LIST OF STAFF S.N o. Name of Employee Designati on Work Load Name of Work Sanction Cost (in Lacs)...

23

Transcript of LIST OF STAFF S.N o. Name of Employee Designati on Work Load Name of Work Sanction Cost (in Lacs)...

LIST OF STAFFS.No.

Name of Employee

Designation

Work Load

Name of Work

Sanction Cost (in Lacs)

Work Executed up to date

Remaining work

1. Sh. A.B. Pandey

Resident Engineer

Const. of ROB at Tijara Phatak

1875.00 115.44 1759.56

2. Sh. R.K. Mali Asstt. Resident Engineer

Const. CFC Building Gola ka bas

88.65 63.53 25.12

3. Sh. N.K. Bhatnagar

Accountant

Total = 1963.65 178.97 1784.68

A/R to Chanduki under PMGSY

ALWAR BHIWADI ROAD (BOT)

A/R TO AKBARPUR (RMUP)

RAC BARRACK 100MEN (PHASE-I)

RAC BARRACK 100MEN (PHASE-I&II)

PRESENT SCENARIO

FUTURE SCENARIO

PROJECT AT A GLANCE• Name of Work :- Construction of RoB at L.C. No. 111 ( Tizara

Phatak) on Alwar – Bhiwadi Road ( T.P. No. 71/3-4 B.G.)• Name of Client :- UIT, Alwar• A & F Sanction :- Vide No. P.8(1) UDH/1/2006 Dated 17th Sept.

2008 for Rs. 20.55 Crores.• Technical Sanction :- Rs. 20.55 Crores on dated 06.01.2009• St date of start :- 01-09.2008• St. date of completion :- 08.01.2010• Expected dated of completion: 31.12.2011• Funds received from client upto 4th Dec. 2009 :- Rs. 150.00

Lacs• Expenditure as on 4th Dec. 2009 :- Rs. 115.44Lacs.

( including liabilities)

Land marks :-• GAD approved by Railway :-

01.05.08• Pile foundation work is in progress• Funds Received from client :- • (a) Rs. 25.00 Lacs on 29.05.07 for

preparation of DPR• (b) Rs. 75.00 Lacs on 02.07.09• (c) Rs. 50.00 Lacs on 20.11.09

Hindrances :- • Encroachment removed by UIT on 19.06.09 but matter

is pending in the Rajasthan High Court, Jaipur for Payment of Compensation for land & Buildings.

• Shifting of utilities such as:- • (a) Water supply lines shifting are still in process• (b) Electric poles are still in process• (c) Removing of trees- Application for permission

submitted by UIT, Alwar• (d) The traffic is not diverted till date from LC No. 111• Agitation by local citizens for land and building

compensation since 16.07.09 to 22.10.09.

CFC BUILDING AT GOLA KA BAS

CFC BUILDING AT GOLA KA BAS

PROJECT AT A GLANCE• 1.Name of Work :- Construction of Common Facility Center for Murtikala

Cluster Gola ka Bas, Tehsil-Rajgarh District- Alwar (Raj.)• 2. Name of Client :- DIC, Alwar• 3. A & F Sanction :- Rs. 88.65 Lacs• 4. Technical Sanction (Revised) :- Rs. 88.65Lacs• 5. St. date of start :- 02-11-07• 6. St. date of completion :- 22-01-10 • 7. Funds received from client as on 31th Oct. 2009 :- Rs. 88.65 Lacs• 8. Expenditure as on 04TH Dec. 2009 :- Rs. 63.53 Lacs.• 9. Bottlenecks:-Revised funds received late as on 09-03-09.

– Plate form Drawing received as on 09-06-09.– Encroachment on land for Culvert and approach road has not yet been

cleared till today as on 04.12.09.

PROPOSED ROAD

WIDENING OF ALWAR WIDENING OF ALWAR ––BHIWADI BHIWADI ROAD (SH-25)KM 146/0 TO 225/0 ROAD (SH-25)KM 146/0 TO 225/0 FROM 2 LANE TO 4LANE DEVIDED FROM 2 LANE TO 4LANE DEVIDED

HIGHWAYHIGHWAYLENGTH : 79.00KM

PROJECT COST : 222.26 CroresPERIOD OF CONSTRUCTION : 18 Months PERIOD OF CONCESSION : 19 YEARS

Total Period : 20 Years 6 Mths

Toll Booth : 2 Nos. Booth

1. on KM 160

2. on KM 211