Long Span and High-rise Steel Construction

download Long Span and High-rise Steel Construction

of 89

Transcript of Long Span and High-rise Steel Construction

  • 8/10/2019 Long Span and High-rise Steel Construction

    1/89

    2007-4-24

    Long Span and High-riseSteel Construction

    C&S SEMINARC&S SEMINAR

    20th April 200720th April 2007

    ii--Connect room, 1st storeyConnect room, 1st storey SurbanaSurbanaOne, 168One, 168 Jalan Bukit MerahJalan Bukit Merah

    SingaporeSingapore

    J Y RichardJ Y Richard LiewLiew

    Ph.D, P.Eng (Ph.D, P.Eng (SSporepore),), CEngCEng,, MIStructEMIStructE,,

    Associate ProfessorAssociate Professor

    Director, Hazard, Risk and MitigationDirector, Hazard, Risk and Mitigation ProgrammeProgrammeDepartment of Civil EngineeringDepartment of Civil EngineeringNational University of SingaporeNational University of Singapore

    Email:Email:cveljycveljy@@nusnus..eduedu..sgsg

  • 8/10/2019 Long Span and High-rise Steel Construction

    2/89

    Quality Steel is a high quality, dimensionally accurate material

    Efficiency/speed Steel components are pre-fabricated in efficientfactory processes, and installed rapidly on site minimisingthe use of site labour

    Light Weight Steel has a higher strength-to-weight ratio; lessrequirement on foundation.

    Aesthetics Attractive appearance; long span floor beam system up to 20free span

    Minimum waste Steel construction is not wasteful in production, andall waste can be recycled

    Recycling Steel can be recycled and reused at the end of life. 50% ofcurrent steel use is from a recycled source

    Re-use Steel components can be dismantled and re-used

    Sustainable andSustainable and BuildableBuildable SteelSteelConstructionConstruction

  • 8/10/2019 Long Span and High-rise Steel Construction

    3/89

    Buildability of Large VolumeSpace Frame Structures

    1.1. SingleSingle integrated elements or system

    2. Simplifiedjoint design to facilitate

    construction3. Speed of Construction

    Minimise temporary works/ low-level working

    Maximise off-site fabrication

    Exploit high strength products to reduce weight

    Minimise applied fire protection

  • 8/10/2019 Long Span and High-rise Steel Construction

    4/89

    Integrated Roof Systems

    Integrated metal roof on steel trusses

    Metal roof on steel trusses or beams

  • 8/10/2019 Long Span and High-rise Steel Construction

    5/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    6/89

    - Before LiftingBefore Lifting

    SingaporeSingapore ChangiChangiInternational Airport Hangar 5International Airport Hangar 5

  • 8/10/2019 Long Span and High-rise Steel Construction

    7/89

    Main Trusses (92m) are rigidly weldedSecondary trusses are bolted.

    SIA Hangar 5

  • 8/10/2019 Long Span and High-rise Steel Construction

    8/89

    SingaporeSingapore ChangiChangiInternational Airport Hangar 5International Airport Hangar 5

    --85 m x72m Single Integrated Roof System85 m x72m Single Integrated Roof System

    11

    21 J

    A

    ~27.0 M

    0.0

    M

    Power

    Pack

    HydraulicHoses

    StrandJack

    Temporary

    Walkways &

    Working

    Platforms

    Lattice

    Column

    Minimise temporary works/ low-level working

  • 8/10/2019 Long Span and High-rise Steel Construction

    9/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    10/89

    -After LiftingAfter LiftingSingaporeSingapore ChangiChangiInternational Airport Hangar 5International Airport Hangar 5

  • 8/10/2019 Long Span and High-rise Steel Construction

    11/89

    Sports Complex Roof

    - Curved arches

  • 8/10/2019 Long Span and High-rise Steel Construction

    12/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    13/89

    1mm 2mm

    38.59m

    (0, 0)

    (16m, 27.67m)

    (10m, 15.67m) (22m, 15.3m)

    38.65m

    13m

    60 Degree

    60 Degree

    9.5m Overhang Cantilever

    8m OverhangCantilever

    2mm

    10ton Chain Block to control &

    adjust the level & displacement

    Temporary

    Erection Plate

    7.5m

    2m

    6m 31KN(CG)

    15.8KN

    3.9KN3.9KN

    10 ton x 12m webbing slings

    Temporary Tower

    Support 2mx2m

    Temporary Tower

    Support 2mx2m

    3mm

    Need 2 cranes for erection3-Segment constructionNeed Temporary Supports

  • 8/10/2019 Long Span and High-rise Steel Construction

    14/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    15/89

    Lateral stability during installation

  • 8/10/2019 Long Span and High-rise Steel Construction

    16/89

    TheThe WhampoaWhampoa FootbridgeFootbridge use of tubular sectionsuse of tubular sections

  • 8/10/2019 Long Span and High-rise Steel Construction

    17/89

    60m

    TheThe WhampoaWhampoa FootbridgeFootbridge

  • 8/10/2019 Long Span and High-rise Steel Construction

    18/89

    PROPOSED WHAMPOA FOOTBRIDGE

    TTJ/ER/PROP-03

  • 8/10/2019 Long Span and High-rise Steel Construction

    19/89

    Erectioncompleted inthe morning

    Lift footbridge to bargePull the bridgto the otherend

  • 8/10/2019 Long Span and High-rise Steel Construction

    20/89

    Suntec City Convention Center(120m x 160m)

  • 8/10/2019 Long Span and High-rise Steel Construction

    21/89

    FabricationFabrication

    done on thedone on thefloor slabfloor slab

  • 8/10/2019 Long Span and High-rise Steel Construction

    22/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    23/89

    Keppel Distribution Park

  • 8/10/2019 Long Span and High-rise Steel Construction

    24/89

    Keppel Distribution Park

    Six warehouses: 120m x 90m each

  • 8/10/2019 Long Span and High-rise Steel Construction

    25/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    26/89

    Building services or part of the roof cladding can be pre-installed on the ground before lifting

    P bl d

  • 8/10/2019 Long Span and High-rise Steel Construction

    27/89

    Bolted JointsAvoid site welding

    Pre-assembledspace frames

  • 8/10/2019 Long Span and High-rise Steel Construction

    28/89

    Preinstalled on the ground using ball-jointed space frame system

  • 8/10/2019 Long Span and High-rise Steel Construction

    29/89

    Lifting of steel roof

  • 8/10/2019 Long Span and High-rise Steel Construction

    30/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    31/89

    Economy of Steel Joints

    Rigid joints cost more thannominally pinned joints

    Joints that require a large amount

    of stiffening are more expensive Connections which require specialjigs to fabricate will be relatively

    expensive. Site welded joints cost more thanfield bolted joints.

  • 8/10/2019 Long Span and High-rise Steel Construction

    32/89

    Rigid joints with many stiffeners

    Congested node Overlapping Joint

  • 8/10/2019 Long Span and High-rise Steel Construction

    33/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    34/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    35/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    36/89

    f &

  • 8/10/2019 Long Span and High-rise Steel Construction

    37/89

    In-line production based on

    Computerized NumericallyControlled machinery.

    Prefabrication &

    Accuracy

    Sea Front

    Access

    CNC Pipe Profile Cutting MachineCNC Pipe Profile Cutting MachineFCAW WeldingFCAW Welding

    CNC Hole Drilling/ PunchingCNC Hole Drilling/ PunchingCNC Drilling/Cutting LineCNC Drilling/Cutting Line

    CNC Plate Profile Cutting MachineCNC Plate Profile Cutting Machine

  • 8/10/2019 Long Span and High-rise Steel Construction

    38/89

    CNC Pipe Profiling

  • 8/10/2019 Long Span and High-rise Steel Construction

    39/89

    fire safety designfire safety design

    Realistic FireRealistic Fire

    Modeling,Modeling,

    CFD, Parametric fire, etcHeat TransferHeat Transfer

    AnalysisAnalysisFEM

    StructuralStructural

    ResponseResponse

    CalculationCalculationNLFEA

    Fire engineering of large spanFire engineering of large spanstructuresstructures

    Liew, J Y R, Tang, L K and Choo, Y S (2002), Advanced analysis for performance-based design of steel structures exposed to fires,J of Structural Engineering,

    ASCE, USA, 128(12), 1584-1593

    Fire Detection/Alarm

    Fire suppression

    egra at on o stee

  • 8/10/2019 Long Span and High-rise Steel Construction

    40/89

    egra at on o steestrength and stiffness

    0 300 600 900 1200

    100

    80

    60

    40

    20

    % of normal value

    Temperature (C)

    Effective yield strength

    (at 2% strain)

    SS

    Elastic modulus

    SS

    Strength and stiffness

    reductions very similar

    for S235, S275, S355

    structural steels and

    hot-rolled reinforcingbars. (SS)

  • 8/10/2019 Long Span and High-rise Steel Construction

    41/89

    Minimise passive fire protection

  • 8/10/2019 Long Span and High-rise Steel Construction

    42/89

    Fire protection is not required!

    i i i i d

  • 8/10/2019 Long Span and High-rise Steel Construction

    43/89

    Fire protection is not required!

    MAJOR STEEL BUILDING

  • 8/10/2019 Long Span and High-rise Steel Construction

    44/89

    MAJOR STEEL BUILDING

    PROJETS IN SINGAPORE

    Name No. of Storey Weight (tons) Yr Completed

    OUB Centre 67* 11,000 1986

    Treasury Building 52 15,000 1986

    Ocean Tower 30 5,800 1991

    John Hancock Tower 26 2,350 1992

    Hitachi Tower 37 6,000 1992

    The Concourse 42 8,000 1992

    UOB Plaza 66* 10,000 1992

    Republic Plaza 66* 8,217 1995

    *Tallest in Singapore, 280m

  • 8/10/2019 Long Span and High-rise Steel Construction

    45/89

    Name No. of Storey Weight (tons) Yr Complete

    STEEL BUILDING PROJETS IN SINGAPORE

    (Cont)

    UE Square 18 2,000 1996

    Suntec City NA 27,000 1996

    Bank of China 37 3,000 1997Singapore Post Centre 14 7,000 1999

    Springleaves Tower 37 4,200 2000

    Cuppage Centre 10 3,000 2000

    Capital Tower 52 9,600 2000One Raffles Link 8 3,000 2000

    ParkView Square 30 8000 2002

    ORQ 50 8,000 2006

    B ild bilit f M lti t St l

  • 8/10/2019 Long Span and High-rise Steel Construction

    46/89

    Buildability of Multi-storey Steel

    Building

    Standardization - repetition of grids, sizes ofcomponents and connection details

    SSimplicity - simple building constructionsystems and installation details.Speed of Construction

    Exploit long span advantage

    Reduce no. of floor joints. Integrate building services Adopt composite construction

    Typical commercial building

  • 8/10/2019 Long Span and High-rise Steel Construction

    47/89

    Typical commercial buildingLong Span Construction reduce floor joint

  • 8/10/2019 Long Span and High-rise Steel Construction

    48/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    49/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    50/89

    Integration of building services

  • 8/10/2019 Long Span and High-rise Steel Construction

    51/89

    Composite TrussComposite Truss

    Suntec City

  • 8/10/2019 Long Span and High-rise Steel Construction

    52/89

    Suntec City

    Composite Truss System

  • 8/10/2019 Long Span and High-rise Steel Construction

    53/89

    Composite Truss System

    >25m

    OUB Building

  • 8/10/2019 Long Span and High-rise Steel Construction

    54/89

    OUB Building

    Hybrid

    system of

    steel

    frames with

    concretecore

    20m

    950

  • 8/10/2019 Long Span and High-rise Steel Construction

    55/89

    Shallow floor systemsShallow floor systems

    A wide flat plate iswelded to theunderside of H-section.

    The wide plate supports

    the precast concrete slab

    reducing the overall

    thickness of the floor.

    Advantages of shallow floor

  • 8/10/2019 Long Span and High-rise Steel Construction

    56/89

    Advantages of shallow floorsystems

    Shallow floor depth reduces the overallheight of the building Flexibility of service layout

    One-hour fire resistancebecause major parts of thesteel section is encased inconcrete.

    Longer periods can beachieved by protecting theexposed bottom flange

  • 8/10/2019 Long Span and High-rise Steel Construction

    57/89

    Deep metal deckingDeep metal decking

    Deep metal deck permits the use of in-situ concreteacting compositely with the metal deck. This reduces the dead load of the floor and removes

    the need to manoeuvre heavy precast sections intoplace.

    M t l d kiM t l d ki

  • 8/10/2019 Long Span and High-rise Steel Construction

    58/89

    Metal deckingMetal decking

    Steelwork ready to receive

  • 8/10/2019 Long Span and High-rise Steel Construction

    59/89

    Steelwork ready to receivedecking

    Pl i t l d kiPl i t l d ki

  • 8/10/2019 Long Span and High-rise Steel Construction

    60/89

    Placing metal deckingPlacing metal decking

    D ki i lDecking in place

  • 8/10/2019 Long Span and High-rise Steel Construction

    61/89

    Decking in placeDecking in place

    P mping conc etePumping concrete

  • 8/10/2019 Long Span and High-rise Steel Construction

    62/89

    Pumping concretePumping concrete

    Compa ison of compositeComparison of composite

  • 8/10/2019 Long Span and High-rise Steel Construction

    63/89

    Comparison of compositeComparison of composite

    flooring systemsflooring systems

    Building ABeam +

    slab

    depth

    Overall floor

    zone

    Building

    height

    Floor slab

    dead load

    Total steel

    weight per

    floor area

    STRUCTURAL FORM mm mm m KN/m2 Kg/m2

    Composite beams & composite slab 435 800 14.0

    2.8 51.7

    2.7 42.2

    2.0 38.9

    13.4

    Slimflor with deep metal deck (propped

    deck, unpropped beam)295 650 13.4

    3.0 43.4Slimflor with pre-cast slab 237 550 13.0

    Slimflor with deep metaldeck

    (unpropped)305 650

    Composite beams with web openings 725 1050 15.0

    2.0 46.6

    2.0 50.2

    Cellular beams with composite slab 775 1100 15.2

    Summary on Composite Floor

  • 8/10/2019 Long Span and High-rise Steel Construction

    64/89

    Summary on Composite FloorSystem

    Large column free spaces often require

    deep beams

    Service integration reduces overall depth

    Shallow floor systems combine floor and

    slab in the same vertical space reducing

    the overall structural depth.

    Composite ColumnsComposite Columns

  • 8/10/2019 Long Span and High-rise Steel Construction

    65/89

    pp

    Tube used as permanent form work

    2 1 1 Advantages ofAdvantages of CFSTsCFSTs

  • 8/10/2019 Long Span and High-rise Steel Construction

    66/89

    Circular

    Square and rectangular

    +>

    2OR

    `

  • 8/10/2019 Long Span and High-rise Steel Construction

    67/89

    `

    Concrete filled Tubular Column

    Applications oApplications ofCFTsCFTs

  • 8/10/2019 Long Span and High-rise Steel Construction

    68/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    69/89

    Slim column sizeSlim column size

    No fire protectionNo fire protection

    Internal steel core can resist the serviceInternal steel core can resist the service

    load during fire.load during fire.

    Steel Core CFT (SCSteel Core CFT (SC--CFT)CFT)

    Flat slabconstruction

    -- Concrete Filled ColumnsConcrete Filled Columns

  • 8/10/2019 Long Span and High-rise Steel Construction

    70/89

    Tube-in-tube

    composite

    columnsPunching shear connector

    (encased in slabs, protected from fire)

    Concrete Filled ColumnsConcrete Filled Columns

    (HSCF)(HSCF)Ultra high strength

    concrete; 200MPa

    Normal concrete,

    35 MPa

    Latest Innovation

  • 8/10/2019 Long Span and High-rise Steel Construction

    71/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    72/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    73/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    74/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    75/89

    Column Free

    Space

    Project Capital Tower

    ArchitecturalConsultant

    RSP Architects, Planners &Engineers (Pte) Ltd

    Structural Consultant Maunsell Consultants(Singapore) Ptd Ltd

    Main Contractor Parsons Brinckerhoff

    Consultant Pte Ltd

    Client CapitaLand CommercialLimited

    Construction cost US$152.0 million

    Construction Period 29 months

    Gross Floor Area 95,5545 m2

    Buildability Scores 81

    52-storey officebuilding with six

    levels of basementcar park

    Buildability Features

  • 8/10/2019 Long Span and High-rise Steel Construction

    76/89

    Standardised grids, beam spans andsymmetrical layout about central axis

    Autoclimb Slip Form

    ConstructionSequenceConstructionSequence

  • 8/10/2019 Long Span and High-rise Steel Construction

    77/89

    Construction SequenceConstruction Sequence

    f ll d l

  • 8/10/2019 Long Span and High-rise Steel Construction

    78/89

    Concrete filled Column

    Composite column

  • 8/10/2019 Long Span and High-rise Steel Construction

    79/89

    Composite column

    Finplate connection

  • 8/10/2019 Long Span and High-rise Steel Construction

    80/89

    Finplate connection

  • 8/10/2019 Long Span and High-rise Steel Construction

    81/89

    Through-plate connection

    Reverse channel- and T-section

  • 8/10/2019 Long Span and High-rise Steel Construction

    82/89

    connections

  • 8/10/2019 Long Span and High-rise Steel Construction

    83/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    84/89

    Typical Steel

  • 8/10/2019 Long Span and High-rise Steel Construction

    85/89

    Typical SteelResidential

    Building

    Integrated Dr Wall Panel

    Top Track

    S l S d

    Joints &

    fasteners

    finished with

  • 8/10/2019 Long Span and High-rise Steel Construction

    86/89

    Integrated Dry Wall PanelSteel StudAcoustic Insulation

    (if required)

    2 layers 15mm

    Plasterboard on

    both sides

    Fasteners on firstlayer @ 400mmcentres

    Bottom Track

    Lafarge JointCompound

    Fasteners

    10mm-15mmfrom edge ofsheet

    Fasteners @

    200mm centres

    max staggered onedges

  • 8/10/2019 Long Span and High-rise Steel Construction

    87/89

  • 8/10/2019 Long Span and High-rise Steel Construction

    88/89

    ConclusionsConclusions

  • 8/10/2019 Long Span and High-rise Steel Construction

    89/89

    ConclusionsConclusions Use reusable steel frame and percast concrete to

    reduce site labor, increase productivity and qualityfor sustainable construction.

    Use composite design for long span beam, compact

    floor, smaller column size, and better fire and

    structural resistance.

    Numerous projects provide illustration of the

    benefits of buildable design using composite

    construction. Successful implementation requires close

    collaboration and information sharing between

    various parties