Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013...

27
Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by renewable energy sources Alberto Cucatto – Quality Air Service and Energy Resources of the Province of Turin

Transcript of Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013...

Page 1: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Local Agenda 21 in territorial planning in energy and waste management

Torino 29th January 2013

Permits for power plants for electricity production by renewable energy sources

Alberto Cucatto – Quality Air Service and Energy Resources of the Province of Turin

Page 2: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 2

Energy plants permissions

It is not the production of electrical energy that must be authorized but the construction and operation of the production plant, according to:

•Emissions to the atmosphere for thermoelectric plants (> 3 MW for gaseous fuels> 1 MW for liquid and solid fuels)

•Hydroelectric derivations

•Waste treatment (in case of energy recovery from waste)

•Permissions for the construction of structures

•Permissions for specific constraints existing on the project site

Page 3: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 3

Energy plants permissions

Verification phase of VIA (L.R. 40/1998)• Power hydroelectric plants hydroelectric plants > 100 kW 100 kW and derivation of flow> 260 l / s260 l / s

•Thermal plants Thermal plants with total combustion power> 50 MW > 50 MW (Environmental Integrated Authorization)

•Power wind and photovoltaic plants > 1 MWPower wind and photovoltaic plants > 1 MW, excluding PV on buildings and those on the ground in industrial areas (as classified by PRGC)

Thermoelectric power plants> 300 MW

Unique process of national competence, including environmental impact assessment (April 9, 2002 Law No. 55.)

Page 4: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Authorizing procedures semplification

The Leg. Decree 387/2003 provides a unique license for plants producing electricity from renewable sources.

• Issued by the competent Authority (delegated Regions or Provinces) in accordance with local regulations concerning the protection of the environment, the landscape and the historical and artistic heritage.

• Within 90 days from the filing of the petition.• It is entitled to build and to operate the plant in accordance with the

approved design and, if it is necessary, the declaration of public, unpostponability and urgency.

• It represents, whenever necessary, the variant planning instrument

Page 5: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 5

Guidelines approved by the L.D. September 10, 2010 Guidelines approved by the L.D. September 10, 2010

Finalities• Standardize the process• Ensure a proper integration of the plants, especially with regard to

wind plants.

Plants placement in the landscape and in the territory: general criteria

1. Good plant design, proven with adhesion of the designer to quality and environmental management systems

2. Exploitation of the potential energy of the various renewable resources in the area and their ability to replace fossil fuels

3. Design criteria in order to get the lowest possible consumption of land, making the most of available energy resources

4. Rehabilitation of areas already degraded by past activities or currently in activity (brown field), including industrial sites, quarries, landfills, etc. ...

Page 6: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 6

5. Planning related to the area specificities, especially in agricultural areas the integration in the context of agricultural traditions and local rural landscape.

6. Research and development of design solutions and innovative technologies

7. Involvement of citizens (preliminary information/training staff and future workers)

8. Effective exploitation of the recovery of thermal energy produced in the process of cogeneration in biomass fueled plants.

Unsuitable areasThere is the possibility that the Regions indicate areas and sites unsuitable for the

installation of specific types of plants according to criteria established by the guidelines themselves.

Guaranties: costs for divestment plant at the end of its life and recovery sites

Preliminary charges: Max 0.03% of the investment in favor of the previous administration

Page 7: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 7

Plants liable to unique authorization ex art. 12 L. D. Plants liable to unique authorization ex art. 12 L. D. 387/2003387/2003

Table A added from L. 24 December 2007 n. 244 to D. Lgs. 387/2003Table A added from L. 24 December 2007 n. 244 to D. Lgs. 387/2003

Source Threshold Biomass 200 kWBiogas 250 kWSolar photovoltaic 20 kWWind 60 kWHydraulic 100 kW

For plants with a lower production it is provided the semplified certifying For plants with a lower production it is provided the semplified certifying procedure (PAS) ex art. 6 D. Lgs. 28/2011 (municipal competence)procedure (PAS) ex art. 6 D. Lgs. 28/2011 (municipal competence)

Page 8: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo 8

Unique Authorization Contents

In addition to what is accepted in the art. 12 of Legislative Decree no. 387/03:

• It includes all acts of authorization, rating, opinion, consent expressed or tacit consent however provided by the single regulations and made by the authorities occurred in Conference

• It include any requirements to which the construction and the running plants are subordinate

• It provides a deadline for the start and conclusion of works, after which it loses its effectiveness, unless extension is provided

• Can be defined conference services any compensating measures for municipalities of environmental and territorial nature and not only financial ones.

Page 9: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Photovoltaic plant of about 2.800 kW on a hazardous waste landfill - BARRICALLA - Collegno

Page 10: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.
Page 11: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Tot. 2.770 kW

Page 12: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.
Page 13: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.
Page 14: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Plant present conditions

Page 15: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Photo simulation – definitive condition

Page 16: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Wood biomass cogeneration plant from around 12 MW - Airasca

Page 17: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Wood biomass cogeneration plant: characteristics

Biomass fueled steam generator of 49 MW from the heat source Combustion in kiln with moving grating Production of 50 t/h of steam at 60 bar and 460 ° C

Steam turbine of nominal electrical power 13.5 MW with tapping for cogeneration (6 MW)

Water-cooled condenser through 3 evaporative towers

Line treatment and ejection fumes

Storage systems and supply of biomass to the boiler

Demineralized water production system

System recovery and storage ashes

Plant connection to the grid

Exchangers for heat providing for industrial adjacent plant

Page 18: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Pellet Lading

Page 19: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Evaporating towers

Page 20: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Biogas plant produced with agricultural products and zootechnic refluents of 800 kW

Page 21: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Plant layout

Page 22: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Anaerobic Digester

Page 23: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Cogenaration powered container

Page 24: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Digestate storage by separating solid – liquid

Page 25: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Cogenerator with vegetable oil in an industrial site

• Section of electrical cogeneration in soundproof container:

– Thermal power input: 2,500 kW electrical power: 998 kW

– Thermal recovery system (800 kW approx):

•Steam generator by fumes recovery: 200 kW•Heat exchanger for hot water by fumes: 280 kW•Heat exchanger with cooling engine fluids (around 300 kW)•Treatment fumes System:

– Oxidative catalyzer for CO and unburnt– Urea injection SCR or ammonia for reducing NOx– No. 2 chimneys (bypass and GVR)

Page 26: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

Cogenerator with vegetable oil: functioning model

Page 27: Local Agenda 21 in territorial planning in energy and waste management Torino 29 th January 2013 Permits for power plants for electricity production by.

Il Programma ENPI CBC Bacino del Mediterraneo

THANK YOU FOR YOUR ATTENTION