Link SDVOSB Past Performance Summaries

41

description

Sample Energy Projects

Transcript of Link SDVOSB Past Performance Summaries

Page 1: Link SDVOSB Past Performance Summaries
Page 2: Link SDVOSB Past Performance Summaries

TABLE OF CONTENTS

.................................................................................................................................................................................. 1

INTRODUCTION TO LINK RESOURCES ............................................................................................................................ 4

BIOFUEL: CELLULOSIC ETHANOL .................................................................................................................................... 5

Cellulosic Ethanol from Municipal Solid Waste ......................................................................................................... 5

BIOFUEL: BIODIESEL FROM BEEF TALLOW .................................................................................................................... 7

Australian Biodiesel Group Technology Development, Plant Startup, and North American Market Penetration ... 7

Key Issues Relevant to Transition Success ................................................................................................................ 7

Technology Optimization: ..................................................................................................................................... 7

Economic ............................................................................................................................................................... 8

Marketing .............................................................................................................................................................. 8

Operations and Maintenance ............................................................................................................................... 8

Link Scope re: Developing ISO-9000 Consistent Processes ....................................................................................... 8

Level 1 Processes per ISO-9000 Quality Manual ................................................................................................... 8

Level 2 Processes .................................................................................................................................................. 8

Level 3 Processes .................................................................................................................................................. 9

DEPARTMENT OF ENERGY: BIOFUELS/BIOMASS ......................................................................................................... 10

Summary ................................................................................................................................................................. 10

WGS ENERGY: BIOMASS POWER PLANT ..................................................................................................................... 12

Introduction ............................................................................................................................................................ 12

Why LINK Was Selected .......................................................................................................................................... 12

LINK Scope and Accomplishments .......................................................................................................................... 13

Outage Philosophy and Plan ............................................................................................................................... 13

Management of Outages .................................................................................................................................... 13

Staffing ................................................................................................................................................................ 14

Utilization of Outside Contractors ...................................................................................................................... 14

NATIONAL TRIGENERATION CHP COMPANY ............................................................................................................... 15

Introduction ............................................................................................................................................................ 15

Link’s Role ............................................................................................................................................................... 15

Project Description ............................................................................................................................................. 16

SOURCE ENERGY .......................................................................................................................................................... 18

Introduction ............................................................................................................................................................ 18

Why LINK Was Selected ...................................................................................................................................... 18

LINK Scope and Accomplishments ...................................................................................................................... 19

Page 3: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Cellulosic Ethanol

NATIONAL COMMERCE BANK ..................................................................................................................................... 22

Introduction ............................................................................................................................................................ 22

Why LINK Was Selected .......................................................................................................................................... 22

LINK Scope and Accomplishments ...................................................................................................................... 23

NORTH BRANCH GENERATING STATION ..................................................................................................................... 24

Executive Summary: ................................................................................................................................................ 24

Facility Description .................................................................................................................................................. 24

Link Scope and Accomplishments ........................................................................................................................... 25

BELLEMEADE GENERATING STATION: COGENERATION .............................................................................................. 28

Summary ................................................................................................................................................................. 28

LINK Scope: .............................................................................................................................................................. 28

Combustion Turbines/generators ....................................................................................................................... 28

Heat Recovery Steam Generators ....................................................................................................................... 28

Steam Turbine/generator and Cooling System ................................................................................................... 29

Fuel Supply .......................................................................................................................................................... 29

Water Supply ...................................................................................................................................................... 29

Budget ................................................................................................................................................................. 29

INTERNATIONAL PAPER: COGENERATION ................................................................................................................... 30

Background ............................................................................................................................................................. 30

Facility Description .................................................................................................................................................. 30

Link’s Scope ............................................................................................................................................................. 30

PORTSMOUTH GASEOUS DIFFUSION FACILITY: TRANSITION MANAGEMENT ............................................................ 32

Background ............................................................................................................................................................. 32

Link Scope ............................................................................................................................................................... 32

Link Accomplishments............................................................................................................................................. 34

TRANSITION MANAGEMENT: GENERAL ...................................................................................................................... 35

Introduction ............................................................................................................................................................ 35

Page 4: Link SDVOSB Past Performance Summaries

INTRODUCTION TO LINK RESOURCES

Founded in 1994, Link Resources, Inc. (LINK) is a Service Disabled Veteran Owned Small

Business with broad operations-related capabilities in the energy space, including O&M,

commissioning, construction management, energy consulting, and so on. LINK has more

energy-related experience than any other SDVOSB.

LINK’s core competence lies in the operation and transitioning of complex facilities. We take a

holistic perspective, integrating technical, contractual, organizational, human, and operational

matters. LINK has provided full-scope facility management services to an array of diverse

clients - - both domestic and international, with turn-key responsibility for staffing, maintenance,

interface with stakeholders, and ultimate facility performance that exceeded expectations. LINK

has also executed dozens of projects relating to energy services, transition management, and

general consulting to the broadest range of clients, often focusing on designing and

implementing transition plans or portions thereof.

LINK is staffed with a team of senior personnel all of whom had experience in operations and/or

maintenance - - across a spectrum of fuels, energy technologies and contexts:

Fuels: Coal, waste coal, natural gas, refined oils, crude oil, wood, other cellulose,

garbage, other waste fuels, nuclear;

Traditional Technologies: PC/stoker/CFB boilers, steam and gas turbines, combined-

cycle, simple-cycle, tri-generation, large chillers, condensers (including air-cooled), water

treatment, and the spectrum of associated balance-of-plant equipment;

Renewable Technologies: Biofuels (including non-food based biodiesel and bioethanol),

cellulosic ethanol, biomass combustion, biomass gasification, wind, and solar;

Applications: Steam for electricity, steam for process and heating, waste heat for steam,

electricity for cooling, waste heat for regenerative cooling, biofuel for transportation;

Clients: Commercial, industrial, utility, Federal. Domestic and Off-shore.

Page 5: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Cellulosic Ethanol

BIOFUEL: CELLULOSIC ETHANOL

Cellulosic Ethanol from Municipal Solid Waste In 1999 Link was awarded a project to

assist Masada Resource Group in the

development and planning of a large

cellulose-to-ethanol project using a

strong-acid approach on Municipal Solid

Waste feedstock. Link was also awarded

EPC oversight (including pilot projects

for particularly troublesome sub-

systems), commissioning and long-term

operations contracts for the yet-to-be-

constructed plant in Middletown, NY. The

complex plant included MSW sorting, drying, hydrolyzation and cellulose conversion, acid

recovery, fermentation, and distillation. The plant utilized dried sewage sludge converted to

steam via a fluidized bed boiler, and had several profitable byproducts such as typical MSW

rejects (e.g. aluminum), CO2, soil treatment, and green fuel. Link’s assignments during the

project period included oversight of the prime EPC contractor, Kvaerner, during engineering and

procurement; Link’s prime focus was the constructability and the operability of the processes

and systems. Link also, in joint effort with Kvaerner, developed all O&M policies and procedures

for plant equipment and systems. The first facility has not yet been constructed due to difficulties

in obtaining investors in the $400M facility.

Link’s Full-scope O&M Contract included:

Develop Accounting infrastructure Develop HazCom plan for post-Acceptance

Develop Administrative processes Procure Accounting Software

Develop Filing System for post-Acceptance Procure Human resource software

Develop list of Furnishings Procure Information management software

Develop list of tools for Operator Procure Inventory & warehousing software

Develop Operating Plan Procure Network and office software

Develop Information management infrastructure Procure Planning/scheduling software

Develop Environmental emissions documentation/reporting formats

Procure Trending, predictive maintenance, data analysis software

Develop Sustainability & Environmental Mgt program

Develop Operability and maintainability specifications

Develop specification for Vendor manuals & documentation

Develop Warranty program management plan for post-Acceptance

Page 6: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Cellulosic Ethanol

Recruiting/Interview trips & expenses

Develop manpower loading/mobilization chart

Develop Human resource infrastructure Develop Training program

Develop program/list Employee recognition programs

Develop Performance and condition monitoring plan

Procure Predictive maintenance equipment Develop Safety Program for Post-Acceptance

Develop Inventory Mgt & warehousing policy Develop Maintenance policy & programs

Develop Spare parts inventory mgt system Procure Procurement software

Procure Office furnishings and equipment for operator

Develop Engineering Program for Post-Acceptance

Develop numbering convention: Design equipment/system numbering convention for construct

Training Video library

Procure Timekeeping Software

Procure all tools

Identify and risk mitigate possible alternate scenarios, including construct delays, early completions, and need for additional personnel, with resultant impact on Link staffing and associated costs

Page 7: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Biodiesel

BIOFUEL: BIODIESEL FROM BEEF TALLOW

Australian Biodiesel Group Technology Development, Plant Startup, and

North American Market Penetration Link Resources, Inc. was engaged by Australian Biodiesel Group (ABG) to complete the startup

of their first full-scale (40 MMgpy) biodiesel plant in Australia, and then develop and transition

their organization, processes, and technology into the North American market. The scope

included development of the entire business, administrative, process, technical, and human

infrastructure. The transition and infrastructure development had to be in compliance with the

requirements of ISO-9000.

The final organization would have approximately 120 staff at distributed facilities across North

America, requiring a comprehensive yet efficient communications and reporting process that

can support quality control requirements, team-working, regulatory compliance, and advance

economies of scale. Budgets managed by Link will exceed $200 million, and annual revenues

are anticipated at $300 million.

Australian Biodiesel Group (ABG), a subsidiary of Transfield,

initially utilized Link in the startup and commissioning of its

40 mgpy continuous transesterification facility in

Queensland. Link’s contract expanded into creating the turn-

key administrative process, financial, and administrative

infrastructure for the fleet of biodiesel facilities they intended

to build in the U.S. This infrastructure included plans and

schedules for EPC/commissioning/operations, draft

specifications and contracts for EPC, all personnel and

organizational policies/procedures, all O&M policies and procedures, staffing and compensation

plans, and the Operating Plan.

Key Issues Relevant to Transition Success

Technology Optimization: Quality control when utilizing used oils animal fat feedstocks

Production quality control

Ability to quickly/smoothly switch between/blend different feedstocks (possibly including eventually palm oil)

Page 8: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Biodiesel

Economic Quality of North American business modeling

Feedstock delivery pricing and predictability

Final biodiesel production cost and sensitivity to petro-diesel prices

Marketing Clarity of target markets

Facility proximity to target markets

Operations and Maintenance Although the cost of operations and maintenance is proportionally small compare to

feedstock costs, prudent and high-quality operating practices can reduce production costs and add to income. During periods where margins get squeezed, the more efficient plants will have the competitive edge.

Quality control of product is critical to ABG reputation and to achieve top dollar for the market.

State of the art maintenance practices lead to reduced downtime and therefore increased plant production.

Link Scope re: Developing ISO-9000 Consistent Processes

Level 1 Processes per ISO-9000 Quality Manual

Link to Quality Level 3 Processes

Management Responsibility

Quality System

Internal Quality Audits

Document and Data Control

Control of Quality Records

Process Control

ID and Traceability

Inspection and Testing

Nonconforming Product

Corrective and Preventive Action

References

Level 2 Processes

Policies

Link-Generated References that will fade away

Internal Procurement Specifications

Board Governance

LLC Operating Agreement

Note: Quality Policy is a "Level 1"

Page 9: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Biodiesel

Level 3 Processes

Safety & Health (SH) Processes (Manual)

Security Processes

Human Capital (HC) Processes

Commercial Management (CM) Processes

Commissioning Processes (Manual) 01 91 00

Standard Operating Processes (SOP)

Training Processes

Index of Archived Processes

Quality Program Processes (QPPs)

Work Mgt (WM) Processes

Material Capital (MC) Processes

Sustainability (SU) Processes

Information & Communications (IC) Processes

Page 10: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 DOE Biofuel/Biomass

DEPARTMENT OF ENERGY: BIOFUELS/BIOMASS

Summary Link Resources, Inc. has been engaged by the Department of

Energy and the Department of Agriculture in several projects to

assist in the evaluation of solicitations from biofuel and/or

biomass technology companies interested in receiving Federal

grants or loans for the Demonstration pilot and demonstration

plants using technologies that could be commercially viable in

the short term. During the assignments Link provided

DOE/DOA with perspectives using a broad spectrum of

technologies and different contexts including:

MSW (cellulosic portion) to ethanol processes using strong acids (see separate project description)

Ethanol Generation from Waste Sugars using immobilized microbe bioreactor technology: including waste water treatment and recycling of waste carbon sources.

Conversion of Agricultural residue (corn stover and other lignocellulose biomass) to Ethanol and Ethyl Acrylate: included pretreatment of feedstock into pellets and subsequent hydrolyzation of cellulosic and hemi-cellulosic fractions, as well as other subsequent and other chemical treatments

Production of Cellulosic Ethanol from Corn Stover: using yeast technology for the fermentation of both five and six carbon sugars while simultaneously co-produces high value co-products such as the cellulases, hemi-cellulases, or other important industrial enzymes.

Fuel Ethanol from Barley: producing parasitic electricity and thermal energy from available biomass (waste wood and other plant based products); recovering CO2 from the ethanol fermentation process to produce commercial grade liquid CO2 for the production of dry ice and to use in the on-site greenhouses. Utilizing waste process heat, available water, available land and CO2 in on-site greenhouses.

Cellulose to Ethanol Conversion using Enzymes: implementation of 2nd generation technologies to improve the overall performance of existing cellulose to ethanol conversion using enzymes. Feedstock to be further investigated included bagasse, energy cane, high biomass, sorghum, wood, switchgrass, corn stover, and miscanthus.

“Drop-In” Bio-refineries: improving harvest operations and maximizing the ethanol yield/acre of fermentation of sweet sorghum, and establishing small

Page 11: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 DOE Biofuel/Biomass

commercially viable “drop in place” bio-refineries, combined with a decentralized network of fueling stations where the ethanol would be blended “at the pump”.

Re-purposing of a Corn-based Ethanol Facilities: redesigning corn-based ethanol facilities to use alternative feedstocks.

Biomass gasification: for steam generation.

Biomass combustion: utilizing a variety of technologies including stationary and moving stoker grates, and fluidized beds.

Link’s scope included comprehensive reviews of financial, technical,

and commercialization plans within proposals. Reviews were followed

by panel discussions with cross-disciplined panelists, oral

summaries, written summaries and final formal evaluations.

Page 12: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 WGS Energy- Biomass

WGS ENERGY: BIOMASS POWER PLANT

Introduction WGS Energy builds and acquires green/sustainable energy generation and energy

transformation facilities. A representative project is the 65MW (gross) electric production facility

in Twiggs County Georgia that gasifies biomass to develop steam for direct conversion to

electricity and for heating and drying of incoming feedstock. LINK was engaged after a

competitive bidding process to select the multi-year Operator, wherein LINK offered a more

comprehensive and yet more detailed and credible than a much larger rival.

Why LINK Was Selected Since biomass plants have a high degree of complexity, one of WGS concerns was having an

Operator who had direct experience and also the predisposition to 1) customize the plant for the

specific needs of the client, and 2) focus on maintenance and outage management. The

technology and equipment complexities include chipping the incoming organic waste, drying,

storing, conveying, feeding, gasification, gas cleaning, combustion, waste heat-to-steam

generation, large electric turbine-generators, switchyard and interconnection with grid, ash

handling and disposal, heavy truck traffic in/out leading to safety, security, and local neighbor

concerns, and so forth

One particular aspect of LINK’s “Conduct of Maintenance” approach that impressed WGS was

our planning for Short Notice Outages (SNOs). With the amount of equipment, the complexity of

the processes, and the overall lack of redundancy in design, there is no doubt that equipment

will fail; the issue is really how quickly the Operator can get it back on line at full capacity. LINK

developed a protocol for SNOs that involves:

1. A basic Reliability Centered Maintenance (RCM) approach that utilizes the Operator’s

experience and information from equipment vendors to identify points-of-likely-failure.

2. A review of spare parts requirements to ensure replacement parts are available to make

associated repairs.

3. Storing associated sets of spare parts so that they can be immediately retrieved “as a

package” if/when a pre-identified SNO occurs.

4. Identification and pre-location of tools necessary to make specific SNO repairs.

5. Preparation (and sometime even rehearsal) of the maintenance team to optimize their

mobilization and task-performance to complete the repair in the minimum time.

Page 13: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 WGS Energy- Biomass

6. Iteration on the above as lessons are learned.

LINK Scope and Accomplishments In addition to the broad scope associated with a multi-year O&M contract (some elements of

which are addressed elsewhere in this document), the following focuses on Outage Philosophy

and Planning which was particularly important on the Twiggs County project.

Outage Philosophy and Plan Plant outages are scheduled in the Spring and Fall, to avoid peak seasons and any

demonstration periods established by Georgia Power. The philosophy of the Spring

outage is characterized by:

complete maintenance essential to operate until Fall

thoroughly inspect systems in order to plan for the Fall inspection

test and challenge the plant planning, scheduling, contracting, parts ordering, and outage management skills so that an improvement plan can be accomplished prior to Fall outage

execute the predictive maintenance program that includes boiler and turbine predictions based on inspection & test criteria.

The philosophy of the Fall outage is:

complete all maintenance necessary to operate for 18 months without another outage

double-check inspection to ensure spring outage inspection process was adequate

again test & challenge the outage management system & try to improve

prepare for winter (i.e. plant winterization)

Management of Outages The formality of the maintenance planning and scheduled activities warrants attention.

For example, planning for major scheduled outages begin 18 months in advance, with

very clear accountabilities established. Major vendors are notified and invited to

participate in the planning exercise, and requested to justify their cost-effectiveness on

the outage. Depending on the specific skills of the management team, planning and

scheduling software may be appropriate for outages.

Pending maintenance for equipment that can only be accomplished during shutdowns

are closely managed and preparations made such that the facility can effectively utilize

any unscheduled outage to complete such maintenance. Additionally, the maintenance

Page 14: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 WGS Energy- Biomass

department continually plans routine maintenance, inspections, and predictive

maintenance that can only be performed when equipment is off-line, so that it will be

performed during periods when the plant is dispatched off-line

Staffing Major OEM vendors are urged to provide maximum input regarding their experiences

and lessons learned in their recent outage support roles. Refractory deterioration

remains a major concern OEMs are closely consulted to ensure cost-effective

management of the high cost and high impact problems. The entire staff is utilized to

maximum potential in order to reduce the requirements for outside contractors and

temporary employees.

Utilization of Outside Contractors Reliance on contractors can readily become excessive. In particular, mechanical

contractors, welding, and cleaning/vacuum services can often be reduced given the

capabilities of the work force; and the money that is saved can be better spent the

capital purchase a vacuum/cleaning truck.

LINK’s philosophy on the use on contractors is clear. They are necessary only when: 1)

personnel on site have no additional capacity to perform the function, and failure to

complete the work will or could likely result in expenditures or loss of revenues in excess

of the cost of the contractor; or 2) when the work to be done in accordance with the

Operating Plan requires skills, tools, or licenses not held by the facility.

LINK’s contractor selection process/criteria includes a solid program for competitive bidding,

closely assessing experience, resources, price, responsiveness, and risk-sharing

concepts. Value is considered more important than low price. Disadvantaged

businesses are seriously considered for all subcontracted work.

LINK believes that general services agreements can frequently be a cost-saving mechanism

for frequently utilized services and such contracts will be pursued for construction,

welding, civil work, etc. The client’s resources are considered at all stages of the

purchasing and contracting process to ensure that the client’s resources are utilized if

cost effective and appropriate.

Page 15: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

Aerial View of KKMC

NATIONAL TRIGENERATION CHP COMPANY

Introduction NTCC is a leading energy services company in the Middle East, delivering reliable and

environment-friendly cooling, heating, and power (CHP) to commercial, industrial and

governmental organizations. NTCC is at the forefront of the Middle East in acquiring inefficient

energy facilities and improving the performance by adding cogeneration and trigeneration

solutions. NTCC also builds energy efficient facilities at greenfield and brownfield sites. They

offer build-own-transfer (BOT), as well as build-own-operate (BOO) solutions in power,

cooling/steam, and water desalination.

Although NTCC is a relatively young company, NTCC is now either managing or in the process

of assuming control of 100,000 tons of cooling, 80 MW of electrical generation, and 59,000 lb/hr

steam. LINK has been a partner with NTCC since 2008 since NTCC recognized they had

neither the O&M skillsets nor infrastructure to operate and maintain their facilities.

Link’s Role LINK was engaged to develop NTCC’s entire organizational, process, and administrative infrastructure for its O&M division while it operated and maintained current and imminent energy facilities. LINK is included as a “partner on NTCC’s web page http://www.ntcc.com.sa/index.php?option=com_content&view=category&id=69&Itemid=91&lang=en).

NTCC’s traditional energy generation/transformation technologies utilized at facilities:

Electric chillers

Regenerative chillers (using waste heat input)

Steam Boilers

Power generation

Plus balance of plant to include of course cooling

towers, condensers, piping, valves, motors,

pumps, motor control centers, transformers,

programmable logic controllers (PLCs),

distributed control systems (DCS including Mark V, WDPF &

Emerson Delta V), compressed air, water purification, etc.

Page 16: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

With the award of the King Khalid Military City contract, additional larger frame technologies

include a (CHP) plant consisting of 200MW of Westinghouse 251B Gas Turbine electricity

generation, eight 6,500 ton chillers, GE/Woodward DCS controls, 10 CW pumps, and a

distributed CW/HW pipe feed and return system to over 80 buildings on the 5000-man KKMC

military city. Gas Turbines are being upgraded to combined cycle with Heat Recovery Steam

Generators (HRSGs).

Project Description As part of LINK’s broad scope to operate and maintain existing and future facilities, it was necessary for Link to establish a standard corporate-wide O&M program; and operated and maintained existing and newly acquired/built CHP energy facilities. Total scope included:

Identified, recruited and hired operators, technicians, and manual labor

Developed and executed transition plans that optimized the assumption of O&M responsibilities of existing facilities

Developed and implemented Operating Plans

Provided management and supervision as necessary

Provided recruiting, policies/procedures;

Developed and implemented QC programs

Developed and implemented safety training programs

Developed and implemented commissioning plans and services

Prepared O&M budgets for existing plants as well as in proposals for new plants

Developed transition budgets

Designed and set-up Computerized Maintenance Management Systems (CMMS)

Assisted the client in the preparation of proposals for new projects

Working with Performance Improvements (PI) Ltd, designed and installed PI control system remote monitoring system that interfaced with control systems including Mark V, WPDF, and Emerson Delta V

Managed environmental compliance

Assumed direct interface with on-site clients which was essential to the customer relationship management (CRM)

Performed numerous other tasks LINK built a world class O&M organization and infrastructure that became an effective part of the NTCC business model. NTCC energy facilities have high operational demands; in other words, NTCC clients expect cooling, heating, and power 24/7/365 and failure to provide such services is not an option. In the exacting environment, LINK’s O&M services exceeded expectations by delivering 24/7 CHP even during severe circumstances (e.g. weather), that otherwise could have been claimed as force majeure.

Page 17: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

Page 18: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

SOURCE ENERGY

Introduction In partnership with its customers, Source Energy (SE) finances, develops, builds, operates and

maintains advanced power technologies that serve the long-term heating, cooling, and power

requirements of commerce, industry, and government. Backed by significant financial resources

and an extensive network of influential relationships, Source Energy takes full responsibility for

ensuring customers efficient, sustainable and reliable district energy and district cooling

services, tailored to custom needs, from a single outsourced provider.

Source Energy provides cooling, heating and power solutions on a Build-Own-Operate-Transfer

(BOOT) basis. Source Energy recently won a Saudi Arabian Riyal (SAR)1 BILLION Saudi

Arabian contract from for providing the 2nd Industrial City in Jeddah with central cooling &

power services. It will supply the industrial city with about cooling and electrical power. The

district cooling network will be operated by Source Energy for 30 years. LINK is under contract

to operate and maintain projects engaged by Source Energy.

Source Energy provides cooling, heating and power solutions on a Build-Operate-Transfer basis. An example of one large project includes:

Jeddah Industrial City 2: A SAR 1 billion contract from MODON provides the 2nd Industrial City in Jeddah with a central CHP facility. Source Energy supplies the City with approximately 80,000 tons of cooling, and produces over 50 MW of electrical power.

Smaller projects include:

Al Anoud Tower in Riyadh

King Road Tower CHP Plant in Jeddah,

Al Khobar Lakes Power Plant in Al Khobar.

Each of which has either electric chillers, and/or regenerative

chillers, and/or steam boilers, and/or power generation (e.g.

diesels), plus extensive balance of plant, water treatment, and large cooling towers.

Why LINK Was Selected LINK was engaged for some of the same reasons elaborated in the NTCC section above. The

selection was also heavily influenced by LINK’s operating philosophy and culture, since SE was

Page 19: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

convinced that the following critical components must form the basis of any contractual

operator-client relationship for a multi-year engagement:

1. a willingness to “partner” and work in an honest, trusting environment to achieve mutual

goals

2. flexibility, since over the long term it is not possible to consider all the combinations of

events that may occur; agreements don’t govern good relationships as much as good

relationships govern the agreements, and

3. sufficient depth to provide necessary scope: for example, there has been a general

tendency for many companies to undervalue the administrative, human resource, and

security skills that are required to ensure compliance with law as well as maintain a

workforce that can provide the exceptional levels of service

Source Energy was also impressed with LINK’s focus on developing comprehensive Operating

Plans for existing and new CHP projects, which would comprehensively address operating

formality, maintenance skillsets, compliance with policy and procedure, training,

planning/scheduling/budgeting, safety, and response to emergency/non-routine situations.

LINK's initial assessment of existing SE facilities led to the conclusion that, in order to attain the

largest short-term improvement in plant reliability, the first year's focus of investment should be

on safety training, and programmatic maintenance.

LINK Scope and Accomplishments LINK was initially hired to provide elements of SE’s operational infrastructure and scope

expanded into LINK’s provision of complete O&M services. Since then it has managed the

development of the infrastructure and functionality of the entire Operations Division of Source

Energy.

With respect to safety, the focus that LINK stressed to SE centered around two equally

important factors: 1) an emotional investment in safety, and 2) the the lack of a safe work

environment is an unaffordable cost. Thus LINK developed a Safety Program encompassing:

1. a monthly newsletter on safety issues and/or lessons learned 2. safety training for all employees during first 30 days 3. a required safety review course for each new employee and each employee annually 4. periodic safety drills for each shift, such as fire drills, at least quarterly 5. management and supervisory safety goals with bonus and/or salary impact 6. a modified work recovery program to return injured employees to work sooner.

In the safety training arena, LINK developed:

Training Requirements and Guidelines

Page 20: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

Safety Program Self-Evaluation

Safety Inspection Checklists

Record-keeping Handbook

Safety Presentation for Classroom Training

Safety Procedures (e.g. hotwork, electrical, lockout/tagout, confined space entry, etc.)

LINK’s maintenance program upgrade consisted of a focus on optimization-centered

maintenance. In other words, LINK utilized the concepts of reliability centered maintenance

where there are critical components that are likely to affect availability or safety. However, not

all aspects of RCM were used due to the fact that it is seldom cost-effective to perform the

degree of analysis often required in a true RCM program. The optimization-centered program

also integrated equipment history, event recording, trending, and root cause analysis into the

program to improve performance. The real key to the successful maintenance program,

however, was the basic due diligence from managers and supervisors, rather than the level of

sophistication of the program.

LINK’s goal for the Source Energy plants was to be the most reliable CHP producer in its

category in a safe and socially responsible manner. LINK achieved these objectives by setting

short and long term goals for each facility in the following areas:

improved profitability,

enhanced reliability,

low cost production,

environmental and safety consciousness,

cooperative working relationships with each client/steam host,

a rewarding work environment,

and responsible corporate citizenship.

At King Road Tower in Jeddah, LINK was asked to come in and rescue a

failing construction project. LINK re-organized the construction staff and

refined the plan leading to the accomplishment of a 1 August 2011

construction milestone, thus avoiding a multimillion dollar construction penalty.

LINK prepared budgets, managed construction crews, provided liaison service

with main building contractor, hired new contractors and staff, and managed

the procurement of all supplies including interfacing with delinquent suppliers

to force delivery completion.

At Al Anoud Tower, LINK provided design input along with equipment and supply

recommendations during construction process and managed the facility into commercial

operations. LINK organized and recruited new facility staff to include new equipment training at

Broad in China and with Emerson in Riyadh.

Page 21: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Source Energy-CHP

At Al Khobar Lakes power project, LINK took over control of the construction process at the

25% stage of completion. LINK recruited and deployed staff to the site including managing all

HR and admin tasks to support the staff living requirements in Al Khobar. LINK managed all

phases of the project, taking it to commercial operation. LINK connected this sites’ DCS

(Emerson Delta V) into its remote control and monitoring capabilities for Source Energy.

LINK’s administrative scope included:

operating procedures,

training,

safety,

environmental compliance,

transition management,

recruiting,

proposal preparation,

budgeting,

construction management,

commissioning,

warehousing protocols,

preventive & predictive maintenance, and

major unplanned and planned outage management.

Page 22: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 National Commerce Bank-CHP

NATIONAL COMMERCE BANK

Introduction The National Commerce Bank is the largest bank in the Kingdom of

Saudi Arabia. NCB has multiple facilities including bank buildings,

administrative buildings, and a large IT center where proper cooling

and/or heating is critical to servicing the bank’s customers,

maintaining continuity of bank operations, and indeed security. Most

of the NCB complex has its own CHP facility yet reliability was poor,

and since the local electric utility grid was unreliable it was essential

for NCB to improve the capacity and the reliability of its energy

facilities.

Why LINK Was Selected LINK was selected for some of the same reasons expressed elsewhere in this document - - for

the sake of brevity not repeated in this section. Yet after LINK made a preliminary assessment

that NCB’s reliability and capacity concerns were primarily driven by poor maintenance, LINK

developed a Maintenance Rejuvenation Approach that impressed NCB:

immediate "conduct of maintenance" training in order to address maintenance philosophy and motivational issues, and communicate that each discipline shares a role in maintenance, followed by technical/skills training in deficient areas for maintenance personnel

realignment of preventive & routine maintenance responsibilities for roving operators

endorsement of reliability centered maintenance (RCM) where there are critical components that are likely to affect availability or safety

transition equipment history, event recording, trending, and root cause analysis to improve performance

management training to identify accountabilities for preventive and predictive maintenance at the shift supervisors, operations manager, and maintenance manager levels

evolutionary execution of a cost-effective predictive maintenance program to include (in order of priority) vibration analysis on critical components, lubricant analysis, thermographic analysis, motor circuit testing, on-line performance monitoring, ultrasonic detection, and gas analysis

progress toward a maintenance mix goal of 45%/35%/20% for corrective/ preventive/predictive maintenance, respectively

evaluation of the functionality of the CMMS system, including unused capabilities

increased formality of the maintenance planning and scheduling activities

invitation to major vendors to participate in the maintenance planning.

Page 23: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 National Commerce Bank-CHP

LINK Scope and Accomplishments LINK provided operations and maintenance services for the Saudi National Commercial Bank in

both Riyadh and Jeddah. Through initial audits, LINK established the need for and executed

multiple improvement projects:

1. Efficiency Project…results were a reduction in 2009 of 241,777 kwh for a savings of

$25,000 with a reduction of 1,370,214 kg /yr less Green House Gas emissions.

2. Reliability Project - NCB IT Center and Regional Office- 24 months without a service

interruption. Maintenance improvements resulted in the elimination of a planned

equipment replacement project costing in excess of $3 million.

3. Housekeeping Project - Facilities cleaned, organized, and maintained to a higher

standard. All facility walls and floors cleaned and re-painted. Tools, parts, and supplies

were categorized and organized.

4. Safety Project – OSHA based Safety procedures were written and tailored for each sites’

equipment and hazards. Safety Showers, eyewash stations, first aid kits, fall protection,

PPE, Fire protection upgrades were implemented and a safety culture was cultivated

thru training and program implementation.

5. Remote Monitoring Project - SECURE Offsite Control Performance & Diagnostic Center

implemented in Riyadh to manage both facilities. Night Shift was eliminated at all NCB

Facilities upon project completion.

6. Client Management Project – A re-focus on client relationship management resulted in a

successful PR campaign centered around 2 years of project upgrades, customer

satisfaction, and facility performance improvements which culminated with the facilities

considered to be the best maintained at NCB. During the 2011 Jeddah floods…LINK’s

facility staff was pivotal in assisting NCB manage the devastation wrought on their

facilities, even though this was outside of LINK’s scope of work.

7. Staff Training Project – Vendor training, Safety Training, Environmental Training and On

the Job Training culminated in a $600,000 savings in 12 months. All personnel were re-

trained to be a multi-skilled work force resulting in a 75% drop in contract labor.

8. CMMS Project – LINK implemented 2 CMMS systems. A temporary CMMS within 30

days while a managing the implementation of a million dollar Oracle suite. Electronic

rounds were integrated to give staff technological flexibility in data and maintenance

record keeping. Digital Thumbprint Scanners were also implemented to log & track

employees work hours.

Page 24: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 North Branch-Electric Plant

NORTH BRANCH GENERATING STATION

Executive Summary: Dominion Virginia Power awarded LINK this multi-year full-scope

operations and maintenance agreement after a competitive

solicitation that included Bechtel, Babcock & Wilcox, and Stone &

Webster (subsidiary of Shaw Group) among others. North Branch

was an existing 80 MW waste-coal fired electric generation

station utilizing two circulating fluidized boilers (395,000 lb/hr

steam each), a single turbine generator, an air-cooled

condenser, and a staff of originally sixty-five (65). LINK

dramatically cut costs from $35/mwhr to $25/mwhr - - reducing

staff to 46.

Facility Description

Electrical generating equipment consist of two 1770 psi, 395,000 lb/hr, natural circulation,

circulating fluidized bed (CFB) boilers (coal fired) and one ABB VAX type steam turbine

generator rated at 93,500 KW. The station can generate approximately eighty megawatts net

power. The boiler and steam turbine is controlled by a Bailey INFI 90 distributed control system.

Station cold start-up power is supplied through a 69000/4160 volt, 6,250 KVA step-down

transformer. After the steam turbine generator is placed on line, station power is supplied

through two 13800/4160 volt, 10000 KVA step-down transformers feeding two separate 4160

volt bus bars. Power is delivered to the utility grid through a 13,800/115,000 volt step-up

transformer.

Steam exiting from the steam turbine passes through horizontal ductwork to an air-cooled

condenser. Hogging and a holding ejector system removes non-condensables from the

condenser. The condensate drains by gravity to a collection hotwell tank. A 200 HP vertical

turbine pump takes suction on the hotwell tank and pumps the condensate through two low

pressure feedwater heaters to the deaerating/storage tank. A 1500 HP electric driven feedwater

pump takes suction on the deaerating/storage tank and pumps the feedwater through two high

pressure feedwater heaters to the boilers. Auxiliary cooling water for pumps, coolers, seals, and

bearings is supplied from a 2 cell cooling tower located on the roof.

Waste coal (gob) burned in the boilers is delivered to the station by truck and is purchased from

Buffalo Coal Company and Mettiki Company. The gob is sized in a Pennsylvania Crusher

Page 25: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 North Branch-Electric Plant

Hammermill and is stored in one of four storage bins (800 ton capacity each). Normally, three

days worth of coal is kept on premises.

The circulating fluidized bed (CFB) boilers operate on the principle that limestone fed into the

combustion chamber will reduce sulfur dioxide (SO2) emissions to the atmosphere. The

limestone is delivered to the station by truck, sized in a Williams DFM crusher and stored in a

1250 ton capacity storage tank. The crushed limestone is fed into the boiler’s combustion

chamber and burned with the coal. Two cyclones circulate the burned coal and limestone in the

combustion chamber. Propane is used as start-up fuel for the boilers. It is stored in six 30,000

gallon capacity storage tanks. Each boiler requires 94,200 SCFM of propane, feeding four

start-up burners. The waste-coal is very poor quality (as low as 5000 btu/lb, 60% ash, and 35%

moisture) and added considerable complexities to the conveyance (1 mile), hogging, storage,

and feeding, and combustion.

Station service and control air is supplied by three direct driven rotary screw air compressors.

Each compressor can deliver 411 SCFM of air at a pressure of 125 psi.

Link Scope and Accomplishments

Link had turn-key accountability for all staff, operations, maintenance, security, procurement,

accounting, reporting, environmental and regulatory compliance, and interface with dispatch.

Link successfully planned and managed a comprehensive Transition Plan to assume

accountability for the people, processes, and equipment from an incumbent O&M contractor, as

well as to rejuvenate the performance of the below-par facility. The following charts are

representative of the performance improvement:

Page 26: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 North Branch-Electric Plant

Page 27: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 North Branch-Electric Plant

Purchase Order BKF 496399

Page 28: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Bellemeade Generation Plant: Cogeneration

BELLEMEADE GENERATING STATION: COGENERATION

Summary Link had the full-scope, turnkey contract to operate and

maintain the Bellemeade Facility was a 225 MW (net) /

250 MW (gross) electric gas/oil fired cogeneration

system. The facility consisted of turbine systems with

heat recovery steam generators that produced steam for

steam turbines as well as for cogeneration purposes. The

offsite steam host was a cardboard recycling facility that

required a continuous high-quality and predictable 150#

steam supply, and included an extensive array steam

piping, condensate return, and condensing systems. Twin

gas/oil fired package boilers were capable of supplying

steam needs if the larger plant was shut down.

Major equipment at the facility consists of two (2) combustion turbines/generators, two (2) heat recovery steam generators with integrated Selective Catalytic Reduction (SCR) for NOx control, one (1) steam turbine/generator, mechanical draft cooling tower, demineralizer, auxiliary boiler, and various support equipment.

LINK Scope:

Combustion Turbines/generators The combustion turbines are two ABB Model GT-11 N machines each driving a Brush Electric

generator normally rated at 88 MW each. Each machine has on line fuel switching capabilities

between distillate oil and natural gas.

Heat Recovery Steam Generators

The HRSG’s consist of two triple pressure ENTEC heat recovery boilers capable of 475,000 pounds per hour of steam flow. Each HRSG is equipped with duct burners (natural gas only) to provide supplemental heat and a Hiatachi Selective Catalytic Reduction (SCR) system for NOx control. The SCR catalyst base material is titanium oxide with a substrate material of stainless steel 430. The SCR system also utilizes a 18,000 gallon anhydrous ammonia feed system.

Page 29: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Bellemeade Generation Plant: Cogeneration

Steam Turbine/generator and Cooling System The HRSGs provide steam to drive one ABB Vax model condensing extraction steam turbine nominally rated at 75 MW. This is the same model turbine that is in use at the North Branch and Morgantown projects. The cooling system is a closed loop utilizing a Yuba horizontal in-line condenser and a Thermal Dynamic Towers three cell cooling tower with three Ingersoll-Rand 400 horsepower, 200 gpm circulating pumps.

Fuel Supply The natural gas system consists of one 10 inch and one 4 inch gas main, owned by the City of Richmond, at 300 psi gas pressure to the site. There are also two Ingersoll-Rand 600 horsepower gas compressors owned by the project that have never been used. The distillate oil system includes an on-site 50,000 gallon storage tank which provides approximately one day of fuel supply to both units. The day tank is supplied through a nearby oil storage tank farm facility (several storage tanks are leased from the Little Oil Company) utilizing a pipeline and fuel forwarding facility.

Water Supply All water is supplied from the City of Richmond water supply system and is stored in a 1,000,000 gallon storage tank. Process makeup water is purified through an on-site Glegg deminer-alization system and stored in a 500,000 gallon storage tank. All waste water from the site is discharged, after neutralization treatment and oil separation, into the City of Richmond’s waste water treatment system.

Budget Link’s budget requirements to operate this facility at or near requisite capacity factors were $4,293,515 per year for normal operation and maintenance.

Purchase Order BKF 496475

Page 30: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 International Paper: Cogeneration

INTERNATIONAL PAPER: COGENERATION

Background International Paper operates substantial power generation facilities at multiple mill locations in

Eastover, SC, Franklin, VA, Prattville AL, and Savannah, GA. Each was originally developed as

an integral part of pulp and paper operations, employing a reasonably balanced, efficient

cogeneration cycle producing electricity and steam for the plant. Wood waste is used as a fuel

to the extent available. Black liquor recovery boilers are utilized for chemical recovery as well

as steam production. Environmental equipment has been installed consistent with the

increasing demands for clean air and water discharges. Some locations such as Franklin have

expanded the power facility off-site, and furthermore have introduced natural gas as a non-

traditional fuel source.

After considerable delays in the construction and startup of the new gas/oil fired cogeneration

plant at the Franklin mill, Link was engaged to get the commissioning and startup program back

on schedule. Link mobilized an experienced staff within 14 days to replace the commissioning

staff of the EPC contractor; and subsequently mobilized an O&M staff to operate and maintain

the facility, with the ultimate objective to train unionized labor staff employed by International

Paper.

Facility Description International Paper’s “910 Facility” in Franklin, VA consisted of a 55 MW

(gross) and 45MW (net) gas/oil-fired turbine generator with a heat

recovery steam generator providing process steam to the adjacent

paper mill. The system additionally included cooling towers, water

purification, condensers, emissions controls, laboratory, and traditional

balance-of-plant systems such as air compressors, PLC’s leading to the

distributed control system (DCS), building and grounds maintenance,

and so forth.

Link’s Scope Link’s scope included:

oversight of EPC completion

Page 31: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 International Paper: Cogeneration

system walkdowns

punch-list generation, and management to correction

system turnover checklists

o mitigation of risks associated with walk-downs, including

alignment and calibration checks

hydros/pressurizations/NDT

equipment startup readings (e.g. volts, amps, etc.)

O&M policies and procedures

o Consistent with existing labor union contracts yet attempting to incorporate a

more “cross-disciplined” approach

And of course, full-time turn-key operation and maintenance of the 910 cogeneration

facility,

Culminating in a seamless turnover to International Paper’s local O&M staff.

Purchase Order 97852iP.O. Box 178, Franklin, Virginia 23851

Page 32: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Portsmouth Transition

PORTSMOUTH GASEOUS DIFFUSION FACILITY: TRANSITION MANAGEMENT

Background The Portsmouth Gaseous Diffusion Plant (part

of the Portsmouth site) is a uranium

enrichment plant that was constructed in the

mid 1950's and operated by the Department of

Energy (DOE) and its predecessor agencies to

supply both high-and low-enriched uranium for

defense purposes and commercial nuclear fuel

sales. The uranium enrichment program

utilizing the gaseous diffusion process resulted

in the generation of significant quantities of

radioactive, hazardous, and mixed waste,

which is referred to as legacy waste, and other

contaminants. Waste and contaminants at the

site include those regulated under the Resource Conservation and Recovery Act (RCRA), the

Toxic Substances Control Act (TSCA), and the Atomic Energy Act (AEA), including construction

debris, sanitary waste, hazardous waste (HW), radioactive low-level waste (LLW), and mixed

low-level waste (MLLW).

LATA/Parallax Portsmouth developed and submitted a winning proposal to the Department of

Energy in response to Request for Proposal to replace the Bechtel Jacobs Company whose

contract was expiring. The Scope included the Clean Up and Remediation/Environmental

Management Services at the Portsmouth Gaseous Diffusion Plant.

Link Scope In support of the requirements of LPP’s efforts to respond to DOE’s RFP and to execute the

awarded contract, Link provided an estimate of all employee and labor related transition costs in

sufficient detail to be included in the target cost of this contract, and assisted determining other

transition costs. Proposed costs were broken down by the following major cost elements:

direct labor (including labor categories, and labor hours in each category),

relocation,

travel,

Page 33: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Portsmouth Transition

materials & supplies,

subcontracts,

and all other costs.

Link led the development of a Transition Plan, and supported LPP to enable submittal within 3

days after any award to LPP. Detail and scope had to be sufficient to meet the requirements of

DOE. The objectives were: (1) achieve an orderly transition; (2) be fair to incumbent employees

and maintain a productive and flexible work force; (3) minimize the cost of the transition and its

impacts on other DOE programs; (4) promote those practices which will result in stable

collective bargaining relationships; (5) adhere to DOE’s Workforce Restructuring Plan for the

facility; (6) integrate ES&H into the transition phase to ensure safety and regulatory compliance;

and (7) ensure compliance with DOE’s Request for Proposal.

The Plan had to address LPP’s approach, methods and processes for the integration and

interfaces with other contactors and private corporations on site. This included LPP’s

organizational structure, strategy and understanding of respective site roles, methods of

resolving disputes and addressing issues, and approach to transition including continuation of

remediation activities, seamless transition of human resources, and strategy for assumption of

the directed or any other subcontracts. It was also understood that Link’s main focus and

responsibility as it related to the Transition Plan was focused on employee and labor related

transition activities. Link managed the Transition Team during the transition period to ensure all

Transition Objectives were achieved while also ensuring transition costs incurred are allowable,

allocable, and reasonable.

Transition Objectives can be summarized as:

Informed incumbent employees about the transition and various stages of the review

and hiring process through various means of communication

Engaged Union Labor leadership to achieve mutual understanding early in the transition

Achieved seamless transition of payroll and benefits

Initiated alignment with DOE (PPPO and POOG) and other site contractors through a

series of meetings and MOUs to ensure clarity of interfaces, jurisdictions, protocols, and

continuity of support

Maintained tight accountability of nuclear material and the security of all site assets

Maintained safety envelope for all facilities and operations

Ensured readiness to maintain compliance with DOE Orders, local, state, and federal

regulations, and all remediation requirements

Transitioned (“blue-sheeting”) all existing Policies & Procedures (several thousands) to

ensure compliance while streamlining and adapting to a new culture

Set the stage for future rejuvenation of people and processes to achieve DOE

objectives.

Page 34: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Portsmouth Transition

Assisted LPP in conducting labor relations in accordance with applicable laws and

DOE’s intent that labor relations policies and practices reflect the best experience of

American industry in aiming to achieve the stable labor-management relations essential

to successful accomplishment of DOE’s programs at reasonable cost.

Link provided assistance in recruiting, interviewing, and selecting the LPP staff. Thereafter, Link

provided ongoing labor relations and HR consultation and advice as needed.

Link Accomplishments Link completed the transition at Portsmouth on time and under budget, allowing LPP to assume

accountability for the facility. All transition activities were completed, including an extensive risk

mitigation and opportunity rejuvenation process that led to a very successful and profitable 5-

year project for LPP.

Steven B. Treibel, 2400 Louisiana Blvd, Albuquerque, NM, (505) 884-3800

Page 35: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

TRANSITION MANAGEMENT: GENERAL

Introduction Over the past 18 years, Link Resources has provided Transition Management1 services to well

over 100 clients - - from utilities to independent energy developers to government, industrial and

commercial companies, both domestically and offshore. Whether transitions are precipitated by

mergers, acquisitions, restructurings, or other changes in control of operation, they are complex

periods during which client objectives can be optimized - - of if not properly managed can lead

to disaster. For instance, over 75% of all M&As fail to achieve major objectives, and the hind-

sight of CEO’s generally blames failures on lack of comprehensive transition planning and

execution.

Each transition is different and requires an approach that is customized - - incorporating the

appropriate lessons-learned across the spectrum of industries and circumstances. During a

transition, staff not only expect change but also typically welcome it. In other words, there is a

window-of-opportunity that can be used to advantage if the transition is planned and executed

effectively. And it is important to note that the transition does not end on the “turnover” date, but

continues for months thereafter. Thus it is important to retain a transition team to pursue

transition objectives concurrently with day-to-day operations.

Although the transition process is complex, if can be summarized by the following stages:

Define the New Organizational Objectives

Analyze and Evaluate the Current Organization, Systems, Environment & Infrastructure

Develop a Transition Plan

Implement the Transition Plan and Manage the Change Process

Feedback on Performance, and Iteration

1 Link Resources’ trademark is “the Transition Company®”

Page 36: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

A list of sample clients to whom Link provided transition services includes:

American Electric Power Lockheed Martin Energy Systems

Babcock & Wilcox Lockwood Greene

Bechtel/B&W Idaho Los Alamos National Lab

Brooklyn Energy Center Manitoba Hydro International

BWX Technologies Masada Resource Group

Carolina Power & Light McGraw-Hill

CH2M Hill Merchant Energy Group

Constellation Energy Mettiki Coal

Department of Energy Mirant

Dominion Virginia Power MyFacility.com

Duke Engineering & Services National Trigeneration CHP Company

Dyplast Products, LLC Navigant Consulting

Enron Northeast Generation Services

Entergy NRG

ESB International Oak Ridge National Lab

Evantage Permatherm

Fluor-Hanford Source Energy

Foster Wheeler Standard Power & Light

Page 37: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

GPU International Step Management

Idaho National Energy Lab Synetics

International Paper Universal Resources

J.A. Jones Construction Battelle

LATA/Parallax World Automation & Technology

The following is a sample table of contents of a comprehensive Transition Plan:

PRE-TRANSITION ACTIVITIES MOBILIZATION

Identify and form Transition Team Orientation to facility and Client

Mobilization Orientation to client

Schedule & inform candidates re: mobilizations Introductions

Plan for Airline ticket/travel mgt Tours

Pre-trip briefings Lodging and local essentials

Team Organization Access to computers, software, internet, cell phones, etc.

Team member Responsibilities/Assignment Matrix Readiness for 1st week agenda

Prepare 1st week schedule ASSESSMENT AND REJUVENATION PLANNING

Client Transition Preparations Engineering

Identify client candidates for Transition Team Capital upgrades, improvement planning & execution

Pre-Transition Interfaces with client/investors Configuration management

Coordinate info collection from client Drawing upgrade, control

Stakeholder relations plan Key parameter trending & analysis

Hardware/Software/IT plan for client Root Cause Analysis

Communications/phones/internet.networks Engineering

Laptop/software/printers Chemistry

"Intra-Transition-Team communications plan, including e-mails"

Environmental Compliance

Set up FTP (or Basecamp) site to use for sharing files in preparation of transition

Code compliance requisites

Communicate log-ins to Team Certificates

Develop e-mail distribution lists for different groups associated with transition

Compliance, monitoring, reporting

Exchange names and contact information for LINK and client staff to be involved in Transition

Permits

Transportation Risk Management

Transportation to/fm client General Condition Assessment

Arrange local transportation to/fm hotel Inventory analysis

Coordinate local transportation to/fm lodging Spare & replacement parts (equipment obsolescence, write-off, quantity & adequacy), condition, storage condition, pedigrees, re-order system, availability)

Client Logistics Tools (hand, special, shop, etc.)

Security clearances/access for client Complete Equipment Condition Assessment

Photo Badges? Visual inspection

Introductions/tours at site Operational trial

Arrange offices at site Maintenance & record review

Coordinate local lodging Equipment history review & incident reports

Identify local restaurants Assessment of adequacy of maintenance record results

Page 38: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

Identify any local security issues Fuel Procurement

Logistics Transition Fuel procurement out of military control

Hotel reservations Review of root cause analysis records or lesson learned records

Hardhats for Transition Team Code compliance (design, installation, maintenance, ops)

Check into what legal resources are available and necessary to client?

Administration

Prepare Transition Budgets Record-keeping & retention

Prepare O&M Budgets Office Automation

Client Transition Preparations Regulatory Compliances

Action plan for client mgt IT, MIS, networking, communications

Client transition team assignments Decision Approval Matrix

HR/Administration Business Records

Client send announcement letter to client employees) Filing system

Briefing plan for client managers Office Automation

Distribute Condensed Transition Plan to client managers (maybe)

Infrastructure Services

Identify HR areas requiring immediate evaluation Human Resources

Set up an client document control system to start using prior and during transition

Termination (whether/how client has done this)

Negotiate/Execute any Contracts Outplacement services?? (interview training, resume writing, referral, new-skill training, etc.)

Finalize Transition Contract Employment Contracts? Severance??

Support client/MODA Contracts Job Descriptions, role definitions, Job Task Analysis

Complete any Contracts with LINK Team Mgt & employee handbooks

Check into what legal resources are available and necessary to client?

Policies & procedures (which ones must be done before transition complete & which one can wait?)

Complete Guides/Checklists for Assessments Complete HR Audit/Checklist

ASSESSMENT AND REJUVENATION PLANNING Compensation

Review of Reliability Centered Maintenance data, if any High vs. Low

Emergency response (war & regional conflict, typhoons, earthquake, strike, deaths, bomb-threats, terrorist attacks, security breaches, other)

Overtime philosophy

Agreements & interfaces (internal & external) Managers vs. Supervisors vs. Labor

Equipment Shift differentials

Relationships and pre-planned communications with supporters and stakeholders

Emergency call-out compensation

Safety & Security Skill based pay consideration

Quality/accessibility of policies & procedures Raise & promotion philosophy

Emergency response (see Emergency Response) Benefits

Safety training (see Training) Social security and benefits

Equipment & availability (fire fighting, protective clothing, respiratory protection, etc.

Pension funds

Safety code compliance Staffing & Recruiting

Perimeter security Recruitment & selection (expatriates, key managers, labor) (communications plan)

Security access through military Plan to retain key managers & employees

Operations/Production Personnel Records & Attention

Role in maintenance Training

Level of formality Mgt training/orientation

Log keeping: automation vs manual Employee training/orientation

Page 39: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

Control system: automation vs manual What training prior to Turnover

Emergency roles What training is high priority after Turnover

Laboratory work Development of priority Lesson Plans

Training, cross-training (see Training) Organization

Information management/technology, archiving, trending Culture

Degree of automation Work ethic

Shift Operations Control system: automation vs manual

Shift philosophy Emergency roles

Shift schedules Laboratory work

Fuel preparation and handling Training, cross-training (see Training)

Production Reporting Information management/technology, archiving, trending

Accounting/Financial Degree of automation

Establish payroll/benefits system Shift Operations

Transition payroll/benefits out of military control Shift philosophy

Inventory & Procurement Shift schedules

Create new Procurement system Fuel preparation and handling

Transition Procurement out of military control Production Reporting

Establish accounting/cash control systems Accounting/Financial

Transition Accounting out of military control Establish payroll/benefits system

Revise chart of accounts as necessary Transition payroll/benefits out of military control

Checks & Balances Inventory & Procurement

Cash control Create new Procurement system

Conservatism & controls Transition Procurement out of military control

Expenditure approvals/authorities Establish accounting/cash control systems

Reports Transition Accounting out of military control

Policies & procedures Revise chart of accounts as necessary

Assess Significant policies and practices Checks & Balances

Adopt/Re-write Policies & Procedures Cash control

Expenditure Approval Matrix Conservatism & controls

Empowerment Expenditure approvals/authorities

Loyalty Reports

Organizational authority vs accountability Policies & procedures

Management philosophy (clarity of role, comparison to superintendents and supervisors, relationship to subordinates, accountability, selection criteria, etc.)

Assess Significant policies and practices

Communications & reporting (on-site, to client, to home office)

Adopt/Re-write Policies & Procedures

Maintenance Expenditure Approval Matrix

Conduct of maintenance philosophy Fuel Procurement

Quality/accessibility of maintenance policies & procedures Transition Fuel procurement out of military control

Predictive maintenance Create new Fuel procurement/management system

Equipment history Use of Contractors

Outage planning & management Capital Improvement Planning

Contractor management PRE-TURNOVER REJUVENATION

Safety relations Execute critical training, if any

Tool management Preparation for Capital Improvements

Inventory Management Design new policies, procedures, and/or processes

Training Engineering

Multi-discipline philosophy & cross-training General Condition Assessment

Page 40: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

Shift philosophy Administration

Roles in emergencies Human Resources

Maintenance Support Organization

Preventive Maintenance Accounting/Financial

Corrective Maintenance & Outage Management Maintenance

Outage Management Emergency Response

Work Order System POST-TURNOVER REJUVENATION

Cost & man-hour tracking Complete re-organization design & recruitments

"CMMS system design, selection, configuration, input, utilization, procedure for use, & training"

Initiate culture change?

Maintenance Planning & Scheduling Relationship between ops, maintenance, production, etc.

Use of Contractors Work ethic?

Emergency Response / Action Plans Empowerment?

Policies & procedures Revise or create new policies, procedures, and/or processes as necessary

Emergency response (war & regional conflict, typhoons, earthquake, strike, deaths, bomb-threats, terrorist attacks, security breaches, other)

Engineering

Agreements & interfaces (internal & external) General Condition Assessment

Equipment Administration

Relationships and pre-planned communications with supporters and stakeholders

Human Resources

Safety & Security Organization

Quality/accessibility of policies & procedures Maintenance

Emergency response (see Emergency Response) Emergency Response

Safety training (see Training) Training

Equipment & availability (fire fighting, protective clothing, respiratory protection, etc.

Safety & Security

Safety code compliance Operations

Perimeter security Accounting/financial

Security access through military Execute Capital Improvements

Operations/Production Agenda: Balance Of First Week after Turnover

Role in maintenance Establish goals and objectives for first year of operations

Level of formality Safety

Log keeping: automation vs manual Safety Training

Training Hold daily staff meetings first thing in morning with management staff

Safety & Security "Commence safety & security audits, revise safety program as appropriate and plan training"

Operations HR

Develop Initial Operating Plan Ensure employees have completed all administrative forms

Develop Initial Operating Budget Finalize of Operating budget

Establish functional accounting/procurement/payroll Finalize all critical soft/hard systems/processes up and running

Establish functional HR/employment process Vendor Continuity/Contracts

Establish functional fuel management process Meet with key vendors

Ensure all legal permits/authorities in place Finalize critical accounts with plant vendor

Correct critical safety deficiencies Review Capital Improvement Plans

Correct critical operational deficiencies Operational Issues

Correct any critical personnel deficiencies Hold daily staff meetings with management staff

Page 41: Link SDVOSB Past Performance Summaries

SAMPLE PAST PERFORMANCE PROJECT SUMMARIES

October 2012 Transition: General

Correct ""other"" critical processes to meet Turnover Day objectives

Complete review/revision of existing operating procedures

Prepare Agenda for "First Day after Turnover" Complete review of other documents

Otherwise prepare for Turnover Continue Equipment Condition Assessment

TURNOVER Continue Other Assessments

Execute Agenda: First Day Complete "First 30-day Agenda”

Ensure Safety and Security Agenda: First 30 Days after Turnover

Ensure Continuity of Operations Conduct Short Term Training

Management and Supervision Meetings Complete training audit and finalize long-range training plan

Conduct staff meeting with all managers and supervisors -- state forth in clear terms roles, responsibilities, and accountabilities of management team

Complete safety and security training

Clarify goals and objectives of short term plant operations; generally discuss long term, with emphasis on continuity of operations

Conduct Phase I management basic training, on accountabilities, responsibilities, and authorities

Discuss 90 day action plan Complete Conduct of Maintenance training??

Review what will be covered in “All Employees Meetings” Complete Correction of Assessment Deficiencies or Rejuvenation Plans

Questions and answer period Complete Agenda for "First-90 Days"

Employees Meetings Agenda: First 90 Days after Turnover

Commence meetings with all employees (why, what, when) Training

Time line for changeover Complete Conduct of Operations training

Philosophy and Vision Commence Phase II managerial training on operating and administrative procedures

Culture and Performance Expectations Conduct Phase III managerial training

Commitment to operations Complete other training

Commitment & plan for training Finalize any revision of operating and administrative procedures

Question and answer period Finalize 5-year capital improvement plan

Execute Safety Plan (1st day and 1st week plan) Finalize 5-Year Operating Plan

Execute Continuity of Operations Plan (1st day and 1st week plan)

Finalize 5-Year Budget

Execute Communications Plan (1st week plan, internal and external comms)

Continue Implementation of Capital Improvements

Execution of Mutual Employment Obligations

E.g. Payroll, management, etc.

Execution of Care/Custody/Control Obligations

E.g. Insurance, compliance, reporting, etc.

Initiate accounting, payroll, procurement, employment, and other processes