LNG RECEIVING TERMINAL NYNÄSHAMN Facts Project Description Full containment Tank 20.000 cbm - Design and Engineering City/Country Nynäshamn / Sweden Client AGA Linde Gas, Lidingö Contract Value € 1,03 Mio. Construction Period 1/2009 - 1/2010 (24 months) .
Transcript of LNG RECEIVING TERMINAL NYNÄSHAMN · 2016. 7. 7. · LNG RECEIVING TERMINAL NYNÄSHAMN Facts...
-
LNG RECEIVING TERMINALNYNÄSHAMN
Facts Project DescriptionFull containment Tank 20.000 cbm - Design and Engineering
City/Country
Nynäshamn / Sweden
Client
AGA Linde Gas, Lidingö
Contract Value
€ 1,03 Mio.
Construction Period
1/2009 - 1/2010 (24 months)
.