LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number:...
Transcript of LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number:...
![Page 1: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/1.jpg)
LOGAN WATER ALLIANCE
JIMBOOMBA WWTP CAPACITY ASSESSMENT & STAGING PLAN
TASK NUMBER: 90-12-53
MAY 2014
![Page 2: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/2.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 2 of 94 Rev: 1
Approval Register
Date
Project Manager Submitted
Planning & Project Management Team Review
Program Review
Controlled Document – Change Register
Revision Section Changed Change Description Initial Date
A All Draft Report BM/LF 05/05/2014
B All Format draft for Program Review SS 07/05/2014
C 4.1, 6.2.1, Appendix B Reviewed and amended TP/LF 22/05/2014
1 Final Format SS 23/05/2014
![Page 3: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/3.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 3 of 94 Rev: 1
TABLE OF CONTENTS
EXECUTIVE SUMMARY ................................................................................................................................. 8
1. INTRODUCTION ............................................................................................................................... 11
1.1 Objectives ...................................................................................................................................... 11
1.2 Scope ............................................................................................................................................. 11
1.3 Business Drivers ............................................................................................................................ 12
2. PLANNING CONTEXT ...................................................................................................................... 13
2.1 Background .................................................................................................................................... 13
2.2 Previous Studies ............................................................................................................................ 14
2.3 Existing Situation ........................................................................................................................... 15
3. METHODOLOGY .............................................................................................................................. 20
3.1 Key LCC Stakeholders .................................................................................................................. 21
3.2 Assumptions .................................................................................................................................. 22
3.2.1 Desired Standards of Service .................................................................................................... 22
3.2.2 General ...................................................................................................................................... 22
3.2.3 Cost Assumptions ...................................................................................................................... 22
4. WWTP EXTERNAL CONSTRAINING FACTORS............................................................................ 24
4.1 Jimboomba Wastewater Infrastructure and Flows ........................................................................ 24
4.1.1 Population and Flows ................................................................................................................ 24
4.1.2 Existing Wastewater Network .................................................................................................... 25
4.1.3 Future Wastewater Upgrades and Network Strategy ................................................................ 26
4.1.4 Catchment Growth and Pumped Flows ..................................................................................... 27
4.2 Effluent Disposal and Discharge Allowances ................................................................................ 28
4.2.1 Recycled Water Users and Requirements ................................................................................ 28
4.2.2 Future DA negotiations – Lagoon Overflow ............................................................................... 29
4.3 External Constraining Factors Summary ....................................................................................... 30
5. EXISTING WWTP CAPACITY AND PERFORMANCE .................................................................... 31
5.1 WWTP Overview ........................................................................................................................... 31
5.2 Hydraulic Assessment ................................................................................................................... 31
5.2.1 Hydraulic Infrastructure .............................................................................................................. 31
5.2.2 Observed Hydraulic Performance.............................................................................................. 33
5.2.3 Hydraulic Modelling Outcomes .................................................................................................. 34
5.3 Biological Assessment ................................................................................................................... 34
5.4 WWTP Capacity ............................................................................................................................ 35
6. PRELIMINARY OPTIONS DEVELOPMENT .................................................................................... 37
6.1 Upgrade Requirements .................................................................................................................. 37
![Page 4: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/4.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 4 of 94 Rev: 1
6.2 Preliminary Options ....................................................................................................................... 37
6.2.1 Pumped Flow Management ....................................................................................................... 37
6.2.2 Inlet Works and Associated Considerations .............................................................................. 39
6.2.3 Treatment Process Options Considerations .............................................................................. 40
6.2.4 Chlorine Contact Tank Options .................................................................................................. 43
6.3 Preliminary Options Workshop Outcomes ..................................................................................... 43
6.4 Options for Further Development .................................................................................................. 44
7. DETAILED OPTION ANALYSIS ....................................................................................................... 47
7.1 Option 1 – Upgrade SBR and Peak Instantaneous Flows Balancing Tank .................................. 47
7.2 Option 2 – Upgrade SBR and Wet Weather Balancing Tank ........................................................ 50
7.3 Option 3 – Upgrade SBR and Wet Weather Bypass ..................................................................... 53
7.4 Option 4 – Duplicate SBR .............................................................................................................. 56
7.5 Option 5 – Parallel Package Plants ............................................................................................... 59
8. OPTION EVALUATION ..................................................................................................................... 62
8.1 Cost Analysis ................................................................................................................................. 62
8.1.1 Population Sensitivity Analysis .................................................................................................. 63
8.2 Multi Criteria Analysis .................................................................................................................... 64
8.3 Preferred Option and Staging ........................................................................................................ 66
8.3.1 Future considerations for the preferred option development ..................................................... 69
9. CAPITAL WORKS PROGRAM IMPLICATIONS .............................................................................. 70
10. CONCLUSION ................................................................................................................................... 71
11. RECOMMENDATIONS ..................................................................................................................... 72
12. REFERENCES .................................................................................................................................. 73
FIGURES
Figure 2-1: Jimboomba WWTP General Arrangement Plan ...................................................................... 17 Figure 2-2: Recycled Water User locations for Jimboomba WWTP .......................................................... 19 Figure 3-1: Task Methodology ................................................................................................................... 20 Figure 4-1: Jimboomba WWTP Current and Future Population Projections ............................................. 25 Figure 4-2: Jimboomba Wastewater Catchment ......................................................................................... 26 Figure 5-1: Jimboomba WWTP Aerial View ............................................................................................... 31 Figure 5-2: Jimboomba WWTP Infrastructure Schematic .......................................................................... 32 Figure 5-3: Jimboomba WWTP Future Loads and Current Capacity. ....................................................... 36 Figure 6-1: Jimboomba WWTP Pump Station Connection points with Current and Proposed flow
Monitoring ................................................................................................................................................. 40 Figure 7-1: Option 1 Infrastructure Schematic ........................................................................................... 49
![Page 5: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/5.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 5 of 94 Rev: 1
Figure 7-2: Option 2 Infrastructure Schematic ........................................................................................... 52 Figure 7-3: Option 3 Infrastructure Schematic ........................................................................................... 55 Figure 7-4: Option 4 Infrastructure Schematic ........................................................................................... 58 Figure 7-5: Option 5 Infrastructure Schematic ........................................................................................... 61 Figure 8-1: Preferred Option Site Master Plan ........................................................................................... 68 Figure -B1: Jimboomba Wastewater Catchment ........................................................................................ 79 Figure -B2: Jimboomba Wastewater Configuration (Up to 2021) - Schematic ......................................... 79 Figure B-12-3: Stage A SPS73 – Duty / Assist Single Pump Operation (RM DN80, n = 100%) ............. 85 Figure B-12-4: Stage A SPS74 – Duty / Standby Single Pump Operation (RM DN150, n = 88%) ......... 85 Figure B-12-5: Stage B SPS73 – 2021 Duty / Standby Single Pump Operation (RM DN150, n = 90%) 87 Figure B-12-6: Stage B SPS74 – 2021 Duty / Standby Single Pump Operation (RM DN150, n = 95%) 87
TABLES
Table 0-1: Cost and Non-Cost Comparison Between Upgrade Options .................................................... 9 Table 2-1: Overview of Recycled Water Users and controls for Jimboomba WWTP Effluent ................. 18 Table 3-1: Consultation with Key LCC Stakeholders ................................................................................ 21 Table 4-1: Population projections and wastewater loads for the Jimboomba WWTP .............................. 24 Table 4-2: Pump Station Capacity – Existing and 2016 PWWF ............................................................... 27 Table 4-3: Jimboomba WWTP RWMP Critical and Quality Control Points and their respective critical
limits and alert levels ....................................................................................................................................... 28 Table 4-4: Jimboomba WWTP TN and TP performance 2010-2013, including adopted upgrade limits .. 29 Table 5-1: WWTP key infrastructure and their capacities ......................................................................... 33 Table 5-2: Indicative outcomes of simplstic hydraulic modelling .............................................................. 34 Table 6-1: Upgrade Requirements for Jimboomba WWTP ...................................................................... 37 Table 6-2: Upstream pump controls and resulting maximum WWTP inflow rates ................................... 38 Table 6-3: Preliminary Options Workshop Options Overview ................................................................... 44 Table 6-4: Overview of Developed Upgrade Options for Further Analysis ............................................... 46 Table 7-1: Option 1 - Description of Works ............................................................................................... 47 Table 7-2: Option 1 – Capital Cost Estimate, Staging and Schedule ....................................................... 48 Table 7-3: Option 1 – Benefits and Disadvantages .................................................................................. 48 Table 7-4: Option 2 - Description of Works ............................................................................................... 50 Table 7-5: Option 2 – Capital Cost Estimate, Staging and Schedule ....................................................... 51 Table 7-6: Option 2 – Benefits and Disadvantages .................................................................................. 51 Table 7-7: Option 3 - Description of Works ............................................................................................... 53 Table 7-8: Option 3 – Capital Cost Estimate, Staging and Schedule ....................................................... 54 Table 7-9: Option 3 – Benefits and Disadvantages .................................................................................. 54
![Page 6: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/6.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 6 of 94 Rev: 1
Table 7-10: Option 4 - Description of works ................................................................................................ 56 Table 7-11: Option 4 – Capital Cost Estimate, Staging and Schedule ....................................................... 56 Table 7-12: Option 4 – Benefits and Disadvantages .................................................................................. 57 Table 7-13: Option 5 - Description of Works ............................................................................................... 59 Table 7-14: Option 5 – Capital Cost Estimate, Staging and Schedule ....................................................... 59 Table 7-15: Option 5 – Benefits and Disadvantages .................................................................................. 60 Table 8-1: Capital, Operational and NPV Cost Comparison Across Jimboomba WWTP Upgrade Options
................................................................................................................................................. 62 Table 8-2: Population Sensitivity Assessment – NPV Comparison .......................................................... 63 Table 8-3: MCA Framework and Weighting ............................................................................................. 64 Table 8-4: MCA Outcomes........................................................................................................................ 65 Table 8-5: Preferred Option Costs and NPV Compared with Option 4 .................................................... 66 Table 8-6: Preferred Option Itemised Works and Staging ........................................................................ 67 Table 9-1: Capital Works Program Amendments ..................................................................................... 70 Table B-1: Jimboomba Network Loadings – 2014 to 2021 Planning Horizons ......................................... 80 Table B-2: Pump Station Capacity – Existing and 2016 PWWF ............................................................... 83 Table B-3: Stage A Network Operation – Prior to Jimboomba WWTP Capacity Augmentation ............... 84 Table B-4: Stage B Network Operation – Post Jimboomba WWTP Capacity Augmentation ................... 86
APPENDICES
Appendix A Desired Standards of Service Appendix B Jimboomba Wastewater Catchment Pump Station Management Analysis Appendix C Jimboomba WWTP Performance Assessment and Existing SBR Upgrade Reports (Hartley,
2014) Appendix D Preliminary Options Matrix Appendix E Capital Cost and NPV
![Page 7: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/7.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 7 of 94 Rev: 1
ABBREVIATIONS
ADWF Average Dry Weather Flow
BOD Biological Oxygen Demand
CED Common Effluent Drainage
CCT Chlorine Contact Tank
CWP Capital Works Program
DA Development Approval
DEHP Department of Environment and Heritage Protection
DSS Desired Standards of Service
EP Equivalent Population
FY Financial Year
HRT Hydraulic Retention Time
IDM Infrastructure Demand Model
LCC Logan City Council
LWA Logan Water Alliance
MCA Multi-Criteria Assessment
MLSS Mixed Liquor Suspended Solids
NPV Net Present Value
PDF Peak Dry Flow
PPS Private Pump Station
PWWF Peak Wet Weather Flow
RWMP Recycled Water Management Plan
SBR Sequencing Batch Reactor
SPS Sewerage Pump Station
TN Total Nitrogen
TP Total Phosphorus
TWL Top Water Level
VSD Variable Speed Drive
WWTP Wastewater Treatment Plant
![Page 8: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/8.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 8 of 94 Rev: 1
EXECUTIVE SUMMARY
The Jimboomba Wastewater Treatment Plant (WWTP) currently services the township of Jimboomba.
Recent upgrades in the wastewater network have increased peak instantaneous flows to the WWTP,
disturbing the biological process of the plant and affecting the overall effluent quality. On occasions, the
process has been effectively ‘washed away’, resulting in poor effluent quality until the biological process can
recover. Since September 2013, blue-green algal blooms have consistently been sighted in the effluent
storage lagoon, attributed to poorer effluent quality. Blue-green algae sightings have restricted recycled
water use, which is the main form of effluent disposal.
Strategic Planning includes the construction of the proposed Cedar Grove WWTP by 2021; with network
growth to be accommodated at the Jimboomba WWTP up to this time; however, the Jimboomba WWTP is
currently operating at (or near) capacity. As the WWTP is intended as an ‘interim’ asset until construction of
Cedar Grove WWTP, any interim upgrades need to be considered to balance between adequate treatment
and capital expenditure.
This current planning study includes an assessment of the current capacity and performance of the
Jimboomba WWTP and identifies cost effective works to improve plant performance and increase plant
capacity in the short-term to facilitate forecast population growth up to 2021.
Jimboomba WWTP Capacity Assessment
The Jimboomba WWTP consists of an inlet works with coarse screening, a continuously fed, intermittently
decanted sequencing batch reactor (SBR), a chlorine contact tank (CCT), and an 18 ML recycled water
storage lagoon. The site also has two sludge lagoons and an onsite sludge dewatering facility. The treatment
plant is producing Class C effluent after the effluent storage lagoon, which is distributed to recycled water
users via their private infrastructure.
Based on biological and hydraulic assessments, the Jimboomba WWTP has a biological capacity of 1,500
EP and is limited to a flow of approximately 30 L/s in the SBR. Observed constraints at the plant include
MLSS (sludge) overflow from the SBR at plant inflows greater than around 30 L/s, whereas, the biological
capacity is limited to the tank volume and aeration capacity.
The inlet works are also constrained to approximately 35 L/s and the Chlorine Contact Tanks to 31 L/s (at a
9 minute hydraulic retention time).
Population, Flows and External Constraints
The population growth in Jimboomba is uncertain. An assessment of the previous planning estimates in the
Jimboomba WWTP Upgrade Project Development (LWA, 2011) and recent development applications and
changes result in a population estimated for 2021 of 2,730 EP. These estimates are yet to be verified against
the new Infrastructure Demand Model (still in progress). Due to the high proportion of CED systems in the
current network, the revised 2021 biological load is approximately 2,530 EP.
![Page 9: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/9.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 9 of 94 Rev: 1
The LCC pump stations that discharge direct to the WWTP have no VSD or systemic controls and can be as
high as 49 L/s with the current infrastructure configuration, increasing to a maximum of 78 L/s through
planned upgrades and reconfigurations. This inflow is far above the treatment limit of the SBR at 30 L/s. A
range of pump station management strategies were investigated and the preferred and most practical option
is the management of pump stations to reduce peak instantaneous flows to the WWTP to 54 L/s:
· SPS73 and SPS74 include VSD flow limitations to restrict peak pumped flow to the minimum
required for adequate pipe velocity, while meeting PWWF
· Systemic controls between pump stations to ensure that the two LCC pump stations do not pump at
the same time, except in extreme wet weather events
Negotiations with DERM are underway for operational license modifications to allow lagoon effluent release
to Hendersons Creek during wet weather. Additional water quality and receiving environment restrictions are
anticipated, and are assumed as the same or better than current performance for this study.
Options Assessment
Five detailed upgrade options were developed, based on a future maximum pumped flow of 54 L/s and
contributing population of 2,600 EP by 2021:
· Option 1 – Upgrade SBR and Peak Instantaneous Flows Balancing Tank
· Option 2 – Upgrade SBR and Wet Weather Balancing Tank
· Option 3 – Upgrade SBR and Wet Weather Bypass to CCT
· Option 4 – Duplicate SBR
· Option 5 – Parallel Package Plant.
Options 1 to 3 involve increasing the SBR tank capacity, weir length and aeration capacity. The duplicate
SBR and parallel package plant options were anticipated to cater for both biological and hydraulic
requirements. All options include an upgrade to the inlet works and CCTs and also assume that pumped flow
management is adopted in the catchment, reducing peak instantaneous flows to 54 L/s.
Table 0-1 shows the cost and non-cost assessment between WWTP upgrade options.
Table 0-1: Cost and Non-Cost Comparison Between Upgrade Options
Option 1 –
Upgrade SBR and peak flow balancing tank
Option 2 – Upgrade SBR &
wet weather balancing tank
Option 3 – Upgrade SBR
and wet weather bypass
Option 4 – Duplicate SBR
Option 5 – Parallel
Package Plant
Capital cost (2014 $) $2.4m $2.6m $2.5m $2.6m $3.6m
NPV (over 25 year period) $12.7m $12.8m $12.6m $12.3m $13.9m
![Page 10: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/10.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 10 of 94 Rev: 1
% Variation from lowest NPV 3.1% 4.2% 2.3% 0.0% 14.8%
Cost Rank 3 4 2 1 5
MCA Score (out of 10) 2.52 5.32 2.42 8.62 8.66
Non-Cost Rank 4 3 5 2 1
Based on the cost and non-cost considerations, duplicating the SBR to accommodate hydraulic and
biological increases (Option 4) is the preferred option, with a low capital and NPV cost, a high MCA scoring
and the flexibility to stage works with flow balancing during the initial stages.
The preferred option is a modified version of Option 4, which included the small balance tank, for balancing
instantaneous average day pumped flows, followed by duplication of the SBR to accommodate hydraulic and
biological increases. Due to the anticipated scheduling for design completion and construction funding, the
SBR upgrade is proposed to be completed in one stage. The duplicate SBR option also allows for some
flexibility in the construction of the transfer pipeline to the proposed Cedar Grove WWTP. The preferred
staging and capital works to be added to the capital works budget equates to a total of $2.8m for the upgrade
of Jimboomba WWTP:
· FY14/15 – inlet works upgrade and installation of an instantaneous peak flow balance tank ($0.37m)
· FY15/16 – new SBR unit and upgrade CCTs ($2.4m)
Recommendations
The Logan Water Alliance recommends that Logan City Council (LCC):
1. Adopt the construction of a duplicate SBR as the preferred upgrade strategy for the Jimboomba
WWTP, which incorporates the following works:
a. Stage 1 (FY14/15) – install new inlet works and fine screen with 30 kL flow balancing tank
b. Stage 2 (FY15/16) – commission a duplicate SBR and chlorine contact tanks
2. Proceed with the detailed design of the inlet works and 30 kL balance tank
3. Implement pump station management of the upstream LCC operated pump stations, which involves:
a. Stage A (pre-WWTP commissioning) – delaying SPS73 connection to 150 mm rising main,
VSD control and duty/standby operation of SPS74, and installing systemic control between
SPS73 and SPS74
b. Stage B (post WWTP upgrade) – VSD control, duty/standby operation and limiting flows to
minimum velocity requirements for SPS73 and SPS74
![Page 11: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/11.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 11 of 94 Rev: 1
1. INTRODUCTION
The Jimboomba Wastewater Treatment Plant (WWTP) currently services the township of Jimboomba, which
forms part of the Logan South wastewater network.
Recent upgrades within the local wastewater network have increased the peak instantaneous flows that can
be transferred to the WWTP. The increased peak flows have disturbed the biological process of the
treatment plant and affected overall effluent quality. On occasions, the process has been effectively ‘washed
away’, resulting in poor effluent quality until the biological process can recover.
Since September 2013, blue-green algal blooms have consistently been sighted in the WWTP effluent
storage lagoon. These algae blooms have been attributed to the poorer effluent quality from increased flows
to the WWTP and also the detrimental effects from contamination by Hendersons Creek during a peak storm
event in January 2013. Blue-green algae sightings have restricted recycled water use, which is the main
form of effluent disposal.
The proposed Cedar Grove WWTP is scheduled for construction in 2021 and will replace the Jimboomba
WWTP; however, the Jimboomba WWTP is suspected to operating at or near capacity. A capacity
assessment is required to determine timing for interim upgrades before the transfer to Cedar Grove WWTP
can be constructed. As the Jimboomba WWTP is intended only to be an ‘interim’ asset, a balance between
adequate treatment upgrade and capital expenditure is imperative.
This planning report outlines the capacity assessment of the current Jimboomba WWTP and details upgrade
strategies to maintain adequate operation of the WWTP until the network flows are diverted to the proposed
Cedar Grove WWTP.
Objectives The objective of this planning study is to confirm the current capacity and performance of the Jimboomba
WWTP and to identify works required to improve plant performance and meet capacity projections prior to
the transfer of flows to the proposed Cedar Grove WWTP.
Scope
The scope for this planning study includes a number of processes:
· Review related planning documentation and monitoring data
· Review population forecasts in consultation with LCC Water Development Services
· Undertake site visit to identify constraints/opportunities with LCC Treatment Operators
· Identify process bottlenecks in terms of equivalent populations (EPs)
· Investigate short term solutions to relieve peak inflows to WWTP
· Identify minor works that can be undertaken to improve plant capacity
· Undertake a first principles cost estimation for all options
· Undertake population sensitivity analysis for identified options
![Page 12: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/12.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 12 of 94 Rev: 1
· Undertake stakeholder workshop with LCC Planning, LCC Asset Management and LCC Treatment
· Select the preferred option in conjunction with key stakeholders
· Develop a master plan for WWTP site
· Prepare draft and final reports
The scope of this current study does not include the management and control of effluent.
Business Drivers The business drivers for undertaking works at the Jimboomba WWTP are identified as follows:
Growth A review of previous planning, the 2010 Infrastructure Demand Model (IDM) and current development
applications has indicated that the contributing catchment population to the Jimboomba WWTP is projected
to increase from approximately 1,680 EP (Equivalent Population) in 2014 to approximately 8,150 EP at
ultimate development (nominally 2051). This increase represents an average annual growth rate of
approximately 4.4%.
The catchment contains areas of common effluent drainage (CED) systems, which effectively reduces the
biological load (in EPs) to approximately 1,480 EP for the 2014 (current) system.
Previous planning has indicated that the WWTP has a capacity of approximately1,500 EP, and is anticipated
to reach this limit by 2015.
Compliance Compliance with the WWTP development approval (DA) (or operating licence) is part of the legal
requirement for operating the plant. LCC also has a general environmental duty to prevent or mitigate the
risk of environmental harm, as outlined in the Environment Protection Act 1994. The current DA does not
stipulate water quality limits for disposal, however, does indicate that recycled water guidelines needs to be
adhered to for safe practice of recycled water use. No releases to waterways are allowed under the current
DA.
The DA is currently under review for release of treated waters to the nearby Hendersons Creek during wet
weather. Any released flows will need to have no negative impact on the receiving waters.
Ineffective treatment due to biological overload, or alternatively hydraulic overload impacts such as sludge
and solids carryover from the treatment into the effluent, will likely decrease the stored effluent water quality.
This could negatively impact third party users of recycled water or future releases to Hendersons Creek.
Improvement Recent improvements to the SPS74 (JMSP2) pump flowrate in August 2013 and a lack of private pump
stations control, has resulted in high peak pumped flows to the plant during both wet and dry weather. These
high flow rates have impacted the inlet screen pit and caused biological process loss or ‘washout’ on several
occasions.
Managing these flow variations is essential to ensuring the existing and future WWTP processes are not
impacted.
![Page 13: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/13.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 13 of 94 Rev: 1
2. PLANNING CONTEXT
Background
The Jimboomba WWTP services the Jimboomba village population of around 1,600 EP. During the 2008
Water Reform, Jimboomba WWTP was transferred to Logan City Council’s (LCC’s) jurisdiction from
Beaudesert Shire Council. It is now located in LCC’s Southern District.
Approximately 60% of the existing Jimboomba catchment is serviced via a common effluent drainage (CED)
system. The CED system involves primary settlement of wastewater in on-site septic tanks, before the
effluent is discharged to the treatment plant via reduced diameter mains, lowering the biological and
hydraulic load on the treatment plant by around 25%.
All wastewater from the catchment is currently pumped to the WWTP via four pump stations: SPS73, SPS74
and two private pump stations. Recent rising main upgrades at SPS74 in 2013 have increased the pumped
flowrate to the plant. Upgrades at SPS73 have recently been completed (but not commissioned) and will also
increase pumped flow to the WWTP.
All treated effluent flows historically have been used for land irrigation, primarily to the Hills College and Golf
Course. An additional recycled water user in a local horse paddock has also been approved. A minor amount
of effluent is also used to irrigate vegetation within the treatment plant boundaries. All effluent is stored in an
onsite effluent storage lagoon, prior to transfer. DA requirements only stipulate a level of quality that meets
local recycled water guidelines, with no unique quality limits for the Jimboomba WWTP. There is currently no
allowance in the DA for overflow from the lagoon into the adjacent Hendersons Creek, however, negotiations
for an overflow discharge with DEHP are being progressed.
A WWTP process refinement and tuning study was conducted in 2008/09 in conjunction with an upgrade and
irrigation strategy to accommodate estimated flow projections. Following this study, designs for a conversion
to an MBR was rejected in 2010 due to significant costs and acknowledgement that a high level of water
quality was not required for golf course irrigation purposes. The Jimboomba WWTP Upgrade – Project
Development planning study (LWA, 2012) included revised population projections, indicating that growth was
not as high as originally estimated and concluded that only minor operational improvements were required
until population growth reached plant capacity.
Strategic planning impacts within the area include a deferral of the transfer of the Jimboomba wastewater
catchment to Cedar Grove until 2021. Approximately $10m of infrastructure is required to complete the
transfer, prior to the decommissioning of Jimboomba WWTP.
![Page 14: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/14.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 14 of 94 Rev: 1
Previous Studies Previous planning studies that provide background to this current planning study are outlined below:
n 90-10-87-001 - Jimboomba WWTP Upgrade Project Development (LWA, November 2011) – This
report identified that the plant currently has the capacity to treat a biological loading of 1,500 EP. The
Development Approval did not allow for discharge to water bodies. All effluent was stored at the effluent
storage lagoon located at the treatment plant or pumped to the Hills Education Foundation Irrigation
Lagoon. The effluent is currently treated to a Class C recycled water standard.
The outcomes of this study determined that:
- management of peak wet weather flows to the plant is required to protect the biological process
- only minor works and operational adjustments were required in the short term
- a conveyance solution from Jimboomba to the new Cedar Grove WWTP is the preferred servicing
strategy and would be required between 2015 and 2021
n LWA Work Package 7603 - Jimboomba WWTP Upgrade - In 2009 and 2010, the design of a upgrade
at Jimboomba WWTP was undertaken as part of Work Package 7603. The design proposed to upgrade
the plant to a Membrane Biological Reactor (MBR) process with a capacity of 2,600 EP. This design was
approximately 50% complete when it was identified that the Cedar Grove WWTP was likely to be the
preferred WWTP location for the Logan South wastewater network. The design was subsequently put on
hold until the Jimboomba WWTP Upgrade Project Development Report (November 2011) verified the
preferred servicing strategy for Jimboomba.
n LWA Work Package 7617 - Jimboomba Sewerage Rising Main Upgrade - The existing DN80 rising
mains from pump stations SPS73 and SPS74 were upgraded to DN150 in 2012 and the SPS74 rising
main was brought online by September 2013. Variable speed drives (VSDs) were proposed to be fitted to
these pump stations to provide flow control, though are yet to be completed. Due to uncertainty
surrounding the effects of increased flows to the plant on the biological process, it was recommended
that only SPS74 be switched over to the new DN150 main.
n 90-11-46 - Jimboomba WWTP Recycled Water Management Plan (LWA, 2013) – A legal document
outlines the recycled water users, key recycled water infrastructure, recycled water guidelines and any
adopted risk mitigation for the effluent disposal of Jimboomba WWTP. This document contains reference
to recycled water agreements between users and highlights guideline practices and key control
measures adopted by LCC.
n 90-12-42 - Jimboomba WWTP - Wet Weather Overflow Mitigation Strategy (LWA, ongoing) – The
review of wet weather overflows from the WWTP effluent (and irrigation storage) lagoon was driven by a
Show Cause notice from DEHP for uncontrolled overflow during dry weather, resulting from flooding of
the lagoon from Hendersons Creek and previous weeks of continuous rainfall. This study identified
controlled release measures to manage the lagoon levels during low irrigation periods. The DA with
![Page 15: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/15.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 15 of 94 Rev: 1
DEHP is currently under revision to allow controlled release to Hendersons Creek during wet weather. A
number of options for wet weather storage were considered and discarded as part of this study.
n 90-12-33 - East Street Jimboomba Wastewater Conveyance - Detailed Planning and Preliminary Design (LWA, December 2013) – Planning for the conveyance of waste water flows from the
undeveloped south east of the catchment was revised in light of developer applications and delay of
Cedar Grove WWTP. The revised Jimboomba wastewater network operation was incorporated into
pumped flow estimates for this report.
n 90-12-21 - Revision of Logan South Wastewater Network Servicing Strategy (LWA, January 2014)
– This report re-examined the preferred servicing strategy for the Logan South wastewater network
based on new population forecasts provided by Economic Development Queensland for the Yarrabilba
and the Greater Flagstone Priority Development Areas. This study identified Jimboomba and Flagstone
WWTP capacities of 1,500 EP and 2,550 EP respectively. It concluded that conveyance to the new
Cedar Grove WWTP remains the preferred option for the Jimboomba Township; however, the
construction of the Cedar Grove WWTP could be deferred until 2021.
Existing Situation
Jimboomba Wastewater Catchment
As part of Work Package 7617 – Jimboomba Sewerage Upgrade, the existing DN80 rising mains from pump
stations SPS73 and SPS74 were upgraded to DN150. This rising main upgrade effectively increased the
pumping capacity at these two pump stations from approximately 6 L/s to 21 L/s (with one pump running at
each pump station).
Variable speed drives (VSDs) have been installed but not yet commissioned at these pump stations to
provide flow control and to reduce peak pumping to peak wet weather flow rates. At the time of SPS73 and
SPS74 rising main installation, only SPS74 was at capacity during wet weather events and therefore it was
connected to the new DN150 main. SPS73 is anticipated to be connected to its new rising main when
SCADA data indicates that it is unable to accommodate peak wet weather flows through the smaller
diameter rising main.
Overflow structures have been installed at both pump stations, with basic screening on SPS73 and a baffle
plate on SPS74 (pers. comms, L Bridgham, LCC, 14th April 2014).
Wastewater Treatment Plant (WWTP)
The Jimboomba WWTP consists of:
· a 20 mm bar-screen inlet works
· a single continuously fed sequence batch reactor (SBR) with intermittent decant
· a 17 kL chlorine contact tank (CCT)
· an 18 ML effluent storage lagoon
![Page 16: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/16.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 16 of 94 Rev: 1
· two sludge lagoons
· a mobile fan press for sludge dewatering
The inlet screen is planned to be upgraded in 2014.
The WWTP is currently operates with 5 cycles per day and produces a standard quality effluent for a
continuously-fed SBR on dry weather days. Increased peak flows regularly disturb the biological process of
the plant affecting the overall effluent quality, particularly when the plant is in ‘settle’ mode, resulting in
settled sludge uplifting over the weir into the chlorine contact tanks.
Recent storm events (March 2013) have highlighted the impact of the upgraded peak instantaneous flows to
the WWTP. Consistent wet weather pumped flows to the WWTP above 30 L/s impacted the biological
process, causing the mixed liquor suspended solids (MLSS) to be ‘washed away’. The loss of MLSS due to
high flows has occurred on a number of occasions, and typically results in poor effluent quality until the
biological process recovers (approximately 2 weeks). In the March 2013 event, raw wastewater also backed
up from the inlet works through associated pipework and into the sludge storage lagoon, which was able to
contain the raw wastewater as it was almost empty at the time of the storm event. Shorter periods of high
flowrate pumping have occasionally resulted in near spills from the Inlet Screen Pit (November 2013).
Figure 2-1 shows the general arrangement plan of Jimboomba WWTP.
![Page 17: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/17.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 17 of 94 Rev: 1
Figure 2-1: Jimboomba WWTP General Arrangement Plan
![Page 18: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/18.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 18 of 94 Rev: 1
Recycled Water Storage and Users
All recycled water is disposed through local irrigation and generally meets recycled water guidelines and
requirements. Table 2-1 and Figure 2-2 outlines the current recycled water users for Jimboomba WWTP.
Table 2-1: Overview of Recycled Water Users and controls for Jimboomba WWTP Effluent
User 1 User 2 User 3
Proprietary Name Logan City Council Hills Educational Foundation Ltd Brisbane Property Pty Ltd
Land Parcel RP859595/28 RP859595/1 RP151380/2 SP203522/3
Recycled Water Permitted Use
WWTP open space irrigation
Golf course and school garden irrigation Horse paddock irrigation
Type of Irrigation Traveller irrigation Spray Irrigation Traveller irrigation Recycled Water Quality Requirement
Class C Recycled Water 95% of samples <1000 cfu/100 mL
Support Documentation Recycled Water management Plan: Exemption Guidelines – Appendix 1
Key on-site control measures
· Signage and colour coding
· Training and inductions
· Low throw sprinklers
· Vegetation barriers · Cease irrigation
during windy days
· Signage and colour coding · Staff training and awareness · Restricted access · Buffer zone (40 m) · Withholding period (no
access during or for 4 hours after irrigation)
· Midnight irrigation · No high pressure sprinklers
for school gardens · Algae control
· Signage and colour coding · Visitor training and
awareness · Fencing · Buffer zone (>50 m) · Cease irrigation during windy
days · Protect horse water trough · Restrict horses until grass
paddock is dry · Restrict use if any algal
blooms sighted Recycled Water Agreement in place NA Yes Yes
![Page 19: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/19.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 19 of 94 Rev: 1
Figure 2-2: Recycled Water User locations for Jimboomba WWTP
The Golf Course (User 2) is supplied via a privately-owned pump station, which conveys effluent to the Hills
Golf Course lagoon on-site. The horse paddock (User 3) and WWTP site (User 1) is supplied via a separate
council-owned pump station located on the other side of the lagoon.
Recent consistent blue-green algae outbreaks have limited the use of recycled water for irrigation to local
horse paddocks due to the risk to livestock and public. The consistent outbreaks have been attributed to
poorer treatment quality which has likely occurred due to the recent catchment upgrades. LCC has installed
an algae management unit, consisting of a carbon filter, in the attempt to mitigate blue-green algae
outbreaks.
No overflow discharge is allowed in the current DA; however, negotiations with DEHP are planned to
incorporate this into the licence. Ideally, the changes will include discharge to the adjacent Hendersons
Creek during wet weather events when the creek is flowing. The discharge limits in a revised DA are
uncertain for overflow during wet weather, although it is expected that there may be quality limits and creek
dilution factors.
![Page 20: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/20.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 20 of 94 Rev: 1
3. METHODOLOGY Figure 3-1 describes the methodology for this Task.
Stage 1 Background
•Review background information •Confirm project drivers including business case reviiew •Review existing population forecasts •Review historical WWTP monitoring data
Stage 2 Minor Works Options
Assessment
• Identify process bottlenecks • Investigate short term solutions to relieve peak flows • Identify minor works to improve plant capacity •Hold stakeholder workshop to confirm minor works augmentation strategy •Undertake population sesnitivity analysis for minor works augmentation strategy
Stage 3 Major Works Options
Assessment
•Develop detailed options for longer term augmentation strategy (next 10 – 15 years)
•Undertake first principles cost estimation for all options •Hold a stakeholder MCA workshop to discuss the costs, benefits and challenges of each option
•Agree preferred option and develop master plan for WWTP site
Figure 3-1: Task Methodology
![Page 21: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/21.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 21 of 94 Rev: 1
Key LCC Stakeholders Table 3-1 summarises the key stakeholders that were consulted at various stages during this study. An
options workshop was held at Jimboomba WWTP with LCC stakeholders to identify potential options, and a
final MCA workshop was held at LWA office with LCC stakeholders. Regular meetings and site visits were
held with LCC plant operations to discuss project progress and to investigate option feasibility, and to
present findings of the investigation.
Table 3-1: Consultation with Key LCC Stakeholders
Function Name Position Level of Consultation
Water Business Daryl Ross Logan Water Business Manager · MCA workshop
Water Development Services Marco Bonotto
Water Development Services Program
Leader · MCA workshop
Treatment Imtiaj Ali Treatment Engineer
· Preliminary options workshop · Site Meetings · Receiving Environment Meeting · Ongoing consultation throughout the
duration of the Task · MCA workshop
Treatment Bill Smith Plant Operator
· Preliminary options workshop · Site Meetings · Ongoing consultation throughout the
duration of the Task · MCA workshop
M&E Operations Darshan Udayaratna
Mechanical & Electrical Operations Program
Leader · Pump Station Management Meeting
M&E Operations Lester Bridgham Mechanical & Electrical Supervisor · Pump Station Management Meeting
Water Product Quality Chris Pipe-Martin Product Quality
Program Leader -
· Preliminary options workshop · Receiving Environment Meeting · MCA workshop
Water Product Quality Amy Flynn
Environmental Management Systems
Officer
· Site Meetings · Preliminary options workshop · Receiving Environment Meeting · MCA workshop
Water Product Quality Kambez Akrami
Product Quality Systems Officer
· Receiving Environment Meeting · MCA workshop
Asset Management Darren Moore Water Asset
Management Program Leader
· MCA workshop
![Page 22: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/22.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 22 of 94 Rev: 1
Asset Management Troy Kasper Water Cycle Planning Coordinator · MCA workshop
Water Cycle Planning Jackie Clutten Water Cycle Planning Coordinator · MCA workshop
Assumptions
3.1.1 Desired Standards of Service Logan City Council’s Desired Standards of Service (DSS) for Wastewater systems and treatment plants and
included within Appendix A.
3.1.2 General In addition to the DSS, the following general assumptions are adopted for this planning study:
Population and inflow:
· CED systems reduce biological and hydraulic loading by 25%
· No future CED systems to be incorporated to WWTP catchment
· 2010 IDM populations are adopted as a basis for further adjustment based on LCC development
information, taken from the report Jimboomba WWTP Upgrade Project Development (LWA,
November 2011) and adjusted.
Hydraulic assumptions:
· Inlet screen headloss equates to upstream overflow at the sludge lagoon at 37 L/s
· Site contributions to inlet pit flows are less than 1 L/s, thus not significant
Treatment assumptions:
· The existing SBR weir only lowers 0.45 m, not the full 0.6 m (as observed by LCC Operators)
· Alum dosing will be required for blue green algae management in future
· Alum and pH dosing assumed to be part of a package plant (so not itemised separately)
· All upgrades should produce effluent of similar standard or better to meet potential DEHP lagoon effluent release requirements (negotiations currently on hold).
3.1.3 Cost Assumptions Cost estimates were developed for all identified options and are based on the following assumptions:
Capital costs:
· Quotations from suppliers
· First principles estimates for civil works provided by LWA estimator (where appropriate)
· 30% contingency allowance
![Page 23: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/23.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 23 of 94 Rev: 1
· All capital costs are shown in 2014 dollars and are provided in the appendices
Operational costs:
· cost of electricity = $0.15/kWh
· Maintenance costs = 1% of capital costs
· Yearly allowance of extra chemical use of $5,000 p.a.
· Labour allowance, at $50/hr, up to 3 days/week, dependant on upgrade operational complexity
· The Operational Cost Estimates are shown in 2014 dollars and are provided in the appendices
NPV Analysis:
· Net present value (NPV) assessments will be undertaken over a period of 25 years
· The discount rate applied is LWA standard 4.75%
![Page 24: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/24.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 24 of 94 Rev: 1
4. WWTP EXTERNAL CONSTRAINING FACTORS This section details the upstream and downstream constraining factors that affect Jimboomba WWTP
process, including a review of the catchment contributing population (refer to Appendix B for more detail).
Jimboomba Wastewater Infrastructure and Flows
4.1.1 Population and Flows The Jimboomba WWTP operational records indicate that the WWTP currently receives approximately
241 kL/d average daily flow, increasing from 222 kL/d in 2012/13. The plant has also received peak daily
flows of 1027 kL/d within a 24 hour period (March 2014).
The updated IDM projections were not available for this current study; therefore, population projections for
the Jimboomba WWTP were adopted from the Jimboomba WWTP Upgrade Project Development (LWA,
November 2011). These estimates were adjusted to incorporate recent development applications and
planning changes, as detailed in Table 4-1 and Figure 4-1. The impact of the CED system (approximately
60% of the existing catchment) is a reduction of 25% biological load and 50% PWWF, also shown in Table
4-1 and Figure 4-1 below.
Table 4-1: Population projections and wastewater loads for the Jimboomba WWTP
2014 2016 2021 2026
Total EP 1,678 2,144 2,735 3,840
Total ADWF Load (kL/d) 335 430 548 767
Biological EP 1,480 1,940 2,530 3,630
![Page 25: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/25.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 25 of 94 Rev: 1
Figure 4-1: Jimboomba WWTP Current and Future Population Projections
These population and flow estimates are slightly less conservative than the Logan South Wastewater
Servicing Plan (LWA, January 2014) which did not provide detail on division of EP across the catchment
pump stations flowing directly to the WWTP. Wastewater loads have been calculated based on the Logan
Water Desired Standards of Service (DSS) which incorporate the reduced loads and flow of the CED
systems.
4.1.2 Existing Wastewater Network The existing wastewater network consists of traditional gravity sewers, common effluent drainage (CED)
systems, five Council owned sewerage pump stations (SPS), two existing and one future private pump
stations (PPS). Figure 4-2 provides an overview of the Jimboomba wastewater catchment and its
infrastructure.
0
20
40
60
80
100
120
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
2014 2016 2021 2023 2026 2031 ULTIMATE
Hydr
aulic
PW
WF
(L/s
)
Biol
ogic
al L
OAD
EP
Jimboomba WWTP - Predicted Loads
TOTAL EP:
Biological EP:
PWWF (L/s)
![Page 26: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/26.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 26 of 94 Rev: 1
Figure 4-2: Jimboomba Wastewater Catchment
The WWTP receives flows directly from SPS73, SPS74, Hills College PPS and the Johanna St Child Care
Centre PPS. An additional private pump station is planned for the catchment, which will be associated with a
future Stockland development (i.e. Stockland PPS).
The rising main arrangement associated with SPS73 and SPS74 is as follows:
· Pump station SPS73 transfers flows to the WWTP via a DN80 rising main. A new DN150 rising
main augmentation has been constructed, but is yet to be commissioned.
· Pump station SPS74 has recently been connected to an augmented DN150 rising main to increase
the capacity of the pump station due to its history of wet weather overflows.
4.1.3 Future Wastewater Upgrades and Network Strategy The East Street Jimboomba Wastewater Conveyance – Detailed Planning and Preliminary Design (LWA,
Jan 2014) Planning Report outlines the current adopted servicing strategy for Jimboomba. The high level
servicing strategy for the Jimboomba catchment is based on the transfer of flows to the planned regional
Cedar Grove WWTP in 2021. At this time the transfer infrastructure, consisting of a new pump station and
7.5 km of DN375 rising main, will be constructed to convey flows from Jimboomba to Cedar Grove allowing
the decommissioning of the Jimboomba WWTP. During the expected life of Jimboomba WWTP (i.e. up to
2021) the following catchment changes are anticipated:
1. Growth in the south east (i.e. near East Street) will require a new SPS76 to transfer flows to SPS74
until 2021, and a new SPS80 pumping flows to SPS73
![Page 27: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/27.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 27 of 94 Rev: 1
2. SPS73 will be connected to its new DN150 rising main to increase capacity
3. Stockland development along the west of the Mount Lindsay Highway is likely to be completed in the
next few years. It is proposed to connect the Stockland private pump station to the disused SPS74
DN80 rising main
4.1.4 Catchment Growth and Pumped Flows Five pump stations will contribute flows directly to the Jimboomba WWTP between now and 2021. These
include:
· Two Council owned pump stations (i.e. SPS73 and SPS74)
· Three privately owned pump stations, which include two existing pump station assets (i.e. Hills
College and the Johanna St child care facility) and the future pump station to service the Stockland
development.
Table 4-2 shows the current pump station capacities compared to PWWF up to 2021.
Table 4-2: Pump Station Capacity – Existing and 2016 PWWF
Pump Station RM Nominal Diameter
Single Pump (Duty) Flow
Dual Pump (Duty / Assist)
Flow
2014 PWWF
2016 PWWF
2021 PWWF
[-] [mm] [L/s] [L/s] [L/s] [L/s] [L/s]
SPS73 80 6.7 1 7.0 1 7.6 8.4 10.9
SPS74 150 25.7 1 29.7 1 9.9 13.8 19.6
Hills College 100 8.3 3 - 3 2.0 2.0 2.0
Johanna St Child Care 50 2 2.4 4 4.0 5 0.2 0.3 0.3
Stockland 80 4.5 6 6 6 NA 1.8 2.1
Total 47.6 55 19.7 26.3 34.9 Notes: 1 – Capacity was based on pump station drawdown test with SPS73 connected to a DN80 rising main and SPS74 connected to the existing DN150 rising main 2 – A DN50 rising main has been assumed. This will need to be confirmed in the field. 3 – Flow rate based on ‘as constructed’ drawings and system resistance curves provided. No information provided as to pump configurations and a single pump configuration is assumed. 4 – Minimum flow based on a minimum 0.9 m/s velocity requirement and DN50 rising mains. The DN50 pipe would have a 45 mm internal diameter for an assumed PE pipeline. 5 - Maximum flow based on a maximum 2.5 m/s velocity requirement and assuming DN50 rising mains. The DN50 pipe would have a 45 mm internal diameter for an assumed PE pipeline. 6 - Minimum flow based on a minimum 0.9 m/s velocity requirement and DN80 rising mains. A maximum flow rate based on a maximum 2.5 m/s velocity requirement in a DN80 rising main is likely to concur high head loss and unlikely to meet this requirement. Therefore, the flow is unlikely to exceed 6 L/s.
The following can be deduced:
· The current capacity of SPS73 (i.e. PWWF 7.0 L/s) is below the expected DSS requirement in 2016
(i.e. PWWF 8.4 L/s). However, a review of actual SCADA suggests that flows into the pump station
are currently less than current projected flows.
· The current capacity of pump station SPS74 is well in excess of DSS requirements in 2016
![Page 28: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/28.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 28 of 94 Rev: 1
· Drawdown test results used for this study show a close correlation with theoretical calculations for
SPS73, but a significant error is applicable in relation to SPS74 (refer Appendix B). Further
investigation is required to confirm asset characteristics for SPS74.
· The total peak flows entering the WWTP are estimated at 49 L/s (excluding Stockland at present
time). However, when SPS73 is connected to the 150 mm rising main and increases peak flows at
this pump station to 30 L/s (duty/assist operation), the total peak flows in 2021 could be as high as
78 L/s.
Effluent Disposal and Discharge Allowances
4.1.5 Recycled Water Users and Requirements The existing DA does not stipulate any nutrient or physical parameter limits and only indicates that relevant
guidelines should be adhered to for effluent disposal. No discharge to environment is allowed under this
licence.
A Recycled Water Management Plan (RWMP) and recycled water user agreements were collated in July
2013 to provide a framework for safe practice and use of effluent irrigation. The three main users are:
· Jimboomba WWTP onsite irrigation
· Hills Golf Course and College
· Adjacent horse paddocks
Of the three users, the onsite WWTP irrigation accounts for a comparatively minor amount of effluent
disposal.
The RWMP adopts limits outlined under Appendix 1 of the Recycled Water Exemption Guidelines. Key
critical and quality control points from the RWMP are outlined in Table 4-3.
Table 4-3: Jimboomba WWTP RWMP Critical and Quality Control Points and their respective critical limits and alert levels
Critical and Quality Control Points Critical Limits Alert Levels
E. coli count Water in the effluent storage pond: 1000 cfu/100mL*
Water leaving WWTP (outlet of chlorine contact tank): 100 cfu/100mL
Free chlorine residual (Minimum) Leaving WWTP (outlet of chlorine contact tank): 0.2 mg/L
Leaving WWTP (outlet of chlorine contact tank): 0.3 mg/L
Algal or cyanobacterial bloom 15,000 cells/mL Visual inspection results in suspicion of algal bloom
Free chlorine residual (Maximum) Leaving WWTP (outlet of chlorine contact tank): 2 mg/L
Leaving WWTP (outlet of chlorine contact tank): 1.7 mg/L
NB: * Equivalent Class C Recycled Water
![Page 29: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/29.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 29 of 94 Rev: 1
According to the RWMP (July 2013):
If E.Coli levels reach the critical limit, the operator will inform each recycled water user and shut the
pumps off. The pumps will remain off until the chlorine residual and E.Coli levels are brought to within the
alert limits. The effluent storage lagoon will be used to hold the off-spec effluent.
In addition to on-line monitoring, the effluent lagoon is sampled for E.Coli on a weekly basis. If any
sample exceeds 1,000 cfu/100 mL, a follow-up sample is taken and the recycled water users are notified
of the possible exceedances.
Algae/cyanobacteria are sampled when a bloom is suspected. If the presence of algae is confirmed
(greater than 15,000 cells/mL), the recycled water users will be notified to suspend irrigation. Once
irrigation has ceased, the operator will manage the algal/cyanobacterial bloom at the effluent lagoon by
referring to the Jimboomba WWTP Lagoon Management Strategy (developed and managed by Logan
City Council).
As no nutrient indicators have been outlined in the DA or the RWMP, the effluent standards are expected to
be the same or better after any WWTP upgrades. Table 4-4 shows the performance of Jimboomba WWTP
from 2010 to 2013.
Table 4-4: Jimboomba WWTP TN and TP performance 2010-2013, including adopted upgrade limits
Year Total Nitrogen (mg/L) Total Phosphorus (mg/L)
Median Maximum Median Maximum
2010 10 23 8 10
2011 10 66* 8 13
2012 7 22 6 18
2013 9 28 7 11
Adopted Current Standard 10 30 8 20
NB: * Indicates that maximum during 2011 was during a period of biological inactivity, likely sludge wash-out, therefore not
adopted as current standards
An adopted median TN:TP of 10:8 (in mg/L) has been identified as the current standard of the WWTP. A
standard similar or better should be the basis for future upgrades.
4.1.6 Future DA negotiations – Lagoon Overflow Negotiations with DEHP are underway to include allowances for emergency lagoon overflow into the
adjacent Hendersons Creek.
Hendersons Creek experiences intermittent stream flows, primarily during wet weather events, and is
considered a sensitive receiving environment. The creek water level and flowrate increase quickly during a
![Page 30: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/30.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 30 of 94 Rev: 1
wet weather event to velocities suitable for effluent dilution. Previous discussions between LCC and DEHP
have indicated lagoon effluent releases will not be allowed when the creek is not flowing.
Additional effluent release requirements from DEHP are anticipated, and may include zero negative impacts,
effluent TN/TP ratios and/or a creek dilution factor.
As this negotiation process is still in progress, uncertainties currently exist regarding the level of quality and
quantity of lagoon effluent allowed. For this reason, it is assumed that all upgrades should produce effluent
of similar standard to current performance (or better), and additional treatment will occur in the lagoon to
accommodate the future release limits.
External Constraining Factors Summary Based on an assessment of the future population projections and catchment pump capacities, the estimated
future maximum instantaneous flow in 2021 is 78 L/s, without pump flow rate control. The estimated
population in 2021 is 2,730 EP. Due to the CED systems in the catchment, this reduces to an equivalent to a
biological EP of 2,530 EP in 2021. The corresponding PWWF flow is approximately 35 L/s.
Although there are no quality limits in the existing DA, it is expected that any upgrades should produce
effluent similar or better than the current standards. A future DA is under negotiation which will allow release
to an intermittently-flowing creek; however, the quality and quantity allowances are still uncertain.
The Jimboomba WWTP RWMP states critical and quality control limits to form guidelines that protect
environment and public health with the practice of effluent irrigation to recycled water users. The RWMP
includes values for:
· The effluent leaving the WWTP:
o alert limits of 1.7 mg/L and critical limit of 2 mg/L maximum free chlorine
o alert limit 100 cfu/100 mL E. Coli
· Effluent in the lagoon:
o critical limit of 1000 cfu/100 mL E. Coli
o alert limit of no visual inspection of blue-green algae
o critical limit of 15,000 cells/100 mL of blue-green algae.
All upgrades should adhere to the alert limits of the effluent leaving the WWTP, as best as practical.
![Page 31: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/31.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 31 of 94 Rev: 1
5. EXISTING WWTP CAPACITY AND PERFORMANCE
WWTP Overview The Jimboomba WWTP consists of an inlet works with coarse screening, a continuously fed, intermittently
decanted sequencing batch reactor (SBR), a chlorine contact tank (CCT), and an 18 ML recycled water
storage lagoon. The site also has two sludge lagoons and onsite sludge dewatering facility. The treatment
plant is producing Class C effluent after the effluent storage lagoon, which is distributed to recycled water
users via their private infrastructure. Figure 5-1 shows an overview of the WWTP.
Figure 5-1: Jimboomba WWTP Aerial View
Hydraulic Assessment
5.1.1 Hydraulic Infrastructure The WWTP is a gravity flow system, and was designed to use the natural slope of the site to maintain gravity
flow throughout the plant, thus requiring no lift pumps within the plant itself. Figure 5-2 shows a schematic of
the infrastructure connectivity.
![Page 32: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/32.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 32 of 94 Rev: 1
Figure 5-2: Jimboomba WWTP Infrastructure Schematic
The WWTP process involves:
· Rising mains from the catchment pump stations transfer inflows to the plant via the two receiving
manholes. External inflows combined with small site flows (including sludge lagoon supernatant (or
overflow) and sludge dewatering filtrate) gravitate to the inlet screen pit
· Screened flows gravitate to the SBR continuously. The mechanically controlled weir slowly lowers at
the end of a treatment cycle to decant flows into the decant pit
· Flows from the SBR are transferred to the chlorine contact tank (CCT) via a flowmeter and control
valve, throttled to 31L/s to ensure an appropriate hydraulic retention time (HRT) within the CCT
· Flows from the fixed CCT outlet weir enter the gravity main, and flow to the effluent storage lagoon.
The SBR contains a large inlet baffle for redirecting inflows to the tank floor, aeration equipment for biological
treatment and wasting equipment for excess sludge removal. The SBR currently operates on a 4.8 hour
cycle, with 80 minutes decant time and an average decant flowrate of 19 L/s (plus WWTP inflows). The 17 kL
CCT has a HRT of 82 minutes during ADWF, or 9 minutes at limited flow of 31 L/s. Plant recycled water
offtakes and pumps are located near the outlet of the CCT. There is no wet weather bypass.
Key hydraulic WWTP infrastructure and their capacity limitations are summarised in the following table.
![Page 33: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/33.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 33 of 94 Rev: 1
Table 5-1: WWTP key infrastructure and their capacities
5.1.2 Observed Hydraulic Performance Observed performance during operation of the WWTP has been used in part to verify the hydraulic
modelling:
· The weir was observed to be submerged during normal operation decant, and does not appear to lower its full 0.6m design level to horizontal or beyond
· During the March 2014 storm event, the WWTP received its highest daily flow of 1027kL, including a continuous maximum pumped flow from SPS 73 and 74 simultaneously (37L/s) over a 3 hour period, plus flows from private pump stations, though duration and frequency cannot be verified. Ongoing high flows resulted in the WWTP inlet pit and upstream infrastructure surcharging and overflowing at the lowest available point, filling Sludge Lagoon 2 with raw wastewater
· On multiple occasions, high pumped flowrates above 30L/s have been observed by LCC operators to scour out the MLSS (sludge) from the SBR
· The inlet screen pit has been observed to reach over 90% full on a number of occasions since the connection of SPS74 to its new rising main in August 2013. The 13th and 24th November 2013 occurrences are additionally observed through inlet pit level data analysis. Additionally, SCADA data indicated a high number of pump runs for SPS73 and 74 at this time, with some combined duty and standby pump runs, though simultaneous pump runs were not verified.
WWTP component Size Capacity
Pipes 225 dia.
24L/s at 75% full (min grade) 26L/s at 100% full (min grade)
300 dia.
44L/s at 75% full (min grade) 48L/s at 100% full (min grade)
Inlet Screen and Pit Pit is 1kL Observed. 37+L/s
Screen is 20mm spaced 15mm coarse bar
SBR
618kL 17 x 12 x 4m
operating volume 92kL
Observed 30+L/s
SBR Weir 3m wide, 0.45m operating depth
SBR Decant Pit
1kL 3.2 x 0.75 x 1.5
Flowmeter and throttling valve 300 dia. Set to 31 L/s
CCT
17kL 22 x 0.7 x 1.6m
31L/s HRT of 9 mins
CCT weir and pit
0.7m slight v notch concrete weir 0.6kL
0.5 x 0.7 x 1.6m
Lagoon 18ML 18ML 0.5m freeboard
![Page 34: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/34.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 34 of 94 Rev: 1
5.1.3 Hydraulic Modelling Outcomes Hydraulic modelling (via a simple excel model) was used to estimate hydraulic performance and key
constraints at nominated flowrates. Modelling was undertaken for both throttled and free flows using the two
scenarios SBR full, and SBR after decant, and assumes no losses at any point in the system. The model has
been aligned with known hydraulic data, however, is not calibrated, and should only be used as a guide. The
results of the model are included in the following table.
Table 5-2: Indicative outcomes of simplstic hydraulic modelling
Asset Surcharge Insufficient Freeboard Overflow
SBR - n/a - around 60L/s - around 100L/s
CCT - n/a - around 35L/s - around 100L/s
CCT Effluent Main - above 40L/s - manhole - around 100L/s - around 100L/s
Inlet Pit - n/a - around 50 L/s - around 60L/s - (around 50 L/s with increased
blinding of screen)
Influent Mains - pipes – around 30L/s - manholes - around 30L/s - manholes - around 40L/s
- sludge lagoon connection – over 36L/s
- manhole near sludge lagoon - around 50L/s
- other manholes - above 55L/s
At inflows at approximately 50 L/s, the sludge lagoon connection and adjacent manhole are likely to be
overflowing, with inlet pits and upstream infrastructure surcharged. Without throttled flow; the CCT is above
its freeboard level. In addition, headloss reduction of around 50% across the inlet screen pit would reduce
the risk of overflows from upstream manholes, though the sludge lagoon connection may still overflow at
inflows above 50 L/s (when the screen blinding factor is decreased from 90% to 70%).
The analysis indicates that the SBR is theoretically above its hydraulic capacity at around 60 L/s, and the
CCT at around 35 L/s, though the CCT effluent main and manhole are only likely to spill for flows above
100 L/s. The inlet screen pit and upstream pipework has hydraulic limitations that need to be considered
when developing solutions, especially for managing the sludge lagoon connections and system surcharging.
Biological Assessment A detailed assessment of the current performance of the WWTP (Hartley, 2013 – refer to Appendix C)
concluded summary of the assessment concluded that:
· The design capacity of the current SBR is 1,500 EP
· The estimated population in 2013 is 1,100 to 1,200 EP based on BOD loads and accounting for the
CED systems in the catchment (assuming 25% reduction in BOD)
![Page 35: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/35.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 35 of 94 Rev: 1
· From July 2011 to September 2013, the effluent quality was:
o Median TN and TP concentrations were 8.8 mg/L and 7.1 mg/L, respectively, whereas
maximum concentrations during this period were 66 mg/L and 18 mg/L
o Median E. Coli was <1 cfu/100 mL and 95th percentile was 56 cfu/100 mL
o Median free chlorine residual was 0.4 mg/L and maximum was 2.1 mg/L
· In general, the performance showed that:
o Effluent BOD and SS were low except for high flow periods where significant solids
carryover occurred during decanting
o Nitrogen removal was performing as exhibited by median effluent ammonia-N and TN
concentrations of 0.6 mg/L and 8.8 mg/L
o No enhanced biological P removal was occurring, as the median effluent TP was 7.1mg/L
o Chlorination was effective
Anecdotal evidence from operators indicates that solids carryover occurs above approximately 31L/s to
34L/s. This is limited to the weir length, which is a contributing factor to sludge blanket scouring when
considering the weir approach velocity.
The key bottlenecks in the continuous SBR system that limit the plant to 1,500 EP are the tank operating
volume, the aeration capacity and the operating cycle time.
The CCT is performing at the current dry weather flows, producing Class B recycled water from the outlet of
the CCTs. The current peak flow hydraulic retention time (HRT) for the CCTs is 9 minutes. The operators
have limited the flow upstream of the CCT, by reducing a valve to 31 L/s.
WWTP Capacity Based on the hydraulic and biological assessments, the Jimboomba WWTP has a capacity of approximately
1,500 EP and is limited to a flow of 30 L/s in the SBR. The inlet pit and upstream pipework are currently
constrained at approximately 35 L/s, and the CCT at 31L/s (for adequate treatment).
Figure 5-3 shows the predicted loads and current capacity of the WWTP. According to the estimates, the
biological capacity will be reached by 2015; however, actual flows and loads indicate development in the
catchment is slightly lower than the theoretical EP predictions. An effluent water quality analysis indicates the
plant is currently able to effectively treat inflows, except during significant peak inflow (wet weather) events.
![Page 36: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/36.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 36 of 94 Rev: 1
Figure 5-3: Jimboomba WWTP Future Loads and Current Capacity
Peak wet weather flows are received at the plant as pumped flows, and the current peak pump flow capacity
of 49 L/s maximum instantaneous flow is substantially higher than the 2021 PWWF estimate of 35 L/s, due
to current operating parameters (no VSD or system flow controls). This pumping capacity also allows high
flows from extreme wet weather events to be pumped continuously to the plant, effectively flooding the plant,
washing out MLSS, and contaminating the effluent lagoon. This impacts the treatment performance for
around the next one to two weeks.
Based on the assessment, hydraulic upgrades for Jimboomba WWTP are required as soon as practical, with
biological upgrades required by 2016 to maintain discharge requirements (subject to realised growth rates
and treatment plant performance).
0
10
20
30
40
50
60
70
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
5,000
2014 2016 2021 2023 2026
Hydr
aulic
PW
WF
(L/s
)
Biol
ogic
al L
OAD
EP
Jimboomba WWTP - Predicted Loads and Current Capacity
Biological EP:
WWTP biological capacity (EP)
PWWF (L/s)
Hydraulic Capacity (L/s)
![Page 37: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/37.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 37 of 94 Rev: 1
6. PRELIMINARY OPTIONS DEVELOPMENT This section provides a brief overview of the preliminary options development prior to determining detailed
options for further investigation and analysis.
Upgrade Requirements Table 6-1 shows the adopted upgrade requirements for the Jimboomba WWTP in different areas of the
WWTP based on the constraining factors and current WWTP capacity.
Table 6-1: Upgrade Requirements for Jimboomba WWTP
Catchment Inlet Works Biological Process Chlorine Contact Tanks
Capacity at 2021 with no upgrade 78 L/s 35 – 40 L/s 30 L/s 1500 EP 3 min HRT (at
peak flow)
Requirement for Upgrade
<78 L/s flow based on upstream pump station flow management
2530 EP or greater
9 min HRT or greater (at peak
flow in 2021)
All final options will be developed to accommodate the required capacity to meet the future projections in
2021 (assumed year for Cedar Grove WWTP diversion).
Preliminary Options
6.1.1 Pumped Flow Management Managing the flows reaching the WWTP is a simple effective measure to reduce the hydraulic impacts
currently being experienced at the WWTP. Options to reduce the WWTP pumped inflow include:
1. Do nothing
2. Delaying connection of SPS73 to the 150 mm dia. rising main (limiting flow from this SPS to 6.5 L/s
until diversion through the new rising main)
3. Restrict pump operation at SPS74 (and SPS73 in future) to a Duty/Standby arrangement
4. Implement systemic control to ensure that only one key pump station can operate at the one time
(though this restriction will be overridden if the pump stations are close to overflow as per operation
licence requirements)
5. Implement VSD controls to limit pumping flow rates at SPS73 and SPS74. This requires
consideration of minimum velocity requirements
Apart from the do nothing scenario, all options were considered for implementation in order to reduce peak
flows entering the WWTP as best as practicable.
VSDs have been installed at SPS 73 and SPS74; however; have not been commissioned. A review of the
system curve for both pump stations indicates that VSD-controlled reduction is within the feasible range,
![Page 38: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/38.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 38 of 94 Rev: 1
though this will need verification onsite to ensure effective solids lifting. In addition, the pumps may need to
run at full speed for a very short time on a regular cycle (i.e. once a day) to maintain operability.
In addition, system controls currently being rolled out across the LCC network should be implemented in this
catchment to manage dry weather pumping peaks that are reaching the WWTP, to reduce simultaneous
pumping flow impacts on the WWTP process and regulating the plant inflows.
To limit immediate peak flow impacts, the SPS73 future 150 mm main should not be connected until SCADA
data indicates pump station overflow events (or high risk of overflow) during reasonable storm events.
Current SCADA data indicates SPS73 has not been overflowing in recent years, including the large March
2014 storm event.
Based on the status of the existing Jimboomba WWTP and the potential upgrade of the plant to
accommodate future growth and network constraints out to 2021, network capacity needs to be considered
in two stages. These stages include:
· Stage A Existing – Consideration needs to be given to the capacity constraints of the existing plant
to ensure its effective operation up to the resolution of the WWTP capacity constraints
· Stage B Future – Based on current network assets and catchment growth, a suitable capacity
constraint needs to be established for consideration in the development of Jimboomba WWTP
capacity options
Table 6-2 shows the proposed pump station strategies for pre and post WWTP upgrade. These strategies
are compared to do nothing estimates for the existing and future network configurations. Refer to Appendix B
for more detailed information.
Table 6-2: Upstream pump controls and resulting maximum WWTP inflow rates
Option Existing (do nothing)
Future (do nothing)
Stage A Existing (pre WWTP upgrade and commissioning period)
Stage B Future (post WWTP upgrade)
SPS 73 7 30 7 17.3
SPS 74 29.7 29.7 17.3 19.6
Hills College 8.3 8.3 8.3 8.3 Johanna St Child Care 4 4 4 4
Stockland - 6 4.5 4.5
Total (L/s) 49 78 Up to 34.1 53.7
Comment · Impacts WWTP
· Impacts WWTP
· Systemic control between SPS73 and SPS74
· VSD control · Delay SPS73 connection · Reduce Stockland PPS to
minimum velocity · Total flows reduced to
29.6 L/s if Stockland connection is delayed
· No systemic control required
· VSD control · Reduce Stockland
PPS to minimum velocity
![Page 39: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/39.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 39 of 94 Rev: 1
If systemic and VSD control is implemented in the short-term (i.e. Stage A), the maximum flow rate reaching
Jimboomba WWTP is estimated as 34.1 L/s. This is likely to cause some process issues at the WWTP if
sustained for long pumping periods. To avoid process issues at the WWTP, the flow may be reduced further
to 29.6 L/s if Stockland connection is delayed until after any WWTP upgrades.
Upgrade options for the Jimboomba WWTP should consider 53.7 L/s as an appropriate capacity (i.e. Stage
B). However, this assumes some form of restrictions can be achieved in terms of flows received from private
pump stations, with the Stockland pump station as a prime candidate.
6.1.2 Inlet Works and Associated Considerations Inlet screen capacity
The current inlet works consist of a manually-cleaned 20 mm bar screen located within a small 1 kL concrete
pit. At times, the inlet pit is known to temporarily surcharge to over 90% full, though has not yet spilt from this
location (as per the inlet pit level sensor data 2013-14 provided by LCC).
A recent storm event in March 2014 flooded the inlet works and backed up raw wastewater into one sludge
holding lagoon, which was partially empty at the time of the event. The hydraulic assessment has indicated a
capacity of approximately 35 L/s upstream of the SBR, due to a combination of constraints including the inlet
screen and pit, associated upstream and downstream pipework and the sludge lagoon inflow connection.
With flow management control in the catchment pump stations, the maximum flow can be reduced to
maximum instantaneous peaks of approximately 54 L/s prior to diversion of flows to the proposed Cedar
Grove WWTP, which far in excess of the 35 L/s capacity. As such, the inlet works requires an upgrade.
Upgrade considerations have been limited to fine screening and increasing the inlet works capacity to
accommodate peaks prior to screening. Fine screening is preferred over the current bar screens, as this will
help improve ragging entering the SBR and protect the operating assets. The two types of fine screening
units considered were a sieve screw screen or a step screen. The step screen was discounted due to
associated difficulties with installing screens within a retrofitted inlet works and the requirement of a long
approach channel. The sieve screw screen has been successfully operated at the Flagstone WWTP and
therefore has been adopted for the purposes of this planning study. The screen will have the capacity to treat
54 L/s and have appropriate overflow in the case where the screen fails.
The inlet works pit volume should be increased appropriately to allow for reasonable instantaneous flow
fluctuation upstream of the sieve screw screen. The screen and pit should be designed to minimise headloss
and potentially overflow to storage, to assist in avoiding wastewater backing up to the sludge lagoons, or
overflowing from the adjacent manhole. Automated valves should also be installed in the inlets to the sludge
lagoons to protect overflow into the lagoons.
The inlet works upgrade will be applied across all options.
![Page 40: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/40.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 40 of 94 Rev: 1
Flow Monitoring Considerations
The WWTP currently has no control of the pumped flows that enter via the catchment. Flow monitoring is
available in the new connection of SPS74 but is not yet available for SPS73 until it is connected to its new
rising main. There is no control or monitoring of current private pump stations (Hills College and Johanna
Road Child Care Centre). Figure 6-1 shows the current flow monitoring arrangement.
The ideal flow monitoring arrangement to ensure all external instantaneous flows can be monitored at the
plant, is upstream of the inlet works collection manhole as indicted in Figure 6-1. This flow monitoring
upgrade will be applied across all options.
Figure 6-1: Jimboomba WWTP Pump Station Connection points with Current and Proposed flow Monitoring
6.1.3 Treatment Process Options Considerations Treatment process hydraulic and biological considerations result in a 30 L/s limitation, with any higher
instantaneous flows likely to cause settled sludge blanket uplift (i.e. sludge blanket scour) and may cause
solids loss in the SBR. This flow rate corresponds to the WWTP design capacity of 1,500 EP.
Any process upgrades of the SBR will need to be sufficient to cater for peak instantaneous flows of 54 L/s
(managed pump station flows) and average dry weather loads from 2,530 EP (the projected population
estimates for 2021).
![Page 41: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/41.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 41 of 94 Rev: 1
Hydraulic Upgrade Options
Potential hydraulic upgrade options could include:
· Upstream balance tank
· Wet weather bypass
· Increasing plant capacity.
Assuming upstream pump station flow management is implemented, all options will be required to
accommodate 54 L/s instantaneous flows.
Hydraulic constraints could be simply resolved through duplicating the biological treatment process train.
Increasing the plant capacity would require a parallel process train of at least 22 L/s, to limit the capacity in
the existing SBR to 30 L/s and avoid sludge blanket scouring. Several process options are available and are
discussed in the biological upgrade option section.
Flow balancing with upstream balance tanks could reduce or possibly avoid the requirement to upgrade the
SBR, and provide a near steady flow of waste water through the SBR, allowing for consistent treatment at
the plant. Flow balancing options include storage of temporarily high flows within:
· Small overflow balance tank at the inlet screen (post processing) to cater for instantaneous peak
flows during dry weather
· Large overflow balance tank at the inlet screen (post processing) to cater for all wet weather flows
· Multiple balance tanks throughout the treatment process which could mitigate the various sections of
hydraulic restrictions within the current system
Installing multiple balance tanks throughout the treatment process would have hydraulic constraints and
complicate the process, which could effectively be mitigated with a balance tank at the inlet works.
A wet weather bypass located at the inlet works could avoid the need for upgrading the hydraulic capacity of
the existing WWTP. Potential bypass options include:
· Bypass SBR only, super chlorinate at CCT
· Bypass SBR and CCT
· Bypass to separate storage, with intention of return to SBR for treatment (e.g. divided lagoon)
· Bypass to Hendersons Creek
· Bypass to Logan River
Any bypassing to local waterways would require a DA licence amendment. LCC Environment Management
officers have identified that discharge of ‘untreated wastewater’ to Hendersons Creek would not be viewed
favourably by DEHP. The current DA stipulates zero effluent discharge to the environment. Bypassing to
local waterways is not considered viable. A segmented portion of the storage lagoon is not ideal as raw
![Page 42: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/42.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 42 of 94 Rev: 1
wastewater would be regularly drained to the lagoon is small amounts and the cost would be significantly
higher to pump the flows back to the WWTP than a balance tank at the inlet works. The options for further
consideration are the bypass options within the WWTP and do not discharge to the environment directly.
These would still require an amendment to the DA.
Biological Upgrade Options
Potential biological upgrade options include:
· Do nothing (shut down WWTP during peak flows)
· Sequential upgrade of the existing SBR process
· Upgrade SBR process to MBR process
· Install parallel package plant
· Install parallel SBR plant
· Transfer flows to Flagstone WWTP
The Do Nothing option would not resolve anticipated biological capacity issues at the WWTP that will result
from the projected contributing population increase. As such, the WWTP capability to remove nutrients and
produce ‘Class C’ recycled water will become compromised in the near future and would result in
proliferating algal blooms in the effluent lagoon and hinder the ability to supply recycled water to agreed
customers. The Do Nothing approach will only be considered suitable only if minimal growth is experienced
within the catchment prior to the construction of the Cedar Grove WWTP (currently scheduled for 2021).
Sequentially upgrading the existing SBR process would involve a staged approach to increase biological
capacity based on an assessment of the existing SBR (see Appendix C). Stage 1 would involve increasing
the biological capacity from 1,500 EP to 2,100 EP, with Stage 2 further increasing the biological capacity to
2,600 EP. Required works involve increasing the existing SBR wall height by 225 mm, modifying cycle times
and increasing the decanter weir length from 3 metres to 6 metres.
The option to upgrade the SBR process to an MBR process was assessed as part of the Jimboomba WWTP
Upgrade Project Development Task (LWA Task No: 90-10-87-001, November 2011) and will not be
progressed further as part of this current study. The capital cost was estimated at approximately $6.1m
(2011$) and would provide high quality ‘Class A’ recycled water when only ‘Class C’ standards are required.
The option to transfer flows to the Flagstone WWTP would initiate an appropriate upgrade at the Flagstone
WWTP to accommodate these flows. The transfer main will not be in alignment with the future Cedar Grove
WWTP transfer main and is expected to cost $5m to $10m.
The options considered viable for further analysis are the parallel package plants and duplicating the SBR
plant. These options will provide both hydraulic and biological upgrade requirements to cater for growth and
flows until 2021.
![Page 43: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/43.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 43 of 94 Rev: 1
6.1.4 Chlorine Contact Tank Options The current CCT has a 9 minute hydraulic retention time (HRT) during peak flow periods at the current
population levels. The HRT would reduce to 3 minutes with the current tank volume at the projected
populations, adjusted operations and flows in 2021.
Based on the RWMP (2013), the critical limit for maximum free chlorine from the WWTP is 2 mg/L and the
alert limit is 1.7 mg/L, which would not be met with the reduced HRT.
Potential chlorination options include:
· Increasing the CCT volume
· Install upstream flow balancing tank
· Superchlorination (and appropriate dechlorination if necessary)
Based on the projected peak flows and expected SBR mode of operation (which has a limited decant period
as opposed to continuous operation), the ultimate peak flow through the CCTs is estimated at 95 L/s for the
2021 projected population and flow. A 3 minute HRT is not expected to produce consistent disinfection
requirements during peak flows and therefore the CCT volume should be tripled to account for population
projections at 2021. This will achieve a 9 minute HRT with a free chlorine residual of 1.5 mg/L.
Another viable option is to install upstream flow balancing, to be situated between the SBR and the CCTs.
This will effectively balance the flows and produce a more continuous operation, which will reduce the
capacity requirement. A 260 kL tank (Hartley, 2009) would be required with associated pumping (as the
hydraulics would not be sufficient to promote complete gravity flow). The balance tank option would prove
more expensive than increasing the CCTs to 51 kL.
Another option is to superchlorinate the flows and dechlorinate if appropriate. Without dechlorination, the
discharge will be greater than the 2 mg/L limit, (with a 2.3 mg/L free chlorine residual if the chlorine tanks
were doubled in size). A 3 minute HRT is not considered sufficient lag period for disinfection, even with
dechlorination and therefore this option was discounted.
The option to upgrade the CCTs to 51 kL will be applied across all options, except where a parallel package
plant duplication is installed. This would reduce the upgrade requirement to 43 kL due to its continuous
operation.
Preliminary Options Workshop Outcomes A preliminary options workshop was held at Jimboomba WWTP on 5th February 2014 and included the LWA
and key LCC stakeholders.
Table 6-3 outlines the preliminary options discussed in the workshop for hydraulic and biological upgrade, as
well as catchment control options.
![Page 44: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/44.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 44 of 94 Rev: 1
Table 6-3: Preliminary Options Workshop Options Overview
Hydraulic Upgrade Preliminary Options* Biological Upgrade Preliminary Options ** Catchment Control Options WWTP Infrastructure Options
a) Do nothing
b) Pump Station Flow Pacing
(VSD controlled)
c) Sequencing Pump Stations for
systemic control
a) Do nothing
b) Flow Balancing – balance
tank
c) Wet weather bypass and
treatment plant licence
amendment
d) Increase WWTP capacity
a) Do nothing
b) Sequential upgrade of the
existing SBR process
c) Upgrade SBR process to
MBR process
d) Add parallel package plant
e) Add parallel SBR plant
f) Transfer flows to Flagstone
WWTP
NB: * Each option can be applied separately or in combination to obtain the required hydraulic flowrate. ** Options are unlikely to be viable in combination with other biological upgrade options, however will be implemented with one or more of the hydraulic upgrade options. Outcomes of the workshop are as follows:
· The do nothing option was considered unacceptable as a biological or hydraulic option
· Flow balancing of upstream pump controls should be applied to all options, though the hydraulic capacity must be able to manage maximum pumped flow without spilling (in case controls fail)
· Transfer to Flagstone WWTP is discounted as it is too far away, with an expected cost of around $5m to $10m for infrastructure that is not in alignment for the future Cedar Grove transfer pipeline
· Wet weather treatment bypass will be problematic, as it will impact the upcoming DEHP operating license negotiations for wet weather release to Hendersons Creek from the effluent storage lagoon, but should be pursued
· Altering the existing operation philosophy to intentionally create treatment short circuiting may also be problematic regarding DEHP negotiations, however should be pursued
· Upgrading the SBR to MBR process should not be considered further, as it has previously been proven to be a significantly higher cost.
Options for Further Development The following detailed options were developed from the preliminary options:
· Option 1 – Upgrade the SBR and install a Peak Instantaneous Flows Balancing Tank
· Option 2 – Upgrade the SBR and install a Wet Weather Balancing Tank
· Option 3 – Upgrade the SBR and install a Wet Weather Bypass to CCT
· Option 4 – Duplicate the SBR
· Option 5 – Install a Parallel Package Plant
![Page 45: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/45.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 45 of 94 Rev: 1
Discounted inclusions
These options were developed using a matrix for combining the hydraulic and biological solutions,
determining which solutions meet the treatment and planning criteria (refer to Appendix D for more detail).
The options were reviewed by the LCC Operations Supervisor to remove higher operational risk. The
outcomes of this process, resulted in the following inclusion being discounted from the options due to high
risks or not meeting the planning and treatment discharge criteria:
· Wet weather bypass of the plant (to CCT outlet, Hendersons Creek or Logan River) was discounted
due to the potential impact on the lagoon (including increased nutrients and algae blooms), and/or
receiving waters. Accessibility issues, easement acquisition and significant infrastructure
requirements deterred the Logan River option
· Use of the existing effluent lagoon to store wet weather flows (with divide wall and return pump) was
discounted due to the wet weather storage complications and overflow risks, and the time required to
treat (or retreat ) the separated lagoon waters
· Undertaking an SBR upgrade without a peak instantaneous flow balance tank would risk sludge
washout during normal to high flow operation conditions.
· No controlled pumping, due to the additional hydraulic capacity of 46 L/s (from 22 L/s), effectively
doubles the managed wet weather volume (and instantaneous pumped flow volume).
Common inclusions
A number of inclusions were considered common to all options:
· System pump controls (VSD and systemic) with appropriate overflow from PS overflow location and
sufficient flow monitoring
· Hydraulic Upgrade:
· Inlet screen upgrade with sieve screw screen
· Sludge lagoon overflow valves
· Biological Upgrade:
· CCT upgrade (51kL)
· Chlorine dosing system upgrade
· Alum dosing system upgrade pH dosing system
![Page 46: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/46.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 46 of 94 Rev: 1
Table 6-4: Overview of Developed Upgrade Options for Further Analysis
Catchment Inlet Works Treatment Process Chlorine Contact Tanks
Constraint Maximum of 78 L/s 35 L/s 30 L/s 1,500 EP 3 min HRT at peak flow in 2021
Adopted Requirement for Upgrade Maximum of 54 L/s 2,530 EP or better 9 min HRT at peak flow in 2021
Option 1
Pump station VSD commissioning*
Upgrade inlet works and install fine screening**
Instantaneous flow balance tank Upgrade SBR (raise
walls, increase aeration capacity,
extend weir length, modify cycle times) Upgrade CCT volume
Option 2 Wet weather flow balance tank
Option 3 Wet weather bypass to CCTs
Option 4 Duplicate SBR
Option 5 Parallel Package Plant
NB: * Operation to include overflow at SPS 73 and SPS74 above 6.5 x ADWF as per DA allowance
** Flow monitoring to be applied at upstream manhole
![Page 47: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/47.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 47 of 94 Rev: 1
7. DETAILED OPTION ANALYSIS
Option 1 – Upgrade SBR and Peak Instantaneous Flows Balancing Tank Option 1 involves installing a 30 kL balancing tank adjacent to an upgraded inlet works, and upgrading the
existing SBR capacity. The small balancing tank will cater for peak instantaneous flows during dry weather
and consist of an overflow into the SBR when its capacity is reached. The balancing tank will protect the
treatment process by maintaining flows below 30 L/s The SBR will be upgraded to a 2,600 EP capacity,
therefore meeting the projection load requirements of 2,530 EP through upgrades to the tank capacity, weir
length and aeration capacity. The inlet works and CCTs will be upgraded as per all options.
Option 1 incorporates the following works (Table 7-1), to meet a population of 2,600 EP and a maximum
instantaneous flow capacity of 54 L/s.
Table 7-1: Option 1 - Description of Works
Stage Description of Work New Capacity Trigger for Work
1
· Install small storage tank, pump and overflow to SBR · Increase decanter length from 3 metres to 6 metres and
raise by 225mm · Raise SBR walls by 225mm · Common hydraulic upgrade – Inlet works and sludge
lagoon overflow valves
54 L/s hydraulic capacity upgrade
>30L/s pumped flow to plant – required now
2
· Increase aeration capacity · Upgrade of aeration and decanting controls · Upgrade electrical switchboard and building · Reduction of SBR operation cycle to 3 hours (from 4.8hrs) · Common biological upgrade works
2,600 EP biological capacity
1,500 EP biological capacity (CED
adjusted) – required nominally
2016
The small balance tank would smooth the instantaneous peak pumped flows of 54L/s, returning flows to the
inlet works. The new weirs would double the overall length, allowing for additional decant volume without
sludge scouring, and the wall height extension is also completed at this time.
With the increased treatment and decant volume, an aeration capacity increase, and control upgrade
increase for the loading treated, a reduced cycle time would be adopted, allowing for more treatment batches
per day. The CCT and dosing equipment would be upgraded to accommodate the increased treatment
volume.
The SBR upgrade requirements were previously determined by K. Hartley; however, the scheduling of works
has been modified to accommodate the urgent hydraulic capacity improvements.
Modelling was undertaken to verify the balance tank volume. A minimum 26 kL tank is sufficient for most
scenarios, based on 3hrs. at constant LCC pumping, with variation of set duration of 10 minutes and variable
pumping for the private pump stations: the Hills and Stockland pumps running ¾ of the time (30 min in 40
minute cycle) and the Child Care Centre pumps running a quarter of the time (10 minutes in 40minute cycle).
![Page 48: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/48.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 48 of 94 Rev: 1
A 30kL tank is currently available and unused by LCC, and sufficient to manage excess flows for 20 minutes
under continuous 54L/s pumped flows, or 30 minutes for reduced private pump station flow.
Capital Cost Estimate
The following table shows the staged capital cost estimate for Option 1.
Table 7-2: Option 1 – Capital Cost Estimate, Staging and Schedule
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1
Inlet works and sludge lagoon valves Small storage tank, pump and overflow to SBR Upgrade SBR weirs and walls - New weirs and pits, raise SBR walls 225mm Minor electrical and SCADA work
$949,000 2014/15
2
Biological upgrade – aeration system upgrade Chlorine Contact tank duplication Chemical dosing upgrade Electrical switchboard, and building (electrical or blower) upgrade Minor electrical and SCADA work
$1,468,000 2016/17*
Total $2,417,000
* biological upgrade requirement assumed to be delayed to 2016/17 as per current population estimate, to be verified
against new IDM.
All works should be designed together, to ensure hydraulic issues are consistently resolved. Project cost
efficiencies may outweigh the delayed investment for Stage 2 by undertaking a combined construction works
package, given the short period between required works.
Benefits and Risks The benefits/advantages and risks/disadvantages of this option are listed in the following table:
Table 7-3: Option 1 – Benefits and Disadvantages
Advantages and Benefits Disadvantages and Risks
§ Works can be staged to accommodate delayed biological load/ catchment growth
§ The existing SBR is fully utilised to beyond its original capacity
§ The small tank and inlet works can be implemented as soon as the design is finished (original funding in 2013/14)
§ There is less infrastructure than other options (no wet weather infrastructure)
§ Hydraulic constraints are significant and restrictive for design of the inlet screen pit and small balance tank
§ The inlet screen pit is submerged as the increased TWL of the SBR is above the inlet pit IL
§ The plant is dependent on upgraded SBR to accommodate wet weather flows. The risk of sludge overflow due to high inflows is still present, though reduced to flows above 44L/s for an extended period
§ The risk of compromised treatment quality is present, as the reduced treatment time and increased volume per cycle may not be as effective, or have resilience for treatment spikes, additional loading or environmental changes.
§ The change of process at high flows is disruptive to the treatment process and cycle timing
§ Biological upgrade is not staged, 2600EP is implemented as one stage
§ There is no further upgrade potential on the SBR § Works need to occur on an operating plant – there is
no option for diversion or shutdowns
![Page 49: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/49.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 49 of 94 Rev: 1
Figure 7-1: Option 1 Infrastructure Schematic
![Page 50: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/50.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 50 of 94 Rev: 1
Option 2 – Upgrade SBR and Wet Weather Balancing Tank Option 2 involves installing a 250 kL wet weather balancing tank adjacent to the proposed new inlet works
and upgrading the existing SBR capacity. The wet weather balancing tank will cater for peak instantaneous
flows during dry weather periods and be able to contain wet weather peak flows, pumping the excess flows
through the treatment process when flows have subsided. This option will protect the treatment process by
maintaining below 30 L/s. The SBR will be upgraded to a 2,600 EP capacity, therefore meeting the projection
load requirements of 2,530 EP through upgrades to the tank capacity, weir length and aeration capacity. The
inlet works and CCTs will be upgraded as per all options.
Option 2 incorporates the following works (in Table 7-4), across three stages to firstly meet a 54 L/s
instantaneous flow capacity, then a population of 2,100EP and finally 2,600EP.
Table 7-4: Option 2 - Description of Works
Stage Description of Work New Capacity Trigger for Work
1 Install 250kL storage tank, pump and overflow to SBR Common hydraulic upgrade – Inlet works and sludge lagoon overflow valves
54 L/s hydraulic capacity upgrade
>30L/s pumped flow to plant – required now
2
Increase aeration capacity Upgrade of aeration and decanting controls Upgrade electrical switchboard and building Reduction of SBR operation cycle to 3 hours (from 4.8hrs) Common biological upgrade – pH and alum dosing only
2,100EP biological capacity
1,500 EP biological capacity (CED
adjusted) – required nominally
2016
3
Increase decanter length from 3 metres to 6 metres and raise by 225mm Raise SBR walls by 225mm Common biological upgrade works – CCT tank and chlorine dosing only
2,600 EP biological capacity
2,100 EP biological capacity (CED
adjusted) – required nominally
2018
The large balance tank will cater for wet weather flows in addition to smoothing out the instantaneous peak
pumped flows of 54 L/s during dry weather periods.
The SBR upgrade requirements were previously determined by K. Hartley and are the same as for Option 1,
though timing of the hydraulic component is able to be delayed due to the large balance tank. The aeration
capacity and control upgrade increase the biological load treated per batch, with the reduced cycle time
allowing for more treatment batches per day so as to meet 2100EP biological capacity. To meet 2600EP
biological capacity, the wall and weir increase at the SBR is required for treatment capacity increase (to
increase volume treated per cycle) and decant volume increase.
The CCT and chlorine dosing also required upgrading to accommodate the increased treatment volumes.
The 250kL balancing tank is sized to meet 8 hrs of constant 54 L/s pumping (for a future SBR capacity of 44
L/s), and 3hrs constant pumping for the existing SBR. In addition, the large tank is also sized to meet 70% of
PDF (peak day flow) in 12hrs, 50% of PDF in 8 hrs and 30% of PDF in 4 hrs, where PDF is the maximum
plant inflows of 1027 ML/d (received 28 March 2014) escalated to 2021 volumes.
![Page 51: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/51.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 51 of 94 Rev: 1
Capital Cost Estimate
The following table shows the staged capital cost estimate for Option 2.
Table 7-5: Option 2 – Capital Cost Estimate, Staging and Schedule
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1 Inlet works and sludge lagoon valves 250kL storage tank, pump and overflow to SBR Minor electrical and SCADA work
$419,000 2014/15
2
Increase aeration capacity Upgrade of aeration and decanting controls Chemical dosing upgrade – pH and alum dosing Electrical switchboard, and building (electrical or blower) upgrade Minor electrical and SCADA work
$1,139,000 2016/17*
3
SBR weirs and walls - New weirs and pits, raise SBR walls 225mm Chemical dosing upgrade – chlorine dosing only Chlorine Contact tank duplication Minor electrical and SCADA work
$1,066,000 2017/18
Total $2,624,000
* biological upgrade requirement assumed to be delayed to 2015/16 as per current population estimate, to be verified against new IDM.
All works should be designed together to ensure hydraulic issues are consistently resolved. Inlet works
should be installed as soon as the design is completed and funding permits, preferably before the 2014/15
wet season.
A Stage 3 Biological upgrade will be required when the plant biological load reaches 2,100EP, currently
expected in 2017/8.
Project cost efficiencies may outweigh a delayed investment approach if the biological upgrade installation
work (Stage 2 only, or Stage 2 and 3) is delivered with the hydraulic upgrade (Stage 1) as a combined
construction works package.
Benefits and Risks The benefits/advantages and risks/disadvantages of this option are listed in the following table:
Table 7-6: Option 2 – Benefits and Disadvantages Advantages and Benefits Disadvantages and Risks
§ Works are staged to accommodate delayed biological load/ catchment growth
§ The existing SBR is fully utilised to beyond its original capacity
§ The inlet works can be implemented as soon as the design is finished (original funding in 2013/14)
§ The large storage tank will allow for storage of over 1 day at ADWF, allowing shut down of the SBR for maintenance or capital works.
§ Hydraulic constraints are significant and restrictive for design of the inlet screen pit and large balance tank
§ The inlet screen pit is submerged near the end of each treatment cycle as the increased TWL of the SBR is above the inlet pit IL
§ The risk of sludge overflow due to high inflows is still present, though reduced to high flows for an extended period, which overflow the large storage tank
§ The risk of compromised treatment quality is present, as the reduced treatment time and increased volume per cycle may not be as effective, or have resilience for treatment spikes, additional loading or environmental changes.
§ There is no further upgrade potential of the SBR § Some works need to occur on an operating plant
![Page 52: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/52.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 52 of 94 Rev: B
Figure 7-2: Option 2 Infrastructure Schematic
![Page 53: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/53.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 53 of 94 Rev: 1
Option 3 – Upgrade SBR and Wet Weather Bypass Option 3 involves installing a wet weather bypass from the inlet works to the CCTs and upgrading the
existing SBR capacity. Dry weather peak instantaneous flows will be accommodated by a small balance tank
adjacent to the inlet works. Wet weather peak flows will be bypassed around the main treatment process to
protect the SBR by maintaining below 30 L/s. In order to maintain a Class C effluent in the lagoon as best as
practical, a high chlorine dose will be applied to the bypass flow. The SBR will be ultimately upgraded to a
2,600 EP capacity, therefore meeting the projection load requirements of 2,530 EP, through upgrades to the
tank capacity, weir length and aeration capacity. The inlet works and CCTs will be upgraded as per all
options.
Table 7-7: Option 3 - Description of Works
Stage Description of Work New Capacity Trigger for Work
1
· Install 30kL storage tank, pump and overflow to a wet weather bypass
· Install Wet Weather Bypass to CCT inlet · Common hydraulic upgrade – Inlet works and sludge
lagoon overflow valves
54 L/s hydraulic capacity upgrade
>30L/s pumped flow to plant – required now
2
· Increase aeration capacity · Upgrade of aeration and decanting controls · Upgrade electrical switchboard and building · Reduction of SBR operation cycle to 3 hours (from 4.8hrs) · Common biological upgrade – pH and alum dosing only
2,100EP biological capacity
1,500 EP biological capacity (CED
adjusted) – required nominally
2016
3
· Increase decanter length from 3 metres to 6 metres and raise by 225mm
· Raise SBR walls by 225mm · Common biological upgrade works – CCT tank and
chlorine dosing only
2,600 EP biological capacity
2,100 EP biological capacity (CED
adjusted) – required nominally
2018
Option 3 is similar Option 2, including staging, except that a small balance tank and wet weather bypass
would replace the large balance tank.
The small balance tank will smooth the instantaneous peak pumped flows of 54 L/s, returning flows to the
inlet works, and the bypass will cater for wet weather flows, transferring them to the CCT inlet for
chlorination.
Capital Cost Estimate
The following table shows the staged capital cost estimate for Option 3.
![Page 54: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/54.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 54 of 94 Rev: 1
Table 7-8: Option 3 – Capital Cost Estimate, Staging and Schedule
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1
Inlet works and sludge lagoon valves 30kL storage tank, pump and overflow to WW bypass 30m of 225mm wet weather bypass Minor electrical and SCADA work
$246,000 2014/15
2
Increase aeration capacity Upgrade of aeration and decanting controls Chemical dosing upgrade – pH and alum dosing Electrical switchboard, and building (electrical or blower) upgrade Minor electrical and SCADA work
$1,136,000 2015/16*
3
SBR weirs and walls - New weirs and pits, raise SBR walls 225mm Chemical dosing upgrade – chlorine dosing only Chlorine Contact tank duplication Minor electrical and SCADA work
$1,080,000 2017/18
Total $2,462,000
* biological upgrade requirement assumed to be delayed to 2015/16 as per current population estimate, to be verified against new IDM.
All works should be designed together to ensure hydraulic issues are consistently resolved. Inlet works
should be installed as soon as the design is completed and funding permits, preferably before the 2014/15
wet season.
Benefits and Risks
The benefits/advantages and risks/disadvantages of this option are listed in Table 7-9:
Table 7-9: Option 3 – Benefits and Disadvantages
Advantages and Benefits Disadvantages and Risks
§ Works are staged to accommodate delayed biological load/ catchment growth
§ The existing SBR is fully utilised to beyond its original capacity
§ The inlet works can be implemented as soon as the design is finished (original funding in 2013/14)
§ The SBR treatment process is protected against high flow sludge impacts
§ Hydraulic constraints are significant and restrictive for the design of the inlet screen pit and large balance tank
§ The inlet screen pit is submerged near the end of each treatment cycle as the increased TWL of the SBR is above the inlet pit IL
§ Raw wastewater bypass may increase lagoon nutrients and impact the lagoon quality, compromising the end use of effluent, as Class C recycled water.
§ The risk of compromised treatment quality is present, as the reduced treatment time and increased volume per cycle may not be as effective, or have resilience for treatment spikes, additional loading or environmental changes.
§ There is no further upgrade potential of the SBR § All works need to occur on an operating plant , there is
no storage or shutdowns available.
![Page 55: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/55.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 55 of 94 Rev: 1
Figure 7-3: Option 3 Infrastructure Schematic
![Page 56: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/56.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 56 of 94 Rev: 1
Option 4 – Duplicate SBR This option involves installing a new 618 kL SBR unit adjacent to the existing SBR, as originally anticipated
in the initial plant design. The peak flows can be distributed between the two SBR units, maintaining peak
flows below 30 L/s in each SBR and protecting the treatment process. Doubling the SBRs will cater for the
required load of 2,530 EP by increasing the total capacity to 3,000 EP and also meeting the 54 L/s
instantaneous flow capacity. No upgrades will be required in the existing SBR. The inlet works and CCTs will
be upgraded as per all options.
Table 7-10 outlines the works required for Option 4.
Table 7-10: Option 4 - Description of works
Stage Description of Work New Capacity Trigger for Work
1
· Construct SBR tank, install weir and pipework, return pump and pipework
· Common hydraulic upgrade – Inlet works and sludge lagoon overflow valves
54 L/s hydraulic capacity upgrade
>30L/s pumped flow to plant
(required now)
2
· Install aeration equipment, and WAS system · Upgrade electrical switchboard and building · Install common biological upgrade - CCT and dosing
systems
3,000 EP biological capacity
1,500 EP biological capacity (CED
adjusted) – required nominally
2016
The proposed SBR tank will be installed to run in parallel with the existing SBR, mirroring the current
treatment once stage two is finished, and providing 60L/s and 3,000 EP capacity.
In the interim, to meet the hydraulic capacity requirements, the SBR tank will act as a large balance tank,
with return pump and pipework for peak pumped flows of 54 L/s. Though not included in this option, it may
be advantageous to also install the small balance tank, to accommodate daily pump flow variations. Note
that the return pump or small tank will not be required if Stage 2 is completed with Stage 1.
Capital Cost Estimate The following table shows the staged capital cost estimate for Option 4.
Table 7-11: Option 4 – Capital Cost Estimate, Staging and Schedule
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1
Inlet works and sludge lagoon valves Construct SBR tank, install weir and pipework (with return pump and pipework if stage 2 is delayed) Site access road relocation Minor electrical and SCADA work
$1,112,000 2014/15
2
Install aeration equipment, and WAS system Install common biological upgrade - CCT and dosing systems Chemical dosing upgrade – pH and alum dosing Electrical switchboard, and building (electrical or blower) upgrade Minor electrical and SCADA work
$1,473,000 2016/17
Total $2,585,000
* biological upgrade requirement assumed to be delayed to 2015/16 as per current population estimate, to be verified against new IDM.
![Page 57: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/57.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 57 of 94 Rev: 1
All works should be designed together, to ensure hydraulic issues are consistently resolved. Inlet works
should be installed as soon as the design is completed and funding permits, preferably before the 2014/15
wet season.
Project cost efficiencies may outweigh delayed investment, if biological upgrade installation work (Stage 2) is
delivered with the hydraulic upgrade (Stage 1) in a combined construction works package. For Option 4,
some minor infrastructure works will not be required where both stages are completed simultaneously.
Benefits and Risks
The benefits/advantages and risks/disadvantages of this option are listed in the following table:
Table 7-12: Option 4 – Benefits and Disadvantages
Advantages and Benefits Disadvantages and Risks
§ Works are staged to accommodate delayed biological load/ catchment growth
§ The existing SBR is fully utilised to its original capacity § The inlet works can be implemented as soon as the
design is finished (original funding in 2013/14) § The large storage tank will allow for storage of over 1
day at ADWF, allowing shut down of the SBR for maintenance or capital works.
§ The risk of sludge overflow due to high inflows is very low, as two SBRs double the capacity to 60L/s
§ The risk of compromised treatment quality is low, with two SBRs in parallel being both effective and resilient to treatment spikes, additional loading or environmental changes.
§ Opportunity for improved effluent quality § Duplicate parallel systems provide redundancy and
ease maintenance constraints § The additional capacity provided with a second SBR
delays the next stage of infrastructure – diversion to Cedar Grove WWTP at $9.5 million – by 2 years. Additional WWTP upgrades are also available to further delay this infrastructure.
§ Hydraulic constraints are moderate for the design of the inlet screen pit and large balance tank
§ Raw wastewater will be stored in the SBR until flows reduce enough to be treated, potentially creating an odour issue.
§ Infrastructure is greater than the need for capacity until 2021
![Page 58: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/58.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 58 of 94 Rev: 1
Figure 7-4: Option 4 Infrastructure Schematic
![Page 59: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/59.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 59 of 94 Rev: 1
Option 5 – Parallel Package Plants This option involves installing parallel package plants adjacent to the existing SBR. The peak flows can be
distributed between the two process trains (i.e. existing the SBR and a new package plant unit), maintaining
peak flows below 30 L/s in the existing SBR to protect the treatment process. The existing SBR and the new
package plants will cater for the required load of 2,530 EP, increasing the total capacity to 2,600 EP and
meeting the 54 L/s instantaneous flow capacity. No upgrades will be required in the existing SBR. The inlet
works and CCTs will be upgraded as per all options.
Table 7-13 outlines the works required for Option 5.
Table 7-13: Option 5 - Description of Works
Stage Description of Work New Capacity Trigger for Work
1
· Install 500EP package plant, foundation and pipework · Common hydraulic upgrade – Inlet works and sludge
lagoon overflow valves · Upgrade electrical switchboard and building · Install common biological upgrade - CCT and dosing
systems
54 L/s hydraulic capacity upgrade
2,000 EP biological capacity
>30L/s pumped flow to plant
(required now) 1,500 EP biological
capacity (CED adjusted)
2 · Install 600EP package plant, foundation and pipework 2,600 EP biological capacity
2,000 EP biological capacity (CED
adjusted) – required nominally
2016
The package plants will be installed to run in parallel with the existing SBR. The first parallel plant will cater
for 500 EP and also high flows of 22 L/s. The second plant will cater for an additional 600 EP, and has the
flexibility of being increased, once future growth is more clearly understood, as are the planning for and
benefits of Cedar Grove infrastructure delays.
Capital Cost Estimate
The following table shows the staged capital cost estimate for option 5.
Table 7-14: Option 5 – Capital Cost Estimate, Staging and Schedule
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1
Inlet works and sludge lagoon valves Install 500EP Parallel Package Plant, foundation and pipework Upgrade electrical switchboard and building Install common biological upgrade - CCT and Cl dosing systems
$1,468,000 2014/15
2 Install 600EP Parallel Package Plant, foundation and pipework Minor electrical and SCADA work $2,078,000 2016/17
Total $3,546,000
![Page 60: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/60.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 60 of 94 Rev: 1
All works should be designed together, to ensure hydraulic issues are consistently resolved. Inlet works
should be installed as soon as the design is completed and funding permits, preferably before the 2014/15
wet season.
Benefits and Risks
The benefits/advantages and risks/disadvantages of this option are listed in the following table:
Table 7-15: Option 5 – Benefits and Disadvantages
Advantages and Benefits Disadvantages and Risks
§ Works are staged to accommodate delayed biological load/ catchment growth and provide flexibility for future plant sizing
§ The existing SBR is fully utilised to its original capacity § The inlet works can be implemented as soon as the
design is finished (original funding in 2013/14) § The risk of sludge overflow due to high inflows is very
low, as the first new package plant will provide adequate hydraulic capacity
§ The risk of compromised treatment quality is low, with two plants in parallel likely to be both effective and resilient to treatment spikes, additional loading or environmental changes
§ Parallel systems provide redundancy and ease maintenance constraints
§ The second stage of this infrastructure can be upsized to delay the diversion to Cedar Grove WWTP at $9.5 million, by a number of years, and sized when growth is more visible.
§ Hydraulic constraints are moderate for the design of the inlet screen pit and large balance tank
§ Raw wastewater will be stored in the SBR until flows reduce enough to be treated, potentially creating an odour issue.
§ Infrastructure is greater than the need for capacity until 2021
§ Division of flows will not be 50/50, thus creating flow control requirements at the flow splitter (inlet works)
§ Multiple treatment technologies require operator training, different process understanding and provide additional scope for errors.
![Page 61: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/61.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 61 of 94 Rev: 1
Figure 7-5: Option 5 Infrastructure Schematic
![Page 62: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/62.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 62 of 94 Rev: 1
8. OPTION EVALUATION A dual cost and non-cost assessment was undertaken to determine the preferred upgrade option for the
Jimboomba WWTP.
Cost Analysis The five options were compared by using an NPV analysis of capital and operational costs, with the results
outlined in Table 8-1. The NPV analysis spans 2014 to 2039 (25 year period), using the standard LWA
discounted rate of 4.75%.
Capital Costs are developed as design estimates for each option, incorporating unit costs from a variety of
sources including our LWA estimator and suppliers. Capital cost estimates include 30% contingency, and
have been staged to accommodate immediate hydraulic constraints and biological constraints (staged where
applicable). Details for the capital costs for each option are contained within Appendix E.
Existing operational costs are based on K. Hartley estimates and adjusted according to actual flows received
at the WWTP. Future additional operational costs were estimated based on new equipment electricity use (at
$0.15/kWh), maintenance costs at 1% p.a. of total capital works, additional chemicals ($5,000/year) and
additional labour at a workload increase of up to 3 days, dependant on upgrade operational complexity (at
$50/hr).
Table 8-1: Capital, Operational and NPV Cost Comparison Across Jimboomba WWTP Upgrade Options
Option 1 – Upgrade SBR and peak flow balancing tank
Option 2 – Upgrade SBR
and wet weather
balancing tank
Option 3 – Upgrade SBR
and wet weather bypass
Option 4 – Duplicate SBR
Option 5 – Parallel
Package Plant
Capital cost (2014 $) $2,416,696 $2,623,708 $2,462,079 $2,585,373 $3,546,399
Operational cost (2014 $)
(2014/15-2039/40)
$5,809,658 $5,832,131 $5,784,127 $5,956,966 $6,029,288
NPV $12,665,380 $12,778,156 $12,575,630 $12,328,301 $13,921,010
Rank 3 4 2 1 5
% Variation from lowest NPV 3.1% 4.2% 2.3% 0.0% 14.8%
Options 1-4 have similar capital costs, with Option 5 - Parallel Package Plants having a significantly higher
capital cost, by around $1m. As expected, Option 1 had the lowest capital cost due to the minimal proposed
infrastructure.
![Page 63: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/63.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 63 of 94 Rev: 1
Operational costs vary only slightly across the options, primarily due to the timing of the upgrades. Details for
the operational costs for each option are contained within Appendix C. Option 3 has the lowest associated
operational cost.
Option 4 has a higher final capacity (3,000 EP as opposed to 2,600 EP for all other options), which can
provide a two year delay on the Cedar Grove infrastructure, based on current short term growth predictions.
Given the Jimboomba WWTP capacity is the primary driver for the Cedar Grove Transfer Infrastructure, the
associated $9.5m infrastructure capital costs and operational cost (including proportional treatment costs -
Logan South Waste Water Servicing Strategy, LWA 2014) have been included in the NPV comparison.
8.1.1 Population Sensitivity Analysis The current short-term population projection is for 13% per annum growth over 2015 and 2016, with growth
rates estimated between 5% and 8% p.a. until 2031. This rate is lower than Logan South Region growth rate
predictions (Logan South Waste Water Servicing Strategy, LWA 2014) and excludes the potential of either
advanced development or development out of sequence with current planning in the small Jimboomba
catchment.
A sensitivity assessment was conducted to determine the impact of varied short term growth rates on
infrastructure timing and the outcomes of the overall NPV. The current growth estimate was compared
against bulk growth at 200 EP/yr over 2 years (from 2015 to 2016) on top of the assumed growth rates, and
also varied growth rates of 10%, 5% and 2% (from 2014 until the ultimate expected growth rate was
reached).
The impact on the NPV of varied growth rates is detailed in Table 8-2.
Table 8-2: Population Sensitivity Assessment – NPV Comparison
NPV (25 yr) NPV (31 yr) *
Current +400EP over 2015 &2016
10% growth rate 5% growth rate 2% growth rate
Option 1 $12,665,380 $13,770,203 $13,365,420 $11,890,921 $19,523,200
Option 2 $12,778,156 $13,943,489 $13,449,761 $11,855,958 $19,747,813
Option 3 $12,575,630 $13,759,042 $13,258,440 $11,635,445 $19,402,731
Option 4 $12,328,301 $12,393,161 $13,264,608 $11,446,646 $20,270,423
Option 5 $13,946,892 $15,028,153 $14,624,036 $13,277,371 $21,531,845
* 31 year NPV assumed for 2% growth rate due to delayed capital works
NPV variations are most significant when the timing of capital costs of new works are delayed or advanced
for each option. The delay of infrastructure from the proposed staging of 2014, 2016 and 2017 is shown in .
The population sensitivity analysis shows that:
· Option 4 remains the preferred option due to the delay of the $9.5m capital works to transfer flows to
Cedar Grove WWTP by up to 3 years relative to other options. The cost difference to Option 3 for the
10% growth rate is only minimal.
![Page 64: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/64.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 64 of 94 Rev: 1
· For the 2% scenario, the operational costs at the Jimboomba WWTP has a greater impact on the
NPV than the cost of the Cedar Grove transfer infrastructure, which indicates that transferring flows
to Cedar Grove, is more cost effective than running the Jimboomba WWTP indefinitely.
· Both an additional 400 EP and 10% growth rate will bring forward Stage 3 of the Jimboomba WWTP
upgrades and Cedar Grove transfer infrastructure, whereas 5% and 2% growth rate delay both
Stage 3 of the WWTP upgrades and Cedar Grove transfer infrastructure relative to the proposed
upgrade timing.
Multi Criteria Analysis A multi-criteria (non-cost) assessment workshop has held on the 3rd April 2014 to identify non-cost
benefits/constraints/risks and opportunities for the identified strategies. This workshop engaged LCC
stakeholders from the following areas:
· Treatment
· Water Business
· Asset Management
· Water Product Quality
Table 8-3 summarises the categories and associated weightings adopted for this assessment as agreed in
MCA workshop.
Table 8-3: MCA Framework and Weighting
Assessment Criteria
Criteria Weighting Sub Criteria Description Sub Criteria
Weighting
Technical/ Operational/
Risk 30%
Process redundancy, reliability and flexibility
Risk (likelihood and impact) of failure of biological process or hydraulics, including
redundancy. 40%
Operability, maintainability, safety
aspects
The ability to operate, maintain and access infrastructure in a safe and efficient manner. 40%
Constructability & risk
Ease of implementation on working plant Risks associated with construction of
infrastructure, including safety, construction method and unknown factors.
20%
Environmental 40%
License compliance
Risk of License non-compliance; ability to discharge only.
Impact on re-negotiations of new license for controlled wet weather releases to creek
30%
Impact to waterways Lagoon water quality and impact on Hendersons creek when released. 30%
Impact to land Irrigation impacts (to soil, animals etc) from any reduction of effluent water quality in lagoon. 40%
Social 30%
Ability to supply 3rd party reuse water to
customers
Lagoon water quality of Class C guideline (preferably) with no BGA or BGA toxins
present. 60%
Local resident impacts Impacts of noise and odour on local residents including SES office, Public health risk re BGA 40%
![Page 65: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/65.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 65 of 94 Rev: 1
The agreed primary categories were social, environment, and technical/operational/risk. Table 8-4
summarises the outcomes of the MCA workshop.
Table 8-4: MCA Outcomes
Assessment Criteria Sub Criteria
Option 1 – Upgrade SBR and peak flow
balancing tank
Option 2 – Upgrade
SBR and wet weather
balancing tank
Option 3 – Upgrade SBR and
wet weather bypass
Option 4 – Duplicate
SBR
Option 5 – Parallel Package
Plant
Technical/ Operation/
Risk
Process redundancy, reliability and flexibility 2 4 3 9 9
Operability, maintainability, safety aspects 2 5 2 9 7
Constructability & risk 2 4 2 9 7
Environmental
License compliance 1 5 2 10 10
Impact to waterways 2 7 1 10 10
Impact to land 3 4 2 7 8
Social
Ability to supply 3rd party reuse water to customers 2 8 1 10 10
Local resident impacts 6 4 7 5 7
MCA Score (out of 10) 2.52 5.32 2.42 8.62 8.66
MCA Rank 4 3 5 2 1
The MCA analysis indicates that based on non-cost criteria, Options 5 and 4 are preferred. The MCA
demonstrated that:
· Options 1 to 3 all upgrade the existing SBR, with the restrictions for hydraulic capacity,
constructability issues, lack of redundancy and wet weather impacts on the SBR and/or effluent to
the storage lagoon
· Options 1 and 3 pass raw wastewater, or near raw wastewater, to the CCT tank, during peak wet
weather flows (over half an hour of pumping). Lagoon water quality is paramount to the end use, as
Class C irrigation water for third party irrigation of a golf course and horse paddocks. Toxic algae
outbreaks, partially due to high nutrients, inhibit the use of this water.
· Options 4 and 5 both provide redundancy, total wet weather management (to 54 L/s), staged
implementation and potential for an improvement of effluent quality
![Page 66: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/66.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 66 of 94 Rev: 1
Preferred Option and Staging Based on both the MCA and NPV cost assessment results, the duplicate SBR (Option 4) provides the best
NPV solution and comparative best non-cost benefits. This option represents a reduced risk of operations,
while providing flexibility for growth beyond 2021 (if the transfer to Cedar Grove is deferred) and for varying
growth rates in the short-term.
Due to the anticipated scheduling for design, funding and period between stages (12 months) the SBR
upgrade should ideally be completed in 2015/16 financial year, with the small balance tank and inlet upgrade
works designed and installed early in 2014/15 financial year. The immediate works will bring relief to the
treatment process, by reducing peak instantaneous flows during dry weather days, while the upgrade is
undergoing detailed design.
The revised capital cost and NPV for this preferred option are provided in the following table and compared
to Option 4. The variation from the lowest NPV cost is approximately 1.6%, indicating that constructing Stage
1 and 2 consecutively does not significantly affect the overall cost profile.
Table 8-5: Preferred Option Costs and NPV Compared with Option 4
Costs Option 4 Preferred Option
Capital Cost $2,585,373 $2,603,531*
Operational Cost (2014/15-2039/40) $5,956,966 $6,116,766
NPV $12,328,301 $12,502,235
% Variation from Lowest NPV NA 1.6%
* Does not include $200,000 for inlet works fine screening equipment (already in CWP)
The small balance tank and associated infrastructure were not originally costed in option 4, and have
resulted in a marginal cost increase in the preferred option in comparison to Option 4.
Table 8-6 below shows the preferred option itemised works, and staging (year).
![Page 67: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/67.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 67 of 94 Rev: 1
Table 8-6: Preferred Option Itemised Works and Staging
Stage Description of Work Capital Cost Estimate (2014 $) Scheduled
1 Inlet works and sludge lagoon valves Small tank, foundations, pipework and pump $369,000* 2014/15
2
Construct SBR tank, install weir and pipework (with return pump and pipework if stage 2 is delayed) Minor electrical and SCADA work Install aeration equipment, and WAS system Install common biological upgrade - CCT and dosing systems Chemical dosing upgrade – pH and alum dosing Electrical switchboard, and building (electrical or blower) upgrade Minor electrical and SCADA work
$2,435,000 2015/16
Total $2,804,000
*Additional cost of $200,000 for inlet works fine screening equipment (already in CWP) included in above
Stage 1
Figure 8-1 shows the future site master plan, and illustrates the layout of the proposed works.
![Page 68: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/68.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 68 of 94 Rev: 1
SITE MASTER PLAN
Figure 8-1: Preferred Option Site Master Plan
![Page 69: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/69.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 69 of 94 Rev: 1
8.1.2 Future considerations for the preferred option development A number of issues will need to be managed, considered and addressed throughout the development of the
preferred option:
· Timeliness of delivery of the final SBR, due to current biological limits and hydraulic capacity
· The hydraulic constraints on the existing plant, upstream and downstream of the inlet pit, which
will impact the inlet screen design, inlet pit modifications and small tank TWL (and operation),
pipework configuration, inlet pit overflow weir height, and sludge lagoon valves and their
operational parameters
· SBR design improvements, which should be pursued and may be retrofitted to the existing SBR
if they prove effective
· SBR operations may be sequential batch reactor style during normal flows, changing to
continuous inflow batch reactor during high flows (where cost effective)
· Potential future upgrade of both SBRs to maximise the life of the plant, and thus another
upgrade of the CCT may also occur
· Shallow manhole at the CCT outlet, management of flows and surcharge, at this manhole and
the short section of main upstream (fall rate downstream of this point is 9.75%).
· The 30kL storage tank has potential for creating odour issues due to short term storage of raw
wastewater. The tank may be fitted with automated wash down sprinkler. If odours become
significant, odour management such as a carbon filter should be fitted to the tank vent.
· A new switchboard being installed in May-June 2014 will allow the installation of new blowers.
Space within the 2014 switchboard should be utilised and the blowers could be relocated to the
new proposed building, allowing both switchboards in one building and blowers in the other
· DEHP negotiations for lagoon effluent release to Hendersons Creek may result in lagoon
effluent quality compliance limits, which will need to be considered in terms of the SBR biological
process and CCT treatment.
![Page 70: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/70.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 70 of 94 Rev: 1
9. CAPITAL WORKS PROGRAM IMPLICATIONS The following table provides the four capital works items for the 2014/15 and 2015/16 capital works
programs. The preferred staging and capital works to be added to the capital works budget is as follows:
· FY14/15 – inlet works upgrade ($0.20m) and installation of an instantaneous peak flow balance tank
($0.17m)
· FY15/16 – new SBR unit and upgrade CCTs ($2.44m)
This equates to a total of $2.8m for the upgrade of Jimboomba WWTP.
Table 9-1: Capital Works Program Amendments
CWP ID Task Description Status Year Scheduled
Cost ($XXXX)
Amendments
Unassigned 90-12-53
Jimboomba WWTP Stage 1 – Upgrade inlet works and install instantaneous balance tank · delivery and
installation, return pump, pipework, inlet pit diversion weir
· new inlet screen and civils
· upstream flow monitoring
· sludge lagoon valves
Detailed planning 2014/15 $369,000
Add new
item
Unassigned 90-12-53
Jimboomba WWTP Stage 2 – SBR Upgrade: · new SBR · upgrade CCTs · upgrade chemical
dosing · new switch board
/blower room
Detailed planning 2015/16 $2,435,000
Add new
item
![Page 71: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/71.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 71 of 94 Rev: 1
10. CONCLUSION The Jimboomba WWTP is currently limited to a 1,500 EP biological load and a 30 L/s hydraulic load,
ensuring that sufficient treatment is maintained in accordance with current limits. This capacity will avoid
settled sludge blanket uplift/scour and the carryover of solids into the CCTs or a complete ‘wash-out’ of
suspended solids. The WWTP is further constrained to 35 L/s at the inlet works (based on the inlet screens
and upstream sludge lagoon connections and manhole levels) and 31 L/s at the CCT to maintain adequate
disinfection.
An internal assessment of the population growth (based on the previous IDM and expected development
within the area), indicates an estimated 2,730 EP by 2021. The equivalent biological load for this population
is approximately 2,530 EP, due to a high number of existing connections serviced by a CED system. The
maximum instantaneous pumped flow to the WWTP could reach 78 L/s by 2021 for the assumed network
pumping configuration, which is far above the corresponding catchment PWWF of 35 L/s for that year. By
commissioning the existing VSDs in the key pump stations, the projected instantaneous peak flows could be
reduced to approximately 54 L/s until 2021.
Several upgrade options were developed based on the assumed maximum pumped inflow of 54 L/s and a
contributing population of 2,600 EP by 2021. At this time, Strategic Planning assumed that the Jimboomba
WWTP will be decommissioned and flows transferred to the proposed Cedar Grove WWTP. Five options
were assessed in detail, included upgrading the existing SBR while mitigating peak flows (in the form of flow
balancing tanks or wet weather bypass) or alternatively duplicating the treatment train.
All three upgraded SBR options (with mitigated peak flows) and the duplicated SBR option had a similar
range of capital costs, from $2.4million to $2.6million. NPV costs over a 25-year period (including the future
transfer main costs to Cedar Grove and associated operational costs) ranged from $12.3million to
$12.8million. The parallel package plant option was approximately $1million higher in both capital and NPV
costs.
The upgraded SBR options (Options 1 to 3) included either a small balance tank or a wet weather bypass for
peak flows scored poorly in the MCA (2.42 to 5.32 out of 10) due to reduced treatment standards during
peak flows, which would impact on recycled water users and the environment and reduced process
redundancy and maintainability. The parallel treatment options 4 and 5 (duplicate SBR and parallel package
plant options) scored the highest in the MCA (8.62 and 8.66 out of 10).
Based on the cost and non-cost considerations, duplicating the SBR to accommodate hydraulic and
biological increases is the preferred option, with a low capital and NPV cost, a high MCA scoring and the
flexibility to stage works with flow balancing during the initial stages. The duplicate SBR option also allows
for some flexibility in the construction of the transfer pipeline to the proposed Cedar Grove WWTP.
![Page 72: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/72.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 72 of 94 Rev: 1
11. RECOMMENDATIONS The Logan Water Alliance recommends that Logan City Council (LCC):
1. Adopt the construction of a duplicate SBR as the preferred upgrade strategy for the Jimboomba
WWTP, which incorporates the following works:
a. Stage 1 works (FY14/15) – install new inlet works and fine screen with 30 kL flow balancing
tank
b. Stage 2 works (FY15/16) – commission a duplicate SBR and chlorine contact tanks
2. Proceed immediately to with the detailed design of the inlet works and 30 kL balance tank
3. Implement pump station management of the upstream LCC operated pump stations, which involves:
a. Stage A (pre-WWTP commissioning) – delaying SPS73 connection to 150 mm rising main,
VSD control and duty/standby operation of SPS74, and installing systemic control between
SPS73 and SPS74
b. Stage B (post WWTP upgrade) – VSD control, duty/standby operation and limiting flows to
minimum velocity requirements for SPS73 and SPS74
4. Continue to monitor effluent performance and impacts of the WWTP changes on the effluent storage
lagoon.
![Page 73: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/73.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Page 73 of 94 Rev: 1
12. REFERENCES Hartley, 2009, Jimboomba WWTP EVOP Review
Hartley, 2009, Jimboomba: Detailed Planning for 2015/16 Wastewater Treatment and Effluent Management Scheme - Planning Report for WWTP Upgrade
Hartley, 2010, Jimboomba WWTP - Assessment of Capacity Potential
LWA, 2011, Jimboomba WWTP Upgrade Project Development (Task Number 90-10-87-001). Prepared in November 2011.
LWA, 2013, Jimboomba Recycled Water Management Plan (Task Number 90-11-46). Prepared in July 2013.
LWA, 2013b, Jimboomba WWTP Wet Weather Effluent Management Strategy (Task Number 90-12-42). Prepared in December 2013.
LWA, 2014, Revision of Logan South Wastewater Network Servicing Strategy (Task Number 90-12-21). Prepared in January 2014.
![Page 74: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/74.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Appendix A Desired Standards of Service
![Page 75: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/75.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
WASTEWATER NETWORK DSS
Parameter Criteria
Sewage load
ADWF 200L/EP/day
PDWF 2 x ADWF
PWWF
Residential 1300 L/EP/d For CED PWWF = 660 L/EP/d Commercial 1300 L/EP/d
Light Industrial 1000 L/EP/d
Heavy Industrial 840 L/EP/d
Gravity sewer design
Flow equation Manning's 'n' or Colebrook White can be used. For modelling Colebrook–White is preferred
Pipe roughness general Manning's 'n' =0.013 or Colebrook White k = 1.5 mm
Minimum velocity @ PDWF 0.35 m/s
Maximum velocity @ PWWF 3 m/s Depth of flow @ PWWF — existing Up to 1 m below MH surface level and no spillage through overflow structures
Depth of flow @ PWWF — proposed 75% of pipe depth
Minimum grades
Diameter Grades (mm, 1 in X)
150 150 (80 in last section between last manholes or to an end)
225 290
300 400
375 500
450 600
525 700
600 850
675 925
750 1000
825 1000
900 1090
1050 1270
1200 1450
Sewerage pump stations
Wet well operating requirements
V (m3) = 0.9 x pump rate (L/s) N Where N is the acceptable number of starts per hour Pump Rate (L/s) = capacity of the largest duty pump N = 12 for motors <= 15 kW N = 8 for motors 15kW - 200 kW N = 5 for motors > 200 kW Control levels are based on Table 5.1 of WSA04-2005. The minimum depth between duty start and duty off is 100 mm and ideally should be 300 mm or greater.
![Page 76: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/76.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
WASTEWATER NETWORK DSS
Parameter Criteria
Emergency storage
Four hours of ADWF (local gravity catchment only) Except where otherwise specified to meet the requirements of the overflow risk assessment If there is an overflow pipe, storage in the system is measured between the alarm level and overflow pipe invert level. If there is no overflow pipe, storage is measured between the alarm level and 300 mm below the lowest upstream manhole or top of wet well.
Pump capacity
If PWWF <20L/s, then two pumps (duty/standby arrangement) will be provided, with each pump being capable of delivering PWWF. If PWWF >20L/s and <200L/s, then two pumps (duty/duty assist arrangement) will be provided, with each pump being sized so that the two pumps running in parallel are capable of delivering PWWF. It is desirable that a single pump be sized on C1 if appropriate. i.e. From QDNRM. C1 = 15 x EP-0.1587 minimum 3.5, maximum 6.5. If PWWF >200L/s, then minimum of three pumps (duty/duty assist/standby arrangement) will be provided. Duty/duty assist pumps being capable of delivering PWWF with each pump being sized in consultation with Allconnex Water.
Pump operation VSD will only be used subject to special approval from Allconnex Water. If approved by Allconnex Water, the VSD operating regime will be selected to ensure sufficient self-cleansing velocities, and will meet the pump supplier’s requirements.
NPSH Refer Clause 6.4 of WSA04-2005
Rising mains
Flow equation Hazen Williams or Colebrook–White. For modelling, Colebrook–White is preferred
Friction mains
100–300 mm diameter, C =110 > 300 mm diameter, C =130 Colebrook–White to follow method in WSA04. The pump curve will include the minimum static head with C=140 to confirm that the pump operates over the full range (i.e. to the overflow level) in the wet well.
Minimum velocity Minimum velocity will be not less than 0.9 m/s, but preferred minimum is 1.5 m/s. Refer Clause 10.3.5 of WSA04-2005.
Maximum velocity 2.5 m/s proposed systems
Max detention time
Maximum time of detention in pressure main and SPS wet well is six hours (two hours in wet well and four hours in rising main) based on daily average flows to minimise potential for odour or hydrogen sulfide generation. Where high retention times are likely to occur, odour and sulfide control measures will be required to the satisfaction of Allconnex Water. (Refer WSA 07-2007-1.1 section 3.15)
Reduced infiltration gravity sewers (RIGS)
As per gravity sewers except Not permitted without Allconnex Water approval
PWWF 1000L/EP/d
Single pump capacity Standard: C1 x ADWF
C1 = 9.322 x EP-0.1249 minimum 3.0, maximum 4.
Total PS capacity 1000L/EP/d
Low pressure sewers / vacuum pumps Low pressure sewers / vacuum pumps Are not preferred and will only be allowed subject to approval from Allconnex Water.
Private pump stations and rising mains
Private pump stations and rising mains are permitted for single users only and no connection or sharing will be permitted without approval from Allconnex Water
Common effluent discharge
Common effluent discharge (CED)
Not permitted without approval from Allconnex Water.
![Page 77: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/77.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Appendix B Jimboomba Wastewater Catchment Pump Station Management Analysis
![Page 78: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/78.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
The Jimboomba wastewater treatment plant (WWTP) experiences excessive flows at times due to the
operation of pump stations assets in the wastewater network. The implications of excessive flow on the
WWTP include:
· Washout of the treatment plant process (impacting treatment for up to two weeks and contaminating
the downstream effluent lagoon)
· Surcharging of the inlet works and upstream infrastructure
These issues were observed in March 2014, when a large wet weather event triggered two Council pump
stations (i.e. SPS73 and SPS74) to pump continuously for 3 and 5 hours respectively, which surcharged the
inlet works, flooded the sludge lagoon, and washed out the treatment plant.
There are opportunities in the current and future operational configuration of the upstream network to
minimise pumped flows to the WWTP. The analysis performed on network assets as part of this study aims
to address the current hydraulic issues and to determine the future flows between the network and the
Jimboomba WWTP. This will assist in the development of appropriate treatment capacity options.
Jimboomba Wastewater Catchment
The existing wastewater network consists of traditional gravity sewers, common effluent drainage (CED)
systems, five Council owned sewerage pump stations (SPS), two existing and one future private pump
stations (PPS).
Figure -B1 and Figure -B2 provide an overview of the Jimboomba wastewater catchment and its
infrastructure.
![Page 79: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/79.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Figure -B1: Jimboomba Wastewater Catchment
Figure -B2: Jimboomba Wastewater Configuration (Up to 2021) - Schematic
Jimboomba WWTP
SPS73 Pump Station
Hills College PPS Pump Station
SPS80 Pump Station
SPS73 Gravity Catchment
SPS77 Pump Station
SPS76 Pump Station
SPS75 Pump Station
SPS74 Gravity Catchment
SPS74 Pump Station
Child Care PPS Pump Station
DN80 RM (Future commissioning of DN150 RM)
DN150 RM (DN80 RM – Not in existing use)
DN100 RM
DN50 RM DN50 RM
DN50 RM
Private PS RM
Private PS RM
Gravity Network Gravity Network
Gravity feed to inlet works
Stockland PPS Future Pump Station
Future DN80 RM (former SPS74 RM)
![Page 80: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/80.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
The WWTP receives flows directly from SPS73, SPS741, Hills College PPS and the Johanna St Child Care
Centre PPS. An additional private pump station is planned for the catchment, which will be associated with a
future Stockland development (i.e. Stockland PPS).
The rising main arrangement associated with SPS73 and SPS74 is as follows:
· Pump station SPS73 transfers flows to the WWTP via a DN80 rising main. A new DN150 rising
main augmentation has been constructed, but is yet to be commissioned.
· Pump station SPS74 has recently been connected to an augmented DN150 rising main to increase
the capacity of the pump station due to its history of wet weather overflows.
Servicing Strategy
The East Street Jimboomba Wastewater Conveyance – Detailed Planning and Preliminary Design (LWA,
Jan 2014) Planning Report outlines the current adopted servicing strategy for Jimboomba. The high level
servicing strategy for the Jimboomba catchment is based on the transfer of flows to the planned regional
Cedar Grove WWTP in 2021. At this time the transfer infrastructure, consisting of a new pump station and
7.5 km of DN375 rising main, will be constructed to convey flows from Jimboomba to Cedar Grove allowing
the decommissioning of the Jimboomba WWTP. During the expected life of Jimboomba WWTP (i.e. up to
2021) the following catchment changes are anticipated:
1. Growth in the south east (i.e. near East Street) will require a new SPS76 to transfer flows to SPS74
until 2021, and a new SPS80 pumping flows to SPS73
2. SPS73 will be connected to its new DN150 rising main to increase capacity
3. Stockland development along the west of the Mount Lindsay Highway is likely to be completed in the
next few years. It is proposed to connect the Stockland private pump station to the disused SPS74
DN80 rising main
Population and Loadings - Jimboomba Catchment
Table 12-1 shows the Jimboomba network loading by terminal pump station from the 2014 to 2021 planning
horizons, which correlates with the expected remaining life of the Jimboomba WWTP.
Table 12-1: Jimboomba Network Loadings – 2014 to 2021 Planning Horizons Pump Station Loading Planning Horizon
2014 2016 2021
SPS73 / JMSP 1
EP 504 573 743 ADWF [kL/s] 101 115 149 PWWF [L/s] 7.6 8.4 10.9
SPS74 / JMSP 2
EP 1,012 1,283 1,684 ADWF [kL/s] 202 257 337 PWWF [L/s] 9.9 13.8 19.6
Hills College PPS EP 134 134 134 ADWF [kL/s] 27 27 27 PWWF [L/s] 2.0 2.0 2.0
1 SPS74 receives all the common effluent drainage (CED) systems as well as some gravity and upstream pumped flows.
![Page 81: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/81.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Pump Station Loading Planning Horizon 2014 2016 2021
Johanna St Child Care Centre PPS
EP 28 34 34 ADWF [kL/s] 5 7 7 PWWF [L/s] 0.2 0.3 0.3
Stockland PPS EP 0 120 140 ADWF [kL/s] 0 24 28 PWWF [L/s] 0.0 1.8 2.1
Jimboomba Catchment
EP 1,678 2,144 2,735 ADWF [kL/s] 335 430 548 PWWF [L/s] 19.7 26.3 34.9
Existing Capacity – Pump Stations and Jimboomba WWTP
To aid the development of WWTP capacity options out to 2021 it is important to understand the current
capacity of critical assets over this period. This includes terminal pump station assets and the Jimboomba
WWTP.
Based on the status of the existing Jimboomba WWTP and the potential upgrade of the plant to
accommodate future growth and network constraints out to 2021, network capacity needs to be considered
in two stages. These stages include:
· Stage A Existing – Consideration needs to be given to the capacity constraints of the existing plant
to ensure its effective operation up to the resolution of the WWTP capacity constraints
· Stage B Future – Based on current network assets and catchment growth, a suitable capacity
constraint needs to be established for consideration in the development of Jimboomba WWTP
capacity options
Jimboomba WWTP Capacity Constraints
The Jimboomba WWTP has an estimated hydraulic capacity of 30 L/s. Any flows above this are anticipated
to cause solids carryover out of the bioreactor and affect the biological process through eventual process
washout. The existing inlet works has an estimated hydraulic capacity of 35 L/s.
On this basis, Stage A will need to consider a limit of 30L/s or less up until the resolution of any Jimboomba
WWTP capacity constraint resolution.
Pump Station Capacity
Five pump stations will contribute flows directly to the Jimboomba WWTP (refer Figure -B2) between now
and 2021 (refer Table 12-1). These include:
· Two Council owned pump stations (i.e. SPS73 and SPS74)
· Three privately owned pump stations, which include two existing pump station assets (i.e. Hills
College and the Johanna St child care facility) and the future pump station to service the Stockland
development.
![Page 82: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/82.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
For the purpose of the Stage A and B assessments it will be assumed that all five pump stations will contribute flows to the WWTP.
Stage A - Existing Assessment
The current capacity of the key pump stations is shown in Table 12-2. The following can be deduced:
· The current capacity of SPS73 (i.e. PWWF 7.0 L/s) is below the expected DSS requirement in 2016
(i.e. PWWF 8.4 L/s). However, a review of actual SCADA suggests that flows into the pump station
are currently less than current projected flows.
· The current capacity of pump station SPS74 is well in excess of DSS requirements in 2016 (i.e.
25.7 L/s / 29.7 L/s actual PWWF capacity versus a 2016 PWWF of 13.8 L/s). In addition, the
ultimate PWWF estimated for SPS74 is 14.6 L/s.
· The overall Jimboomba catchment PWWF in 2016 is expected to be 26.3 L/s, which is less than the
current 30 L/s restriction at the Jimboomba WWTP
· Drawdown test results used for this study show a close correlation with theoretical calculations for
SPS73, but a significant error is applicable in relation to SPS74 (refer Table 12-2 and Figure B-12-4).
Further investigation is required to confirm asset characteristics for SPS74.
![Page 83: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/83.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Table 12-2: Pump Station Capacity – Existing and 2016 PWWF
Pump Station RM Nominal Diameter
Single Pump (Duty) Flow
Dual Pump (Duty / Assist) Flow
2016 PWWF
Ultimate PWWF
[-] [mm] [L/s] [L/s] [L/s] [L/s] SPS73 80 6.7 1 7.0 1 8.4 27.3 SPS74 150 25.7 1 29.7 1 13.8 14.6 Hills College 100 8.3 3 - 3 2.0 2.0 Johanna St Child Care 50 2 2.4 4 4.0 5 0.3 0.3 Stockland 80 4.5 6 6 6 1.8 2.6
Total 47.6 55 26.3 46.8 Notes: 1 – Capacity was based on pump station drawdown test with SPS73 connected to a DN80 rising main and SPS74 connected to the existing DN150 rising main 2 – A DN50 rising main has been assumed. This will need to be confirmed in the field. 3 – Flow rate based on ‘as constructed’ drawings and system resistance curves provided. No information provided as to pump configurations and a single pump configuration is assumed. 4 – Minimum flow based on a minimum 0.9 m/s velocity requirement and DN50 rising mains. The DN50 pipe would have a 45mm internal diameter for an assumed PE pipeline. 5 - Maximum flow based on a maximum 2.5 m/s velocity requirement and assuming DN50 rising mains. The DN50 pipe would have a 45 mm internal diameter for an assumed PE pipeline. 6 - Minimum flow based on a minimum 0.9 m/s velocity requirement and DN80 rising mains. A maximum flow rate based on a maximum 2.5 m/s velocity requirement in a DN80 rising main is likely to concur high head loss and unlikely to meet this requirement. Therefore, the flow is unlikely to exceed 6 L/s.
Based on the above the following should be implemented in the short term:
· Pump Station SPS73 – Delay the commissioning of the DN150 rising main and monitor the
performance of the pump station.
If actual ADWF flows for SPS73 exceeds the 2014 ADWF of 1.17 L/s (i.e. 101 kL/day), then
consideration will need to be given to the commissioning of the DN150 rising main. However, this
would require variable speed drive (VSD) control to limit flows to achieve the minimum velocity of
0.9 m/s, a duty / standby mode of operation and systemic control with SPS74 to ensure these pump
stations do not operate in unison.
· Pump station SPS74 – The following measure are required:
o Ensure the pump station operates in a duty / standby mode
o Limit the flows from SPS74 through the use of a VSD to 16 L/s (i.e. minimum velocity of
0.9 m/s)
· Private pump stations – Investigate the ability to limit flows from these sites to achieve minimum
velocity requirements (i.e. 0.9 m/s).
· Systemic control – Program logic into the control of SPS73 and SPS74 to ensure that only one pump
station can function at one time.
These measures should result in a maximum flow being received by the WWTP to be in the order of 29.8 L/s
(refer Table 12-3).
![Page 84: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/84.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Table 12-3: Stage A Network Operation – Prior to Jimboomba WWTP Capacity Augmentation
Pump Station RM Nominal Diameter Flow Operational Measures
[-] [mm] [L/s] [-]
SPS73 80 7.0
· Systemic control with SPS74 · Delay the DN150 rising main commissioning · Monitor ADWF and consider risk of operation
with respect to DN150 rising main commissioning
SPS74 150 17.3 · VSD control to limit flow to 16 L/s to 17.3 L/s
(refer Figure B-12-4) · Systemic control with SPS73
Hills College 100 8.3
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
· Based on ‘as constructed’ drawings
Johanna St Child Care 50 4.0
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
· Limit flow to minimum velocity requirements i.e. 0.9 m/s
Stockland 80 4.5 1
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
· Limit flow to minimum velocity requirements i.e. 0.9 m/s
Maximum flow rate 34.1 2
(29.6 without Stockland)
· Flow rate to remain below 30 L/s · Operation to continue until Jimboomba
WWTP upgrade works are commissioned 1 – The flow from the Stockland pump station has been included as there is a possibility that the SPS73 DN80 rising main may become available during Stage A network operations 2 – The maximum flow rate has excluded the SPS73 flow due to the proposed systemic control measures
Therefore, if systemic and VSD control is implemented, the maximum flow rate reaching Jimboomba WWTP
is estimated as 34.1 L/s. This is likely to cause some process issues at the WWTP if sustained for long
pumping periods.
To avoid process issues at the WWTP, the flow may be reduced further to 29.6 L/s if Stockland connection is
delayed until after any WWTP upgrades.
![Page 85: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/85.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Figure B-12-3: Stage A SPS73 – Duty / Assist Single Pump Operation (RM DN80, n = 100%)
Figure B-12-4: Stage A SPS74 – Duty / Standby Single Pump Operation (RM DN150, n = 88%)
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
50.0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0
HEAD
(m)
FLOW (L/s)
Jimboomba - Stage B Pump Station SPS73 (DN80 Rising Main)
Single Pump n=100% (FLYGT NP3127.181) Dual Pump (Parallel) n=100% (FLYGT NP3127.181)SYSTEM CURVE (MAX/MIN OPERATION) PWWF - 2014 (7.6L/s) & 2016 (8.4L/s)Minimum / Maximum Flow Velocity Duty Point - Single PumpDuty Point - Dual Pump (Parallel)
Minim
um Velocity
0.9m/s Flow
-4.5L/s
Maxim
um Velocity 2.5
m/s Flow
-12.6 L/s
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0
HEAD
(m)
FLOW (L/s)
Jimboomba - Stage A Pump Station SPS74 (DN150 Rising Main)
Single Pump n=100% (FLYGT NP3127.181) Dual Pump (Parallel) n=100% (FLYGT NP3127.181)SYSTEM CURVE (MAX/MIN OPERATION) Min / Max Flow - Velocity Min 0.9 m/s Max 2.5 m/sDuty Pump (Min) Duty Pump (Max)VSD Control - Single Pump n=88% (FLYGT NP3127.181) VSD Control - Dual Pump (Parallel) n=88% (FLYGT NP3127.181)SPS74 DSS 2016 PWWF
Minim
um Velocity
0.9m/s Flow
-15.9L/s
Maxim
um Velocity 2.5
m/s Flow
-44.2 L/s
![Page 86: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/86.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Stage B – Future Assessment
The Jimboomba WWTP useful life based on the regional strategy for Logan South is currently considered to
be out to 2021. The WWTP has licence restrictions, which restricts releases to the environment. On this
basis the WWTP must be able to pass through DSS PWWF as a minimum.
The following aspects need to be considered in the determination of a suitable design flow rate for any
proposed Jimboomba WWTP capacity augmentation:
· PWWF – DSS 2021 PWWF 34.9 L/s (refer Table 12-2)
· Network Characteristics – Based on current knowledge on existing network assets and envisaged
flows through private pump stations a flow requirement of 53.7 L/s would be required (refer Table
B-4)
Table B-4: Stage B Network Operation – Post Jimboomba WWTP Capacity Augmentation
Pump Station RM Nominal Diameter 2021 Flow Operational Measures
[-] [mm] [L/s] [-]
SPS73 150 17.3
· Commissioning of the DN150 rising main · VSD control to limit flow 16 to 17.3 L/s (refer
Figure B-12-5) · Duty / standby operation
SPS74 150 19.6
· VSD control to limit flow to 18 to 19.6 L/s (refer Figure B-12-6)
· DSS 2021 PWWF 19.6 L/s · Duty / standby operation
Hills College 100 8.3
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
Johanna St Child Care 50 4.0
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
Stockland 80 4.5
· Confirm PPS operation, flow and asset characteristic (i.e. pump curves, operational mode, rising main diameter / material / alignment)
· Limit flow to minimum velocity requirements i.e. 0.9 m/s
Maximum flow rate 53.7 · Operation to commence once Jimboomba WWTP upgrade works are commissioned
Therefore, the upgrade options for the Jimboomba WWTP should consider 53.7 L/s as an appropriate
capacity. However, this assumes some form of restrictions can be achieved in terms of flows received from
private pump stations, with the Stockland pump station as a prime candidate.
![Page 87: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/87.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Figure B-12-5: Stage B SPS73 – 2021 Duty / Standby Single Pump Operation (RM DN150, n = 90%)
Figure B-12-6: Stage B SPS74 – 2021 Duty / Standby Single Pump Operation (RM DN150, n = 95%)
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0
HEAD
(m)
FLOW (L/s)
Jimboomba - Stage B Pump Station SPS73 (DN150 Rising Main)
Single Pump n=100% (FLYGT NP3127.181) Dual Pump (Parallel) n=100% (FLYGT NP3127.181)SYSTEM CURVE (MAX/MIN OPERATION) Min / Max Flow - Velocity Min 0.9 m/s Max 2.5 m/sDuty Pump (Min) Duty Pump (Max)VSD Control - Single Pump n=90% (FLYGT NP3127.181) VSD Control - Dual Pump (Parallel) n=90% (FLYGT NP3127.181)SPS73 DSS 2021 PWWF
Minim
um Velocity
0.9m/s Flow
-15.9L/s
Maxim
um Velocity 2.5
m/s Flow
-44.2 L/s
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0
HEA
D (m
)
FLOW (L/s)
Jimboomba - Stage B Pump Station SPS74 (DN150 Rising Main)
Single Pump n=100% (FLYGT NP3127.181) Dual Pump (Parallel) n=100% (FLYGT NP3127.181)SYSTEM CURVE (MAX/MIN OPERATION) Min / Max Flow - Velocity Min 0.9 m/s Max 2.5 m/sDuty Pump (Min) Duty Pump (Max)VSD Control - Single Pump n=95% (FLYGT NP3127.181) VSD Control - Dual Pump (Parallel) n=95% (FLYGT NP3127.181)SPS74 DSS 2021 PWWF
Minim
um Velocity
0.9m/s Flow
-15.9L/s
Maxim
um Velocity 2.5
m/s Flow
-44.2 L/s
![Page 88: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/88.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Summary of Recommendations
The Logan Water Alliance recommends that Logan City Council (LCC) should:
1. Confirm asset characteristics for terminal pump stations in the Jimboomba Catchment with priority
given to SPS74. This would include the following:
a. Undertaking pump station drawdown tests to confirm the results noted in this report
b. Confirm the pump characteristics i.e. model, type and pump curve
c. Develop an appropriate system curve for comparison to pump curves and compare theoretical
to test duty flow characteristics
d. Undertake further investigation if discrepancies exist to confirm system operations at the
commencement of detailed design works for the Jimboomba WWTP
2. Modify network operations in the Jimboomba Catchment to ensure that maximum flows do not
exceed 30-35 L/s to the Jimboomba WWTP (refer Table 12-3) in the lead up to the commissioning of
any Jimboomba WWTP capacity augmentation. This will involve the implementation of the following
Stage A operational measures:
a. Delay to the commissioning of the DN150 rising main to pump station SPS73
b. Implementation of systemic control between pump stations SPS73 and SPS74 to ensure that
only one pump station can operate at the one time
c. Implement VSD control at SPS74 to limit flows to minimum velocity requirements (i.e. V = 0.9
m/s)
d. Duty / standby operation for SPS74
3. Seek to limit flows from private pump stations to minimum requirements to provide opportunities for
operational flexibility and or reduction in WWTP upgrade requirements
4. Adopt a maximum flow criteria of 53.7 L/s in the development of Jimboomba WWTP capacity
augmentation options
5. Adjust network operations post the commissioning of the Jimboomba WWTP augmentation works to
include the following (i.e. Stage B operations):
a. Commissioning of the DN150 rising main associated with pump station SPS73, when required
b. Facilitate variable speed drive control at SPS73 and SPS74 to achieve the following:
· Pump station SPS73 - Limit flows to between 16 to 17.3 L/s (i.e. restrict flow to minimum
velocity criteria of 0.9 m/s, which correlates to 16L/s)
· Pump station SPS74 - Limit flows to between 18 to 19.6 L/s (i.e. 2021 PWWF of 19.6 L/s to be
achieved)
c. Duty / standby operation at pump stations SPS73 and SPS74
![Page 89: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/89.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Appendix C Jimboomba WWTP Performance Assessment and Existing SBR Upgrade Reports (Hartley, 2014)
![Page 90: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/90.jpg)
1 16118:Ken Hartley 2-Dec-13
Jimboomba WWTP Performance Review Jul-11 to Sep-13 1. Background The design capacity of the Jimboomba Wastewater Treatment Plant is 1500 EP. It is planned to retain the plant until a new regional facility is constructed at Cedar Grove, possibly around 2021. Three previous reports have assessed the capacity and potential upgrade strategies of the Jimboomba plant; Jimboomba operating data have also been published in a technical paper and a reference text: ¨ Hartley Ken (Sep-08), Jimboomba WWTP: Assessment of Capacity Potential, Logan Water. ¨ Hartley Ken (Jun-09), Jimboomba: Detailed Planning for 2015/16 Wastewater Treatment and
Effluent Management Scheme – Planning Report for WWTP Upgrade, Logan Water. ¨ Hartley Ken (Nov-09), Jimboomba WWTP: EVOP Review to 30-Sep-09, Logan Water. ¨ Hartley KJ & Lant PA (2010), Sludge Settleability in BNR Processes, Water, Jnl Australian
Water Ass, 37, 3, 77-83. ¨ Hartley Ken (2013), Tuning Biological Nutrient Removal Plants, pp 78, 81, 129, IWA
Publishing, London. This memo reviews the plant operating data for the most recent period, Jul-11 to Sep-13. 2. Plant Description Figure 1 shows the plant flowsheet and Table 1 the process details. 3. Loading Plant loading parameters for the twenty seven months Jul-11 to Sep-13 are listed in Table 2 and trended in Plots A1-A3 appended. Median flow and BOD loading for the period were 213 kL/d and 47 kg/d respectively. Assuming a 120 gCOD/EP, a BOD:COD ratio of 2.4 and a 25% reduction in BOD loading via the CEDs in the system, the estimated connected population is 1100-1200 equivalent. Peak daily flow was 4.3 times the median.
Figure 1 Plant flowsheet
SBR F ContactTank
LagoonsSludge
B
B
P WAS
Screen
Sewage Supernatant
P-37
EffluentLagoon
PGolf course
irrigation
Chlorine
DryingBed
PP
Underdrainage
![Page 91: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/91.jpg)
2 16118:Ken Hartley 2-Dec-13
Table 1 Existing Plant – Process Details Item Details Process Units SBR Volume at TWL Volume at LWL Max decant volume Max water depth Chlorine contact tank Volume Effluent lagoon Volume Sludge lagoons Volume Drying bed Area Equipment Capacities Aeration system Blowers Diffusers SOTR WAS pump Decanting weir
Side walls: upper 1.2m vertical, lower sloping 618 kL 526 kL (0.45m maximum decanter travel) 115 kL (with continuous inflow, decanting 20% of cycle time) 4.0m 17 kL 15 ML approx 2 No. ea 280 kL 75 m2 2 No. ea 140 L/s high speed, 50 L/s low speed Rehau fine pore membrane diffusers 35 kg/h per blower, HS (calculated) 1 No. 3 L/s 3m long, max decant depth 0.45m
Table 2 Plant Loading for 27 Months, Jul-11 to Sep-13 Parameter Load
Total Period
Median 90 Percentile Maximum
MASS LOAD Rainfall Raindays / total days Flow kL/d BOD load kg/d
2492 mm 205 / 823
--- ---
--- --- 213 47
--- --- 264 68
160 mm/d
--- 907 177
SEWAGE QUALITY BOD mg/L TN mg/L TP mg/L
--- --- ---
260 66 10
336 81 14
680 130 24
Table 3 Plant Performance for 27 Months, Jul-11 to Sep-13 Parameter Effluent Licence Standards Effluent Quality
Min 50%ile 80%ile Max Min 50%ile 80%ile Max BOD mg/L SS mg/L NH3-N mg/L TN mg/L TP mg/L pH units DO mg/L TDS mg/L E.coli cfu/100mL Free chlorine mg/L
--- --- --- --- --- 6.5 2 --- --- ---
--- --- --- --- --- --- ---
1000 --- ---
10 15 --- --- --- --- --- --- --- ---
20 30 --- --- --- 8.5 --- ---
10001
---
1 1
0.1 2.7 0.1 7.0 0.4 33 <1 0
4 6
0.6 8.8 7.1 7.5 2.1 508 <1 0.4
6 9
3.4 12 8.4 7.7 4.1 626 6
1.0
50 70 22 66 18 8.0 6.7
1150 561
2.1 195%ile – nominal concentration limit from Qld Public Health Regulation 2005.
![Page 92: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/92.jpg)
3 16118:Ken Hartley 2-Dec-13
4. Performance Effluent quality for the twenty seven months Jul-11 to Sep-13 is summarised in Table 3 and trended in Plots B1-B3 appended. Significant features are: ¨ BOD and SS were low except for high flow periods where significant solids carryover
occurred during decanting. ¨ Nitrogen removal was good with median NH3-N and TN levels of 0.6 and 8.8 mg/L. ¨ Effluent median TP was 7.1 mg/L, indicating that no enhanced biological P removal
occurs. ¨ Chlorination was effective, producing low E.coli levels. 5. Operation Process operating parameters for the data period are summarised in Table 4. Figure 2 shows the current 4.8 hour operating cycle. The recorded daily wasting volumes vary and it is uncertain whether the cycle has been consistent over the full data period. The 60 day moving median SRT for the period is 57 days (based on both wasting and effluent SS loss). However as shown in Trend Plot C1 the value varied from 38-96 days, suggesting that the operating cycle may have been varied over the data period. The median MLSS concentration was 3.3 g/L (range 2.1-4.7 as shown in Plot C1). Table 4 Plant Operating Parameters for 27 Months, Jul-11 to Sep-13 Parameter Median Value (and Range) SRT (60d moving average) d MLSS g/L DSVI (since 27-Nov-11) mL/g Effluent NH3-N:NO3-N ratio Cycles: Cycles per day Cycle time min Unaerated fraction: Primary anoxic Secondary anoxic Total
57 (38-96) Plot C1 3.3 (2.1-4.7) Plot C1 101 (42-209) Plot C2 0.12 (0.012-220) Plot C2 Figure 2 5 288 0.21 Less DO decay periods 0.28 Less DO decay period 0.49 Less DO decay periods
Figure 2 Current 288 minute operating cycle (5 cycles per day).
Waste Sludge
Decant
Settle
Aerate
Feed
0 1 2 3 4 5Hours
![Page 93: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/93.jpg)
4 16118:Ken Hartley 2-Dec-13
The sludge settleability (using the DSVI test since 27-Nov-11) has a median value of 101 mL/g (equivalent to an unstirred SVI of about 160 mL/g.1 Trend Plot C2 shows that there is a strong correlation between the DSVI and the effluent ammonia:nitrate ratio.2 The effluent ammonia:nitrate ratio is apparently driven by variation in the plant load (Plot A2 and A3, which include the 60 day moving averages for the BOD mass load and the influent TN concentration) and associated effects on the operating DO concentration and nitrification efficiency. More sophisticated aeration control could allow a lower DSVI level to be maintained more consistently.
1 Hartley Ken (2013), Tuning Biological Nutrient Removal Plants, IWA Publishing.
![Page 94: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/94.jpg)
TREND PLOTS
A 16118:Ken Hartley 2-Dec-13
0
200
400
600
800
0
50
100
150
200
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
BOD
Con
c (m
g/L)
BOD
Mas
s (k
g/d)
A2. Organic Load BOD mass BOD conc 60 per. Mov. Avg. (BOD mass)
0
5
10
15
20
25
0
30
60
90
120
150
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
Tota
l P (m
g/L)
Tota
l N (m
g/L)
A3. Nutrients TN TP 60 per. Mov. Avg. (TN)
BOD 80% limit
BOD max limit
SS 80% limit
SS max limit
0
10
20
30
0
25
50
75
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
SS (m
g/L)
BOD
(mg/
L)
B. EFFLUENT QUALITYB1. BOD & SS BOD SS
0
5
10
15
0
10
20
30
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
TP (m
g/L)
TN (m
g/L)
B2. TN & TP TN NH3-N TP
0
20
40
60
80
100
120
0
120
240
360
480
600
720
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
Rain
fall
(mm
/d)
Flow
(kL
/d)
A. PLANT LOADINGA1. Flow Rainfall Flow
![Page 95: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/95.jpg)
TREND PLOTS
B 16118:Ken Hartley 2-Dec-13
Class A 50% & max limits
Class C 50% & max limits
Free Cl2 max limit0
2
4
6
8
10
0.1
1
10
100
1000
10000
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
Free
Cl2
Res
idua
l (m
g/L)
F. c
ols
(cfu
/100
mL)
B3. Faecal Coliforms & Chlorine F.cols-contact tank Free Cl2 Residual
0
1
2
3
4
5
6
0
20
40
60
80
100
120
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
MLS
S (g
/L)
SRT
(60d
MA
, d)
WA
S (k
L/d)
C. OPERATING PARAMETERSC1. SRT & MLSS SRT WAS MLSS
DS
VI s
tart
0.001
0.01
0.1
1
10
100
1000
0
60
120
180
240
300
360
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
Efflu
ent
NH3 -
N:NO
3-N
Ratio
SVI /
DSV
I (m
L/g)
C2. DSVI DSVI NH3:NO3 ratio
0
20
40
60
80
100
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
N C
onc
(mg/
L)
C3. Effluent N Sewage TN Effluent TN NH3-N
6.0
6.4
6.8
7.2
7.6
8.0
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
pH
C4. pH - Sewage & ML pH - sewage - ML
![Page 96: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/96.jpg)
TREND PLOTS
C 16118:Ken Hartley 2-Dec-13
0
50
100
150
200
0
0.5
1
1.5
2
01-Jul-11 01-Jan-12 01-Jul-12 01-Jan-13 01-Jul-13 01-Jan-14
Con
tact
Tk
HR
T (m
in)
Hyp
o D
ose
(L/d
)
Cl2
Dos
e/10
(mg/
L)Fr
ee C
l2 R
esid
'l (m
g/L)
C5. Chlorination Chlorine Dose Free Cl2 Residual Contact tank HRT-at ave flow -at decant flow Hypo dose
![Page 97: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/97.jpg)
1 16118:Ken Hartley v2:28-Feb-14
Jimboomba WWTP Upgrade Mechanical & Electrical Requirements The Jimboomba Wastewater Treatment Plant is to be upgraded from 1500 EP to 2600 EP to enable it to handle an increasing load until the proposed Cedar Grove plant comes online around 2021. The upgrade may be implemented in two stages as follows: Stage1 (2100 EP): ¨ Influent screening upgrade. ¨ Increase in SBR aeration capacity. ¨ Upgrade of aeration and decanting controls to allow operation on a reduced 3-hour
cycle. ¨ Duplication of the chlorine contact tank and upgraded chlorination controls. Stage 2 (2600 EP): ¨ Raising of the SBR TWL by 225mm, giving a 50% increase in decanting volume. ¨ Doubling of decanter length from 3m to 6m. The upgraded plant flowsheet is shown in Figure 1 and the functional details are listed in Table 1.
Figure 1 Upgraded plant flowsheet.
SBR ContactorEffluentStorage P
Chlorine
Class C recycling95%ile E.coli
1000 cfu/100mL
Sewage
Overflow to river
Screen
Sludge
Contactor
Caustic Soda
![Page 98: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/98.jpg)
2 16118:Ken Hartley v2:28-Feb-14
Table 1 Functional Details Item Existing
1500 EP Capacity, ADWF 315 kL/d Proposed Changes1 2600 EP Capacity, ADWF 550 kL/d
Process Units SBR: Geometry Surface area Volume at TWL Volume at LWL Max water depth Max decant depth Decant weir length Cycle time Decant Cl2 contact tank volume Chlorination capacity Effluent lagoon volume Sludge lagoon volume Drying bed area SBR Equipment Aeration system: Blowers Diffusers SOTR WAS pump Decanting weir Caustic soda dosing
Side walls: upper 1.2m vertical, lower 45deg 204 m2 618 kL 536 kL 4.0 m 0.4m 3m 4.8h (288 mins, 5 cycles/d) Continuous inflow, decant 20% of cycle time; max
decant 82 kL plus inflow during decant, total 115 kL 1 No. 17 kL 32 L/h of 125 gCl2/L NaOCl solution (4 kgCl2/h) 15 ML approx. 2 No. ea 280 kL 75 m2 2 No. ea 140 L/s high speed, 50 L/s slow speed Rehau fine pore membranes 35 kg/h per blower, HS (calc) 1 No. 3 L/s 3m long, max decant depth 0.40m Max dose rate 200 mgCaCO3/L at ADWF
Raise walls & TWL by 225mm 4.2 m 0.6m 6m 3h (180 mins, 8 cycles/d) Max decant volume increased by 50%. Above 3ADWF (1.65 ML/d) operate in settle mode with continuous decanter overflow. 3 No. 17 kL ea Dose 10 mgCl2/L at 7ADWF, 13 L NaOCl/h; provide effluent flow meter, flow-pacing of dose, monitoring of Cl2 residual at end of contact tanks. Free Cl2 residual required, 1.5 mg/L. Increase aeration capacity by 75%. 6m long, max decant depth 0.60m 50% soln; 2 kL tank; dosing pump 5 L/h max
1 M&E items shown in italics. Some controls may also need upgrades.
![Page 99: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/99.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Appendix D Preliminary Options Matrix
![Page 100: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/100.jpg)
Detailed Options Development - Matrix MethodCombination of Hydraulic and Biological Improvements to create options
hydraulic
With hydraulic controls
a) Do nothing b) Flow Balancing –
upstream pump
controls
c) Flow Balancing –
balance tank
b&c) Flow
Balancing – balance
tank + controlled
pumps
d) Increase through
plant capacity
d&b) Increase
through plant
capacity + controlled
pumps
d&b&c) Increase
through plant
capacity + controlled
pumps+balance tank
e&c) Wet weather
bypass + balance
tank
e&c&b) Wet
weather bypass +
controlled pumping +
balance tanks
f) Transfer flows to
Flagstone WWTP
PS VSD controls to RM min/ PWWF Y Y Y Y Y
balance tank Y Y Y Y
biological
i) Do nothing Y
ii) Sequential upgrade of the existing SBR process Y Y Y Y Y Y Y Y
iii) Upgrade SBR process to MBR process Y Y Y Y Y
iv) Add parallel SBR plant Y Y Y
v) Add parallel package plant Y Y Y Y Y
vi) Transfer flows to Flagstone WWTP Y
Preliminary assessment
Options description protects process
minimises poor WQ
for
lagoon/irrigation/
release quality meets objectives Expected cost comment
develop to final
options
i) Do nothing
a) Do nothingno hydraulic or biological upgrade N N N low not acceptable N (comparison only)
ii) Sequential upgrade of the existing SBR process
d&b) Increase through plant capacity + controlled
pumps SBR upgade for biological and hydraulic plus pump
controlsY Y Y
SBR u/g - 2M?
Pump controls -
0.05M?
smaller SBR tank and
weir - accomodate
52/44 L/s
Y
d&b&c) Increase through plant capacity + controlled
pumps+balance tankSBR upgade for biological and hydraulic plus balance
tank plus pump controlsY Y Y
SBR u/g - 2M?
Tank - 0.3M?
Pump controls -
0.05M?
optimise balance
tank and sbr size
(min 5*ADWF). May
be the same as ii-
b&c)
Y
e&c&b) Wet weather bypass + controlled pumping +
balance tanks
SBR upgrade biological
bypass to take flows > 3 or 5 ADWF, balance tank to
cater for smaller peaks to smooth flow, reduced
inflow peaks
Ypartly - does not
during peak flowsY
SBR u/g - 0.3M?
Bypass - 0.5M?
Tank - 0.1M?
smaller bypass and
tankY
iii) Upgrade SBR process to MBR process
iv) Add parallel SBR plant
b) Flow Balancing – upstream pump controls
New SBR -parallel to sbr, with pump controls Ypartly - does not
during peak flowsY
New SBR - 3M?
Pump controls -
0.05M?
SBRs - high peak
flows, alternate
operation
Y
v) Add parallel package plant
b) Flow Balancing – upstream pump controlsNew Package plant -parallel to sbr, with pump
controlsY
partly - does not
during peak flowsY
PP - 3M?
Pump controls -
0.05M?
new PP - high peak
flowsY
vi) Transfer flows to Flagstone WWTP
![Page 101: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/101.jpg)
Jimboomba WWTP Capacity Assessment and Staging Plan
Document Number: 7600-000-P-REP-PL-8214
90-12-53 Date issued: 23/05/2014 Rev: 1
Appendix E Capital Cost and NPV
![Page 102: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/102.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 (original option 1.2)
Direct Cost Estimate
A‐2 Option 1.2 ‐ Existing SBR Upgrade + Small Balance
Tank
A‐2.1 General
Management & Supervision item 0.000 52,240.00$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$
A‐2.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 1.000 ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 1.000 ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 modification works item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$
A‐2.3 Balance Tank ‐ Small
Transfer existing 30kL concrete tank to site (from
loganholme)
item 1.000 2,050.00$ 2,050.00$ 2,050.00$ ‐$ allowance for truck hire/ movement of tank
Supply and Install Balance Tank foundation item 1.000 4,832.00$ 4,832.00$ 4,832.00$ ‐$ RC estimate
Supply and Install return pump (10L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ allowance, includes electricals, foundation etc
Balance tank inlet pipe ‐ DN 225 x 3m item 1.000 660.00$ 660.00$ 660.00$ ‐$ RC estimate
Balance tank overflow pipe ‐ DN 225 x 12m item 1.000 1,360.00$ 1,360.00$ 1,360.00$ ‐$ RC estimate
Balance tank return pipe ‐ DN 150 x 3m item 1.000 600.00$ 600.00$ 600.00$ ‐$ RC estimate
Total ‐ Balance Tank ‐ Small 29,502.00$ 29,502.00$ ‐$
A‐2.4 Treatment Plant Upgrade
SBR wall increase by 225mm item 1.000 29,860.00$ 29,860.00$ 29,860.00$ ‐$ RC estimate
Replacement Weir 3m x 0.885m (inward folding) +
motor
(cost is for 6m weir)
item 1.000 $150,000.00 150,000.00$ 150,000.00$ ‐$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Discharge Pit ‐ 2 nos for Weir 2 & 3 no 2.000 $5,633.00 11,266.00$ 11,266.00$ ‐$ RC estimate
Supply and Install ‐ weir 2 item 1.000 $75,000.00 75,000.00$ 75,000.00$ ‐$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Supply and Install ‐ weir 3 item 1.000 $75,000.00 75,000.00$ 75,000.00$ ‐$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
wier 2 outlet pipe 300mm 3m, + Tee item 1.000 $5,200.00 5,200.00$ 5,200.00$ ‐$ RC estimate
wier 3 outlet pipe 300mm 1m + Tee item 1.000 $2,400.00 2,400.00$ 2,400.00$ ‐$ RC estimate
Replace/ upgrade existing aeration system and
controls
item 1.000 $250,000.00 250,000.00$ ‐$ 250,000.00$ Aquatec Maxcon
Install pH dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Install Alum dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Small Chemical Bund item 3.000 $6,064.00 18,192.00$ ‐$ 18,192.00$ RC estimate
Inlet Screen Pit modifications (additional) item 1.000 13,688.00$ 13,688.00$ 13,688.00$ ‐$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ 5,065.21$ 9,934.79$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$
Electrical works, trenching and civil works (including
minor wks)
item 1.000 200,000.00$ 200,000.00$ 67,536.12$ 132,463.88$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrade 1,093,106.00$ 457,015.33$ 636,090.67$
A‐2.5 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 0.000 ‐$ ‐$ ‐$ ‐$
Construct new Tank 34kL item 1.000 61,716.00$ 61,716.00$ ‐$ 61,716.00$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 132,016.00$ ‐$ 132,016.00$
TOTAL ‐ OPTION 1.2 1,264,624.00$ 496,517.33$ 768,106.67$
Total Project Cost 0.47 1,858,997.28$ 729,880.48$ 1,129,116.80$
Total Project Cost plus Contingency 0.3 2,416,696.46$ 948,844.62$ 1,467,851.84$
Option 1
![Page 103: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/103.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 2017 (original option 2.1)
Direct Cost Estimate
B Option 2.1 ‐ Existing SBR Upgrade + Large Balance
Tank
B.1 General
Management & Supervision item 0.000 52,240.00$ ‐$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$ ‐$
B.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 1.000 ‐$ ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 1.000 ‐$ ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 and 2 program
modification
item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$ ‐$
B.3 Balance Tank ‐ Large
Supply and Install 250kL Balance Tank including
concrete base
item 1.000 115,208.25$ 115,208.25$ 115,208.25$ ‐$ ‐$ RC estimate
Supply and Install return pump (30L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ ‐$ allowance, includes electricals, foundation etc
Balance tank inlet pipe ‐ DN 225 x 3m item 1.000 660.00$ 660.00$ 660.00$ ‐$ ‐$ RC estimate
Balance tank overflow pipe ‐ DN 225 x 12m item 1.000 1,360.00$ 1,360.00$ 1,360.00$ ‐$ ‐$ RC estimate
Balance tank return pipe ‐ DN 150 x 3m item 1.000 600.00$ 600.00$ 600.00$ ‐$ ‐$ RC estimate
Total ‐ Balance Tank ‐ Large 137,828.25$ 137,828.25$ ‐$ ‐$
B.4 Treatment Plant Upgrade
SBR wall increase by 225mm item 1.000 29,860.00$ 29,860.00$ ‐$ ‐$ 29,860.00$ RC estimate
Replacement Weir 3m x 0.885m (inward folding) +
motor
item 1.000 $150,000.00 150,000.00$ ‐$ ‐$ 150,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Discharge Pit ‐ 2 nos for Weir 2 & 3 no 2.000 $5,633.00 11,266.00$ ‐$ ‐$ 11,266.00$ RC estimate
Supply and Install ‐ weir 2 item 1.000 $75,000.00 75,000.00$ ‐$ ‐$ 75,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Supply and Install ‐ weir 3 item 1.000 $75,000.00 75,000.00$ ‐$ ‐$ 75,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
wier 2 outlet pipe 300mm 3m, + Tee item 1.000 $5,200.00 5,200.00$ ‐$ ‐$ 5,200.00$ RC estimate
wier 3 outlet pipe 300mm 1m + Tee item 1.000 $2,400.00 2,400.00$ ‐$ ‐$ 2,400.00$ RC estimate
Replace/ upgrade existing aeration system and
controls
item 1.000 $250,000.00 250,000.00$ ‐$ 250,000.00$ ‐$ Aquatec Maxcon
Install pH dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ ‐$ Aquatec Maxcon
Install Alum dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ ‐$ Aquatec Maxcon
Small Chemical Bund item 3.000 $6,064.00 18,192.00$ ‐$ 18,192.00$ ‐$ RC estimate
Inlet Screen Pit modifications (additional) item 1.000 13,688.00$ 13,688.00$ 13,688.00$ ‐$ ‐$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ 2,507.58$ 7,134.62$ 5,357.80$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$ ‐$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$ ‐$
Electrical works, trenching and civil works (including
minor wks)
item 1.000 200,000.00$ 200,000.00$ 33,434.41$ 95,128.26$ 71,437.34$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrade 1,093,106.00$ 71,629.99$ 595,954.88$ 425,521.14$
B.5 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 0.000 ‐$ ‐$ ‐$ ‐$ ‐$
Construct new Tank 34kl item 1.000 61,716.00$ 61,716.00$ ‐$ ‐$ 61,716.00$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 132,016.00$ ‐$ ‐$ 132,016.00$
TOTAL ‐ OPTION 2.1 1,372,950.25$ 219,458.24$ 595,954.88$ 557,537.14$
Total Project Cost 0.47 2,018,236.87$ 322,603.61$ 876,053.67$ 819,579.59$
Total Project Cost plus Contingency 0.3 2,623,707.93$ 419,384.70$ 1,138,869.77$ 1,065,453.47$
Option 2
![Page 104: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/104.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 2017 (original option 3.1)
Direct Cost Estimate
D Option 3.1 ‐Existing SBR Upgrade + Small Balance
Tank + Wet Weather Bypass to CCT
D.1 General
Management & Supervision item 0.000 52,240.00$ ‐$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$ ‐$
D.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 1.000 ‐$ ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 1.000 ‐$ ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 modification works item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$ ‐$
D.3 Balance Tank ‐ Small
Transfer existing 30kL concrete tank to site (from
loganholme)
item 1.000 2,050.00$ 2,050.00$ 2,050.00$ ‐$ ‐$ allowance for truck hire/ movement of tank
Concrete Base for Existing Balance Tank item 1.000 4,832.00$ 4,832.00$ 4,832.00$ ‐$ ‐$ RC estimate
Supply and Install return pump (10L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ ‐$ allowance, includes electricals, foundation etc
Balance tank inlet pipe ‐ DN 225 x 3m item 1.000 660.00$ 660.00$ 660.00$ ‐$ ‐$ RC estimate
Balance tank return pipe ‐ DN 150 x 3m item 1.000 600.00$ 600.00$ 600.00$ ‐$ ‐$ RC estimate
Total ‐ Balance Tank ‐ Small 28,142.00$ 28,142.00$ ‐$ ‐$
D.4 WW Bypass pipe
WW bypass to CCT ‐ DN225 x 30m item 1.000 4,860.00$ 4,860.00$ 4,860.00$ ‐$ ‐$ RC estimate
Total ‐ Lagoon as Balance Tank 4,860.00$ 4,860.00$ ‐$ ‐$
D.5 Treatment Plant Upgrade
SBR wall increase by 225mm item 1.000 29,860.00$ 29,860.00$ ‐$ ‐$ 29,860.00$ RC estimate
Replacement Weir 3m x 0.885m (inward folding) +
motor
item 1.000 $150,000.00 150,000.00$ ‐$ ‐$ 150,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Discharge Pit ‐ 2 nos for Weir 2 & 3 no 2.000 $5,633.00 11,266.00$ ‐$ ‐$ 11,266.00$ RC estimate
Supply and Install ‐ weir 2 item 1.000 $75,000.00 75,000.00$ ‐$ ‐$ 75,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Supply and Install ‐ weir 3 item 1.000 $75,000.00 75,000.00$ ‐$ ‐$ 75,000.00$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
wier 2 outlet pipe 300mm 3m, + Tee item 1.000 $5,200.00 5,200.00$ ‐$ ‐$ 5,200.00$ RC estimate
wier 3 outlet pipe 300mm 1m + Tee item 1.000 $2,400.00 2,400.00$ ‐$ ‐$ 2,400.00$ RC estimate
Replace/ upgrade existing aeration system and
controls
item 1.000 $250,000.00 250,000.00$ ‐$ 250,000.00$ ‐$ Aquatec Maxcon
Install pH dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ ‐$ Aquatec Maxcon
Install Alum dosing (with automated controls) item 1.000 $50,000.00 50,000.00$ ‐$ 50,000.00$ ‐$ Aquatec Maxcon
Small Chemical Bund item 1.000 $6,064.00 6,064.00$ ‐$ 6,064.00$ ‐$ RC estimate
Inlet Screen Pit modifications (additional) item 3.000 13,688.00$ 41,064.00$ 41,064.00$ ‐$ ‐$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ 1,570.54$ 7,872.86$ 5,556.60$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$ ‐$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$ ‐$
Electrical works, trenching and civil works (including
minor wks)
item 1.000 200,000.00$ 200,000.00$ 20,940.50$ 104,971.48$ 74,088.02$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrade 1,108,354.00$ 85,575.04$ 594,408.34$ 428,370.63$
D.6 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 1.000 5,000.00$ 5,000.00$ ‐$ ‐$ 5,000.00$
Construct new Tank 34kL item 1.000 61,716.00$ 61,716.00$ ‐$ ‐$ 61,716.00$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 137,016.00$ ‐$ ‐$ 137,016.00$
TOTAL ‐ OPTION 3.1 1,288,372.00$ 128,577.04$ 594,408.34$ 565,386.63$
Total Project Cost 0.47 1,893,906.84$ 189,008.24$ 873,780.26$ 831,118.34$
Total Project Cost plus Contingency 0.3 2,462,078.89$ 245,710.71$ 1,135,914.33$ 1,080,453.84$
Option 3
![Page 105: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/105.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 (original option 4.1)
Direct Cost Estimate
G Option 4.1 ‐ New parallel SBR + pump controls
G.1 General
Management & Supervision item 0.000 83,200.00$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$
G.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 modification works item 1.000 10,000 10,000 10,000.00$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$
G.3 Treatment Plant Upgrades
SBR 2 Tank 618kL(duplicate) ‐ Concrete Structure
ONLY
item 1.000 237,329.00$ 237,329.00$ 237,329.00$ ‐$ RC estimate
Replacement Weir 3m x 0.6m (inward folding) +
motor
item 1.000 150,000.00$ 150,000.00$ 150,000.00$ ‐$ Aquatec Maxcon ‐ costed a 6m weir at $200k,
prorated by length +50%
Supply and Install return pump (10L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ allowance, includes electricals, foundation etc
Plant 2 inlet Pipe ‐ DN 300 x 12m item 1.000 22,600.00$ 22,600.00$ 22,600.00$ ‐$ RC estimate
Plant 2 outlet Pipe ‐ DN 300 x 8m item 1.000 2,000.00$ 2,000.00$ 2,000.00$ ‐$ RC estimate
WAS Pipe ‐ DN80mm x 40m item 1.000 2,260.00$ 2,260.00$ ‐$ 2,260.00$ RC estimate
WAS Pump 2 (3 L/s) item 1.000 20,000.00$ 20,000.00$ ‐$ 20,000.00$ allowance, includes foundation etc
WAS Pump 2 delivery pipe ‐ DN80mm x 2m item 1.000 145.00$ 145.00$ ‐$ 145.00$ RC estimate
WAS Pump 2 suction pipe ‐ DN80mm x 3m item 1.000 160.00$ 160.00$ ‐$ 160.00$ RC estimate
SBR Tank 2 Aeration System and Controls item 1.000 250,000.00$ 250,000.00$ ‐$ 250,000.00$ Aquatec Maxcon
Site road relocation (say 15m *4m) m2 120.000 100.00$ 12,000.00$ 12,000.00$ ‐$ RC estimate
Install pH dosing(with automated controls) item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Install Alum dosing (with automated controls) item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Small Chemical Bund item 3.000 6,064.00$ 18,192.00$ ‐$ 18,192.00$ RC estimate
Inlet Screen Pit modifications (additional) item 1.000 13,688.00$ 13,688.00$ 13,688.00$ ‐$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ 6,454.28$ 8,545.72$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$
Electrical works, trenching and civil works (including
minor wks)
item 1.000 200,000.00$ 200,000.00$ 86,057.00$ 113,943.00$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrades 1,210,874.00$ 572,128.28$ 638,745.72$
G.4 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 0.000 ‐$ ‐$ ‐$ ‐$
Construct new Tank 34kL item 1.000 61,716.00$ 61,716.00$ ‐$ 61,716.00$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 132,016.00$ ‐$ 132,016.00$
TOTAL ‐ OPTION 4.1 1,352,890.00$ 582,128.28$ 770,761.72$
Total Project Cost 0.47 1,988,748.30$ 855,728.56$ 1,133,019.74$
Total Project Cost plus Contingency 0.3 2,585,372.79$ 1,112,447.13$ 1,472,925.66$
Option 4
![Page 106: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/106.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 (original option 4.2)
Direct Cost Estimate
F Option 4.2 ‐ New package plant(parallel to SBR) +
pump controls
F.1 General
Management & Supervision item 0.000 62,560.00$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$
F.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 and 2 program
modification
item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$
F.3 Treatment Plant Upgrades
Package Plant 1 500 EP item 1.000 576,354.56$ 576,354.56$ 576,354.56$ ‐$ supplier estimate
Package Plant 1 Foundation item 1.000 64,884.00$ 64,884.00$ 64,884.00$ ‐$ RC estimate
Package Plant 2 600 EP item 1.000 677,407.69$ 677,407.69$ ‐$ 677,407.69$ supplier estimate
Package Plant 2 Foundation item 1.000 64,884.00$ 64,884.00$ ‐$ 64,884.00$ RC estimate
Plant 2 inlet Pipe ‐ DN 300 x 12m item 1.000 22,600.00$ 22,600.00$ 22,600.00$ ‐$ RC estimate
Plant 2 outlet Pipe ‐ DN 300 x 8m item 1.000 2,000.00$ 2,000.00$ 2,000.00$ ‐$ RC estimate
Plant 3 inlet Pipe ‐ DN 225 x 9m item 1.000 13,600.00$ 13,600.00$ ‐$ 13,600.00$ RC estimate
Plant 3 outlet Pipe ‐ DN 225 x 7m item 1.000 2,000.00$ 2,000.00$ ‐$ 2,000.00$ RC estimate
WAS Pipe ‐ DN80mm x 40m item 1.000 2,000.00$ 2,000.00$ 2,000.00$ ‐$ RC estimate
WAS Pump 2 (3 L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ allowance, includes foundation etc
WAS Pump 2 delivery pipe ‐ DN80mm x 2m item 1.000 145.00$ 145.00$ 145.00$ ‐$ RC estimate
WAS Pump 2 suction pipe ‐ DN80mm x 3m item 1.000 160.00$ 160.00$ 160.00$ ‐$ RC estimate
Small Chemical Bund item 1.000 6,064.00$ 6,064.00$ ‐$ 6,064.00$ RC estimate
Inlet Screen Pit modifications (additional) item 1.000 13,688.00$ 13,688.00$ ‐$ 13,688.00$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ 6,243.97$ 8,756.03$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$
Electrical works, trenching and civil works (including
minor wks)
item 0.500 200,000.00$ 100,000.00$ 41,626.49$ 58,373.51$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrades 1,728,287.24$ 758,014.02$ 970,273.22$
F.4 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 0.000 ‐$ ‐$ ‐$ ‐$ Awaiting costs
Construct new Tank 26kL item 1.000 47,194.59$ 47,194.59$ ‐$ 47,194.59$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 117,494.59$ ‐$ 117,494.59$
TOTAL ‐ OPTION 4.2 1,855,781.83$ 768,014.02$ 1,087,767.81$
Total Project Cost 0.47 2,727,999.29$ 1,128,980.61$ 1,599,018.68$
Total Project Cost plus Contingency 0.3 3,546,399.08$ 1,467,674.80$ 2,078,724.28$
Option 5
![Page 107: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/107.jpg)
Planning Estimate ‐ 90‐12‐53
Jimboomba WWTP Capacity AssessmentRemarks
Item Description Unit Quantity Unit rate Amount 2014 2016 (Option 4 + balance tank)
Direct Cost Estimate
G preferred option ‐ New parallel SBR + pump
controls+ BALANCE TANK
G.1 General
Management & Supervision item 0.000 83,200.00$ ‐$ ‐$ ‐$ RC estimate
Site Establishment item 0.000 10,000.00$ ‐$ ‐$ ‐$ RC estimate
Total ‐ General ‐$ ‐$ ‐$
G.2 Common SPS Control Modification Scope to all
Options
Install VSD Controls item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Install Coms Control item 0.000 ‐$ ‐$ ‐$ ‐$ included in other project
Wet Weather Pumping ‐ SPS 1 modification works item 1.000 10,000 10,000 10,000.00$ ‐$ allowance for control modifications (plc
programming, scada alarms etc)
Total ‐ Common Scope to all Options 10,000.00$ 10,000.00$ ‐$
A‐2.3 Balance Tank ‐ Small
Transfer existing 30kL concrete tank to site (from
loganholme)
item 1.000 2,050.00$ 2,050.00$ 2,050.00$ ‐$ RC estimate
Supply and Install Balance Tank foundation item 1.000 4,832.00$ 4,832.00$ 4,832.00$ ‐$ RC estimate
Supply and Install return pump (10L/s) item 1.000 20,000.00$ 20,000.00$ 20,000.00$ ‐$ allowance, includes electricals, foundation etc
Balance tank inlet pipe ‐ DN 225 x 3m item 1.000 660.00$ 660.00$ 660.00$ ‐$ RC estimate
Balance tank overflow pipe ‐ DN 225 x 12m item 1.000 1,360.00$ 1,360.00$ 1,360.00$ ‐$ RC estimate
Balance tank return pipe ‐ DN 150 x 3m item 1.000 600.00$ 600.00$ 600.00$ ‐$ RC estimate
Total ‐ Balance Tank ‐ Small 29,502.00$ 29,502.00$ ‐$
G.3 Treatment Plant Upgrades
SBR 2 Tank 618kL(duplicate) ‐ Concrete Structure
ONLY
item 1.000 237,329.00$ 237,329.00$ ‐$ 237,329.00$ RC estimate
Replacement Weir 3m x 0.885m (inward folding) +
motor
item 1.000 150,000.00$ 150,000.00$ ‐$ 150,000.00$ Aquatec Maxcon
Plant 2 inlet Pipe ‐ DN 300 x 12m item 1.000 22,600.00$ 22,600.00$ ‐$ 22,600.00$ RC estimate
Plant 2 outlet Pipe ‐ DN 300 x 8m item 1.000 2,000.00$ 2,000.00$ ‐$ 2,000.00$ RC estimate
WAS Pipe ‐ DN80mm x 40m item 1.000 2,260.00$ 2,260.00$ ‐$ 2,260.00$ RC estimate
WAS Pump 2 (3 L/s) item 1.000 20,000.00$ 20,000.00$ ‐$ 20,000.00$ allowance, includes foundation etc
WAS Pump 2 delivery pipe ‐ DN80mm x 2m item 1.000 145.00$ 145.00$ ‐$ 145.00$ RC estimate
WAS Pump 2 suction pipe ‐ DN80mm x 3m item 1.000 160.00$ 160.00$ ‐$ 160.00$ RC estimate
SBR Tank 2 Aeration System and Controls item 1.000 250,000.00$ 250,000.00$ ‐$ 250,000.00$ Aquatec Maxcon
Site road relocation (say 15m *4m) m2 120.000 100.00$ 12,000.00$ ‐$ 12,000.00$ RC estimate
Install pH dosing(with automated controls) item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Install Alum dosing (with automated controls) item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
Small Chemical Bund item 3.000 6,064.00$ 18,192.00$ ‐$ 18,192.00$ RC estimate
Inlet Screen Pit modifications (additional) item 1.000 13,688.00$ 13,688.00$ 13,688.00$ ‐$ allowance
Automated Valves on Sludge overflow item 2.000 6,000.00$ 12,000.00$ 12,000.00$ ‐$ allowance
Flowmeter on inlet main item 1.000 10,000.00$ 10,000.00$ 10,000.00$ ‐$ allowance
Scada upgrade item 1.000 15,000.00$ 15,000.00$ ‐$ 15,000.00$ allowance for general scada modifications for
new infrastructure and operational changes
Additional Switchboard item 1.000 80,000.00$ 80,000.00$ ‐$ 80,000.00$
New Switchboard and Blower Room/Building item 1.000 45,500.00$ 45,500.00$ ‐$ 45,500.00$
Electrical works, trenching and civil works (including
minor wks)
item 1.000 200,000.00$ 200,000.00$ 12,937.12$ 187,062.88$ Aquatec Maxcon
Total ‐ Treatment Plant Upgrades 1,190,874.00$ 48,625.12$ 1,142,248.88$
G.4 Chlorine Contact Tank
New Cl dosing system item 1.000 50,000.00$ 50,000.00$ ‐$ 50,000.00$ Aquatec Maxcon
New Cl dosing storage item 0.000 ‐$ ‐$ ‐$ ‐$
Construct new Tank 34kL item 1.000 61,716.00$ 61,716.00$ ‐$ 61,716.00$ RC estimate
Construct new effluent manhole and short 225dia
pipe
item 1.000 10,000.00$ 10,000.00$ ‐$ 10,000.00$ allowance
Relocate algae toxin removal filter item 1.000 10,300.00$ 10,300.00$ ‐$ 10,300.00$ allowance for truck hire/ movement of tank
Total ‐ Chlorine Contact Tank 132,016.00$ ‐$ 132,016.00$
TOTAL ‐ OPTION 4.1 + small balance tank 1,362,392.00$ 88,127.12$ 1,274,264.88$
Total Project Cost 0.47 2,002,716.24$ 129,546.86$ 1,873,169.38$
Total Project Cost plus Contingency 0.3 2,603,531.11$ 168,410.92$ 2,435,120.19$
Preferred Option: Option 4.1 + balance tank
![Page 108: LOGAN WATER ALLIANCE JIMBOOMBA WWTP ... WWTP Capacity Assessment and Staging Plan Document Number: 7600-000-P-REP-PL-8214 90-12-53 Date issued: 23/05/2014 Page 4 of …](https://reader030.fdocuments.net/reader030/viewer/2022041200/5d406efd88c99391748c46d9/html5/thumbnails/108.jpg)
90‐12‐53 Jimboomba WWTP Capacity Assessment ‐ NPV Tables Including Sensitivity Assessment
NPV Comparison Table
OPTIONS NPV Capital Investment RANK OPTIONS NPVVariation
from lowest
Percentage Variation
from lowest
Capital
Investment
Variation
from lowest
Percentage Variation
from lowest
Option 1 $12,665,380 $2,416,696 4 Option 1 $12,665,380 $337,079 3.1% $2,416,696 $0 0.0%Option 2 $12,778,156 $2,623,708 5 Option 2 $12,778,156 $449,856 4.2% $2,623,708 $207,011 1.9%Option 3 $12,575,630 $2,462,079 3 Option 3 $12,575,630 $247,329 2.3% $2,462,079 $45,382 0.4%Option 4 $12,328,301 $2,585,373 1 Option 4 $12,328,301 $0 0.0% $2,585,373 $168,676 1.6%Option 5 $13,921,010 $3,546,399 6 Option 5 $13,921,010 $1,592,710 14.8% $3,546,399 $1,129,703 10.5%Preferred Option $12,502,235 $2,603,531 2 Preferred Option $12,502,235 $173,934 1.6% $2,603,531 $186,835 1.7%
NPV Comparison Table
OPTIONS NPV Capital Investment RANK OPTIONS NPVVariation
from lowest
Percentage Variation
from lowest
Capital
Investment
Variation
from lowest
Percentage Variation
from lowest
Option 1 $13,770,203 $2,416,696 4 Option 1 $13,770,203 $1,377,042 12.8% $2,416,696 $0 0.0%Option 2 $13,943,489 $2,623,708 5 Option 2 $13,943,489 $1,550,328 14.4% $2,623,708 $207,011 1.9%Option 3 $13,759,042 $2,462,079 3 Option 3 $13,759,042 $1,365,881 12.7% $2,462,079 $45,382 0.4%Option 4 $12,393,161 $2,585,373 1 Option 4 $12,393,161 $0 0.0% $2,585,373 $168,676 1.6%Option 5 $15,000,403 $3,546,399 6 Option 5 $15,000,403 $2,607,242 24.3% $3,546,399 $1,129,703 10.5%Preferred Option $12,465,821 $2,603,531 2 Preferred Option $12,465,821 $72,660 0.7% $2,603,531 $186,835 1.7%
NPV Comparison Table
OPTIONS NPV Capital Investment RANK OPTIONS NPVVariation
from lowest
Percentage Variation
from lowest
Capital
Investment
Variation
from lowest
Percentage Variation
from lowest
Option 1 $13,365,420 $2,416,696 4 Option 1 $13,365,420 $106,980 1.0% $2,416,696 $0 0.0%Option 2 $13,449,761 $2,623,708 5 Option 2 $13,449,761 $191,320 1.8% $2,623,708 $207,011 1.9%Option 3 $13,258,440 $2,462,079 1 Option 3 $13,258,440 $0 0.0% $2,462,079 $45,382 0.4%Option 4 $13,264,608 $2,585,373 2 Option 4 $13,264,608 $6,168 0.1% $2,585,373 $168,676 1.6%Option 5 $14,597,242 $3,546,399 6 Option 5 $14,597,242 $1,338,801 12.5% $3,546,399 $1,129,703 10.5%Preferred Option $13,293,636 $2,603,531 3 Preferred Option $13,293,636 $35,196 0.3% $2,603,531 $186,835 1.7%
NPV Comparison Table
OPTIONS NPV Capital Investment RANK OPTIONS NPVVariation
from lowest
Percentage Variation
from lowest
Capital
Investment
Variation
from lowest
Percentage Variation
from lowest
Option 1 $11,890,921 $2,416,696 5 Option 1 $11,890,921 $444,275 4.1% $2,416,696 $0 0.0%Option 2 $11,855,958 $2,623,708 4 Option 2 $11,855,958 $409,312 3.8% $2,623,708 $207,011 1.9%Option 3 $11,635,445 $2,462,079 3 Option 3 $11,635,445 $188,799 1.8% $2,462,079 $45,382 0.4%Option 4 $11,446,646 $2,585,373 1 Option 4 $11,446,646 $0 0.0% $2,585,373 $168,676 1.6%Option 5 $13,250,577 $3,546,399 6 Option 5 $13,250,577 $1,803,931 16.8% $3,546,399 $1,129,703 10.5%Preferred Option $11,531,687 $2,603,531 2 Preferred Option $11,531,687 $85,041 0.8% $2,603,531 $186,835 1.7%
NPV Comparison Table
OPTIONS NPV Capital Investment RANK OPTIONS NPVVariation
from lowest
Percentage Variation
from lowest
Capital
Investment
Variation
from lowest
Percentage Variation
from lowest
Option 1 $19,523,200 $2,416,696 2 Option 1 $19,523,200 $120,468 1.1% $2,416,696 $0 0.0%Option 2 $19,747,813 $2,623,708 3 Option 2 $19,747,813 $345,082 3.2% $2,623,708 $207,011 1.9%Option 3 $19,402,731 $2,462,079 1 Option 3 $19,402,731 $0 0.0% $2,462,079 $45,382 0.4%Option 4 $20,270,423 $2,585,373 4 Option 4 $20,270,423 $867,692 8.1% $2,585,373 $168,676 1.6%Option 5 $21,504,094 $3,546,399 6 Option 5 $21,504,094 $2,101,363 19.6% $3,546,399 $1,129,703 10.5%Preferred Option $20,653,275 $2,603,531 5 Preferred Option $20,653,275 $1,250,544 11.6% $2,603,531 $186,835 1.7%
NPV Summary Table ‐ Population Sensitivity ‐ D: 2%
Growth
NPV Summary Table ‐ Population Sensitivity ‐ A: +400 EP
NPV Summary Table ‐ Population Sensitivity ‐ B: 10%
Growth
NPV Summary Table ‐ Population sensitivity ‐ C: 5%
Growth
NPV Summary Table ‐ 25 yr