1910.147(a)(1) Scope1910.147(a)(1) Scope

• Covers servicing and maintenance of machines and equipment in which– Unexpected energization or start up or– Release of stored energy could cause– Injury to employees

• Normal operation iscovered in 1910 Subpart O

Page 3: Lockout tagout

1910.147(a)(1)(ii) Exemptions1910.147(a)(1)(ii) Exemptions

• Construction, agriculture and maritime employment;

• Electrical Utilities;• Electrical equipment (covered by Subpart S)• Oil and gas well drilling and servicing• So why comply?

Page 4: Lockout tagout

Control of Hazardous EnergyControl of Hazardous Energy

• Why use lockout/tagout?

– Protects maintenance personnel from power being reapplied by mistake

– Recommended by API RP 54 for electrical systems in drilling and servicing operations

– Recognized hazard

Page 5: Lockout tagout

1910.147(a)(2) Application1910.147(a)(2) Application

• Service and maintenance:– Employee required to remove or bypass a guard

or safety device– Employee required to place part of body into

area that would be a danger zone during machine operation cycle

Page 6: Lockout tagout

1910.147(a)(2) Application1910.147(a)(2) Application

• Exception: Minor adjustments and servicing activities during normal production if– Routine– Repetitive– Integral to production

• Provided that alternative measures provide effective protection

Page 7: Lockout tagout

1910.147(a)(2) Application1910.147(a)(2) Application

• Does not apply to cord and plug connected equipment for which– Exposure to hazard is controlled by

unplugging and– Plug under exclusive control of

employee performing service or maintenance

Page 8: Lockout tagout

1910.147(a)(2) Application1910.147(a)(2) Application

• Does not apply to hot tap operations in transmission and distribution operations in pressurized pipelines provided that:– Continuity of service is essential,– Shutdown of system is impractical, and– Documented procedures and special equipment

provide proven effective protection for employees

Page 9: Lockout tagout

1910.147(a)(3) Purpose1910.147(a)(3) Purpose

• Establish a program and utilize procedures for affixing appropriate lockout devices or tagout devices to energy isolating devices

• Prevent unexpected energization, start up or release of stored energy in order to prevent injury to employees

• Training and procedural requirements for other sections’ LO/TO requirements

Page 10: Lockout tagout

Affected employeeAffected employee

• Job requires employee to – operate or use a machine or equipment on

which servicing or maintenance is being performed under lockout or tagout, or

– work in an area in which such servicing or maintenance is being performed

Page 11: Lockout tagout

Authorized employeeAuthorized employee

• Locks out or tags out machines or equipment in order to perform servicing or maintenance on that machine or equipment

• Affected employee whose duties include servicing or maintenance under this section

Page 12: Lockout tagout

EnergizedEnergized

• Connected to an energy source OR• Containing residual or stored energy

Page 13: Lockout tagout

Energy isolating deviceEnergy isolating device

• A mechanical device that physically prevents the transmission or release or energy– Circuit breakers included– NOT push buttons– NOT selector switches– NOT control circuits

Page 14: Lockout tagout

Energy sourceEnergy source

• Any source of: – Electrical, – Mechanical, – Hydraulic, – Pneumatic, – Chemical, – Thermal, or – Other energy

What kind of energydid the rock have?

Page 15: Lockout tagout

LockoutLockout

• Placement of a lockout device on an energy isolating device, in accordance with an established procedure, ensuring that energy isolating device and equipment being controlled cannot be operated until lockout device is removed

Page 16: Lockout tagout

Lockout deviceLockout device

• Device that uses a positive means such as a lock, either key or combination type, to hold an energy isolating device in the safe position and prevent the energizing of a machine or equipment

• Blank flanges and bolted slip blinds included

Page 17: Lockout tagout

Servicing and/or maintenanceServicing and/or maintenance

• Workplace activities such as:– Constructing, – Installing, – Setting up, – Adjusting, – Inspecting, – Modifying, and – Maintaining and/or servicing machines or

equipment

Page 18: Lockout tagout

TagoutTagout

• Placement of tagout device – on an energy isolating device, – in accordance with an established procedure, – to indicate that energy

isolating device and equipment being controlled may not be operated until tagout device is removed

Page 19: Lockout tagout

General RequirementsGeneral Requirements

1910.147(c)1910.147(c)

Page 20: Lockout tagout

Energy control programEnergy control program

• Energy control procedures• Employee training• Periodic inspections• Any employee who services/maintains any

equipment where unexpected energizing or stored energy release could cause injury isolates and renders it inoperative first.

Page 21: Lockout tagout

1910.147(c)(ii) General Requirements1910.147(c)(ii) General Requirements

• If an energy isolating device is capable of being locked out, the employer's energy control program shall utilize lockout, unless the employer can demonstrate that the utilization of a tagout system will provide full employee protection

Page 22: Lockout tagout

1910.147(c)(iii) General Requirements1910.147(c)(iii) General Requirements

• Energy isolating devices designed to accept lockout devices whenever:– Replacement or major repair, renovation or

modification of equipment is performed or– New machines or equipment are installed

Page 23: Lockout tagout

1910.147(c)(3) Full employee protection1910.147(c)(3) Full employee protection

• When tagout device used on energy isolation device capable of being locked out: – Same location as potential lockout device– Demonstrably equivalent program

• May require additional safety elements

Page 24: Lockout tagout

1910.147(c)(4) Energy control procedure1910.147(c)(4) Energy control procedure• Procedures shall be developed, documented

and utilized for the control of potentially hazardous energy when employees are engaged in the activities covered by this section.– Exception with all 8 elements listed in standard

Page 25: Lockout tagout

1910.147(c)(4) Energy control procedure1910.147(c)(4) Energy control procedure• Outline scope, purpose, authorization, rules,

techniques for control of hazardous energy, including:– Specific intended use of the procedure;– Specific steps for shutting down, isolating,

blocking and securing equipment– Specific steps for placement, removal, transfer

of lockout/tagout devices and responsibility for them

– Specific requirements for testing equipment to verify effectiveness of lockout devices, tagout devices, and other energy control measures

Page 26: Lockout tagout

1910.147(c)(5) Protective materials and hardware1910.147(c)(5) Protective materials and hardware• Locks, tags, chains, wedges, key blocks,

adapter pins, self-locking fasteners, or other hardware shall be provided by the employer for isolating, securing or blocking of equipment from energy sources

Page 27: Lockout tagout

1910.147(c)(5) Protective materials and hardware1910.147(c)(5) Protective materials and hardware• Lockout and tagout devices must be:

– Singularly identified– The only device(s) used for controlling energy– Not used for other purposes– And shall meet the following

requirements:

Page 28: Lockout tagout

1910.147(c)(5) Protective materials and hardware1910.147(c)(5) Protective materials and hardware• Capable of withstanding environment for

maximum time period• Moisture or corrosives must not make tag

deteriorate• Standardized:

– Color– Shape– Size– Print/Format

Page 29: Lockout tagout

1910.147(c)(5) Protective materials and hardware1910.147(c)(5) Protective materials and hardware• Lockout devices:

– Substantial enough to prevent removal without excessive force or unusual techniques such as bolt cutters

• Tagout devices:– Substantial enough to prevent inadvertent or

accidental removal– Non-reusable attachment means– Attachable by hand, self-lockable– At least equivalent to nylon cable tie

Page 30: Lockout tagout

1910.147(c)(5) Protective materials and hardware1910.147(c)(5) Protective materials and hardware• Lockout and tagout devices indicate identity of

employee applying devices

Page 31: Lockout tagout

1910.147(c)(6) Periodic Inspection1910.147(c)(6) Periodic Inspection

• Energy control procedure inspected at least annually:– By authorized employee not using the

procedure being inspected– Correct any deviations– Review employee responsibilities with:

• each authorized employee – lockout• each affected or authorized employee – tagout

Page 32: Lockout tagout

1910.147 (c)(7) Training and communication1910.147 (c)(7) Training and communication• Ensure employees understand purpose and

function of energy control program• Ensure employees acquire skills required for

safe application, usage, removal of energy controls

Page 33: Lockout tagout

Employee Training RequirementsEmployee Training Requirements

• Authorized employee:– Recognition of hazardous energy sources– Type and amount of energy in workplace– Methods and means for energy isolation

• Affected employee: – Purpose and use of procedure

• Other employees in area:– Procedure and prohibition on restarting

Page 34: Lockout tagout

Employee Training Requirements for TagoutEmployee Training Requirements for Tagout• Train on limitations of tags:

– Warning devices do not provide physical restraint that a lock would

– Tag not to be removed without owner’s authorization, bypassed, ignored, defeated

– Must be legible / understandable to work– Must withstand environmental conditions– False sense of security – Attach securely: avoid accidental removal

Page 35: Lockout tagout

Employee RetrainingEmployee Retraining

• For all authorized or affected employees when:– Job assignment changes– Equipment or processes present new hazard– Energy control procedure changes– Knowledge / use of program is inadequate

• Certify employee training up to date

Page 36: Lockout tagout

1910.147(c)(8) Energy Isolation1910.147(c)(8) Energy Isolation

• Only the authorized employees performing the servicing or maintenance may apply lockout/tagout

Page 37: Lockout tagout

1910.147(c)(9) Notification of Employees1910.147(c)(9) Notification of Employees• Affected employees must be notified

– By employer or authorized employee– Of application and removal of lockout and

tagout devices– Before controls are applied– After controls are removed

Page 38: Lockout tagout

Order of Operation for Application of ControlOrder of Operation for Application of Control1. Preparation for shutdown2. Equipment shutdown – orderly3. Equipment isolation 4. Lockout or tagout device application5. Stored energy relieved; continue while

reaccumulating6. Verification of isolation

– Test and return to “off” position

Page 39: Lockout tagout

1910.147(e) Release from Lockout1910.147(e) Release from Lockout

• Before lockout or tagout devices removed and energy restored, ensure:

• Machine or equipment:– Inspect area; remove nonessential items– Ensure equipment components intact

• Employees:– Ensure all employees safe or removed– Before restart, notify affected employees of

removal

Page 40: Lockout tagout

1910.147(e) Release from Lockout1910.147(e) Release from Lockout

• Each lockout/tagout device removed by employee who applied the device– If not available, removed under employer

direction– Specific procedures and training from energy

control program must be in use!• Verify that applying employee is not at facility• Make all reasonable efforts to contact/notify• Ensure authorized employee knows of removal

before resuming work at facility

Page 41: Lockout tagout

1910.147(f)(1) Testing or Positioning1910.147(f)(1) Testing or Positioning

• Temporary removal of lockout/tagout devices for testing/positioning:– Clear tools and materials– Remove employees from equipment area– Remove lockout/tagout devices (as in (e))– Energize and test or position– Deenergize systems and reapply energy control

measures to continue servicing

Page 42: Lockout tagout

1910.147(f)(2) Outside Personnel1910.147(f)(2) Outside Personnel

• Contractors and other outside personnel:– On-site employer and outside employer inform

each other of lockout/tagout procedures– On-site employer complies with outside

employer’s energy control program

Page 43: Lockout tagout

1910.147(f)(3) Group Lockout or Tagout1910.147(f)(3) Group Lockout or Tagout

• Procedure must provide protection equivalent to personal lockout/tagout device

• Primary responsibility is vested in an authorized employee for a set number of employees working under the protection of a group lockout or tagout device (such as an operations lock);

Page 44: Lockout tagout

1910.147(f)(3) Group Lockout or Tagout1910.147(f)(3) Group Lockout or Tagout

• When more than one crew, craft, department, etc. is involved:– Designated authorized employee takes

lockout/tagout control responsibility– Coordinates affected work forces– Ensures continuity of protection

Page 45: Lockout tagout

1910.147(f)(3) Group Lockout or Tagout1910.147(f)(3) Group Lockout or Tagout

• Each authorized employee affixes personal lockout/tagout device to group lockout device when beginning work

• Each removes personal device when stopping work on this equipment

Page 46: Lockout tagout

1910.147(f)(4) Shift or Personnel Changes1910.147(f)(4) Shift or Personnel Changes• Specific procedures in energy control plan• Ensure continuity of lockout/tagout protection• Orderly transfer of lockout/tagout device

protection between shifts• Minimize exposure to hazards from