Well No. 5
Constructed 2016
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Outline
• Design Considerations
– Irrigation/Domestic
– Well Field
– Future Tank
– High Pressure
• Construction Startup
– Anti-Reverse Ratchet
– Dual VFDs
– Safety Features
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Design Considerations
• Capacity
– 2,000 gpm Irrigation Water @ over 200 psi
– 1,000 gpm Domestic Water (Future)
• Well Pump
– Line Shaft Vertical Turbine
– 600 HP, 1800 RPM, Flowserve 15EMM 8-stage Pump
• Irrigation Booster Pump
– Horizontal Split Case Booster
– 400 HP, 1800 RPM, American Marsh 6x8-22 HD Pump
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Design Considerations
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Design Considerations
Future Tank
Pump to Waste
Domestic System
Irrigation System
Well Pump
Booster
Booster
Valve
Check Valve
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Well Pump Maintenance Access: skylight/hatch allows access to well
pump and provides natural light
Room Height: well pump motor dictates your room height, motor
inside the hatch = Heat
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Irrigation Booster Pump
Horizontal Shaft: requires laser alignment
Maintenance Access: provide space on side for maintenance equipment
to pick motor/pump
Expansion Joint: helps reduce vibration in piping
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Electric Room
Smart HVAC: VFD heat vents to pump room when needed
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
BuildingSkylight Hatch: for well pump removal
Double Door: allows large tool access to
well pump
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Building
Large Doors: allow maintenance equipment access to booster
pumps from both sides of building.
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Building
Pump to Waste: with appropriate mesh screens
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Design Considerations
• Irrigation/Domestic
– One well pump multiple booster pumps
• Irrigation Booster (Monitored Flow)
• Single or Dual Domestic Booster(s)
– Meets domestic water standards
– Future reduced pressure backflow preventer
– Temporary pipe paint
• Well Field
– Additional Drawdown
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Design Considerations
• Future Tank
– Adjacent tank in between well pump and
booster pump(s)
– Provide additional storage for domestic
system
• High Pressure
– Lower point in system
– Ductile iron well piping and yard piping
– VFDs allow ramp up and ramp down
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Line Shaft Vertical Turbine Well Pump• Anti-Reverse Ratchet
– Protects motor and
electrical equipment
– Mechanical ratchet that
stops shaft from spinning
in reverse when water is
draining back down the
column
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Line Shaft Vertical Turbine Well Pump• Anti-Reverse Ratchet
– Ratchet engages, slams,
engages, slams, etc.
– Extremely Loud
– Comes to rest
– Manufacturer theory:
• 800 ft x 12” Diameter Column
is about 20 tons of water
• Shaft flexes and reverses
spin
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Line Shaft Vertical Turbine Well Pump• Anti-Reverse Ratchet
– VFD Program was
modified to slow speed
down to near stop before
cutting loose
– May still slam during an
immediate shutdown like
a power outage
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
• Dual VFDs
– Pros• Allows a wide variety of operations
• Allows a complex startup/shutdown that is protective of the system
• Well can target a strictly monitored flow at various operating conditions
– Cons• Complicated startup and programming challenges
• Short span of pipe between well and booster limits flexibility, and holds a high pressure
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Split Case Booster
Well Pump
Check Valve
Pressure Gauge
Pressure Gauge
Check Valve
Pressure Gauge
Air Relief
VFD-Controlled Motors
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Split Case Booster
Check Valve
Pressure Gauge
Pressure Gauge
Check Valve
Pressure Gauge
Air Relief
Well Pump
50 Hz
00 Hz
00 psi 170 psi 210 psi
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Split Case Booster
Check Valve
Pressure Gauge
Pressure Gauge
Check Valve
Pressure Gauge
Air Relief
Well Pump
50 Hz
00 Hz
20 psi 170 psi 210 psi
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Split Case Booster
Check Valve
Pressure Gauge
Pressure Gauge
Check Valve
Pressure Gauge
Air Relief
Well Pump
58 Hz
55 Hz
170 psi 170 psi 210 psi
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
Split Case Booster
Check Valve
Pressure Gauge
Pressure Gauge
Check Valve
Pressure Gauge
Air Relief
Well Pump
58 Hz
55 Hz
40 psi 210 psi 210 psi
2,000 GPMBooster VFD maintains
suction pressure
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
• Shutdown Sequence
– Almost the same as startup but reversed
• Booster slows until flow is near zero
• Booster shuts off
• Well pump slows to about 43 Hz, which is the
minimum speed before the well almost dead heads
• Well shuts off
• Reverse ratchet engages
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.
Construction Startup
• Safety Features
– Pressure Switches
– Zero Flow Timer
– Pump Motor Switches
• Vibration
• Overtemp
– Normal Shutdown for most alarms
• Protects well system and avoids potential shocks
to the water system
• Test them all during startup
Local. Trusted. Advisors. J-U-B ENGINEERS, INC.