BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTED BY
1 M/s. Bharat Heavy Plates and Vessels Ltd, VIZAG,Through EME
FEB.'02 Refractory Dryout
Super Heater for IOCL Barauni
EIL, BHPV, EME
2 Indian Oil Corporation Ltd, Panipat Through Industrial Associates
MAY'02 Refractory Dryout
Main Combustion chamber of Sulpher Recovery Unit
IOCL, INDUSTRIAL ASSOCIATES
3 Indian Oil Corporation Ltd, BarauniThrough ACC
JUL' 02To
AUG' 02
Refractory Dryout
MCC, Thermal Incinerator, Waste Heat Boiler,Reactor, Sulpher Condensor
EIL, IOCL, BHPV, ACC
4 Larsen & Toubro Ltd,Powai Thru. Ciria India Ltd.
APR'03 TO
JUNE’03
Refractory Dryout
Cold Collector, R. G. Boiler, Reaction Furnace
AIR LIQUIDE, ITT, L & T, CIL
5 Oil and Natural Gas Commission, HAZIRAThru Shahani Associates.
JULY’03 Refractory Dryout
Vertical Incinerator ONGC, SHAHANI
6 Godrej, MumbaiThru Ciria India
AUG.’03 TO
SEPT’03
Refractory Dryout
Cold Collector AIR LIQUIDE, ITT, GODREJ,CIRIA
7 BPCL, Chembur, Mumbai thru Ciria India Ltd
SEP.’03 Refractory Dryout
Stack L&T, EIL, CIRIA
8 LNG Petronet, Dahej thru L & T ECC, Ahmedabad
Dec.’03 Refractory Dryout
Heat Exchanger EIL/FOSTER WHEELER-UK,LNG Petronet,TOYO ENGG. INDIA LTD, L&T ECC,
9 Godrej, MumbaiThru Ciria India Ltd.
Feb’04To
Mar’04
Refractory Dryout
Cold CollectorPhase I & II
AIR LIQUIDE, ITT, GODREJ,CIRIA
11 Larsen & Toubro Ltd, Powai, Mumbai Thru Ciria India
Mar’04 Refractory Dryout
Waste Heat Boiler (3 Nos)
L & T,CIRIA
12 Hindustan Petro Chemical Ltd, VizagThru BHPV / Sesha Chooda Thermotech Pvt. Ltd., Hyderabad
Apr’04 Refractory Dryout
43 Mtrs. Height STACK
EIL, HPCL,BHPV,SCTPL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB TYPE OF PLANT INSPECTED BY
13 Bharat Petro Chemicals Ltd, Chembur, Mumbai Thru L & T HARP, Baroda Thru Ciria India Ltd.
May’04 Refractory Dryout
MCC, LBMC & TOMC for SRU Project
EIL, BPCL,L&T,CIRIA
14 Larsen & Toubro Ltd., Mumbai Thru. Ciria India
Jan’05Nov’05Dec’05
Refractory Dryout
R. G. BoilerTotal 3 Nos
L & T,CIL
15 Godrej & Boyce, Vikhroli, Mumbai thru Ciria India Ltd.,
Jan’05 Refractory Dryout
Cold Collector AIR LIQUIDE, ITT, GODREJ,CIL
16 Technip K T, Okhla, New Delhi Thru. Ciria India
Feb.’05Oct.’05
Refractory Dryout
2 Nos Cold Collector
TECHNIP,CIL
17 Indian Oil Corporation Ltd, Vadodara, Thru. L &T- ECC Ahmedabad
April’05 Refractory Dryout
CO Duct EIL, IOCL, L&T-ECC.
18 Reliance Industries Ltd., Jamnagar (Guj.)
May’05,To
June’07
Refractory Dryout
Flare Stack Tip-06 Nos
RIL
19 Indian Oil Corporation Ltd, Mathura Thru. L& T Powai Thru. Ciria India Ltd., Noida
June’05 Refractory Dryout
Reactor IOCL,L&T,CIL
20 Indian Oil Corporation Ltd, Panipat Thru. L&T, Baroda Thru. CIL, Noida
Oct. ‘05 Nov.’05
Supervision for Refractory Dryout
2 Nos Cold Collector
L&T,CIL
21 Larsen & Toubro Ltd., Hazira, Surat Thru. CIL, Noida
Nov’05 Dec’05
Refractory Dryout
Cold Collector2 Nos
L&T,CIL
22 Indian Oil Corporation Ltd, Baroda Thru. L& T , Ciria India Ltd., Noida
Dec’05To
Feb’06
Refractory Dryout
Stack for DHTU Heater:2 Nos
EIL,IOCL, L& T, CIL
23 Larsen & Toubro Ltd., Mumbai Thru CIL, Noida
Mar.’06 June’06
Refractory Dryout
R. G. Boiler3 Nos
L&T,CIL
24 Indian Oil Corporation Ltd, Baroda Thru. Ciria India, Noida
Mar.’06 Refractory Dryout
Flue Duct (3 Nos)
EIL,IOCL,CIL.
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB TYPE OF PLANT INSPECTEDBY
25 Indian Oil Corporation Ltd, Panipat Refinery Thru. L&T, Mumbai
Mar’06 Apr.’06
Supervision for Refractory Dryout
Hot Oil Heater IOCL, L&T.
26 Indian Oil Corporation Ltd, Panipat Thru Nu-Calcutta Constn. Co. Kolkata
April’06To
June’06
Refractory Dryout
2 Nos Reaction Furnace &1 No. Hydro Generation Reactor &2 Nos Converter
IOCL Panipat,EIL,NCCC
27 Rastriya Chemical Fertilizer Ltd., Chembur Thru. Ciria India Ltd.,Noida
June’06 Refractory Dryout
Cold Collector RCF,CIL
28 Indian Oil Corporation Ltd, GuwahatiThru. Ciria India Ltd., Noida
June’06 Refractory Dryout
P. G. Boiler IOCL Guwahati,CIL
29 Indian Oil Corporation Ltd, Mathura Refinery, Mathura Thru. Ciria India Ltd
July’06 Refractory Dryout
R.G. Cooler IOCL,CIL
30 Co-en Bharat Ltd., Dist. Baroda
Aug.’06 Refractory Dryout
Heater with Stack
CBL
31 Indian Petrochemicals Ltd, Baroda Thru. Neo-Structo Constn. Co. Thru. Ciria India, Noida.
Nov.’06 to
Jan.’07
Refractory Dryout
Hot Flue Gas Duct
EIL,IPCL’NSCC,CIL
32 Indian Petrochemicals Ltd, Baroda Thru. Chaney & Co. Thru. Thermax, Pune
Dec.’06 Refractory Dryout
By-Pass Duct, Cold Flue Duct & Damper
EIL,IPCL’C&C,Thermax
33 Larsen & Toubro Ltd., Powai, Mumbai Thru. Ciria India Ltd., Noida
Jan ‘07May’07
Refractory Dryout
Waste Heat Boiler2 Nos RG Boiler3 Nos Riser Duct
L & TCiria
34 Reliance Industries Ltd., Jamnagar (Guj.) Thru. Thermax Engg. Constn. Co. Ltd. Thru. M/s. Pacific Refractories Ltd., Mumbai
Aug ’07To
Dec’07
Refractory Dryout
Stack -9 Nos RIL,TECLPRL
35 Indian Oil Corporation Ltd, Mathura Refinery ThruCiria India Ltd., Noida
July’07 Refractory Dryout
Stack 4 Nos & MCC 1 No
EIL,IOCL,CIL
36 Indian Oil Corporation Ltd, Haldia Refinery, Thru Ciria India Ltd
Oct. ’07 Refractory Dryout
P G Boiler IOCL,CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB TYPE OF PLANT INSPECTEDBY
37 Indian Oil Corporation Ltd, Panipat Thru. Technip KTI India Ltd., Noida
Oct ‘07 Nov.’07
Refractory Dryout
Stack- 2 Nos EIL,IOCL,TKTI
38 Larsen & Toubro Ltd., Mumbai Thru CIL, Noida
Nov’07 Refractory Dryout
R. G. Boiler L&T,CIL
39 Larsen & Toubro Ltd., Powai, Mumbai Thru Ciria India Ltd
Jan.’08 &
Mar.’08
Refractory Dryout
2 Nos R G Boiler L&T,CIL
40 Bharat Oman Refinery Ltd, Bina, Thru. Technip KTI India Ltd., Noida
Mar.’08To
Aug’08
Refractory Dryout
Duct/Stack for CDU/VDU Heater Package -2 Nos
EIL,BORL,TKTI
41 LNG Petronet, Dahej Thru Neo Chemoflon Pvt Ltd
June’08 Refractory Dryout
Heat Exchanger EIL,LNG,NCPL
42 Hindustan Petro Chemicals Limited, Vizag Thru Pacific Refractories Ltd., Mumbai
June’08July’08
Refractory Dryout
5 Nos Duct & Stack for SRU
EIL, HPCL, PCL
43 Larsen & Toubro Ltd, Hazira Thru M/s. Ciria India Ltd., Noida
Oct.’08 Refractory Dryout
Convection Module
L&T/CIL
44 LNG Petronet, Dahej, Thru Neo Structo Construction Ltd., Surat
Dec.’08 Refractory Dryout
Cogen Heat Exchanger - 2 Nos
EIL/TOYO/LNG/NSCL
45 Bharat Oman Refinery Ltd, Bina, thru Pacific Refractories Ltd., Mumbai
Dec.’08To
Mar’09
Refractory dryout
Stack/DUCT EIL/BORL/PCL
46 Bharat Oman Refinery Ltd, Bina, thru Rockwool Insulation, Mumbai
Dec.’08To
Mar’09
RefractoryDryout
Stack Module/ Duct Module
EIL/BORL/RI
47 Larsen & Toubro Ltd., Powai, Mumbai Thru Ciria India Ltd., Noida
Jan.’09 To
May’09
Refractory Dryout
3 Nos R G Boiler L&T/CIL
48 Bharat Petro Chemicals Ltd, Mahul, Chembur, Thru Pacific Refractories Ltd., Mumbai
Feb.’09Mar’09
Refractory Dryout
Duct & Stack for CDU & VDU Heaters – 5 stages
BPCL/PCL
49 Bharat Oman Refinery Ltd, Bina, thruNu Calcutta Contn. Co. Kolkata
Mar.’09To
July’09
Refractory dryout
Stack/Duct EIL/BORL/NCCC
50 Larsen & Toubro Ltd., Powai, Mumbai Thru Ciria India Ltd., Noida
Mar.’09To
May’09
Refractory Dryout
Cold Collector-4 stage
L&T/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB TYPE OF PLANT INSPECTEDBY
51 Mangalore Refinery, Mangalore thru Ciria India Ltd., Noida
May’09 Refractory Dryout
P G Boiler MRPL/CIL
52 Indian Oil Corporation Ltd, Baroda, thru. L & T Ltd Baroda thru. Ciria India Ltd., Noida
May’09To
July’09
Refractory Dryout
Reaction Furnace – 2 Nos, Thermal Incinerator
IOCL/EIL/L&T/CIL
53 Indian Oil Corporation Ltd, Mathura Refinery thru Ciria India Ltd., Noida
July’09 Refractory Dryout
Incinerator, MCC & Sulphur Condenser
EIL/IOCL/CIL/
54 Larsen & Toubro Ltd., Powai Mumbai thru M/s. Ciria India Ltd., Noida
July.’09 To
Dec’09
Refractory Dryout
1 No. R.G. Boiler4 Nos P G Boiler
L&T/CIL
55 Bharat Oman Refinery Ltd, Bina Refinery thru. Ciria India Ltd., Noida
Aug’09 Refractory Dryout
Process Gas Outlet Header
EIL/BORL/CIL
56 Reliance Industries Ltd., Baroda thru Shiv Engineering
Aug’09 Refractory Dryout
Flue Gas Duct RIL/SE
58 Indian Oil Corporation Ltd, Panipat thru M/s. Larsen & Toubro Ltd., Powai, Mumbai
Aug’09 Refractory Dryout
Fired Heater (Charge Heater-301 H 101)
IOCL/JACOBS/L&T
59 Indian Oil Corporation Ltd, Panipat thru M/s. Toyo Engineering Pvt Ltd., Mumbai
Aug’09 Refractory Dryout
HSD Heater (-303 H 201)
IOCL/JACOBS/TOYO
60 Chennai Petrochemicals Limited, Chennai Thru. M/s. Nu Calcutta Contn Co. Kolkata
Sept’09Dec’09
Refractory Dryout
HDS Stack, Off Take Duct & HFG Duct
CPCL/BRIDGE & ROOF/NCCC
61 Bharat Petro Chemicals Ltd, Kochi Refinery Thru. Technip K T India Ltd., Noida
Sept’09 To
Jan’10
RefractoryDryout
Duct/ Stack of NHT& CCR Heater
EIL/BPCL/TKTI
62 Bharat Petro Chemicals Ltd, Kochi Thru. Technocrats, Kochi
Oct’09 Refractory Dryout
Duct-4 Stages(1500Dia x 80 Mtrs Long)
BPCL/TC
63 Bharat Petro Chemicals Ltd, Kochi Thru. Malayil Builders Pvt Ltd., Kochi
Oct.’09To
Feb’10
Refractory Dryout
Stack for Heater EIL/IJT/BPCL/MBPL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
64 Indian Oil Corporation Ltd, Mathura thru. Thermax Ltd., Pune
Nov.’09 To
Dec’09
Refractory Dryout
HDS Heater IOCL/JACOB/THERMAX
65 Hindustan Petro Chemicals Ltd, Vizag, thru. Sri Raja Corporation, Vizag.
Nov.’09 RefractoryDryout
Stack- 2 Stage HPCL/ Bridge &Roof/COSMOS/SRC
66 HPCL Mittal Energy Ltd, Guru Govind Singh Refinery, Bhatinda, PunjabThru. Rockwool Insulation, Mumbai
Nov.’09To
Jun’10
RefractoryDryout
Stack Module for CDU/VDU Heater
GGSR/EIL/RI
67 Bharat Petro Chemicals Ltd, Kochi refinery, Through Technip KT India Ltd, Noida.
Jan’10 Refractory Dryout
5 Stage-CCR Duct of NHT Heater
BPCL/EIL/TKTI
68 HPCL Mittal Energy Ltd, Guru Gobind Singh Refinery, Bhatinda Refinery, Punjab Thru. Rockwool Insulation, Mumbai
Jan’10To
Aug’10
RefractoryDryout
25 Stage- HFG & CFG Duct/Stack for CDU/VDUHeater,3 Stage-Stack of NHT CCR Heater, 2 Stage-Stack of DHDT Heater
GGSR/EIL/RI
69 Bharat Petro Chemicals Ltd, Kochi refinery, Through Malayil Builders, Kochi
Feb’10 Refractory Dryout
4 Stage-Stack for CFBC Boiler
BPCL/MB
70 Indian Oil Corporation Ltd, Gujarat Refinery Thru Thermax Engg. Constn. Ltd., Pune
Feb’10 Refractory Dryout
Reactor Feed Heater
JACOBS/IOCL/TECL/
71 Thermax Ltd.,Savli, Thru Pacific Refractories Ltd., Mumbai
Feb’10To
July’10
Refractory Dryout
8 Nos convection Module of Reactor Feed Heater and Fractionator feed Heater,2 Nos Economiser of FGC Proj, 1 No Convection Header
EIL/TL/PRL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
72 HPCL Mittal Energy Ltd, Guru Gobind Singh Refinery, Bhatinda Refinery Thru M/s. Thermax Engg Constn. Ltd thru M/s. Pacific Refractories Ltd., Mumbai
Feb’10 To
June’10
Refractory Dryout
2 Stage-Convection Module ,1 Stage-Stack for DHDT Heater,1 Stage for HFG Duct of reactor Feed heater
EIL/TECL/PRL
73 Numaligarh Refinery Ltd., Assam Thru Ciria India Ltd., Noida
Mar’10To
May’10
Refractory Dryout
Transfer Line -10 Stages
EIL/NRL/CIL
74 Larsen & Toubro Ltd., Mumbai, Through STG Refractory Services Pvt Ltd., Mumbai
Apr’10 To
Dec’10
Refractory Dryout
1 No-P G Boiler, 7-Stage Cold Collector, 1 No Waste Heat Boiler
SRSPL/L&T
75 Bharat Petro Chemicals Ltd, Kochi thru Nu Calcutta Constn. Co. Kolkata
May’10 Refractory Dryout
SRU – 3 Stages EIL/BPCL/NCC
76 Bharat Petro Chemicals Ltd, Kochi thru Refrac Consultancy, Noida
May’10To
July’10
Refractory Dryout
Stack for SRU-4 Stage, Catalytic Converter, Incinerator, Reduction Furnace
EIL/BPCL/RC
77 Bharat Petro Chemicals Ltd, Kochi thru S K Boiler Pvt Ltd., Kochi
Jun’10To
Aug’10
Refractory Dryout
Stack and Duct-3 stage
EIL/BPCL/SKB
78 HPCL Mittal Energy Ltd, Guru Govind Singh Refinery, Bhatinda Refinery, Punjab, Thru. Ciria India Ltd, Noida
Jun’10To
Dec’10
RefractoryDryout
6 Stage-Stack for Naptha Super Heaters,10 Stage-Reactor/Stack for SRU,3 Stage Stack for Incinerator
GGSR/EIL/L&T/CIL
79 Indian Oil Corporation Ltd, Gujarat Refinery, thru Ciria India Ltd., Noida
June’10 To
July’10
RefractoryDryout
VGO DHT Heater IOCL/Heurty/UDAY/CIL
80 Bongaigaon Refinery & Petrochemicals Ltd, Assam Thru. M/s. Nu Calcutta Contn Co. Kolkata
June’10 To
July’10
RefractoryDryout
Waste Heat Boiler & Main Combustion Chamber
BRPL/EIL/IJT/NCC
81 Larsen & Toubro Ltd., Mumbai, Thru. Ciria India
July’10 To
Dec’10
Refractory Dryout
3 Nos R. G. Boiler L & T, CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
82 HPCL Mittal Energy Ltd, Guru Govind Singh Refinery, Bhatinda Refinery, PunjabThru Thermax Ltd., Pune Thru Pacific Refractories Ltd., Mumbai
July’10 To
Dec’10
RefractoryDryout
Stack/Duct-7 Stage
GGSR/EIL/TEIL/PRL
83 Larsen & Toubro Ltd., Mumbai, Thru. M/s. Kaefer Punj Lloyd
July’10 To
Nov’10
RefractoryDryout
1 No Catalic Cooler- Tube Sheet & Shell side
L&T/KPLL
84 Bongaigaon Refinery & Petrochemicals Ltd, Assam, Thru. M/s. Kaefer Punj Lloyd
Aug’10 To
Oct’10
RefractoryDryout
Thermal Incinerator package, Catalytic Converter & Hydrogen Reactor
BRPL/EIL/KPLL
85 Petrofab Ltd-Dabhasa, Gujarat, Thru. Ciria India Ltd,
Aug’10 To
Dec’10
RefractoryDryout
1 stage- Convection Section, 2 stage -HFG Duct for DHDT Heater, 6 Stage-Duct for DHDT heater.
EIL/CIL
86 Thermax Ltd, Kandla, Gujarat, through pacific Refractories, Mumbai
Aug’10 RefractoryDryout
Sulpher Combustion Chamber
Thermax/PRL
87 Thermax Ltd.,Pune, Thru Pacific Refractories Ltd., Mumbai
Sept’10 Refractory Dryout
3 Nos Economiser EIL/TL/PRL
88 HPCL Mittal Energy Ltd, Guru Govind Singh Refinery, Bhatinda Refinery, Punjab Thru. Chaney & Co, Pune
Oct’10 To
Dec’10
Refractory Dryout
10 Stage- Hot Air Duct for DCU Heater
GGSR/EIL/ACE/CHANEY
89 Bharat Petro Chemicals Ltd, Mehul, Mumbai, Through Pacific Refractories Ltd, Mumbai
Nov’10 Refractory Dryout
2 Stage – Stack BPCL/PRL
90 Reliance Industries Ltd, Jamnagar, Gujarat
Nov’10 To
Dec’10
Refractory Dryout
1 No Flare Stack & 1 No Mock-up Spool
RIL
91 Mangalore Refinery & petrochemicals Ltd, Mangalore, Through Technip KT India Ltd, Noida.
Nov’10 To
Dec’10
Refractory Dryout
26 Stages-Stack Module for PFCC Heater/DCU Heater
EIL/MRPL/TKTI
92 Indian Oil Corporation Ltd,Panipat, Through Nu Calcutta Constn. Co. Ltd, Kolkata
Nov’10 Refractory Dryout
Waste Heat Boiler and Reaction Furnace
EIL/OICL/NCCC
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
93 Oil & Natural Gas Commission Ltd, Dahej Thru M/s. Toyo Engg. India Ltd., Mumbai
Dec’10 Refractory Dryout
Hot Oil Heater ONGC/Foster Wheeler/CIL/TOYO
94 HPCL Mittal Energy Ltd, Guru Govind Singh Refinery, Bhatinda Refinery, Punjab Thru. Chaney & Co, Pune
Jan’11 To
April’11
Refractory Dryout
Hot Flue Gas Duct& Cold Flue Gas Duct for DCU Heater
GGSR/EIL/ACE/CHANEY
95 Hindustan Petroleum Corporation Ltd, Mehul, Mumbai, Through Kaefer Punj Lloyds ltd, Mumbai
Jan’11 to
April’11
Refractory Dryout
Miter Bend for Cooler
HPCL/KPLL
96 HPCL Mittal Energy Ltd,Guru Gobind Singh Refinery, Bhatinda Refinery, Punjab Thru. Pacific Refractories Ltd, Mumbai
Jan’11 To
April’11
Refractory Dryout
Outlet/Inlet Duct & Mediate Duct
GGSR/EIL/TEIL/PRL
97 HPCL Mittal Energy Ltd,Guru Gobind Singh Refinery, Bhatinda Refinery, Punjab Thru. Ciria India Ltd, Noida
Jan’11 To
June’11
Refractory Dryout
1 Stage: Incinerator5 Stage: Duct for
Waste Heat Boiler
GGSR/EIL/KSS/CIL
98 Larsen & Toubro Ltd., Mumbai, Thru. Ciria India Ltd, Noida
Feb’11 To
Dec’11
RefractoryDryout
16 Stage: Cold Collector, 1 No: PG Boiler,2Nos:Waste Heat Boiler, 1No:R.GCooler,2Nos:Methantor Boiler, 1 No: Steam Superheater
L&T/CIL
99 Technip KT India Ltd, Okhla, Thru. Ciria India Ltd, Noida
Feb’11 To
June’11
RefractoryDryout
3 Stage: Stack, 2 Stage: outlet PG header
TKTI/CIL
100 ME Energy Pvt, Ltd, Pune, Thru. Ciria India Ltd, Noida
Mar’11 RefractoryDryout
Convection Module Heurty Petrochem-Mumbai/CIL/MEPL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTEDREFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
101 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Through Technip KT India Ltd, Noida
Mar’11 To
Nov’11
RefractoryDryout
15 Stage: Hot Air Duct for DCU heater,2 Stage :Stack Module,7 Stage: CFG/HFG Duct for DCU heater.
EIL/MRPL/TKTI
102 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Ciria India Ltd, Noida
Mar’11 To
May’11
RefractoryDryout
5 Stage-Stack EIL/MRPL/L&T/CIL
103 HPCL Mittal Energy Ltd,Guru Gobind Singh Refinery, Bhatinda Refinery, Punjab
Mar’11 To
April’11
Refractory Dryout
1 Stage: VDU Heater, 2 Stage: CDU Heater
HMEL/EIL
104 Indian Oil Corporation Ltd, Digboi, AssamThru. Ciria India Ltd., Noida
April’11 Refractory Dryout
1 No: P. G. Boiler of HGU
IOCL/EIL/CIL
105 Petron Engineering Const. Ltd, Dabhasa, Baroda, Gujarat
April’11 To
Oct’11
Refractory Dryout
Hot Air Generator, 2 Stage: Duct for DCU Heater,2 Stage: Duct for Radiant Section,1 Stage: Stack,2 Stage: Convection Section of DCU Heater for IOCL Paradeep Site
PECL-Dabhasa
106 Reliance Industries Ltd, Jamnagar, Gujarat
May’11 to
Aug’11
Refractory Dryout
Flare Tip of Flare Stack
RIL
107 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Pacific Refractories Ltd, Mumbai
May’11 to
Dec’11
RefractoryDryout
1 Stage-Stack Module,7 Stage:HFG Duct& Outlet Duct with Circular Duct,2 Stage: Intermediate Duct
EIL/MRPL/TL/PRL
108 Thermax Ltd, Savli, Baroda, Thru. Pacific Refractories Ltd, Mumbai
May’11 To
June’11
RefractoryDryout
1St and 2nd Layer of Inlet Chanel
Lloyds/TL/PRL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
109 Petron Engineering Const. Ltd, Dabhasa, Baroda, Gujarat, Thru. Ciria India Ltd., Noida
June’11 To
Dec’11
Refractory Dryout
2 Stage: Hot Air Duct, 2 Stage: Flue Gas Duct,3 Stage:FCCU Stack section
PECL-Dabhasa, CIL
110 Indian Oil Corporation Ltd,Barauni Refinery, Barauni, Bihar, Thru. Ciria India Ltd., Noida
July’11 RefractoryDryout
1 No: Inlet Chamber of P.G.Boiler
IOCL/EIL/CIL
111 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Castwel Industries, Nagpur
Aug’11 to
Nov’11
RefractoryDryout
8 Stage : Stack EIL/MRPL/TL/CI
112 Indian Oil Corporation Ltd,Mathura, UP, Through NK Enterprise, Mathura
Oct’11 to
Nov’11
RefractoryDryout
RG Cooler of Hydrogen Reformer, Incinerator for SRU
EIL/IOCL/NK
113 Indian Oil Corporation Ltd,Mathura, UP, Through Refratec Consultancy & Services, Noida
Oct’11 RefractoryDryout
Riger pipe of FCCU Heater
EIL/IOCL/RCS
114 Indian Oil Corporation Ltd,Paradeep Refinery, Paradeep, Orissa, Through Petron Engineering Constn. Ltd, Mumbai
Oct’11To
Nov’11
RefractoryDryout
8 Stages Stack for VGO Heater
Uday India-Mumbai, IOCL/PECL
115 Oil and Natural Gas Corporation, Mangalore Petrochemicals Ltd, Mangalore, Karnataka, Thru. Ciria India Ltd., Noida
Nov’11 to
Dec’11
RefractoryDryout
6 Stage: Convection Section of Heater
Heurtey/ONGC/CIL
116 Hindustan Petroleum Corporation Ltd, Visakh Refinery, Visakhapatnam, Through Swaran Singh & Co, Visakhapatnam (AP)
Dec’11 RefractoryDryout
Hot & Cold Flue Gas Duct
EIL/HPCL/SSC
117 Indian Oil Corporation Ltd,Paradeep Refinery, Paradeep, Orissa, Through Petron Engineering Constn. Ltd, Mumbai
Jan’12 To
Dec’12
RefractoryDryout
29 Stage of HFG of CDU, CFG Duct of VDU & VDU take off Duct, Flue By Pass Duct, Stackfor AVU heater
Foster Wheeler, IOCL/PECL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
118 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Castwel Industries, Nagpur
Jan’12 Feb’12
RefractoryDryout
9 Stage : Stack, 1 Stage: Outlet Duct, 1 Stage: Outlet Hood,1 Stage: Inlet Duct,2 Stage: Incinerator
EIL/MRPL/TL/CI
119 R D Dynamech Infra Pvt. Ltd, Bobbili, Vizianagaram (AP), Thru. Ciria India Ltd., Noida
Jan’12 RefractoryDryout
6 Stage: Piping spool for FCC Unit
TUV/RDDL/L&T/CIL
120 Petron Engineering Const. Ltd, Dabhasa, Baroda, Gujarat, Thru. Ciria India Ltd., Noida
Jan’12 Refractory Dryout
1 Stage: FCCU Stack section
PECL-Dabhasa, CIL
121 Hindustan Petroleum Corporation Ltd, Visakh Refinery, Visakhapatnam, Through Swaran Singh & Co, Visakhapatnam (AP)
Jan’12 RefractoryDryout
4 Stage: Hot & Cold Flue Gas Duct
EIL/HPCL/SSC
122 Indian Oil Corporation Ltd,Mathura, UP, Through NK Enterprise, Mathura
Jan’12 RefractoryDryout
2 Stage Incinerator and Main Combustion Chamber for SRU
EIL/IOCL/NK
123 Reliance Industries Ltd, Jamnagar, Gujarat
Jan’12 RefractoryDryout
2 Stage: Cold Header
RIL
124 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Saarc Engineers, Baroda
Feb’12 RefractoryDryout
Water seal Drum EIL/MRPL/SE
125 R D Dynamech Infra Pvt. Ltd, Bobbili, Vizianagaram (AP), Thru. Ciria India Ltd., Noida
Feb’12To
May’12
RefractoryDryout
29 Stage: Piping spool for FCC Unit
TUV/RDDL/L&T/CIL
126 Mangalore Refinery and Petrochemicals Ltd, Mangalore, Karnataka, Thru. Castwel Industries, Nagpur
Feb-Mar’12
RefractoryDryout
5 Stage : Stack 3 Stage:,1 Stage-Incinerator & 1Stage –Convection Section
EIL/MRPL/TL/CI
127 Essar Oil Ltd., Jamnagar, Gujarat
Feb.’12 RefractoryDryout
Riser at Main FractionatorColumn
EOL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
128 Oil and Natural Gas Corporation, Mangalore Petrochemicals Ltd, Mangalore, Karnataka, Thru. Ciria India Ltd., Noida
Feb-April’12
RefractoryDryout
7 Stage: Convection Section of Heater
Heurtey/ONGC/CIL
129 Thermax Ltd, Savli, Baroda, Thru. Pacific Refractories Ltd, Mumbai
Jan’12To
Nov’12
RefractoryDryout
8 Nos Convection Section, 8 Nos Stack, 8 Nos Transition Duct
TL/PRL
130 Cape Industrial Service Pvt Ltd.,Mumbai
Mar.’12 Refractory Dryout
Transfer Line – 3 stages
CISPL
131 IOCL, Digboi Refinery, Assam Thru M/s. Refrac Consultancy Services
April’12 RefractoryDryout
P G Boiler IOCL/ RCS
132 Esteem Projects Pvt Ltd., Buddy, Himachal Pradesh thru M/s. Ciria India Ltd., Noida
April’12 Refractory Dryout
Stack & Convection Section
EPPL/CIL
133 Indian Oil Corpn. Ltd., Digboi, Assam thru M/s. Refrac Consultancy Services, Noida
April’12 Refractory Dryout
P G Boiler EIL/IOCL/RCS
134 Petron Engineering Constn. Ltd., Petrofab, Dabhasa, Baroda
April’12 RefractoryDryout
Convection Section
PECL
135 L&T Ltd, R&C, Mulund thru Ciria India Ltd., Noida
April’12 RefractoryDryout
Secondary Reformed Waste Heat Boiler
L&T/CIL
136 L&T Ltd, R&C, Mulund thru Ciria India Ltd., Noida
April’12 RefractoryDryout
Waste Heat Boiler L&T/CIL
137 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd.
May’12 RefractoryDryout
2 Stages of DCU Heater
FOSTER WHEEL/IOCL/ JACOB/HERUTEY/CIL
138 Indian Oil Corporation Ltd,Paradeep Refinery Thru M/s. Ciria India Ltd., Noida
May-Jun’12
RefractoryDryout
DHDT Heater IOCL /UDAY/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
139 L&T R&C Mulund, Mumbai thru M/s. Ciria India Ltd., Noida
Mar.’12 Refractory Dryout
Waste Heat Boiler L&T/CIL
140 Thermax Ltd, Savli, Baroda, Thru. Pacific Refractories Ltd, Mumbai
Jan’12To
Nov’12
RefractoryDryout
8 Nos Convection Section, 8 Nos Stack, 8 Nos Transition Duct
TL/PRL
141 Mangalore Refinery & Petrochemical Ltd, Mangalore thru M/s. Kaefer Punj Lloyds Ltd., Gurgaon
April’12 To
May’12
Refractory Dryout
8 stage of Catalytic Convertor Reducing Reactor,
MPRL/KPLL
142 L&T Ltd, R&C Mulund, Mumbai thru M/s. Ciria India Ltd., Noida
June’12 Refractory Dryout
Secondary Reformer Waste Heat Boiler
L&T/CIL
143 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd., Noida
June’12 RefractoryDryout
2 Stage of DHDT Heater
IOCL/CIL
144 L&T Ltd., R&C Mulund, Mumbai thru Ciria India Ltd., Noida
July’12 RefractoryDryout
2 Stage of Steam Super Heater
L&T/CIL
145 Technip K T India Ltd., Okhla thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
Stack TKTI/CIL
146 Heurtey Petrochem India Pvt Ltd., Kolkata thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
8 stages of Convection Module
HEURTEY/CIL
147 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
Fresh Feed Heater IOCL/CIL
148 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
Hot Air Duct of Fresh Feed Heater
IOCL/CIL
149 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
Stack Module of Fresh Feed Heater
IOCL/CIL
150 Indian Oil Corporation Ltd,Paradeep Refinery thru M/s. Ciria India Ltd., Noida
July’12 RefractoryDryout
VGO Heater IOCL/CIL
151 Indian Oil Corporation Ltd., Guwahati Thru M/s. Ciria India Ltd., Noida
Aug’12 RefractoryDryout
P G Boiler IOCL/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
152 Indian Oil Corporation Ltd,Paradeep thru M/s. Five Combustion System Pvt Ltd., Dabhasa, Gujarat
Sept’12 RefractoryDryout
Process Air Heater Stack
IOCL/FCSPL
153 Technip K T (I) Ltd., Okhla, Delhi thru M/s. Ciria India Ltd., Noida
Sept’12 RefractoryDryout
Convection Module TKTI/CIL
154 HPCL Mittal Energy Ltd., Bathinda thru M/s. Ciria India Ltd., Noida
Sept’12 RefractoryDryout
Incinerator and Reaction Furnace
HPCL/CIL
155 L&T, Mulund, Mumbai thru M/s. Ciria India Ltd., Noida
Sept’12 Refractory Dryout
Transition Duct, SAIPEN Waste Heat Boiler & Waste Heat Boiler
L&T/CIL
156 Bharat Oman Refinery Ltd., Bina thru M/s. Refrac Consultancy Ltd., Noida
Sept’12 Refractory Dryout
P G Boiler EIL/BORL/RCS
157 Reliance Industries Ltd., Jamnagar
Oct.’12 Refractory Dryout
Cold Header RIL
158 HPCL Mittal Energy Ltd., Bathinda thru M/s. Ciria India Ltd., Noida
Oct’12 RefractoryDryout
Reaction Furnace of SRU-B
HPCL/CIL
159 L&T Powai, Mumbai thru M/s. Ciria India Ltd., Noida
Nov’12 Refractory Dryout
2 stages of R G Boiler
L&T/CIL
160 Raj Engineering, Murbad thru M/s. Ciria India Ltd., Noida
Nov’12 Refractory Dryout
Incinerator RE/CIL
161 HPCL, Mumbai thru M/s. Toyo Engg. India Ltd, Mumbai
Nov’12 RefractoryDryout
DHT Heater HPCL/CIL/TOYO
162 Indian Synthetics Rubber Ltd, Panipat, thru M/s. Pacific Refractories Ltd., Mumbai
Nov-Dec’12
Refractory Dryout
2 stages of Primary CombustionChamber & 2 Nos Duct of Primary CombustionChamber
ISRL/PRL
163 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Jan’13 RefractoryDryout
Duct of AVU Heater
FosterWheeler/IOCL/PECL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
164 Thermax Ltd., Savli, Vadodara thru M/s. Pacific Refractories Ltd., Mumbai
Jan’13To
Mar’13
Refractory Dryout
Convection Section, Stack, Header Box
TL/PRL
165 Hindustan Petroleum Corporation Ltd., Visakhapatnam thru M/s. Refrac Consultancy & Services, Noida
Mar’13 Refractory dryout
Stack - 4 stages and Inlet & Outlet Channel - 1 stage
EIL/HPCL/FABTECH/RCS
166 M/s. Ciria India Ltd., Noida, Dryout job at POR, Vadodara
Mar-April’13
Refractory Dryout
3 Stages of Convection Section and 3 Stages of Stack/ Ducts
HeurteyPetrochem/CIL
167 Thermax Ltd., Savli, Vadodara thru M/s. Pacific Refractories Ltd., Mumbai
April’13 Refractory Dryout
Stack and Header Box
TL/PRL
168 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
April’13 Stress Relieving
4 stages of Manifold
FosterWheeler/IOCL/PECL
169 GAIL (I) Ltd., Dibiyapur, Dist. Auraiya thru M/s. Petron Engineering Contn Ltd., Mumbai
April’13 RefractoryDryout
Convection Module EIL/GAIL/PECL
170 Hindustan Petroleum Corporation Ltd., Visakhapatnam thru M/s. Refrac Consultancy & Services, Noida
May’13 Refractory Dryout
Incinerator EIL/HPCL/FABTECH/RCS
171 GAIL (I) Ltd., Dibiyapur, Dist. Auraiya thru M/s. Petron Engineering Contn Ltd., Mumbai
May’13 RefractoryDryout
2 Stages of Convection Module
GAIL/EIL/PECL
172 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
May’13 Stress Relieving
6 stages of Manifold
FosterWheeler/IOCL/PECL
173 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
June’13July’13
Refractory dryout
2 Stages NHT Stack Module
FosterWheeler/IOCL/PECL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
174 OMPL Mangalore thru M/s. L&T Ltd., Baroda
June’13, July’13Aug’13
Refractory Dryout
7 stages – Stack & Duct for Heater
TOYO/OMPL/L&T
175 Reliance Industries Ltd., Jamnagar
July’13& Sept’13
Refractory Dryout
2 Nos Cold Header RIL
176 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Aug.13 Refractory dryout
2 Nos HTD Reactor Feed Heater for VGO HDT Unit
FosterWheeler/IOCL/PECL
177 IOCL Refinery, Mathura thru M/s. N Kay Refractory Works Pvt Ltd., Mathura
Aug’13 Refractory Dryout
R G Cooler and Cold Collector
IOCL/NKRPL
178 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Aug.13 Refractory dryout
Hot Flue Gas Duct FosterWheeler/IOCL/PECL
179 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Sept.13 Refractory dryout
Boxed-up Heater for VDU Heater
FosterWheeler/IOCL/PECL
180 Hindustan Petroleum Corporation Ltd., Visakhapatnam thru M/s. Refrac Consultancy & Services, Noida
Sept’13 Refractory Dryout
Reaction Furnace EIL/HPCL/FABTECH/RCS
181 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Oct’13 Refractory dryout
CDU Heater(F-101)
FosterWheeler/IOCL/PECL
182 BPCL, Mahul, Mumbai thru M/s. Jaco Erector (P) Ltd., Mumbai
Nov-Dec’13
Refractory Dryout
2 layers of MCC of SRU
BPCL/JEPL
183 HPCL, Visakhapatnam thru M/s. Refrac Consultancy & Services, Noida
Nov’13-Jan’14
Refractory Dryout
2 Stages of Spool Pieces, 3 stages of Condensor & 3 Stage of Hydrogen Reactor
EIL/HPCL/FABTECH/RCS
184 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Dec’13 Refractory dryout
2 Stages of Cold Flue Gas Duct,2 stage of Stack of CDU Heater & 2 Stage of NHT/CCR Duct
FosterWheeler/IOCL/PECL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
185 IOCL Mathura Refinery thru M/s. N Kay Refractory Works Pvt Ltd., Mathura
Dec’13 Refractory Dryout
Riser Pipe of FCCU Unit
IOCL/NKE
186 Mangalore Refinery & Petrochemicals Ltd, Mangalore thru M/s. Pacific Refractories Ltd.,Mumbai
Dec.’13 Refractory Dryout
Chimney Tray MRPL/PRL
187 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Jan’14 Refractory dryout
CDU Heater(F-201)
FosterWheeler/IOCL/PECL
188 Reliance Industries Ltd.,Jamnagar
Jan.’14 Refractory dryout
LLP Flare Stack RIL
189 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Jan’14-Feb’14
Refractory dryout
Stack Module, HFG & CFG Duct of CCR Heater
FosterWheeler/IOCL/PECL
190 IOCL, Paradeep Refinery thru M/s. Windsor Refractories Pvt Ltd., Mumbai
Feb.’14to Sept’14
Refractory dryout
6 Nos Convertor,Reaction Furnace-1Stage, Waste Heat Boiler 3 Stage, Thermal Oxidiser-1 Stage& Decomposition Furnace-1 Stage.
FosterWheeler/IOCL/WRPL
191 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Mar.’14 Refractory Dryout
VGO Heater & APH of VGO Heater
FosterWheeler/IOCL/PECL
192 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Mar.’14 Refractory Dryout
NHT Heater FosterWheeler/IOCL/PECL
193 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Mar.’14 toMay’14
Refractory Dryout
5 Nos Stack Module of CCR Heater
FosterWheeler/IOCL/PECL
194 HPCL, Visakhapatnam thru M/s. Refrac Consultancy & Services Pvt Ltd., Noida
April’14 ToMay’14
Refractory Dryout
Reaction Furnace, Waste Heat Boiler, Incinerator
EIL/HPCL/FABTECH/RCS
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
195 Technip KT India Ltd., Okhla, DelhiFOR BPCL, MUMBAI
May’14ToJuly’14
Refractory Dryout
3 stages of Convection Section of VDU Heater
EIL/TKTI
196 M/s. Technip KT (I) Ltd., Noida At-Bilfinger Plant Equipment Pvt Ltd., Surat FOR BPCL, MUMBAI
May ’14ToOct’14
RefractoryDryout
4 Stages -Convection Section,4 Stages-Off-take Duct & 3 Stages- Stack Module of CDU Heater
EIL/TKTI
197 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
June.’14 Refractory Dryout
APH &CFG Duct of NHT Heater
FosterWheeler/IOCL/PECL
198 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
May ’14 to
June’14
RefractoryDryout
6 Stage Convection Section& 1 Stage Duct of CDU Heater
EIL/TKTI
199 Bilfinger Plant Equipment Pvt Ltd., Surat
June’14 RefractoryDryout
JNK heater BPEPL
200 L&T Ltd.,Hazira Works, Surat For Reliance Industries Ltd., Jamnagar
June’14 to
Sept’14
Refractory Dryout
36 Stages of Convection Modules
RIL/L&T
201 Reliance Industries Ltd., Jamnagar
July’14 Refractory Dryout
Main Flare Stack RIL
202 Godrej & Boyce Mfg. Co. Ltd., Vikhroli, Mumbai thru M/s. Ciria India Ltd., Noida
July’14 Refractory Dryout
Manway Plug & Nozzle for Secondary reformer
KBR/CIL
203 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
July’14 ToAug’14
RefractoryDryout
3 Stage convection Section, 2 stages of Cold Flue Gas Duct of CDU Heater
EIL/TKTI
204 Heurtey Petrochem, Pali, Raigarh thru M/s. Ciria India Ltd
July’14 ToSept’14
Refractory Dryout
2 stage of Convection Section, 11 stages for Flue Gas Duct,1 Stage for Stack, 2Stage Crude Heater & 3 Stage Charged Heater
Heurtey Petrochem/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
205 L&T Ltd., Powai, Mumbai thru M/s. Totale Global Pvt Ltd., Chennai
Aug’14 Refractory Dryout
2 stages of Transfer Line
KBR/L&T
206 Petron Engineering Ltd., (Petrofab Division),Vadodara- Jambusar Works) Ta. Padra, Vadodara
Aug’14To Oct’14
Refractory Dryout
1 stage of Convection Water Module & 1 stage of Convection Oil Module, 2 Stage Convection Blank Module, HFG-3 Stage,1 stage CFG &2 Stage of Header Box
PECL
207 Heurtey Petrochem, Jamnagar thru M/s. Ciria India Ltd., Noida
Aug’14 Refractory Dryout
3 Nos APH Support Structure and FG Duct & Convection Section
Heurtey Petrochem /CIL
208 ISGEC Hitech Zosen Ltd., Dahej, Dist Bharuch thru M/s. Ciria India Ltd.,Noida
Sept’14 Refractory Dryout
Transfer Line and Manway Cover
KBR/CIL
209 Technip KT (I) Ltd., Okhla shop, New DelhiFOR BPCL, MUMBAI
Sept’14 Refractory Dryout
Convection Module of VDU Heater
EIL/TKTI
210 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Sept’14To
Dec’14
RefractoryDryout
3 Stage CFG Duct of VDU Heater, 1 Stage CFG for CDU & VDU Heater, 3 Stage Convection Module for CDU/VDU Heater& Breaching Section for CDU & VDU
EIL/TKTI
211 BPCL, Mumbai thru M/s. Technip K T (I)Ltd., Noida
Oct’14 RefractoryDryout
Stack SM-1 EIL/BPCL/TKTI
212 M/s. Technip KT (I) Ltd., Noida at M/s Jord Engineers India Ltd., Asoj, Vadodara FOR BPCL, MUMBAI
Oct’14 ToNov’14
RefractoryDryout
4 stages of CFG Duct& 2 Stage HFG Duct for each CDU &VDU Heater i.e. Total 12 Stage
EIL/TKTI
213 Daynite Engineers & Contractors Pvt Ltd., Mahul, Mumbai thru M/s. Ciria India Ltd., Noida
Oct’14 RefractoryDryout
2 stages of Convection Section
CIL/DECPL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
214 Technip K I India Ltd., Okhla, New Delhi thru M/s. Ciria India Ltd., Noida
Nov’14 RefractoryDryout
35 Nos Cone in Temporary Furnace
TKTI/CIL
215 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd
Nov’14 Refractory Dryout
Convection Module of Zone A & Zone B, Stabilizer 2 Stages, Isomer -2 stages and Damper Aeromatic – 2 stages
Heurtey Petrochem/CIL/RIL
216 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd
Dec’14 Refractory Dryout
Isom FGD, Tolune, Tolune Damper, Isom CM, Xylene Damper, Toulene FGD, 2 stage of Xylene FGD and 2 stage of Tolune FGD
Heurtey Petrochem/CIL/RIL
217 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Dec’14 To Jan’15
RefractoryDryout
2 Stage Convection Modulefor DCU Heater
EIL/ Heurtey/ CIL
218 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Jan’15 RefractoryDryout
Hot Flue Gas Duct& Cold Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
219 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd
Jan’15 Refractory Dryout
Isom SM-1, Tolune SM-1, Tolune CFGD-17, Stabilizer CFGD
Heurtey Petrochem/CIL/RIL
220 Daynite Engineers & Contractors Pvt Ltd., Mahul Mumbai thru M/s. Ciria India Ltd., Noida
Jan-Feb’15
Refractory Dryout
2 stages of Radiant Section
DECPL/CIL
221 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Jan-Feb’15
Refractory Dryout
Off Take Duct Module of CCR Heater
FosterWheeler/IOCL/PECL
222 L&T Ltd, Hazira, Surat thru M/s. Ciria India Ltd., Noida
Feb’15 Refractory Dryout
2 stages of Convection Module
L&T/TECHNIP/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
223 Essar Heavy Engineering Ltd., Hazira thru M/s. Lizmontagens India Pvt Ltd., Mumbai
Feb’15 Refractory Dryout
Cross Header of Steam Reformer Outlet
EHEL/LIPL
224 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Feb’15 RefractoryDryout
Convection Module of DCU Heater
EIL/ Heurtey/ CIL
225 IOCL, Paradeep Refinery thru M/s. Petron Engineering Constn Ltd., Mumbai
Feb’15 Refractory Dryout
Off Take Duct Module of CCR Heater
FosterWheeler/IOCL/PECL
226 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Feb’15 RefractoryDryout
2 stages of Off take Duct and 1 stage of Cold Flue Gas Duct
EIL/ Heurtey/ CIL
227 L&T Ltd, Hazira, Surat thru M/s. Ciria India Ltd., Noida
Feb’15 Refractory Dryout
4 stages of Convection Module
L&T/CIL
228 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd
Feb’15 Refractory Dryout
- 2 Stages of HFGD of Stabilizer Heater, HFGD and CFGD of ISOM Heater, HFGD & CFGD of Toulene Heater, 3 stages -Stack support of Xylene Heater & Damper of ISOM heater.
Heurtey Petrochem/CIL/RIL
229 L&T Ltd., Powai Mumbai thru M/s. Totale Global Pvt Ltd, Chennai
Feb’15 Refractory Dryout
P G Boiler L&T/TGPL
230 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Feb’15 RefractoryDryout
Cold Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
231 Reliance Industries Ltd., Jamnagar thru M/s. Castwel Industries, Nagpur
Feb-Mar’15
RefractoryDryout
Stack RIL/THERMAX/CI
232 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Feb’15 RefractoryDryout
2 stages of Off take Duct of DCUHeater
EIL/ Heurtey/ CIL
233 L&T Ltd, Hazira, Surat thru M/s. Ciria India Ltd., Noida
Feb’15 Refractory Dryout
2 stages of Convection Module
L&T/TECHNIP/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
234 Reliance Industries Ltd., Jamnagar A/c. Lizmontagens India Pvt Ltd., Mumbai
Feb’15 RefractoryDryout
First Stage Reactor of Gasifier
RIL/LIPL
235 Furnace Fabrica (I) Ltd., Kandla,Gandhidham
Feb’15 RefractoryDryout
4 stages of Stack Pieces
RIL/FFIL
236 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Feb’15 RefractoryDryout
Cold Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
237 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Feb’15 RefractoryDryout
Convection Module of DCU Heater
EIL/ Heurtey/ CIL
238 Reliance Industries Ltd., Jamnagar thruM/s. Castwel Industries, Nagpur
Mar’15 RefractoryDryout
Stack RIL/THERMAX/CI
239 Heurtey Petrochem, POR, Dist. Vadodara thru. M/s. Phisem Consultancy Services (P) Ltd., Noida
Mar’15 Refractory Dryout
Convection Moduleand Stack
HP/RIL/CIL
240 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Mar’15 RefractoryDryout
Hot Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
241 L&T Ltd., Powai Mumbai thru M/s. Totale Global Pvt Ltd, Chennai
Mar’15 Refractory Dryout
P G Boiler L&T/TGPL
242 L&T Ltd, Hazira, Surat thru M/s. Ciria India Ltd., Noida
Mar’15 Refractory Dryout
4 stages of Convection Module
L&T/CIL
243 Reliance Industries Ltd., Jamnagar A/c. Lizmontagens India Pvt Ltd., Mumbai
Mar’15 RefractoryDryout
First Stage Reactor of Gasifier
RIL/LIPL
244 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Mar’15 RefractoryDryout
Convection Module ofDCU Heater
EIL/ Heurtey/ CIL
245 Heurtey Petrochem, POR, Dist. Vadodara thru. M/s. Phisem Consultancy Services (P) Ltd., Noida
Mar’15 Refractory Dryout
2 Stages of Flue Gas Duct
HP/RIL/CIL
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
246 Reliance Industries Ltd., Jamnagar thruM/s. Castwel Industries, Nagpur
Mar’15 RefractoryDryout
Stack RIL/THERMAX/CI
247 L&T Ltd., Powai, Mumbai thru M/s. STG Refractories Service Pvt Ltd., Mumbai
Mar’15 Refractory Dryout
R G Boiler L&T/SRSPL
248 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Mar’15 RefractoryDryout
Hot Flue Gas Duct & Cold Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
249 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd
Mar’15 Refractory Dryout
HFGD, Stack, FGD, OFD, Damper & 2 Stages of CFGD for Xylene Heater, Stack, Stack Support, Damper & STB for ISOM Heater
Heurtey Petrochem/CIL/RIL
250 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Mar’15 RefractoryDryout
Convection Module of DCU Heater
EIL/ Heurtey/ CIL
251 Reliance Industries Ltd., Jamnagar A/c. Lizmontagens India Pvt Ltd., Mumbai
Apr’15 RefractoryDryout
First Stage Reactor of Gasifier
RIL/LIPL
252 Reliance Industries Ltd., Jamnagar thruM/s. Castwel Industries, Nagpur
Apr’15 RefractoryDryout
Stack RIL/THERMAX/CI
253 Heurtey Petrochem, POR, Dist. Vadodara thru. M/s. Phisem Consultancy Services (P) Ltd., Noida
Apr’15 Refractory Dryout
3 stages of Flue Gas Duct
HP/RILCIL
254 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Apr’15 RefractoryDryout
Convection Module & Cold Flue Gas Duct of DCU Heater
EIL/ Heurtey/ CIL
255 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
Apr’15 RefractoryDryout
2 stages of Cold Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
BARODA HEAT-UP CONTROLS PVT. LTD
LIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
256 Heurtey Petrochem, Jamnagar, thru. M/s. Ciria India Ltd., Noida
Apr’15To May’15
Refractory Dryout
HFGD, FGD & 2 stages of CFGD of Stabilizer Heater & 3 stages of CFGD, HFGD & FGD of Toulene Heater
Heurtey Petrochem/CIL/RIL
257 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Apr’15 RefractoryDryout
Convection Module & Cold Flue Gas Duct of DCU Heater
EIL/ Heurtey/ CIL
258 Reliance Industries Ltd., Jamnagar A/c. Lizmontagens India Pvt Ltd., Mumbai
May’15 RefractoryDryout
First Stage Reactor of Gasifier
RIL/LIPL
259 BORL,Bina Refinery ThruM/s. Ciria India Ltd., Noida
May’15 Refractory Dryout
Train ‘A’ Convertor & Annular portion of Waste Heat Boiler Train ‘A’
EIL/BORL/CIL
260 Reliance Industries Ltd., Jamnagar thruM/s. Castwel Industries, Nagpur
May’15 RefractoryDryout
Stack RIL/THERMAX/CI
261 Technip KT (I) Ltd., CoimbatoreFOR BPCL, KOCHI
May’15 RefractoryDryout
Hot Flue Gas Duct for CDU/VDU Heater
EIL/TKTI
262 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
May’15 To Aug’15
Refractory Dryout
Stack Module for FCCU Heater, CFG Duct for VGO HDT Heater, Total10 Stage
EIL/BPCLPECL
263 Bharat Petroleum Corpn Ltd., Kochi thru M/s. TechnipIndia Ltd., Noida
May-Aug’15
RefractoryDryout
4 stages of Stack for CDU/VDU Heater
EIL/BPCL/TKTI
264 Heurtey Petrochem, POR, Baroda, thru. M/s. Ciria India Ltd., Noida
June’15 To Sept’15
RefractoryDryout
FGC Duct, ECS Module 1 & 2, Stack, Convection Module, Breaching & HFG Duct of CCR Heater; Total18 Stage
Heurtey/RIL/CIL
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
265 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
Sept’15 RefractoryDryout
Stack Module of DCU Heater; Total3 Stage
EIL/ Heurtey/ CIL
266 L&T Ltd., Mumbai thru M/s. STG Refractories Ltd., Mumbai
Sept’15 RefractoryDryout
Double Chamber Waste Heat Boiler
L&T/STGRL
267 Ciria India Ltd., Coimbatore siteFOR BPCL, KOCHI
May-Oct’15
RefractoryDryout
HFG Duct, CFG Duct, Off Take Duct, Stack & Convection Module of DCU Heater & FCCU Heater; Total15 Stage
EIL/ Heurtey/ CIL
268 L&T Ranoli, Baroda thru M/s. Refrac Consultancy & Service Pvt Ltd., Noida
Aug’15 to Oct.15
RefractoryDryout
34 Stages of Cyclones and 5stages of Cross Over Duct and 22stages of Dipleg
L&T/RCS
269 IOCL, Haldia Refinery thru M/s. Dominion Uniseven Industrial Services Pvt Ltd., Kolkata
Sept’15 to Oct’15
RefractoryDryout
7 Stages of Duct IOCL/DUISPL
270 Bilfinger Plant Equipment Pvt Ltd., Sachin, Surat
Oct’15ToNov’15
Refractory Dryout
6 Stages of Convection Module
BFEPL
271 Essar Oil Ltd., Vadinar, Jamnagar thru M/s. Ciria India Ltd., Noida
Oct’15 Refractory Dryout
Cold Flue Gas Duct and Hot Flue Gas Duct
EOL/CIL
272 Bharat Petroleum Corpn Ltd., Kochi thru M/s. TechnipIndia Ltd., Noida
Oct’15 RefractoryDryout
Stack for CDU/VDU Heater
EIL/BPCL/TKTI
273 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
Oct’15To Nov’15
RefractoryDryout
HFG Duct, CFG, Stack & Convection Module
EIL/BPCLPECL
274 Bharat Petroleum Corpn Ltd., Kochi thru Pacific Refractories Ltd., Mumbai
Oct-Nov’15
Refractory Dryout
4 Stages of Stack EIL/BPCLPRL
275 Totale Global Pvt Ltd., Coimbatore siteFOR BPCL, KOCHI
Nov’15 RefractoryDryout
3 stages of Stack of DCU Heater
EIL/ Heurtey/ TGPL
276 Panametrics Engineering Pvt Ltd., Pali, Maharashtra thru M/s. Castwel Industries, Nagpur
Nov’15 Refractory Dryout
Convection Module PEPL/CI
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
277 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
Nov’15 Refractory Dryout
CFG Duct & Stack of VGO HDT Heater
EIL/BPCLPECL
278 L&T Ltd., Ranoli, Baroda thru M/s. Refrac Consultancy Services, Noida
Nov’15 To Dec’15
Refractory Dryout
23 Stages of dust Hopper, Diplegs, Hot strokes & Plenum
L&T/RCS
279 Deepak Nitrite Ltd., Dahej,Dist. Bharuch
Dec’15 Refractory Dryout
Boiler of Furnace DNL
280 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
Dec’15 Refractory Dryout
CFG Duct & Radiant Header Box of VGO HDT Heater
EIL/BPCLPECL
281 Bharat Petroleum Corpn Ltd., Kochi thru M/s. Pacific Refractories Ltd., Navi Mumbai
Dec’15 Refractory Dryout
Stack Module for CDU/VDU Heater
EIL/BPCL
282 L&T Ltd., Powai,Mumbai thru M/s. STG Refractories Pvt Ltd., Mumbai
Dec’15 RefractoryDryout
Steam Super Heater and Spool Piece
L&T/SRPL
283 Heurtey Petrochem Pvt Ltd. POR through M/s. Ciria India Ltd.,Noida
Dec’15 Refractory Dryout
Convection Module and Stack Module
Heurtey/CIL
284 JNK Pvt Ltd.,MIDC, Ambernath (E) Thane thru M/s. Castwel Industries, Nagpur
Jan’16 RefractoryDryout
2 stages of Stack JPL/CI
285 Bharat Petroleum Corpn Ltd., Kochi thru M/s. Pacific Refractories Ltd., Navi Mumbai
Jan’16 RefractoryDryout
3 Stages of Stack Module for CDU/VDU Heater
EIL/BPCL
286 Bilfinger Plant Equipments Pvt Ltd., Sachin, Surat
Jan’16 Refractory Dryout
2 stages of Convection Modules
BPEPL
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
287 Heurtey Petrochem, POR, Baroda, thru. M/s. Ciria India Ltd., Noida
Jan’16 Refractory Dryout
Header Box of CCR Heater
Heurtey/RIL/CIL
288 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
Jan’16 Refractory Dryout
CFG Duct & HFG Duct of VGO HDT Heater
EIL/BPCLPECL
289 Bharat Petroleum Corpn Ltd., Kochi thru M/s. Pacific Refractories Ltd., Navi Mumbai
Feb’16 Refractory Dryout
3 stages of Stack Module for CDU/VDU Heater
EIL/BPCL
290 L&T Ltd., Powai,Mumbai thru M/s. STG Refractories Pvt Ltd., Mumbai
Feb’16 Refractory Dryout
3 Nos Manway Plug of Steam Super Heater
L&T/SRPL
291 L&T Ltd., Wada,Mumbai thruPhisem Consultancy Services (P) Ltd., Noida
Feb’16 Refractory Dryout
6 stages of Stack Section
EIL/L&T/PCSPL
292 Petron Engineering Constn Ltd., CoimbatoreFOR BPCL KOCHI
Feb’16 Refractory Dryout
CFG Duct & Convection Header Box of VGO HDT Heater
EIL/BPCLPECL
293 Reliance Industries Ltd., Jamnagar, Gujarat thru M/s. STG Refractories Pvt Ltd., Mumbai
Feb’16 Refractory Dryout
2 stages of First Stage of Reactor of Gasifier
RIL/SRPL
294 Heurtey Petrochem Pvt Ltd., POR, Vadodara thruM/s. Phisem Consultancy Pvt Ltd
Feb’16 Refractory Dryout
2 stages of Convection Section
HEURTEY/PCSPL
295 Zuari Agro Chemicals Ltd., Goa thru M/s. Ciria India Ltd., Noida
Feb-Mar’16
Refractory Dryout
Secondary Reformer
ZACL/CIL
296 L&T Ltd., Powai, Mumbai thru M/s. PhisemConsultancy Services Pvt Ltd., Noida
Feb-Mar’16
Refractory Dryout
R G Boiler and Spool Piece
L&T/PCSPL
297 Bharat Petroleum Corpn Ltd., Kochi thru M/s. Pacific Refractories Ltd., Navi Mumbai
Mar’16 Refractory Dryout
3 stages of Stack Module for CDU/VDU Heater
EIL/BPCL
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
298 JNK Pvt Ltd.,MIDC, Ambernath (E) Thane thru M/s. Castwel Industries, Nagpur
Mar’16 Refractory Dryout
2 stages of Stack & 1 Stage of Convection Module
JPL/CI
299 L&T Ltd., Wada,Mumbai thruPhisem Consultancy Services (P) Ltd.,Noida
Mar’16 Refractory Dryout
7 stages of Stack Section
EIL/L&T/PCSPL
300 L&T Ltd., Powai., Mumbai thru M/s. Ciria India Ltd., Noida
Mar’16 Refractory Dryout
Double Chamber R G Boiler
L&T/CIL
301 Esteem Projects Pvt. Ltd, Baddi, Himachal Pradesh
Mar’16 Refractory Dryout
HFG Duct & Convection Modules of OHFCU Furnace
EIL/EPPL
302 Heurtey Petrochem Pvt Ltd., POR, Vadodara thruM/s. Phisem Consultancy Pvt Ltd
Mar’16 Refractory Dryout
Convection Section
HEURTEY/PCSPL
303 L&T Ltd., Wada,Mumbai thruPhisem Consultancy Services (P) Ltd.,Noida
April’16 Refractory Dryout
Junction Box with HFG Duct
EIL/L&T/PCSPL
304 Indian Oil Corporation Ltd., Paradeep, Orissa thru M/s. Furnace Tech., Baroda
April’16 Refractory Dryout
Rotary Kiln, Secondary CombustionChamber & Duct
IOCL/FTE
305 Heurtey Petrochem Pvt Ltd., POR, Vadodara thruM/s. Phisem Consultancy Pvt Ltd
April’16 Refractory Dryout
3 Stages of Convection Module &2 Nos Breeching & 2 Stages of Stack for Heater
HEURTEY/PCSPL
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
306 Tata Chemicals Ltd., Babrala thru M/s. Ciria India Ltd., Noida
April’16 Refractory Dryout
Flare Stack, R G Boiler and Cold Collector
TCL/CIL
307 Deepak Fertilizer & Petrochemicals Ltd., Taloja, Raigarh thru M/s. Ciria India Ltd., Noida
April’16 Refractory Dryout
De-hydrogenation of Secondary Reformer
DFPL/CIL
308 L&T Ltd., Wada,Mumbai thruPhisem Consultancy Services (P) Ltd.,Noida
May’16 Refractory Dryout
2 Stages of HFG Duct with CFG Duct & Header Box
EIL/L&T/PCSPL
309 Gopinath Engg Co Pvt Ltd., Taloja, Mumbai thru M/s. Ciria India Ltd., Noida
May’16 Refractory Dryout
J- Bend GECPL/CIL
310 Deepak Fertilizer & Petrochemicals Ltd., Taloja, Raigarh thru M/s. Ciria India Ltd., Noida
May’16 Refractory Dryout
Secondary Reformer
DFPL/CIL
311 L&T Ltd., Ranoli, Vadodara thru M/s. Refrac Consultancy & Services Pvt Ltd., Noida
May’16 Refractory Dryout
5 stages of Riser Arm & 4 stages of Dipleg
L&T/RCSPL
312 Reliance Industries Ltd., Jamnagar thruM/s. Ciria India Ltd., Noida
May-June’16
Refractory Dryout
SRU Piping – 10 stages
RIL/CIL
313 L&T Ltd., Ranoli, Vadodara thru M/s. Refrac Consultancy & Services Pvt Ltd
June’16 Refractory Dryout
3 stages of Riser Outlet Tube
L&T/RCSPL
314 Bharat Petroleum Corporation Ltd., Mumbai thru M/s. Phisem Consultancy & Services, Noida
June’16 Refractory Dryout
Stack Bottom Portion
BPCL/PCSPL
315 Indian Oil Corporation Ltd., Barauni thru M/s. Ciria India Ltd., Noida
June’16 Refractory Dryout
Convection Module & Off Take Duct
EIL/HEURTEY PETROCHEMIOCL/CIL
BARODA HEAT-UP CONTROLS PVT. LTDLIST OF JOBS EXECUTED
REFINERY/HYDROCARBON INDUSTRIES
Sr. No
CLIENT YEAR TYPE OF JOB
TYPE OF PLANT INSPECTEDBY
316 Mangalore Refinery & Petrochemicals Ltd., Mangalore thru M/s. Lizmontagens India Pvt Ltd., Mumbai
June-July’16
Refractory Dryout
3 Nos Spool/ Duct Pieces
EIL/MRPL/LIPL
317 Oriental Manufacturers Pvt Ltd., Ranoli, Baroda thru M/s. Windsor Refractories Ltd.,Mumbai
June-July’16
Refractory Dryout
Stack Section – 2 Stages
WRL
318 Bharat Petroleum Corporation Ltd., Kochi thru M/s. Windsor Refractories Ltd
July’16ToAug’16
Refractory Dryout
Incinerator & Metallic Bellow, Reduction Furnace, Duct, Outlet Duct and 2 Nos Expansion bellow
EIL/BPCL/WRL
319 Bharat Petroleum Corporation Ltd., Kochi thru. Refrac Consultancy & Services Pvt Ltd., Noida
July’16ToAug’16
Refractory Dryout
Convertor – 5 stages
EIL/Off Shore/BPCL/RCSPL
320 Indian Oil Corporation Ltd., Barauni thru M/s. Ciria India Ltd., Noida
July’16 Refractory Dryout
Convection Section
IOCL/CIL
321 Bharat Petroleum Corporation Ltd., Kochi thru M/s. Ciria India Ltd., Noida
Aug’16ToOct’16
Refractory Dryout
Pre-Reformer – 2 stages and Field Joint of Ducts
BPCL/CIL
322 Bharat Petroleum Corporation Ltd., Kochi thru M/s. Totale Global Pvt Ltd., Chennai
Aug-Oct’16
Refractory Dryout
Main CombustionChamber – 2 stages, Chimney Tray of Fractioner Column
BPCL/TGPL
323 Reliance Industries Ltd., Jamnagar site thru Ciria India Ltd., Noida
Sept’16ToOct’16
Refractory Dryout
2 Nos OA Shift Reactor
RIL/CIL
324 Chennai Petrochemical Corporation Ltd., Chennai thru M/s. Ciria India Ltd., Noida
Sept-Oct ’16
Refractory Dryout
Complete DCU Heater comprisingof Circuit I, Circuit –II & Circuit-III
HEURTEY/JACOBCPCL/CIL