand in all BOM levels. Main intension is to check
the capacity situation, material requirement and vendor /supplier ability to provide the material in proper time.
This is not an actual run but a simulative run where actual plan is not being affected. It is possible to transfer
the plan from simulative area to operative area if through simulation it is found that all capacity and requirement
can be fulfilled.
The main objective of LTP are:
• Reconciliation of capacities.• Forecast of purchasing element• Simulation of demand program at all BOM level
The main intension of LTP is to simulate different versions of the demand program. But it is not necessary
that simulative planning has to be there always with long term. It can be short term also as there is no time
restriction.
Generally planned independent requirement version can be active or inactive. For LTP planned independent
version should be inactive as it is a simulative version. Only active PIR version is being taken for operative
planning.
Existing master data can be used for LTP. But to have a different master data (BOM and Routing) for LTP is
also possible. Below are the setting.
BOM: A special LTP BOM can be created. In customizing “ Define BOM usage” (OS20) and “Defineorder of priority of BOM usage”(OS31) has to be defined. Then selection ID and selection priorityhas to be maintained.
Below are the screens where the data has to be maintained (as already explained this is not mandatory, its the
requirement of individual)
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:002
The customized selection ID has to be given in LTP scenario to have a different master data.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:003
Routing: To have a different routing data in customizing “define scheduling parameters forplanned orders” (OPU5) has to be maintained.
Double click on and select new entries.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:004
To run LTP first we have to create planning scenario (MS31).
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:005
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:006
Initially the status will be not released
Planning period will be the time between which the PIR will be considered.
Opening stock can be considered as per the selection.
As well whether to consider SO or to switch off PTF , whether to consider receipt etc can be decided in
planning scenario.
Here we can also select BOM selection ID if at all we want to use a different master data (BOM).
Now we have to select
We have to assign the version in the scenario.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:007
As well we have to assign plant to the scenario and confirm so that the scenario will be applicable for that
particular plant
Then the scenario has to be released
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:008
After releasing the screen will look like below. The scenario will be released.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:009
If some parameter has to be changed in the scenario in future then in MS02 first wehave to do “cancel release” and then change. Again we have to release after change.
Now create the independent requirement (MD61).
Now check MS04. There will be no change in MD04 as the requirement is with inactive version.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:0010
Now run LTP with MS02
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:0011
Again check MS04. Planned order got created.
By this all the requirement element can be checked for the future availability. As well capacity can be checked
also from CM38.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:0012
Detail overview
The detail can be seen as per the proposals.
Standard overview
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:0013
In this view the load can be seen. This is the deciding factor for considering the requirement in LTP and
whether to enhance capacity. Decisions are being taken for future course of action regarding capacity.
Once the simulation is fine then the version can be copied through MS64.
Long term planning execution - step by step
Generated by Jive on 2015-04-14+02:0014
Generally if the simulation is fine and workable in future dates, the same requirement can be sent in operative
planning. The data can be seen in MD04 once the requirement came in operative planning.
Best regards,
Krishnendu.