Line Station Alternatives Feasibility Study Executive Summary

63
South Bend South Shore Line Station Alternatives Feasibility Study Executive Summary April 2018 FINAL DRAFT

Transcript of Line Station Alternatives Feasibility Study Executive Summary

Page 1: Line Station Alternatives Feasibility Study Executive Summary

 

 

 

 

 

 

 

South Bend South Shore Line Station Alternatives Feasibility Study Executive Summary 

 

April 2018 

FINAL DRAFT 

 

Page 2: Line Station Alternatives Feasibility Study Executive Summary

South Bend South Shore Line Station Alternatives Feasibility Study 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Prepared for the City of South Bend by:

Page 3: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  i 

Table of Contents 1.0  Introduction ................................................................................................................................ 1 

1.1  Background ............................................................................................................................. 3 

1.2  Summary of the Study ............................................................................................................. 3 

1.3  Summary of Evaluation Criteria ............................................................................................... 4 

2.0  Task 1 Summary:  Construction Feasibility .................................................................................. 8 

2.1  Physical and Socio‐Economic Site and Station Area Characteristics ........................................ 8 

2.1.1  Capacity for a station facility and parking ............................................................................ 8 

2.1.2  Land Needs ...................................................................................................................... 8 

2.1.3  Commuter Access ................................................................................................................ 8 

2.1.4  Rail Infrastructure ............................................................................................................ 8 

2.1.5  Socio‐Economic and Environmental Impacts ....................................................................... 8 

2.1.6  Businesses ....................................................................................................................... 9 

2.1.7  Crime ................................................................................................................................... 9 

2.2  Capital Cost Estimation ........................................................................................................... 9 

2.2.1  Range in Capital Station Site Costs ................................................................................ 10 

2.3  Operating & Maintenance Costs ............................................................................................ 12 

3.0  Task 2 Summary:  Rail Operations Impacts ................................................................................ 14 

3.1  Travel Times and Schedules ................................................................................................... 14 

3.2  Ridership Forecasts................................................................................................................ 15 

4.0  Task 3 Summary:  Potential Economic Development Impacts ................................................... 17 

4.1  Development Potential .......................................................................................................... 17 

4.1.1  Developable Parcels ........................................................................................................... 17 

4.1.2  Market Demand ............................................................................................................. 18 

4.1.3  Demand and Development Program ................................................................................. 20 

4.2  Economic Development Summary ........................................................................................ 21 

4.3  Economic and Fiscal Impacts ................................................................................................. 21 

4.3.1  Economic Impacts.............................................................................................................. 21 

4.3.2  Fiscal Impacts ................................................................................................................ 22 

4.4  Summary ............................................................................................................................... 23 

4.5  Notes on this Economic Development and Impact Analysis Research ................................... 24 

5.0  Summary of Alternative Site 1: Chocolate Factory Station ........................................................ 25 

5.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 25 

5.1.1  Capacity for Station Facility and Parking ........................................................................... 25 

Page 4: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  ii 

5.1.2  Land Needs ........................................................................................................................ 25 

5.1.3  Commuter Access .............................................................................................................. 25 

5.1.4  Rail Infrastructure .............................................................................................................. 25 

5.1.5  Socio‐Economic and Environmental Impacts ..................................................................... 25 

5.1.6  Businesses ......................................................................................................................... 25 

5.1.7  Crime ................................................................................................................................. 25 

5.2  Capital Costs .......................................................................................................................... 25 

5.3  Operating and Maintenance Costs ......................................................................................... 26 

5.4  Rail Operations ...................................................................................................................... 26 

5.4.1  Travel Times and Schedule ................................................................................................ 26 

5.4.1  Ridership ............................................................................................................................ 27 

5.5  Economic Impacts ................................................................................................................. 27 

5.5.1  Land Available for Development ........................................................................................ 27 

5.5.2  Development Program and Associated Impacts ............................................................ 28 

6.0  Summary of Alternative Site 2: Honeywell Station .................................................................... 30 

6.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 30 

6.1.1  Capacity for Station Facility and Parking ........................................................................... 30 

6.1.2  Land Needs .................................................................................................................... 30 

6.1.3  Commuter Access .............................................................................................................. 30 

6.1.4  Rail Infrastructure .......................................................................................................... 30 

6.1.5  Socio‐Economic and Environmental Impacts ..................................................................... 31 

6.1.6  Businesses ..................................................................................................................... 31 

6.1.7  Crime ................................................................................................................................. 31 

6.2  Capital Costs .......................................................................................................................... 31 

6.3  Operating and Maintenance Costs ......................................................................................... 31 

6.4  Rail Operations ...................................................................................................................... 32 

6.4.1  Travel Times and Schedule ............................................................................................ 32 

6.4.2  Ridership ........................................................................................................................ 33 

6.5  Economic Development ........................................................................................................ 33 

6.5.1  Land Available for Development ........................................................................................ 33 

6.5.1  Development Program and Associated Impacts ................................................................ 34 

7.0  Summary of Alternative Site 3: Amtrak Station ......................................................................... 37 

7.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 37 

7.1.1  Capacity for Station Facility and Parking ........................................................................... 37 

7.1.2  Land Needs ........................................................................................................................ 37 

Page 5: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  iii 

7.1.3  Commuter Access .............................................................................................................. 37 

7.1.4  Rail Infrastructure .............................................................................................................. 37 

7.1.5  Socio‐Economic and Environmental Impacts ..................................................................... 37 

7.1.6  Businesses ......................................................................................................................... 38 

7.1.7  Crime ................................................................................................................................. 38 

7.2  Capital Costs .......................................................................................................................... 38 

7.3  Operating and Maintenance Costs ......................................................................................... 38 

7.4  Rail Operations ...................................................................................................................... 38 

7.4.1  Travel Times and Schedule ................................................................................................ 39 

7.4.2  Ridership ............................................................................................................................ 39 

7.5  Economic Impacts ................................................................................................................. 40 

7.5.1  Land Available for Development ........................................................................................ 40 

7.5.1  Development Program and Associated Impacts ................................................................ 40 

8.0  Summary of Alternative Site 4: Downtown South Bend Station ................................................ 42 

8.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 42 

8.1.1  Capacity for Station Facility and Parking ........................................................................... 42 

8.1.2  Land Needs .................................................................................................................... 42 

8.1.3  Commuter Access .............................................................................................................. 42 

8.1.4  Rail Infrastructure .......................................................................................................... 42 

8.1.5  Socio‐Economic and Environmental Impacts ..................................................................... 43 

8.1.6  Businesses ..................................................................................................................... 43 

8.1.7  Crime ................................................................................................................................. 43 

8.2  Capital Costs .......................................................................................................................... 44 

8.3  Operating and Maintenance Costs ......................................................................................... 44 

8.4  Rail Operations ...................................................................................................................... 44 

8.4.1  Travel Times and Schedule ............................................................................................ 44 

8.4.2  Ridership ........................................................................................................................ 45 

8.5  Economic Development ........................................................................................................ 45 

8.5.1  Land Available for Development ........................................................................................ 45 

8.5.1  Development Program and Associated Impacts ................................................................ 46 

9.0  Summary of Realigned South Bend Airport Station .................................................................. 48 

9.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 48 

9.2  Capital Costs .......................................................................................................................... 48 

9.3  Operating and Maintenance Costs ......................................................................................... 48 

9.4  Rail Operations ...................................................................................................................... 48 

Page 6: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  iv 

9.4.1  Travel Times and Schedule ............................................................................................ 48 

9.4.2  Ridership ........................................................................................................................ 49 

9.5  Economic Development ........................................................................................................ 50 

9.5.1  Land Available for Development ........................................................................................ 50 

9.5.1  Development Program and Associated Impacts ................................................................ 50 

10.0  Summary of Current South Bend Airport Station ...................................................................... 52 

10.1  Physical and Socio‐Economic Site and Station Area Characteristics ...................................... 52 

10.2  Capital Costs .......................................................................................................................... 52 

10.3  Rail Operations ...................................................................................................................... 52 

10.3.1  Travel Times and Schedule ............................................................................................ 52 

10.3.2  Ridership ........................................................................................................................ 53 

10.4  Economic Development ........................................................................................................ 53 

10.4.1  Land Available for Development .................................................................................... 53 

10.4.2  Development Program and Associated Impacts ............................................................ 54 

 

Table of Figures Figure 1‐1: Alternative Potential Station Sites ......................................................................................... 2 Figure 5‐1. Site 1 Chocolate Factory Station Schedule .......................................................................... 27 Figure 5‐2. Site 1 Chocolate Factory Station Area Half‐Mile Zoning ...................................................... 28 Figure 5‐3. Site 1 Chocolate Factory Station Area Developable Parcels ................................................. 28 Figure 6‐1. Site 2 Honeywell Station Proposed Schedule ...................................................................... 32 Figure 6‐2. Site 2 Honeywell Station Proposed Schedule, w/ Service to Current Airport Station (2A) ... 33 Figure 6‐3. Site 2 Honeywell Station Area Half‐Mile Zoning .................................................................. 34 Figure 6‐4. Site 2 Honeywell Station Area Developable Parcels ............................................................ 34 Figure 7‐1. Site 3 Amtrak Station Proposed Schedule ............................................................................ 39 Figure 7‐2. Site 3 Amtrak Station Area Half‐Mile Zoning ....................................................................... 40 Figure 7‐3. Site 3 Amtrak Station Area Developable Parcels .................................................................. 41 Figure 8‐1. Site 4 Downtown Station Proposed Schedule ..................................................................... 45 Figure 8‐2. Site 4 Downtown Station Area Half‐Mile Zoning ................................................................. 46 Figure 8‐3. Site 4 Downtown Station Area Developable Parcels ............................................................ 46 Figure 9‐1. SSL Proposed Future Schedule w/Double Track, West Lake and Airport Re‐route .............. 49 Figure 9‐2.  Realigned Airport Station Area Half‐Mile Area Zoning ....................................................... 50 Figure 9‐3. Realigned Airport Station Area Developable Parcels ........................................................... 51 Figure 10‐1. Current SSL Schedule (Effective July 2017) ........................................................................ 53 Figure 10‐2. Current Airport Station Area Half‐Mile Area Zoning .......................................................... 54 Figure 10‐3. Current Airport Station Area Developable Parcels ............................................................. 54 

Page 7: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  v 

Table of Tables Table 1‐1: Summary of Proposed Station Metrics ................................................................................... 5 Table 2‐1.  FTA Standard Cost Categories (SCC) ..................................................................................... 9 Table 2‐2. Summary of Estimated Capital Costs by FTA SCC Category ................................................. 10 Table 2‐3. Range of Estimated Capital Costs ......................................................................................... 11 Table 2‐4. Summary of Estimated Annual O&M Costs by Category ...................................................... 13 Table 3‐1. Summary of Time and Distance from Pine Road by Alternative ............................................ 14 Table 3‐2. Westbound Travel Time to Millennium Station ..................................................................... 14 Table 3‐3. Eastbound Travel Time to South Bend .................................................................................. 15 Table 3‐4. South Bend Alternative Station Sites – 2015 Weekday Boardings ........................................ 16 Table 3‐5. South Bend Alternative Station Sites – 2040 Weekday Boardings ........................................ 16 Table 4‐1. Developable Acres within a Half‐Mile by Zoning Classification ............................................. 17 Table 4‐2. Programmed Use in Developable Acres within a Half‐Mile ................................................... 20 Table 4‐3. Estimated New Development Value within a Half‐Mile ........................................................ 21 Table 4‐4.Full Time Equivalent Jobs, 10 Year Development Program ................................................... 22 Table 4‐5.Economic Output, 10 Year Development Program ................................................................ 22 Table 4‐6. Property Tax Impacts, 10 Year Development Program ......................................................... 22 Table 4‐7. Summary of 10 Year Development Program and Associated Economic and Fiscal Impacts .. 23 Table 4‐8. Return on Investment Metrics .............................................................................................. 24 Table 5‐1. Site 1 Chocolate Factory Station Estimated Capital Costs by Category ................................. 26 Table 5‐2. Site 1 Chocolate Factory Station Operations Characteristics ................................................ 26 Table 5‐3. Site 1 Chocolate Factory Station Weekday Boardings ........................................................... 27 Table 5‐4. Site 1 Chocolate Factory Station Area Development Program and Associated Impacts ....... 29 Table 6‐1. Site 2 Honeywell Station Estimated Capital Costs by Category ............................................ 31 Table 6‐2. Site 2 Honeywell Station Operations Characteristics ............................................................ 32 Table 6‐3. Site 2 Honeywell Station Weekday Boardings ...................................................................... 33 Table 6‐4. Site 2 Honeywell Station Area  Mixed‐Use Development Program and Associated Impacts . 35 Table 6‐5. Site 2 Honeywell Station Area  Industrial Development Program and Associated Impacts ... 36 Table 7‐1. Site 3 Amtrak Station Estimated Capital Costs by Category .................................................. 38 Table 7‐2. Site 3 Amtrak Station Operations Characteristics ................................................................. 39 Table 7‐3. Site 3 Amtrak Station Weekday Boardings ........................................................................... 39 Table 7‐4. Site 3 Amtrak Station Area Development Program and Associated Impacts ........................ 41 Table 8‐1. Site 4 Downtown Station Alignment Segment Improvements ............................................. 43 Table 8‐2. Site 4 Downtown Station Estimated Capital Costs by Category ........................................... 44 Table 8‐3. Site 4 Downtown Station Operations Characteristics ........................................................... 44 Table 8‐4. Site 4 Downtown Station Weekday Boardings ..................................................................... 45 Table 8‐5. Site 4 Downtown Station Area Development Program and Associated Impacts .................. 47 Table 9‐1. Realigned Airport Station (Alternative G) Estimated Capital Costs by Category ................... 48 Table 9‐1. Realigned Airport Station Operations Characteristics .......................................................... 49 Table 9‐2. Realigned Airport Station Weekday Boardings..................................................................... 49 Table 9‐3. Realigned Airport Station Area Development Program and Associated Impacts .................. 51 

Page 8: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary  |   April 2018  |  vi 

Table 10‐1. Current Airport Station Operations Characteristics ............................................................. 52 Table 10‐2. Current Airport Station Weekday Boardings ....................................................................... 53 Table 10‐3. Current Airport Station Area Development Program and Associated Impacts .................... 55 

 

 

 

 

Page 9: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary | April 2018 | 1 

1.0 Introduction This study has evaluated alternative station locations in South Bend, Indiana for the South Shore Line (SSL) operated by the Northern Indiana Commuter Transportation District (NICTD). NICTD is currently studying  alternative  routing  options  into  the  South  Bend  Airport,  for  the  purpose  of  enhancing operating  flexibility,  improving  safety, and decreasing  travel  times  for  travel  to and  from downtown Chicago. Based on feedback from the City of South Bend, NICTD paused its current study to allow the City  the  opportunity  to  study  alternative  station  locations  and  routings  that  might  offer  economic development  benefits  to  the  City,  while  still  allowing  NICTD  to  fulfill  its  service  and  operational improvement plans. 

This study reviewed four primary alternative locations in South Bend, including: 

1. Site 1: Chocolate Factory. A new station near the site of a proposed tourist destination southwest of US 31 and US 20. 

2. Site 2: Honeywell. A new station using the current tracks at Westmoor Street, west of Bendix Drive.  

3. Site 3: Amtrak. A joint Amtrak/SSL station at Washington and Meade Streets.  4. Site 4: Downtown South Bend. A new station in downtown South Bend near the Union Station 

Technology Center, along the existing CN and NS freight tracks.  

Figure 1‐1 illustrates the locations of alternative station sites on an overview map of the area.  

Page 10: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY 

Final Draft Executive Summary | April 2018 | 2 

Figure 1‐1: Alternative Potential Station Sites 

 

Page 11: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |3 

1.1 Background The Northern  Indiana Commuter Transportation District  (NICTD) currently operates  five South Shore Line  (SSL)  trains  in  each  direction  between  the  South  Bend  International  Airport  and  Millennium Station  in  downtown  Chicago.  Travel  times  vary  from  just  under  two  hours  to  two  hours  and  40 minutes. This level of service attracts about 190 boardings a day based on counts from November 2015. NICTD’s  Double‐Track  Northwest  Indiana  project,  involving  the  addition  of  a  second  track  between Gary and Michigan City, will enable the operation of more and faster trains. This project is currently in final design, and  is anticipated to be completed  in 2020. These  improvements will benefit all users of SSL east of Gary, including South Bend. The proposed service will involve seven trains in each direction between South Bend and Millennium Station. Travel times will be reduced to between one hour and 24 minutes and one hour and 40 minutes. These  significant  savings are expected  to make  the  service a more attractive option for commuters as well as non‐work travelers. 

The  existing  SSL  station  at  the  South  Bend  Airport  was  moved  to  this  location  in  1992,  having previously been  located at Meade Street and Washington Street (site of the current Amtrak Station). Part of the reason for the move was several incidents that raised concerns for personal safety by riders. The South Bend Airport site afforded a secure location with abundant parking. However, the routing to the  Airport  from  the  SSL  Mainline  track  east  of  Grandview  Avenue  involves  three  miles  of  track, eighteen vehicle grade crossings, multiple curves, and a backtracking alignment that adds two miles to approach  the Airport  from  the east  side. Slow speeds and  roundabout alignment on  the single  track Airport approach track adds more than ten minutes in travel time. 

1.2 Summary of the Study The study included the following four phases: 

1. Construction Feasibility: This task developed conceptual layouts for each of the sites, covering issues such as placement of platform(s), station building, parking, and access. For station sites that require new track, specifics on alignment, right‐of‐way ownership, grade crossings, etc. were identified. In addition, capital and operating & maintenance costs were estimated at a planning level of specificity for the alternative station as well as for a realigned station at the airport. An analysis of current socio‐economic data for the half‐mile station area was prepared.  

2. Potential Rail Operations Impacts: Based on distance and travel times for each site, proposed SSL schedules were developed. This service information was used to forecast ridership for each of the alternative sites. Comparisons to forecasts for the NICTD proposed realignment to the South Bend Airport were made.  

3. Potential Economic Development Impacts: An estimate of economic development that may be possible in the ½ mile radius areas around the proposed station locations and around the proposed and current airport stations was prepared. This included potential redevelopment capacity based on an understanding of permissible uses, as well as market trends and physical and contextual features of sites. This task also included an economic impact analysis. 

4. Final Report:  A synthesis of the preceding tasks was compiled in memorandum (this document) and presentation format. 

This final report provides an overview of each of the phases, synthesized in an evaluation matrix to aid the  City  in  reviewing  the  alternatives.  The  technical  analysis  is  summarized  here,  with  the  detailed technical memoranda from each of the first three phases of this project included as Appendices.  

 

Page 12: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |4 

1.3 Summary of Evaluation Criteria This study analyzed several different variables and metrics for each of the proposed station areas. The results  of  the  analysis  show  that  each  of  the  proposed  sites  has  different  advantages  and disadvantages. The top priorities and goals of the City and NICTD will be the primary factor in choosing sites that should move forward or no longer be considered. Table 1‐1 presents a summary of each of the criteria that were analyzed in this study. 

Page 13: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |5 

 

Table 1‐1: Summary of Proposed Station Metrics 

Criteria  Site 1: Chocolate Factory  Site 2 : Honeywell  Site 3: Amtrak  Site 4: Downtown Proposed Realigned Airport Station (Alt G) 

Current Airport Station (No‐Build) 

Capital Costs ($ 2017)  $44,274,000  $23,870,000  $31,727,000  $102,302,000  $29,480,000  N/A 

Potential Range Capital Costs  ($ 2017) 

$40.7 mm ‐ $44.3 mm  $14.3 mm ‐ $23.9 mm  $28.3 mm ‐ $31.7 mm  $98.4 mm ‐ $102.3 mm  $29.5 mm  N/A 

Summary of Construction Complexity 

Predicated on private owner’s development plans 

Property acquisition for approach alignment 

CSS storage tracks 

Properties owned by Honeywell Corporation 

Access near Honeywell operations 

Impacts to CSS yard tracks 

Compatibility with CSS and NS operations 

Limited ROW for rail and station between Walnut 

and downtown 

Compatibility with NS and CN operations 

Property acquisition for approach alignment 

N/A 

Travel Times WB: 82‐98 min. 

EB: 90‐97 min. 

WB: 82‐98 min. 

EB: 90‐97 min. 

WB: 82‐98 min. 

EB: 90‐97 min. 

WB: 84‐100 min. 

EB: 92‐99 min. 

WB: 84‐100 min. 

EB: 92‐99 min. 

WB: 115‐160 min. * 

EB: 118‐155 min. * 

O&M Costs (Annual)  $247,430  $577,430  $577,430  $577,430  $247,430  N/A 

Forecast Weekday Ridership (2040)  698  729   731  735  727  N/A 

Station Area Acres Available for Development within Half‐Mile 

221  86  64  83  34  63 

Potential New Construction Value within Half‐Mile  $40,230,000 

$73,070,000  (mixed‐use scenario) 

$47,320,000  (industrial use scenario) 

$23,250,000  $147,810,000  $17,820,000  $24,590,000 

Potential Economic Impact (10 yr)  $144,400,000 

$171,500,000 

(mixed‐use scenario) 

$132,000,000 

(industrial use scenario) 

$139,700,000  $415,300,000  $83,800,000  $39,000,000 

Potential Fiscal Impact (10 yr) $5,921,000 (property) 

$15,400,000 (all taxes) 

$8,563,000 (property) 

$19,410,000 (all taxes) 

(mixed‐use scenario) 

$5,640,000 (property) 

$14,110,000 (all taxes) 

(industrial scenario) 

$2,556,000 (property) 

$11,444,000 (all taxes) 

$18,639,000 (property) 

$45,150,000 (all taxes) 

$3,251,000 (property)$8,800,000 (all 

taxes) 

$4,486,000 (property) 

$7,210,000  (all taxes) 

Likely Environmental Action Required Environmental Impact 

Statement Environmental Assessment or Categorical Exclusion 

Environmental Assessment Environmental Impact 

Statement Environmental Assessment  N/A 

Station Area Typology  Special Destination Neighborhood TOD or 

Industrial Neighborhood TOD  Downtown  Industrial  Industrial 

* Travel times reflect current operating schedule without any Double Track improvements or realignment in / near South Bend 

Page 14: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |6 

Criteria  Site 1: Chocolate Factory  Site 2 : Honeywell  Site 3: Amtrak  Site 4: Downtown Proposed Realigned Airport Station (Alt G) 

Current Airport Station (No‐Build) 

Influence of Transit on Development Program 

Moderate – attraction development plans enhanced but not 

dependent  

High – purposeful TOD redevelopment  (mixed‐use 

scenario) 

Moderate – purposeful TOD redevelopment but weaker link between transit and industrial development (industrial scenario) 

Moderate – purposeful TOD redevelopment but weak 

market conditions 

Moderate – development momentum already positive absent rail; will enhance or 

accelerate program 

Low – limited current correlation unlikely to alter 

much with current infrastructure 

Low – limited current correlation unlikely to alter 

much with current infrastructure 

Space Available for Station, Platform & Parking  Good  Good  Good  Adequate  Good  Good 

Displaced / Shared Property Ownership 

South Bend Chocolate Factory 

Various private properties 

Freight railroads 

Honeywell Corporation 

NICTD 

Curtis Products Inc. 

Chicago South Shore 

Freight railroads 

Freight railroads 

Union Station properties 

Rail‐adjacent segments of various private properties, potentially: Kroc/Salvation Army; Housing Authority; private residential; Claey’s 

44 property owners impacted (1 commercial; 1 airport; 42 residential) 

25 property displacements (1 commercial, 24 

residential) 

N /A 

Connectivity  Fair  Good  Fair  Good  Fair  Fair 

    Roads  Good  Good  Fair  Good  Good  Good 

    Bike Lanes  Poor  Good  Good  Good  Poor  Poor 

    Sidewalks  Poor  Good  Fair  Good  Poor  Poor 

Total Number of Crossings  2  1  0  3  6 (approx.)  22 

    Non‐Motorized  0  0  0  3  1 (approx.)  3 

    Motorized  2  1  0  2  5 (approx.)  19 

Wetlands Impacted  0  0  0  0  1  0 

   

Page 15: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |7 

Criteria  Site 1: Chocolate Factory  Site 2 : Honeywell  Site 3: Amtrak  Site 4: Downtown Proposed Realigned Airport Station (Alt G) 

Current Airport Station (No‐Build) 

Current ½ Mile Station Area Characteristics             

    Population (2015)  179  1,347  1,957  2,403  378  429 

    % Minority (2015)  21%  54%  63%  62%  25%  27% 

    % Below Poverty (2015)  17%  37%  35%  53%  17%  17% 

    % Zero‐Car Households (2015)  1%  22%  21%  62%  4%  6% 

    # of Low‐Income Housing Units (2015)  0  174  0  771  0  0 

    # of Schools  0  4  0  2  0  0 

    # of Parks  0  1  2  2  0  0 

    # of Businesses  11  28  80  683  64  68 

    Crime Incidents (3Q and 4Q 2017) 4 

(22 per 1000 capita) 

101 

(75 per 1000 capita) 

202 

(103 per 1000 capita) 

291 

(121 per 1000 capita) 

118 

(312 per 1000 capita) 

175 

(407 per 1000 capita) 

Page 16: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |8 

2.0 Task 1 Summary:  Construction Feasibility Each  of  the  four  potential  station  sites  was  evaluated  for  construction  feasibility.  The  following variables were evaluated to determine whether  it could be feasible to build a station at the proposed location. 

Physical and Socio‐Economic Site and Station Area Characteristics  o Capacity for a station facility and parking o Land needs o Commuter access o Rail infrastructure o Socio‐economic impacts o Businesses o Crime 

Capital Costs  Operating & Maintenance Costs 

An  analysis  of  operational  characteristics  of  serving  the  four  proposed  station  sites  was  prepared, including development of  travel  times  and  schedules,  and  forecasts of potential  ridership.   Detailed findings  are  presented  in  the  South  Bend  Station  Alternatives  Feasibility  Study  Tech  Memo  1: Construction Feasibility technical memorandum. 

2.1 Physical and Socio‐Economic Site and Station Area Characteristics  

2.1.1 Capacity for a station facility and parking 

This  review considered  the context of  the potential site  location and whether  there  is sufficient  land capacity for the station facilities and parking for commuters. 

2.1.2 Land Needs 

This review considered the access needs of the potential station and whether here  is enough  land for the alignment to be constructed. 

2.1.3 Commuter Access 

This review evaluated the ease of access to the station by non‐motorized, motorized and transit users. It also evaluated the number of new at‐grade crossings that would be created.   

2.1.4 Rail Infrastructure 

This  evaluation  presents  the  new  rail  infrastructure  that would be  needed  to  connect  the  proposed station to the current South Shore main line. The required infrastructure includes rail, catenary system, railroad  signalizing,  crossing  protection  at  proposed  crossings,  and  turnouts  at  each  of  the  track connection points.   Where needed,  requirements  for additional  required  sidings, passing  tracks, and storage tracks are also described.   All of these infrastructure elements are accounted for in the capital costs section of the analysis.  

2.1.5 Socio‐Economic and Environmental Impacts 

This review assessed the socio‐economic and environmental context of the proposed station site in the half‐mile radius around the site, i.e., the potential station area.   Current population and households in the station area were calculated, along with the shares that are low income, minority, or without access 

Page 17: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |9 

to a car. Maps were reviewed to determine if there are any schools, parks or other sensitive uses in the station area, along with the presence of low‐income housing units. 

2.1.6 Businesses 

This metric counted the number of businesses within a half‐mile of the proposed station site. 

2.1.7 Crime 

This evaluation addressed concerns about public safety  in the vicinity of the proposed stations.   Real and  perceived  safety  often  factors  into  the mode  choice  of  potential  rail  passengers. To  assess  the current risk associated for each of the station areas, data was collected from the website CrimeReports for a 1.3 square mile area centered on each potential station.   Statistics covered the six month period July‐December 2017. Incidents were classified as Violent, Property, and Quality of Life (e.g., disorderly conduct, vagrancy, or loitering).  It is important to note that this is a short‐period snapshot of incidents but may provide insight into local safety trends.  

2.2 Capital Cost Estimation An  important metric  in evaluating the candidate SSL station sites will be the required  level of capital investment.  Planning‐level  capital  cost  estimates  were  developed  using  the  Federal  Transit Administration’s  (FTA) Standard Cost Categories  (SCC) structure, which provides a consistent  format for estimating costs  for Capital  Investment Grants Program projects. The SCC system uses nine cost categories, as shown on Table 2‐1. Subcategories further break down cost elements under each of the nine major categories.  A detailed description of the capital cost categories can be found in South Bend Station Alternatives Feasibility Study Tech Memo 1: Construction Feasibility.   

 

Table 2‐1.  FTA Standard Cost Categories (SCC)  

  FTA Cost Category 

10  Guideway & Track Elements 20  Stations, Stops, Terminals, Intermodal 30  Support Facilities: Yards, Shops, Admin. Bldgs. 40  Sitework & Special Conditions 50  Systems 60  ROW, Land, Existing Improvements 70  Vehicles 80  Professional Services (Applies to Categories 10‐50) 90  Unallocated Contingency 

 

The  SCC  provides  two  areas  where  estimated  costs  can  be  adjusted  for  project  uncertainty.  An allocated contingency is applied to each subcategory’s unit cost that relates to the degree of unknowns that can affect costs. For example, constructing track for a given length (e.g., per foot or per mile) can be estimated with a relatively high level of certainty; whereas, addressing the need to relocate utilities without  specific  information  has  a  higher  level  of  unknown.  In  these  two  instances,  the  Allocated Contingency for track was assumed at 10 percent and utilities at 40 percent. 

The other area to address unknown factors is to apply an Unallocated Contingency. This percentage is applied  to  all  estimated  costs,  and  should  relate  to  the  level  of  planning  (i.e.,  higher  unallocated contingency) versus engineering (i.e., lower unallocated contingency). 

Page 18: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |10 

The  cost estimates prepared  in  this  study are planning‐level estimates, which means  that  they have been  developed  as  an  initial  review  of  the  proposed  station  sites,  without  the  benefit  of  (and corresponding cost for conducting) additional technical data collection through preliminary engineering design  work,  land  and  geotechnical  surveys,  or  deep  analysis  of  socio‐economic  and  environmental characteristics.   This  level of cost estimation  is appropriate  in the early stages of project evaluation to provide directionally‐correct, order of magnitude cost estimates that can assist determination whether further study of a project is merited. 

Table 2‐2. Summary of Estimated Capital Costs by FTA SCC Category 

 

FTA Cost Category 

Site 1 ‐ Chocolate Factory 

Site 2 ‐ Honeywell 

Site 3 ‐ Amtrak 

Site 4 ‐ Downtown 

Proposed Realigned Airport Station (Alt G) 

10  Guideway & Track Elements  $7,537  $3,434  $3,552  $27,579  $4,424 20  Stations, Stops, Terminals, Intermodal  $7,040  $7,040  $7,040  $7,040  $2,640 30  Support Facilities: Yards, Shops, Admin.   $776  $0  $3,559  $3,785  $0 40  Sitework & Special Conditions  $5,324  $3,056  $4,115  $10,213  $3,854 50  Systems  $7,636  $4,358  $5,759  $11,928  $7,949   CONSTRUCTION SUBTOTAL (10‐50)  $28,312  $17,888  $24,024  $60,544  $18,866 60  ROW, Land, Existing Improvements  $91  $200  $225  $5,400  $3,000 70  Vehicles  $0  $0  $0  $0  $3,769 80  Professional Srvs.  

(Applies to Cat. 10‐50) $10,096  $3,612  $4,594  $15,898 

$25,635 

  SUBTOTAL  $38,499  $21,700  $28,843  $81,842  $25,635 90  Unallocated Contingency  $5,775 

15% $2,170 10% 

$2,884 10% 

$20,460 25% 

$3,845 15% 

  TOTAL   $44,274  $23,870  $31,727  $102,302  $29,480 

Costs are presented in thousands of 2017 dollars. 

 

2.2.1 Range in Capital Station Site Costs 

The estimated capital costs assumed a standard set of  infrastructure elements, which were patterned after the NICTD Airport Reroute project, and from input from NICTD on their requirements to support the anticipated  level of  service. At  the City’s  request, certain elements were  identified  that could be deferred  or  scaled  back,  which  would  impact  the  near‐term  capital  investment  for  the  station’s development. This was  intended to provide the  lower end of a range of possible station facility costs. Three areas were identified, including: 

a. Reduced Opening Day Parking ‐ Demand modeling analysis estimated passengers using park‐n‐ride for the base year 2015 and the forecast year 2040. Assuming straight‐line growth over this 25 year period, a forecast for the year 2030 was made, which could serve as the basis for estimating an opening day capacity.  A design capacity of 85% was assumed in estimating the number of spaces needed to accommodate the forecasted demand. The 2030 demand for each of the sites varied slightly, but to maintain consistency in the costs, the average of 2030 park‐n‐ride demand (285) and spaces (335) were used as the basis for estimating capital costs for all sites. This change represented a one‐third reduction from the 500‐space parking facility assumed in the base capital costs.   

Page 19: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |11 

b. Station Depot Size ‐ Costs of the station building were based on a 5,000 square foot building, which was assumed to cost $4 million. At this level of planning, a smaller facility could potentially meet the needs of the City and NICTD, but would need to be verified in the next phase of the project.  Therefore, a simplifying assumption was made that the investment in the station building could instead be $2 million. 

c. Honeywell Rail Access Options – Of the four study sites and the relocated Airport Station, four require new track connections to the SSL mainline. The Honeywell Station site, however, is on the SSL Airport Branch, which currently connects to the mainline near Grandview Avenue. NICTD has argued that this track should be realigned to increase train speed.   An option to this investment would be to continue to use this railroad infrastructure without realigning or replacing, affecting costs associated with land acquisition, establishing the new rail roadbed/sub‐ballast, installing new track, signals, catenary, and a turnout at the mainline connection.  Potentials costs related to drainage, utilities, and environmental remediation would also be reduced. Remaining rail infrastructure costs would involve the second station terminal track and a storage track.  This approach would reduce rail infrastructure costs for the Honeywell Site 2 by an estimated $6.2 million.   An intermediate variation of this scenario would be to replace the Airport Branch track, but use the existing alignment, which would save on land costs, roadbed preparation, drainage and utilities work. This would result in $1.4 million in reduced costs, versus the $6.2 million savings to not replace current infrastructure. 

Table 2‐3 presents estimates of potential cost reduction for each of the three elements. For parking and stations,  Sites  1‐4  are  impacted,  with  variations  due  to  the  different  assumptions  in  Unallocated Contingency.  The  Relocated  Airport  Station  would  not  be  affected,  since  commuter  parking  would share existing Airport parking as is the case currently and the station platform would lead directly to the Airport terminal, which would serve as the station’s waiting area.  

The  total  reduction  in  costs  would  vary  between  zero  at  the  Relocated  Airport  alternative  to  $9.6 million at Site 2 Honeywell. 

Table 2‐3. Range of Estimated Capital Costs 

     

Site 1 ‐ Chocolate Factory 

Site 2 ‐ Honeywell 

Site 3 ‐ Amtrak 

Site 4 ‐ Downtown 

Proposed Realigned Airport Station (Alt G) 

  Base Capital Cost Estimate  $44,274  $23,870  $31,727  $102,302  $29,480 

a.  Parking for 2030  $43,659  $23,290  $31,149  $101,634  $29,480    Change  ‐$616  ‐$579  ‐$578  ‐$668  0 b.  Reduce Depot Size by 50%  $41,288  $21,063  $28,920  $99,057  $29,480    Change  ‐$2,986  ‐$2,807  ‐$2,807  ‐$3,245  0 c.  Add Terminal/Storage Track only  $44,274  $17,698  $31,727  $102,302  $29,480    Change  0  ‐$6,171  0  0  0    Lower‐End Capital Cost Option  $40,673  $14,312  $28,342  $98,389  $29,480    Change  ‐$3,602  ‐$9,557  ‐$3,385  ‐$3,913  0 

 

   

Page 20: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |12 

2.3 Operating & Maintenance Costs In  addition  to  the  capital  costs  estimated  for  each  station  alternative,  City  staff  requested  that  an additional factor, annual costs for operating and maintaining (O&M) station facilities, be added to the site  evaluation.    Data  were  obtained  from  NICTD  on  typical  station  costs  to  maintain,  serve  with utilities, sell tickets, and secure.   

While costs will likely be similar for each site, the parties responsible will vary.  The following discusses the entities, and their likely respective roles and responsibilities.  It should be noted that these assigned responsibilities are based on  the circumstances at each  station  site as defined  in  this  study, and will require input and ultimately negotiations between the affected parties.  

City of South Bend – commuter  rail agencies are  increasingly partnering with  local governments (usually  municipalities)  to  take  on  the  responsibility  for  maintaining  and  operating  station  and parking  facilities.  This  has  proven  beneficial  elsewhere,  with  local  governments  treating  these facilities as another community asset, giving them the incentive and capability to maintain them at a higher  standard  than  the  railroad would be  able.   Often, municipal  costs  are offset by  station vendor revenues and parking fees. Municipalities can also be supplement security that the railroad provides. 

NICTD – would be  responsible  for  ticket selling.   Depending on perceived  safety  risk at a station site, NICTD would assign officers from their police department. 

South Bend Airport – currently, the SSL Station is part of the physical plant of the Airport, and the issues associated with maintenance, parking operation and security are part of the Airport’s daily operations.   Currently,  the Airport  charges  commuters  for parking, otherwise  all other  activities performed by  the Airport  in  support of  the SSL  are  absorbed  into  the Airport’s operation.   The possibility exists that the Airport would assess an operating fee on the SSL operation in the future.  

Chocolate Factory –  it  is understood  that  this proposed attraction  is willing  to  incorporate a SSL station into their development plans.  It would seem possible that the development could also take on the responsibility for all station operating and maintenance functions other than ticket‐selling.  

The  table  that  follows  shows  the  estimated  cost  by  element,  and  which  entity  would  likely  be responsible for the activity and the cost. The responsible entity for each cost element and station site is color coded, with costs rolled‐up for each at the bottom. One exception to estimated costs that NICTD provided  was  Local  Security  (11)  for  Sites  2‐4,  which  represent  double  the  estimated  security  costs NICTD would  incur.   This would clearly be a point of discussion between  the City and NICTD, and  is intended to provide 24/7 coverage with City police personnel. This could also  include a satellite police department within the station depot. 

Costs related to Local Security (11) were not estimated for Site 1 ‐ Chocolate Factory and the Relocated Airport Station, in part because the level of security attributed to the station is likely to be less than the free‐standing stations.   While there  is undoubtedly some  incremental cost for security attributable to the station and commuter rail passengers, there was insufficient information available to estimate this cost. It is also possible that this cost would be incorporated into a service fee assessed to NICTD and/or SSL passengers.   

   

Page 21: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |13 

Table 2‐4. Summary of Estimated Annual O&M Costs by Category 

  Site 1 ‐ 

Chocolate Factory 

Sites 2 ‐ Honeywell 

Sites 3 ‐ Amtrak 

Sites 4 ‐ Downtown 

Proposed Realigned Airport 

Station (Alt G) 

O&M Cost Elements              1. Janitorial  $12,958   $12,958   $12,958   $12,958   $12,958  2. Routine Maintenance  3,993   3,993   3,993   3,993   3,993  3. Pest Control  600   600   600   600   600  4. Snow Removal ‐ Parking  4,312   4,312   4,312   4,312   4,312  5. Electricity  19,092   19,092   19,092   19,092   19,092  6. Other Utilities  4,885   4,885   4,885   4,885   4,885  7. Ticket Agent ‐ part time  26,532   26,532   26,532   26,532   26,532  8. Security‐Armored Car  8,064   8,064   8,064   8,064   8,064  9. Ticket Vending Mgmt.  1,099   1,099   1,099   1,099   1,099  10. Security‐Police Patrol  165,000   165,000   165,000   165,000   165,000  11. Local Security   TBD  330,000   330,000   330,000    TBD 12. Refuse Pick‐up  895   895   895   895   895  

Total  $247,430   $577,430   $577,430   $577,430   $247,430  

Costs borne by:                 

City of South Bend  $0  $376,735  $376,735  $376,735  $0 NICTD  $200,695  $200,695  $200,695  $200,695  $35,695 South Bend Airport  $0  $0  $0  $0  $211,735 Chocolate Factory Development 

$46,735  $0  $0  $0  $0 

Total  $247,430  $577,430  $577,430  $577,430  $247,430 TBD: to be determined; costs in 2017 dollars

   

Page 22: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |14 

3.0 Task 2 Summary:  Rail Operations Impacts An  analysis  of  operational  characteristics  of  serving  the  four  proposed  station  sites  was  prepared, including development of  travel  times  and  schedules,  and  forecasts of potential  ridership.   Detailed findings are presented in the South Shore Line Alternative Stations Feasibility Study:  Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

3.1 Travel Times and Schedules Travel times were estimated for each of the proposed South Bend station sites to Pine Road, which is a common  location on  the South Shore main  line  2.2 miles west of  the SSL main  line/Airport Branch Junction.    Times  were  estimated  by  segmenting  the  route  from  Pine  Road  east  to  each  proposed station location.   Segments were assigned an estimated speed based on the degree of track tangency or  curvature.  Note  that  these  estimates  were  based  on  judgement,  without  the  benefit  of  detailed engineering  data.  Assumed  segment  speeds  ranged  from  30  to  65mph.    Table  3‐1  summarizes  the distances and estimated travel times from alternative station sites to the Pine Road crossing of the SSL.   

Table 3‐1. Summary of Time and Distance from Pine Road by Alternative 

  Route Length (miles) 

Travel Time (mins) 

Scheduled Speed (mph) 

Site 1 ‐ Chocolate Factory  1.8  2.7  40.8 Site 2 – Honeywell  2.6  2.9  54.7 Site 2A ‐ Honeywell + SB Airport  5.2  15.0  20.9 Site 3 ‐ Amtrak  3.4  3.5  59.2 Site 4 ‐ Downtown  5.2  5.1  61.1 Realigned Airport Station  2.8  5.4  31.2 Current Airport Station *  5.2  15.1  20.7 

 

Based on distance and travel times for each site, proposed SSL schedules were developed. This service information was used to forecast  ridership  for each of the alternative sites. Comparisons to  forecasts for the NICTD proposed realignment to the South Bend Airport was made.  

Travel times for trains traveling west from South Bend, terminating at Millennium Station  in Chicago range from approximately 84 minutes to 100 minutes (Table 3‐2). 

Table 3‐2. Westbound Travel Time to Millennium Station 

  Minimum  Maximum 

Site 1: Chocolate Factory  82 min.  98 min. Site 2: Honeywell  82 min.  98 min. Site 3: Amtrak  82 min.  98 min. Site 4: Downtown  84 min.  100 min. Realigned Airport Station  84 min.  100 min. Current Airport Station *  115 min.  160 min. 

 

 

   

Page 23: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |15 

Travel  times  for  trains  traveling east  from Millennium Station and  terminating  in South Bend  range from approximately 92 minutes to 99 minutes (Table 3‐3). 

Table 3‐3. Eastbound Travel Time to South Bend 

  Minimum  Maximum 

Site 1: Chocolate Factory  90 min.  97 min. Site 2: Honeywell  90 min.  97 min. Site 3: Amtrak  90 min.  97 min. Site 4: Downtown  92 min.  99 min. Realigned Airport Station  92 min.  99 min Current Airport Station *  118 min.  155 min. 

 

* Note that travel times and schedules for the Current Airport Station reflect the current 2017 operating schedule for the present South Bend Airport station.   A “no build” schedule for service to the current South Bend Airport station that includes improvements include other South Shore Line improvements (e.g., Double‐Track NWI) is not available for this report. 

3.2 Ridership Forecasts The City of South Bend and NICTD have the common objective of maximizing the number of people using  the SSL  service  and  a South Bend  station. The  technical  tool  to  estimate use  for  each of  the alternative sites  is the Simplified Trips‐on‐Project Software  (STOPS).     The STOPS model application was developed by various NICTD consultants over the last five years to develop forecasts for the West Lake and Double Track initiatives. These forecasts included realigned access to the South Bend Airport. 

Results were modeled for the 2015 base year and 2040 forecast year. Alternatives included: 

No‐Build (current service to Airport Station)  Baseline Alternative (reroute to new Airport Station)  Site 1 Chocolate Factory Station Site  Site 2 Honeywell Station Site (without service to current Airport station)  Site 2A Honeywell Station Site (with service to current Airport station)  Site 3 Amtrak Station Site  Site 4 Downtown Station Site 

In addition, each model run provided the number of weekday boardings by access mode, including: 

Walk  Kiss‐n‐Ride (i.e., drop‐off)  Park‐n‐Ride  Transfer (i.e., from another mode) 

Results were generated for each of the study stations sites, as well as all other existing and proposed SSL Stations. These provided the opportunity to measure impacts to SSL ridership overall. In addition, the detailed results provide current station boarding counts. 

Table 3‐4 and Table 3‐5 show 2015 and 2040 weekday boardings by access mode and station site. 

 

   

Page 24: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |16 

Table 3‐4. South Bend Alternative Station Sites – 2015 Weekday Boardings 

Alternative  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 

Site 1 Chocolate Factory  4  133  231  1  369  21,549 

Site 2 Honeywell  70  96  191  26  383  21,579 

Site 2A Honeywell Site 2A Current Airport 

71 7 

89 3 

185 5 

0 22 

345 37 

21,577 

Site 3 Amtrak  48  76  175  85  384  21,582 

Site 4 Downtown  54  69  163  100  386  21,584 

Realigned Airport Station  24  60  151  148  383  21,583 

Current Airport Station *  38  101  146  2  287  12,291 

 

Table 3‐5. South Bend Alternative Station Sites – 2040 Weekday Boardings 

Alternative  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 

Site 1 Chocolate Factory  4  245  449  0  698  26,663 

Site 2 Honeywell  131  172  371  55  729  26,730 

Site 2A Honeywell Site 2A Current Airport 

132 9 

160 5 

357 7 

13 47 

662 68 

26,729 

Site 3 Amtrak  79  139  344  169  731  26,736 

Site 4 Downtown  112  122  313  188  735  26,737 

Realigned Airport Station  47  108  295  277  727  26,733 

Current Airport Station *  Not available 

 

The Chocolate Factory station generated the lowest level of boardings, although within four percent of the average 2040 boardings of all sites. The other alternative sites show very little variation, all within one percent of the average of 725 boardings. 

* Note that 2015 ridership for the Current Airport Station reflect the current operating schedule for the present South Bend Airport station.  Ridership forecasts for a “no build” alternative with service to the current South Bend Airport station  location that  includes other South Shore Line  improvements (e.g., Double‐Track NWI) is not available for this report. 

 

   

Page 25: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |17 

4.0 Task 3 Summary:  Potential Economic Development Impacts An  analysis  of  the  current market  conditions was  conducted  to  understand  the  city’s  strengths  and potential areas for growth, particularly in the areas around the potential station sites.  The approach for assessing development potential was as follows: 

Identify the amount of developable land, existing values and compatible land uses in each station area; 

Determine the potential market demand per station based on a share of the city’s capture rate, calibrated to each station’s value premium/discount to market; 

Develop program for each station based on market trends, estimated market demand, developable land, and zoning/density constraints; 

Estimate future property tax revenues of new development using 10‐year assessed values from each scenario; and 

Estimate each alternative’s total economic impact and other tax revenues using construction costs and station capital costs. 

Detailed  documentation  of  this  task’s  findings  is  contained  in  the  South  Shore  Line  Alternative Stations Feasibility Study:  Task 3:  TOD and Economic Analysis technical presentation. 

4.1 Development Potential 

4.1.1 Developable Parcels 

Within  the  half‐mile  station  area  (measuring  502  acres),  vacant  and  underutilized  properties  were identified as candidates for development.  Properties separated by the proposed station site by a major physical barrier that would  impede non‐motorized connections and therefore would not  form part of cohesive  transit‐oriented  development  neighborhood,  were  excluded  from  consideration.    These barriers include active railroad rights of way (SSL and NS/CP) and limited access highways (US 31). 

Table 4‐1. Developable Acres within a Half‐Mile by Zoning Classification 

  Total  Ag  Bus  Com  Ind  Off  MU  PUD Res 

(SF/2) Res (MF) 

Site 1: Chocolate Factory 

220.5 (44%) 

38.0  ‐  ‐  150.5  ‐  ‐  ‐  32.0  ‐ 

Site 2: Honeywell 

86.5 (17%) 

‐  7.4  4.9  63.0  3.7  ‐  ‐  7.5  ‐ 

Site 3: Amtrak 64.4 

(13%) ‐  2.3  ‐  29.4  2.5  0.5  ‐  27.6  2.1 

Site 4: Downtown 

83 (17%) 

‐  4.9  ‐  18.0  0.3  9.6  36.2  4.3  2.4 

Realigned Airport Station 

34.4 (7%) 

  1.4  5.3  15.5  ‐  ‐  ‐  12.2  ‐ 

Current Airport Station 

62.5 (13%) 

  3.1  10.3  24.7  ‐  ‐  ‐  24.4  ‐ 

 

   

Page 26: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |18 

4.1.2 Market Demand 

4.1.2.1 Context ‐ Demographics 

A survey of economic and demographic conditions in South Bend, the surrounding geographies, and its peer cities was conducted.   The City of South Bend’s population of approximately 100,000 has been growing modestly, but more slowly than  its peers, at 0.1% annually between 2010 and 2016.    It has a large higher education student population, with about 7% of its population composed of undergraduate and graduate students.  There is a small (17.5%) and fairly stable segment of retiree population over age 60; other peer cities in Indiana and many university towns have larger and growing shares of retirees.  

South Bend’s household composition includes about 38,500 households, whose makeup is younger and smaller than US averages, with a larger proportion than peers composed of single‐person households.  Median household  income  in 2016 was $35,800, with  individuals’ median earnings at $23,600.   About 57% of South Bend’s employed population work full‐time, year‐round.  Its labor force participation rate is approximately 47% of people of working age; this  is  lower than peer cities but has been consistent over  the  last  two  decades  so  is  probably  due  to  the  university  student  population.    The  City’s unemployment rate in 2017 was slightly above peer cities but still low at 4.1%, down from a high of 13% in 2009. 

4.1.2.2 Context – Economic Base 

In  the South Bend metropolitan area, employment  is  likewise growing more slowly  than  the US and state averages,  just over  1% annually.   The  region’s economy  shows  concentrations as measured by location quotient in the Education, Manufacturing, Wholesale Trade, and Health Care sectors.  There is a  net  inflow  of  workers  from  Illinois  to  jobs  in  Indiana,  with  recent  trends  in  Manufacturing, Administrative & Support Services, and Retail Trade. 

4.1.2.3 Context – Travel Behaviors 

Among the working population of South Bend over age 16, 79% drive to work alone, 11% carpool, and 3% take transit. The current travel profile for South Shore Line riders who use the South Bend station is   skewed more to weekend / leisure ridership, in contrast to other stations on the South Shore Line which primarily serve Chicago‐bound work trips.  Approximately 400 people who work in downtown Chicago live  in  the market area  for  the South Bend  station  for  the South Shore Line.   Based on  comparable service  patterns  and  travel  times  on  Illinois’  Metra  commuter  rail  serving  exurbs  such  as  Harvard, Ingleside, Kenosha, and Fox Lake, as NICTD  implements planned service  improvements on the South Shore Line, there is expected to be growth in work trip commuters to Chicago as well as shifts in travel mode from car to train. 

4.1.2.4 Real Estate Market Conditions ‐ Residential Sector 

South Bend’s residential market  is  improving. Single family residential sales rose by 25 percent  in the last five years. Another positive  indicator  is that permitted building activity has quintupled  in the  last five years. Multi‐family  residential  inventory  is growing  twice as  fast as  the overall market  rate; one thousand units were delivered since 2012. Rent and occupancy has also been growing steadily. 

Historically, downtown South Bend has relatively low levels of housing; four percent of housing units in a 10‐mile inventory are within one mile of downtown. However, downtown inventory has been growing recently. This has included redevelopment of historic structures and new development such as The Ivy at Berlin Place and East Bank developments. There is potential to add more housing to be more on par with typical levels of downtown housing found in peer cities. 

Page 27: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |19 

The student population presents a stable market segment,  limited only by current university policies governing  when  students  may  live  off‐campus.    There  are  typically  rent  premiums  of  25%+  when students rent by the room instead of by unit. 

Key points related to value and performance in the residential sector include: 

Residential sales volumes are relatively stable in the South Bend area.  Sales prices are rising; the value of permitted building activity has grown significantly in the last 

five years.  St. Joseph County assessor data indicates generally lower residential values west of the river.  A substantial amount of demolition of derelict housing has occurred  in the station areas, with 

new construction activity less common.  Lowest single‐family residential per‐square‐foot housing values  located  in the Amtrak station 

area;  a  limited  number  of  comparable  sales  have  occurred  in  the  Chocolate  Factory  and Downtown station areas. 

Newest  current  housing  stock  is  located  in  the  Chocolate  Factory  station  area,  reflected  in average per‐square‐foot values. 

Lot Coverage is correlated to distance from downtown.  Residential values are fairly stable in the Honeywell station area, but show fluctuations in other 

station areas due to limited data points; values are rising across St. Joseph County. 

4.1.2.5 Real Estate Market Conditions ‐ Office Sector 

South Bend’s office market is stable.   Key points related to value and performance in the office sector include: 

The office inventory is about 6.5 million square feet, with average building size of 12,000 square feet. 

Occupancy is strong, with 92% in 2017.  Rents are highest among peer city markets.  20‐30% of new office space in the region is delivered in the City of South Bend, including 90,000 

square feet since 2010.   Since 2012, there has been negative net absorption (i.e., a surplus) of space, with a current surplus of 311,000 square feet in 2017. 

4.1.2.6 Real Estate Market Conditions ‐ Industrial Sector 

With historic economic concentrations  in Manufacturing, South Bend’s  industrial space base  is  large.  Key points related to value and performance in the industrial sector include: 

The  industrial  inventory  is about 25 million  square  feet, with average building  size of 47,000 square feet, differentiated from peers’ smaller average facilities. 

Occupancy is strong, with 93% in 2017.  Rents are highest among peer city markets.  Over half of new industrial space in the region is delivered in the City of South Bend, including 

1.2 million square feet since 2012, or approximately 200,000 square feet annually.    There  is  positive  net  absorption  of  200,000  to  400,000  square  feet  of  space  annually,  a 

promising outlook. 

Page 28: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |20 

This  correlates  to  consumption  of  approximately  15  acres  of  land  annually  for  industrial purposes.   There are approximately 450‐520 acres of developable  industrial  land remaining  in the City, about a 30 year supply. 

The  Honeywell  station  area  is  the  5th  largest  contiguous  site  suitable  for  industrial development in the City. 

4.1.2.7 Real Estate Market Conditions ‐ Retail Sector 

South Bend’s retail market  is stable.   Key points related to value and performance  in the retail sector include: 

The office inventory is about 11 million square feet, with average building size of 9,500 square feet. 

Occupancy is strong, with 98% in 2017.  30% of new retail space in the region is delivered in the City of South Bend (although 7‐8% more 

recently), including 50,000 square feet since 2010.    There is positive net absorption of annually, a promising outlook. 

4.1.2.8 Real Estate Market Conditions ‐ Hotel Sector 

While  recent  hotel  construction  in  South  Bend  has  slowed,  trends  across  the  larger  South  Bend  / Elkhart, IN market point to significant construction.   South Bend represents about 35% of the market.  Between 2016  and 2017, hotel occupancy  softened  slightly  from 60.4%  to  59.1%, due  to  slower  fall performance  in  2017  and  an  increase  in  supply  (4.2%  annualized  growth)  relative  to  demand  (1.3% annualized growth rate). 

4.1.3 Demand and Development Program 

The development program balances the amount of developable land with the feasible market capture. The programs were development with consideration for building density and parking requirements. 

Table 4‐2. Programmed Use in Developable Acres within a Half‐Mile 

  Residential  Industrial  Retail  Office  Open/Storm Water 

Site 1: Chocolate Factory  50%  15%  5%  0%  30% Site 2: Honeywell (Mixed‐Use)  57%  5%  8%  0%  30% Site 2: Honeywell (Industrial)  40%  15%  5%  0%  40% Site 3: Amtrak  60%  5%  5%  0%  30% Site 4: Downtown  45%  12%  8%  5%  30% Realigned Airport Station  0%  50%  20%  0%  30% Current Airport Station  0%  50%  20%  0%  30% 

 

The  potential  development  program  was  quantified  by  the  approximate  value  associated  with  the proposed development. By estimating demand and determining the value per square foot of each type of  development  (residential,  office,  industrial,  or  retail)  an  overall  estimated  value  of  the  potential development at each station area was determined. Table 4‐3 lists the potential new development value in each station area, delivered over a ten‐year period. 

   

Page 29: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |21 

Table 4‐3. Estimated New Development Value within a Half‐Mile 

  Total Value 

Site 1: Chocolate Factory  $40,230,000 Site 2: Honeywell (Mixed‐Use)  $73,070,000 Site 2: Honeywell (Industrial)  $47,320,000 Site 3: Amtrak  $23,250,000 Site 4: Downtown  $147,810,000 Realigned Airport Station  $17,280,000 Current Airport Station  $24,590,000 

 

4.2 Economic Development Summary The economic development and TOD analysis concluded several points: 

The City of South Bend has captured large shares of tri‐county South Bend market deliveries.   There  is  no  shortage  of  vacant  land near  each  site,  though  conflicts with  airport  operations 

constrain airport alternatives near the airport.  To estimate reasonable caps on demand within a ten‐year horizon, we extrapolate occupancy 

trends and assign appropriate shares of market growth to each station area based on value, and assume no demolition of existing structures. 

1.5 acres allotted to station and related parking (except airport stations).  Two scenarios developed for Honeywell due to site’s unique scale of contiguous parcels and rail 

access.  In the Downtown station area, the City would need to convert surface parking to structure, and 

think about consent decree impacts to development potential. 

4.3 Economic and Fiscal Impacts 

4.3.1 Economic Impacts 

AECOM used the input‐output model developed by IMPLAN to trace how the initial investment would circulate throughout the Indiana economy. The impact analysis is for the construction period only and does not consider operating period impacts. 

Economic impacts can be described as the sum of economic activity within a defined geographic region resulting  from  an  initial  change  in  the  economy.  This  initial  change,  also  referred  to  as  the  direct impact, spurs a series of subsequent indirect and induced activities.  

Direct  Impact  results  from  an  initial  change  in  the  economy  such  as  construction  costs,  the operating revenues from a new business, or jobs created. 

Indirect  Impacts  result  when  the  suppliers  to  the  companies  initiating  the  direct  impacts purchase local goods and services. 

Induced Impacts result from the employees purchasing goods and services for their households from the wages they earn. 

Total Impact is the sum of the direct, indirect, and induced impacts. 

Page 30: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |22 

The indirect and induced impacts are often referred to as the multiplier effect. The size of this depends on  the  region  in which  the  impacts occur and  the nature of  the economy within  the  region.   Larger regions that have most of their needs met locally have larger multiplier effects.  

When comparing alternatives, note that it is the nature of an impact analysis that the higher the input, the higher the output—i.e., the more you spend, the greater the impact. 

 

Table 4‐4.Full Time Equivalent Jobs, 10 Year Development Program 

  Direct Indirect  Induced  Total 

Site 1: Chocolate Factory  530  170  230  930 Site 2: Honeywell (Mixed‐Use)  580  280  270  1,140 Site 2: Honeywell (Industrial)  470  190  210  870 Site 3: Amtrak  470  210  220  910 Site 4: Downtown  1,420  610  660  2,680 Realigned Airport Station  320  90  140  540 Current Airport Station  180  30  70  290 

 

Table 4‐5.Economic Output, 10 Year Development Program 

  Direct Indirect  Induced  Total 

Site 1: Chocolate Factory  $82,200,000   $31,300,000   $30,900,000   $144,400,000  Site 2: Honeywell (Mixed‐Use)  $94,100,000   $41,200,000   $36,200,000   $171,500,000  Site 2: Honeywell (Industrial)  $73,400,000   $30,400,000   $28,100,000   $132,000,000  Site 3: Amtrak  $77,100,000   $33,400,000   $29,200,000   $139,700,000  Site 4: Downtown  $229,900,000   $98,500,000   $87,000,000   $415,300,000  Realigned Airport Station  $48,100,000   $17,700,000   $18,000,000   $83,800,000  Current Airport Station  $23,600,000   $6,000,000   $9,400,000   $39,000,000  

 

4.3.2 Fiscal Impacts 

Fiscal impacts are the measure of change in tax revenues.  In the analysis for this study, the property tax revenue  impact  is not an  incremental  revenue assessment of new revenues from development minus previous revenues at prior use. It is exclusively the estimated property tax revenue generated from new development.  The  revenue  from  (primarily  vacant)  existing  parcels  would  need  to  be  subtracted  to estimate a net fiscal impact. The analysis also does not include the potential uplift to existing developed properties due to investment in the station area. 

Table 4‐6. Property Tax Impacts, 10 Year Development Program 

  Property Tax Revenues  All Tax Revenues   Annual  Cumulative  Annual  Cumulative 

Site 1: Chocolate Factory  $592,000  $5,921,000  $1,540,000  $15,400,000 Site 2: Honeywell (Mixed‐Use)  $856,000  $8,563,000  $1,941,000  $19,410,000 Site 2: Honeywell (Industrial)  $564,000  $5,640,000  $1,411,000  $14,110,000 Site 3: Amtrak  $256,000  $2,556,000  $1,145,000  $11,440,000 Site 4: Downtown  $1,864,000  $18,639,000  $4,515,000  $45,150,000 

Page 31: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |23 

  Property Tax Revenues  All Tax Revenues   Annual  Cumulative  Annual  Cumulative 

Realigned Airport Station  $325,000  $3,251,000  $847,000  $8,798,000 Current Airport Station  $449,000  $4,486,000  $721,000  $7,210,000 

 

4.4 Summary  Table 4‐7 summarizes  the potential  redevelopment programs  in each of  the station areas along with the associated economic and fiscal impacts.  Key points of note include: 

• Station  areas  featuring  large  residential  programs  (Downtown,  Honeywell  Mixed‐Use)  show greatest potential impact due to the higher values and densities entailed. 

• The highest estimated development values are  in Downtown, along with highest capital and construction costs.  

• The Amtrak station area’s modest home values are a challenge for new construction. 

• There  is  limited  land  available  near  the  existing  and  the  proposed  Airport  Station  due  to airport/terminal operations and runway protection zones. 

• Airport land use compatibility proximity would tend to dictate non‐residential/industrial uses in Chocolate Factory, Existing Airport Station, and Proposed Airport Station areas. 

• Real  estate  growth  programs  identified  by  AECOM  for  the  Chocolate  Factory  and  Airport station areas are above  identified  long‐term growth  trajectories. Airport Authority  interest  in cargo‐oriented development could support this growth during this 10‐year horizon. 

 

Table 4‐7. Summary of 10 Year Development Program and Associated Economic and Fiscal Impacts 

 

New Construction 

 (sq. ft.) 

Assessed Value  

(2017 $) 

 Construction Cost   

(2017 $) 

Station Capital Cost  

(2017 $) 

Economic Output  (Year of 

Occurrence $) 

 Tax  Revenue  (Year of 

Occurrence $) 

Site 1: Chocolate Factory 

580,000   $40,230,000  $31,300,000  $44,274,000  $144,400,000  $15,400,000 

Site 2: Honeywell (Mixed‐Use) 

740,000   $73,070,000  $60,580,000  $23,870,000  $171,500,000  $19,410,000 

Site 2: Honeywell (Industrial) 

600,000   $47,320,000  $42,460,000  $23,870,000  $132,000,000  $14,110,000 

Site 3: Amtrak  490,000   $23,250,000  $38,400,000  $31,727,000  $139,700,000  $11,440,000 Site 4: Downtown  1,280,000   $147,810,000  $107,440,000  $102,302,000  $415,300,000  $45,150,000 

Realigned Airport Station  330,000   $17,820,000  $15,040,000  $29,480,000  $83,800,000  $8,800,000 

Current Airport Station  460,000   $24,590,000  $20,710,000  N/A  $39,000,000  $7,210,000 

 

Page 32: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |24 

Table 4‐8  interprets development potential  relative  to potential  investment  in  station‐related capital costs.   

Table 4‐8. Return on Investment Metrics 

  % Station Capital Cost Recovered in 

Est. Tax Revenue 

Economic Impact as % of Station 

Capital Cost 

Site 1: Chocolate Factory  33%  310% Site 2: Honeywell (Mixed‐Use)  77%  684% Site 2: Honeywell (Industrial)  56%  526% Site 3: Amtrak  34%  419% Site 4: Downtown  42%  386% Realigned Airport Station  28%  271% Current Airport Station  N/A  N/A 

 

4.5 Notes on this Economic Development and Impact Analysis Research  This  report  is  based  on  estimates,  assumptions,  information  developed  by  AECOM  from  its independent  research  effort,  general  knowledge  of  the  industry,  and  information  provided  by  third parties. No responsibility is assumed for inaccuracies in data provided by third‐party data source used in preparing or presenting the  report. AECOM assumes no duty  to update the  information contained  in the  report  unless  such  additional  services  are  separately  retained  pursuant  to  a  written  agreement signed by AECOM and the City of South Bend. 

 AECOM’s  findings  represent  its professional  judgment. Neither AECOM nor  its parent  corporations, nor  their  respective affiliates or  subsidiaries make any warranty or guarantee, expressed or  implied, with respect to any information or methods contained in or used to produce this report. It shall not be used in conjunction with any public or private offering of securities, debt, or equity, or instruments of a similar nature where  it may be relied upon to any degree by any person other than the City of South Bend and shall not be used  for purposes other than those  for which they were prepared or  for which prior written consent has been obtained from AECOM.  

 This report was prepared solely for the use by the City of South Bend. No third party may rely on the report unless the third party has executed a  reliance  letter  in which case, this report must be used  in their entirety and not on any abstract, excerpt or summary.  

This  report  may  include  “forward‐looking  statements”.  These  statements  relate  to  AECOM’s expectations, beliefs, intentions or strategies regarding the future. These statements may be identified by the use of words like “anticipate,” “believe,” “estimate,” “expect,” “intend,” “may,” “plan,” “project,” “will,”  “should,”  “seek,”  and  similar  expressions.  The  forward‐looking  statements  reflect  AECOM’s views and assumptions with  respect  to  future events as of  the date of  the  report and are  subject  to future  economic  conditions,  and  other  risks  and  uncertainties.  Actual  and  future  results  and  trends could differ materially from those set forth in such statements due to various factors, including, without limitation,  those  discussed  in  the  report.  These  factors  are  beyond  AECOM’s  ability  to  control  or predict. Accordingly, AECOM makes no warranty or representation that any of the projected values or results contained  in the report will actually occur or be achieved. The report  is qualified  in  its entirety by, and should be considered in light of, these limitations, conditions and considerations. 

   

Page 33: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |25 

5.0 Summary of Alternative Site 1: Chocolate Factory Station 

5.1   Physical and Socio‐Economic Site and Station Area Characteristics 

5.1.1 Capacity for Station Facility and Parking 

This station would be integrated into the site plan for the proposed South Bend Chocolate Factory and Dinosaur Museum attraction. It  is currently  largely a greenfield site and there  is sufficient capacity for the station facilities and parking for commuters. 

5.1.2 Land Needs 

In order to locate a station at the Chocolate Factory attraction, a rail spur would need to be constructed, running  north  of  the  current  alignment.  There  is  enough  land  for  the  alignment  to  be  constructed, though acquisition would be required. 

5.1.3 Commuter Access 

Personal  vehicles  would  likely  be  the  predominant  means  of  access  this  site.  The  site  is  not  very accessible for non‐motorized users, with limited sidewalks and bike paths in the area. Currently, there are no bus routes that serve this site.  Access to the airport would need to be provided with a shuttle or scheduled bus service, which should be coordinated with the SSL schedule. 

Two new at‐grade crossings would be added with the construction of the rail spur north.  

5.1.4 Rail Infrastructure 

Approximately  9,000  feet  of  new  track  would  be  constructed  from  the  main  line  to  the  proposed station. A second  terminal  track would also be constructed at  the station;  it would be approximately 1,000 feet  long. Additionally, a 1,600 foot siding would be added south of the station to handle major events  that  would  be  serviced  by  the  SSL  (such  as  Notre  Dame  football  games).  Additional infrastructure would be required such as a catenary system, railroad signalizing, crossing protection at the  two proposed  street  crossings  and  turnouts  at  each of  the  track  connection points. All of  these infrastructure elements have been accounted for in the capital costs section. 

5.1.5 Socio‐Economic and Environmental Impacts 

There are no schools or parks within a half‐mile of the proposed site. The population that currently lives within a half‐mile of the proposed station  is approximately 180 people. Of this population, 21 percent are  minority,  17  percent  of  these  households  are  below  poverty  and  only  one  percent  of  these households do not have a car. There are no low‐income housing units within a half‐mile of this station. 

5.1.6 Businesses 

There are 11 businesses within a half‐mile of the proposed station site. The business with the  largest number of employees  is Forward Air,  Inc., with 300 employees. Total number of employees at all 11 businesses is approximately 440. 

5.1.7 Crime 

During the six month period from July‐December 2017, four incidents were reported in the station area:  one Violent crime and three Property crimes.  All occurred along the US 20 right‐of‐way.  

5.2 Capital Costs Base  capital  costs  for  Site  1:  Chocolate  Factory  are  estimated  at  $44.3  million.    Cost  controls  for reduced parking and station facilities could lower costs to $40.7 million.   The detailed estimate of cost 

Page 34: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |26 

components  is  presented  in  South  Bend  Station  Alternatives  Feasibility  Study  Tech  Memo  1: Construction Feasibility.   

Table 5‐1. Site 1 Chocolate Factory Station Estimated Capital Costs by Category 

 

FTA Cost Category 

Cost, thousands 

of 2017 dollars 

10  Guideway & Track Elements  $7,537 20  Stations, Stops, Terminals, Intermodal  $7,040 30  Support Facilities: Yards, Shops, Admin.   $776 40  Sitework & Special Conditions  $5,324 50  Systems  $7,636   CONSTRUCTION SUBTOTAL (10‐50)  $28,312 60  ROW, Land, Existing Improvements  $91 70  Vehicles  $0 80  Professional Srvs. (Applies to Cat. 10‐50)  $10,096 90  Unallocated Contingency  $5,775   Total   $44,274 

 

5.3 Operating and Maintenance Costs Annual O&M  costs  for Site  1: Chocolate  Factory  are  estimated  at  $247,430, which would be  shared between NICTD and the Chocolate Factory attraction.   

5.4 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the  Chocolate  Factory  station.  Detailed analysis  is provided  in  the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

5.4.1 Travel Times and Schedule 

Table 5‐2 summarizes travel distance and time characteristics to serve the Chocolate Factory station. 

Table 5‐2. Site 1 Chocolate Factory Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  1.8 miles Travel Time to Pine Road  2.7 min Scheduled Speed to Pine Road  40.8 mph Total Westbound Travel Times to Millennium Station  82 min.‐ 98 min. Total Eastbound Travel Times from Millennium Station  90 min.‐ 97 min. 

 

Figure  5‐1  presents  the  proposed  schedule  to  terminate  SSL  South  Bend  service  at  the  Chocolate Factory development  site. The  site  is  one mile  closer  to Millennium Station  than NICTD’s proposed Airport re‐route, which resulted in approximately two minutes of travel time savings.  

 

Page 35: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |27 

Figure 5‐1. Site 1 Chocolate Factory Station Schedule 

 

 

5.4.1 Ridership 

Table 5‐3 summarizes forecasted ridership at the Chocolate Factory station. 

Table 5‐3. Site 1 Chocolate Factory Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 

2015  4  133  231  1  369  21,549 

2040  4  245  449  0  698  26,663 

 

5.5 Economic Impacts This section presents the analysis of development potential in the Chocolate Factory station area, along with an estimation of economic and  fiscal  impacts.   Detailed documentation of  this  task’s  findings  is contained  in  the  South  Shore  Line  Alternative  Stations  Feasibility  Study:    Task  3:    TOD  and Economic Analysis technical presentation. 

5.5.1 Land Available for Development 

There are 221 acres within a half‐mile that are available for development, as shown  in Figure 5‐3. The cloverleaf  interchange  for US 20 and US 31 consumes a significant portion of  the ½ mile  radius, and limits redevelopment potential relative to the train station as a physical barrier.  The total includes the land  of  the  proposed  Chocolate  Factory  and  Dinosaur  Museum.  It  is  assumed  that  the  sparsely developed  land can be acquired and developed. There are 71 acres available for development within a quarter‐mile of the proposed site. 

The majority of the land available for development is zoned for industrial (150 acres). Thirty‐eight acres are zoned for agriculture and 32 acres are zoned for single family residential (Figure 5‐2). 

WESTBOUND

mp Train 6 8 10 12 18 20 422 424 22 426

1.0 Chocolate Factory* 5:26 AM 6:18 AM 7:07 AM 8:57 AM 11:57 AM 4:07 PM 5:47 PM 6:41 PM 7:49 PM 9:12 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

89.7 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

Elapsed T ime (mins) 85 82 92 98 98 98 40 41 98 38

Number of Stops 8 6 11 15 15 15 2 2 14 2

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

1.0 Chocolate Factory* 5:02 AM 5:57 AM 6:49 AM 8:23 AM 10:19 AM 3:20 PM 5:32 PM 6:20 PM 7:02 PM 8:52 PM

Elapsed T ime (mins) 27 33 33 93 94 95 90 90 97 97

Number of Stops 2 2 2 10 14 15 10 11 15 15

*Eastern Time expressed as Central.

Page 36: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |28 

Figure 5‐2. Site 1 Chocolate Factory Station Area Half‐Mile Zoning 

 Source: City of South Bend 

 

Figure 5‐3. Site 1 Chocolate Factory Station Area Developable Parcels 

 Source: City of South Bend 

 

5.5.2 Development Program and Associated Impacts 

The potential 10 year development program for the Chocolate Factory station area and the associated costs and  impacts are presented  in Table 5‐4.   The program anticipates a mix of production and  flex industrial  uses  to  leverage  proximity  to  the  South  Bend  Airport  and  highway  access.    The  retail component is associated with existing Chocolate Factory property redevelopment plans as presented in 

38.0

150.5

32.0

Agricultural Industrial Single-family

Page 37: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |29 

Fall  2017,  and  is  entertainment/destination  oriented.    In  outlying  areas,  low‐density  single‐family residential is envisioned. 

Table 5‐4. Site 1 Chocolate Factory Station Area Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  50%  50 DU  $11,660,000   

Industrial Development  15%  398,000 sf  $19,970,000   

Retail Development  5%  85,000 sf  $8,600,000   

Office Development  0%  ‐  ‐   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    580,000 sf  $40,230,000   

Development Construction Cost (2017)      $31,300,000   

Jobs Generated (FTE:  direct, indirect, induced)      930 FTE   

Economic Output (10 year, year of occurrence)      $144,400,000 

310% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $15,400,000 

33% station cost recovered  

 

   

Page 38: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |30 

6.0 Summary of Alternative Site 2: Honeywell Station This site is located at Westmoor Street and between Bendix Drive and Sheridan Street, just north of the Honeywell Corporation plant. 

6.1 Physical and Socio‐Economic Site and Station Area Characteristics 

6.1.1 Capacity for Station Facility and Parking 

The  NICTD  South  Bend  Airport  park‐n‐ride  is  projected  to  need  approximately  500  parking  spaces, based  on  ridership  modeling  that  assumed  improved  travel  times.  The  land  requirement  for  this amount of parking  is estimated at approximately five acres.   The Honeywell site could accommodate this number of parking spaces. 

It is assumed that the station would be a similar size to other NICTD stations, approximately 100’ x 50’. The covered platform, which would be a separate NICTD facility, would be approximately 700’ long to accommodate an eight car train, the maximum that would run on this line. An ADA compliant ramp to access the platform would be included on both ends of the platform. 

There is adequate space for these facilities at this location. 

6.1.2 Land Needs 

The parcels where the proposed parking, station and new rail track would be located are all owned by the Honeywell Corporation. Approximately five parcels from Honeywell and some of these would also be partial acquisitions. It is anticipated that no businesses would be displaced and there are no wetlands on the immediate station sites. 

6.1.3 Commuter Access 

Currently, this site is accessible for non‐motorized users. There is a bike lane and sidewalks surrounding the proposed site. Appropriate paths and safety features should be designed to allow for safe crossing to the station. Personal vehicles would  likely be the predominant means of access this site. There are three Transpo bus routes that serve this site.  

There are no new at‐grade crossings that would be added to this location.  

This site is approximately 2.5 miles from the airport via the current SSL alignment.  There is discussion about keeping  the existing  tracks east and north of  the proposed  station  site  in place  for  continued service to the airport, with the Honeywell site representing a new infill station.  Opportunities to expand the frequency of service to the Airport are also being considered, striving to achieve a consistent hourly schedule to serve airport‐bound customers.  Alternately, some type of shuttle service to the airport that is timed to coordinate with SSL trains could be implemented to provide a non‐rail connection. 

6.1.4 Rail Infrastructure 

This  station would use  the  existing  track  alignment  along Westmoor  and add  a  second  track  at  the proposed station to the north. This second station track would extend 1,600 feet east from the station to near Bendix Drive,  to provide additional equipment storage  to handle major events served by  the SSL. The existing track between the proposed station and the connection to the SSL main line would be replaced,  smoothing  the  existing  alignment.  Other  infrastructure  improvements  are  proposed  to include catenary, railroad signaling, and turnouts at track connections. It was assumed that the existing  Sheridan Street grade crossing would closed.    

Page 39: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |31 

6.1.5 Socio‐Economic and Environmental Impacts 

There are approximately 1,350 people that live within a half‐mile of the proposed station area. Of that population, 54 percent are minorities, 37 percent of households are living below the poverty line and 22 percent of households do not have a car. There are also 174 low‐income housing units within a half‐mile of this proposed station. 

There are four schools and one park within a half‐mile of the proposed station. The park is LaSalle Park. The  four  schools  are Success Academy, St.  John  the Baptist Catholic School, Dickenson  Immediate Center and Coquillard Primary Center.  

6.1.6 Businesses 

There are 28 businesses within a half‐mile of the proposed station site. Most of these businesses have less  than  10  employees. The  largest  employers are Honeywell, with approximately  1,500 employees and Coquillard Elementary School with 65 employees. 

6.1.7 Crime 

During the six month period from July‐December 2017, a total of 101 incidents were reported, including 46 Violent, 52 Property and 3 Quality of Life incidents.  

6.2 Capital Costs The capital costs  for  serving  the Honeywell  station are estimated at $23.9 million.   Cost controls  for reduced parking and station  facilities, and  reduced or eliminated  track  realignment and  replacement costs could lower costs to $14.3 million to $19.1 million.  Table 6‐1 summarizes the site costs by major category.  The detailed estimate of cost components is presented in South Bend Station Alternatives Feasibility Study Tech Memo 1: Construction Feasibility.   

Table 6‐1. Site 2 Honeywell Station Estimated Capital Costs by Category  

 

FTA Cost Category 

Cost, thousands 

of 2017 dollars 

10  Guideway & Track Elements  $3,434 20  Stations, Stops, Terminals, Intermodal  $7,040 30  Support Facilities: Yards, Shops, Admin.   $0 40  Sitework & Special Conditions  $3,056 50  Systems  $4,358   CONSTRUCTION SUBTOTAL (10‐50)  $17,888 60  ROW, Land, Existing Improvements  $200 70  Vehicles  $0 80  Professional Srvs. (Applies to Cat. 10‐50)  $3,612 90  Unallocated Contingency  $2,170   Total   $23,870 

 

6.3 Operating and Maintenance Costs Annual  O&M  costs  for  the  Honeywell  station  are  estimated  at  $577,430,  which  would  be  shared between NICTD and the City.   

   

Page 40: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |32 

6.4 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the  Honeywell  station.    Detailed analysis  is provided  in the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

6.4.1 Travel Times and Schedule 

Table 6‐2 summarizes travel distance and time characteristics to serve the Honeywell station. 

Table 6‐2. Site 2 Honeywell Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  2.6 miles Travel Time to Pine Road  2.9 min Scheduled Speed to Pine Road  54.7 mph Total Westbound Travel Times to Millennium Station  82 min.‐ 98 min. Total Eastbound Travel Times from Millennium Station  90 min.‐ 97 min. 

 

Travel times to the proposed Honeywell site on Westmoor Street would result in the schedule shown in Figure 6‐1.  

Figure 6‐1. Site 2 Honeywell Station Proposed Schedule 

 

A variant to the Honeywell station site scenario involved continued use of the current Airport Station. In this  case,  the  alternative  Honeywell  station  would  be  a  new  intermediate  station,  and  the  existing station would remain as the South Bend terminal. Track and alignment changes west of the Honeywell Station site would be implemented, resulting in travel time improvements.  Infrastructure between the proposed Honeywell Station and the Airport Station would remain unchanged and travel times would be the same as is currently provided.  The proposed schedule for this scenario is provided on Figure 6‐2. 

mp Train 6 8 10 12 18 20 422 424 22 426

-2.4 Current Airport Station* 5:14 AM 6:06 AM 6:55 AM 8:45 AM 11:45 AM 3:55 PM 5:35 PM 6:29 PM 7:37 PM 9:00 PM

0.2 Honeywell* 5:25 AM 6:17 AM 7:06 AM 8:56 AM 11:56 AM 4:06 PM 5:46 PM 6:40 PM 7:48 PM 9:11 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

89.7 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

86 83 93 99 99 99 41 42 99 39

Number of Stops 9 7 12 16 16 16 3 3 15 3

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

3.5 Honeywell* 5:03 AM 5:58 AM 6:50 AM 8:24 AM 10:20 AM 3:21 PM 5:33 PM 6:21 PM 7:03 PM 8:53 PM

-2.4 Current Airport Station* 5:14 AM 6:09 AM 7:01 AM 8:35 AM 10:31 AM 3:32 PM 5:44 PM 6:32 PM 7:14 PM 9:04 PM

28 34 34 94 95 96 91 91 98 98

Number of Stops 3 3 3 11 14 15 10 11 15 15

*Eastern Time expressed as Central.

Elapsed T ime (mins) from Honeywell

Elapsed T ime (mins) to Honeywell

Page 41: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |33 

Figure 6‐2. Site 2 Honeywell Station Proposed Schedule, w/ Service to Current Airport Station (2A) 

 

6.4.2 Ridership 

Table 6‐3 summarizes forecasted ridership at the Honeywell station. 

Table 6‐3. Site 2 Honeywell Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 

2015 (2)  70  96  191  26  383  21,579 

2040 (2)  131  172  371  55  729  26,730 

2015 (2A) 71 7 

89 3 

185 5 

0 22 

345 37 

21,577 

2040 (2A) 132 9 

160 5 

357 7 

13 47 

662 68 

26,729 

 

6.5 Economic Development This section presents the analysis of development potential  in the Honeywell station area, along with an  estimation  of  economic  and  fiscal  impacts.    Detailed  documentation  of  this  task’s  findings  is contained  in  the  South  Shore  Line  Alternative  Stations  Feasibility  Study:    Task  3:    TOD  and Economic Analysis technical presentation. 

6.5.1 Land Available for Development 

There are 86 acres within a half‐mile that are available for development, see Figure 6‐4. It  is assumed that the parcels that Honeywell currently owns that are undeveloped can be acquired and developed for TOD. There are 48 acres available for development within a quarter‐mile of the proposed site. 

The majority of  the  land available  for development  is zoned  for  industrial  (63 acres). While  this  land could be acquired and redeveloped as commercial or residential, the City needs to determine whether converting industrially zoned land to commercial or residential is a policy decision that they would like to pursue. 

mp Train 6 8 10 12 18 20 422 424 22 426

-2.4 Current Airport Station* 5:14 AM 6:06 AM 6:55 AM 8:45 AM 11:45 AM 3:55 PM 5:35 PM 6:29 PM 7:37 PM 9:00 PM

0.2 Honeywell* 5:25 AM 6:17 AM 7:06 AM 8:56 AM 11:56 AM 4:06 PM 5:46 PM 6:40 PM 7:48 PM 9:11 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

89.7 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

86 83 93 99 99 99 41 42 99 39

Number of Stops 9 7 12 16 16 16 3 3 15 3

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

3.5 Honeywell* 5:03 AM 5:58 AM 6:50 AM 8:24 AM 10:20 AM 3:21 PM 5:33 PM 6:21 PM 7:03 PM 8:53 PM

-2.4 Current Airport Station* 5:14 AM 6:09 AM 7:01 AM 8:35 AM 10:31 AM 3:32 PM 5:44 PM 6:32 PM 7:14 PM 9:04 PM

28 34 34 94 95 96 91 91 98 98

Number of Stops 3 3 3 11 14 15 10 11 15 15

*Eastern Time expressed as Central.

Elapsed T ime (mins) from Honeywell

Elapsed T ime (mins) to Honeywell

Page 42: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |34 

Figure 6‐3. Site 2 Honeywell Station Area Half‐Mile Zoning 

 Source: City of South Bend 

 

Figure 6‐4. Site 2 Honeywell Station Area Developable Parcels 

 Source: City of South Bend 

 

6.5.1 Development Program and Associated Impacts 

The potential 10 year development program (mixed‐use scenario) for the Honeywell station area and the  associated  costs  and  impacts  are  presented  in  Table  6‐4.    The  development  program  includes industrial  flex uses, shopping center  format  retail and a mix of  residential  types:   dense single‐family homes,  duplexes,  townhomes,  and  low‐rise  apartments.   This  redevelopment  program  represents  a significant change in land uses from the current profile, shifting from the current industrial orientation to a renovation biased more towards a more traditional residential neighborhood.  In addition to private sector  investment,  this  redevelopment  would  need  to  be  supported  with  City  investment  in  local 

7.4 4.9

63.0

3.7 6.7 0.8

Page 43: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |35 

infrastructure (streets, sidewalks, streetscaping, bicycle amenities, water/utilities), maintaining security and community cohesion, and supporting  through administrative and planning actions  (rezoning and creating neighborhood plans.) 

Table 6‐4. Site 2 Honeywell Station Area  Mixed‐Use Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  57%  470 DU  $11,660,000   

Industrial Development  5%  48,000 sf  $19,970,000   

Retail Development  8%  80,000 sf  $8,600,000   

Office Development  0%  ‐  ‐   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    740,000 sf  $73,070,000   

Development Construction Cost (2017)      $60,580,000   

Jobs Generated (FTE:  direct, indirect, induced)      1,440 FTE   

Economic Output (10 year, year of occurrence)      $171,500,000 

684% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $19,410,000 

77% station cost recovered  

 

The potential 10 year development program  (Industrial scenario)  for the Honeywell station area and the  associated  costs  and  impacts  are  presented  in  Table  6‐5.    The  development  program  includes industrial  flex uses, shopping center  format  retail and a mix of  residential  types:   dense single‐family homes,  duplexes,  townhomes,  and  low‐rise  apartments.   This  redevelopment  program  represents  a modest change  in  land uses from the current profile, still allowing  important employment‐generating industrial uses but encouraging more traditional residential neighborhood  infill.    In addition to private sector  investment,  this  redevelopment  would  need  to  be  supported  with  City  investment  in  local infrastructure (streets, sidewalks, streetscaping, bicycle amenities, water/utilities), maintaining security and community cohesion, and supporting  through administrative and planning actions  (rezoning and creating neighborhood plans.) 

   

Page 44: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |36 

Table 6‐5. Site 2 Honeywell Station Area  Industrial Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  40%  220 DU  $11,660,000   

Industrial Development  15%  184,000 sf  $19,970,000   

Retail Development  5%  68,000 sf  $8,600,000   

Office Development  0%  ‐  ‐   

Open Space  40%  ‐  ‐   

Total Value (Assessed Value, 2017)    600,000 sf  $47,320,000   

Development Construction Cost (2017)      $42,460,000   

Jobs Generated (FTE:  direct, indirect, induced)      870 FTE   

Economic Output (10 year, year of occurrence)      $132,000,000 

526% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $14,110,000 

56% station cost recovered  

 

 

 

   

Page 45: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |37 

7.0 Summary of Alternative Site 3: Amtrak Station This  site  is  located  at  the  existing  South  Bend  Amtrak  station  at  2702  West  Washington  near  the intersection of Meade and Washington Streets. 

7.1 Physical and Socio‐Economic Site and Station Area Characteristics 

7.1.1 Capacity for Station Facility and Parking 

The NICTD South Bend Airport Station  is projected to require 500 parking spaces, based on ridership modeling  assuming  travel  time  improvements.  The  land  requirement  for  this  amount  of  parking  is estimated at five acres. The proposed parking at the Amtrak site is six acres, more than enough to meet the demand for parking at the South Bend Airport station. 

The covered platform, which would be a separate NICTD facility, would be approximately 700’ long to accommodate an eight car train, the maximum that would run on this  line.   ADA compliant ramps to access the platform at both ends would be included. The width of the platform would be 15’, following NICTD practice. 

The station would include two terminal tracks on either side of the center platform. 

7.1.2 Land Needs 

The parcels  that would be used  for  this  site are owned by NICTD, Curtis Products  Inc., and Chicago South Shore. It is anticipated that no businesses would be displaced. There are no wetlands are on the immediate station site. 

7.1.3 Commuter Access 

Personal  vehicles would  likely be  the  predominant means of  access  this  site.     However,  this  site  is accessible  for non‐motorized users, with a bike  lane and sidewalks surrounding  the proposed station site  and  through  the  station  area.    Nevertheless,  the  railroad  tracks  and  complex  intersections  of several roads (Meade, Washington, Orange and Bendix on the north side of the tracks, and Meade and Colfax on the south side of the tracks) do not present an  inviting non‐motorized access environment.  Appropriate paths and safety features should be designed to allow for safe crossing to the station.  

There are three Transpo bus routes that serve this site. This site is approximately three miles from the airport. Unlike Site 2, which has the potential to continue to provide direct rail service, this site would require a bus shuttle. 

No new at‐grade crossings would be added to this location.  

7.1.4 Rail Infrastructure 

The existing NICTD/CSSSB tracks serving the site are used to store CSSSB freight cars. The three tracks of varying lengths would need to be shifted to the west a distance of between 1,000 and 1,500 feet.  In addition,  a  new  SSL  track  would  be  constructed  from  the  Main  Line/Airport  Branch  Junction,  near Grandview Avenue, involving an estimated 6,400 feet. A second 1,000‐foot station terminal track would be  added,  which  would  extend  another  1,600  feet  westward  to  store  equipment  for  special  event service. Other  infrastructure  improvements are proposed  to  include  catenary,  railroad  signaling, and turnouts at track connections.    In addition, a 1,000‐foot siding would be added west of the station to service major events. 

7.1.5 Socio‐Economic and Environmental Impacts 

There  are  nearly  2,000  people  who  live  within  a  half‐mile  of  the  proposed  station  area.  Of  that population, 63 percent are minorities, 35 percent of households are living below the poverty line and 21 

Page 46: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |38 

percent of households do not have a car. There are no  low‐income housing units within a half‐mile of this proposed station. 

There are two parks within a half‐mile of the proposed station, Kennedy Park and LaSalle Park. There are no schools within a half‐mile of the proposed station area. 

7.1.6 Businesses 

There are 80 businesses within a half‐mile of the Amtrak site. Most of these businesses have less than 10 employees. The largest employer is Curtis Products Inc., with 250 employees, followed by Kennedy Elementary School with 85 employees. 

7.1.7 Crime 

During the six month period from July‐December 2017, a total of 202 incidents were reported, including 99 Violent, 92 Property and 11 Quality of Life incidents. 

7.2 Capital Costs The capital costs  for Site 3: Amtrak are estimated at nearly $31.7 million.   Cost controls  for  reduced parking and station facilities could lower costs to $28.3 million.  Table 7‐1 summarizes the site costs by major  category.  The  detailed  estimate  of  cost  components  is  presented  in  South  Bend  Station Alternatives Feasibility Study Tech Memo 1: Construction Feasibility. 

Table 7‐1. Site 3 Amtrak Station Estimated Capital Costs by Category  

 

FTA Cost Category 

Cost, thousands 

of 2017 dollars 

10  Guideway & Track Elements  $3,552 20  Stations, Stops, Terminals, Intermodal  $7,040 30  Support Facilities: Yards, Shops, Admin.   $3,559 40  Sitework & Special Conditions  $4,115 50  Systems  $5,759   CONSTRUCTION SUBTOTAL (10‐50)  $24,024 60  ROW, Land, Existing Improvements  $225 70  Vehicles  $0 80  Professional Srvs. (Applies to Cat. 10‐50)  $4,594 90  Unallocated Contingency  $2,884   Total   $31,727 

 

7.3 Operating and Maintenance Costs Annual O&M costs for the Amtrak station are estimated at $577,430, which would be shared between NICTD and the City.   

7.4 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the  Amtrak  station.    Detailed analysis  is provided  in the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

   

Page 47: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |39 

7.4.1 Travel Times and Schedule 

Table 7‐2 summarizes travel distance and time characteristics to serve the Amtrak station. 

Table 7‐2. Site 3 Amtrak Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  3.4 miles Travel Time to Pine Road  3.5 min Scheduled Speed to Pine Road  59.2 mph Total Westbound Travel Times to Millennium Station  82 min.‐ 98 min. Total Eastbound Travel Times from Millennium Station  90 min.‐ 97 min. 

 

The schedule for Site 3: Amtrak Station at Washington and Meade Streets is presented in Figure 7‐1.    

Figure 7‐1. Site 3 Amtrak Station Proposed Schedule 

 

 

7.4.2 Ridership 

Table 7‐3 summarizes forecasted ridership at the Amtrak station. 

Table 7‐3. Site 3 Amtrak Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 

2015   48  76  175  85  384  21,582 

2040   79  139  344  169  731  26,736 

 

   

WESTBOUND

mp Train 6 8 10 12 18 20 422 424 22 426

-0.6 Amtrak* 5:26 AM 6:18 AM 7:07 AM 8:57 AM 11:57 AM 4:07 PM 5:47 PM 6:41 PM 7:49 PM 9:12 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

89.7 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

Elapsed T ime (mins) 85 82 92 98 98 98 40 41 98 38

Number of Stops 8 6 11 15 15 15 2 2 14 2

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

-0.6 Amtrak* 5:00 AM 5:55 AM 6:47 AM 8:23 AM 10:19 AM 3:20 PM 5:32 PM 6:20 PM 7:02 PM 8:52 PM

Elapsed T ime (mins) 25 31 31 93 94 95 90 90 97 97

Number of Stops 2 2 2 10 14 15 10 11 15 15

*Eastern Time expressed as Central.

Page 48: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |40 

7.5 Economic Impacts This section presents the analysis of development potential  in the Amtrak station area, along with an estimation of economic and fiscal impacts.  Detailed documentation of this task’s findings is contained in the South Shore Line Alternative Stations Feasibility Study:  Task 3:  TOD and Economic Analysis technical presentation. 

7.5.1 Land Available for Development 

There are 64 acres within a half‐mile that are available for development, see Figure 7‐3.  It  is assumed that the unimproved parcels currently zoned for industrial can be acquired and developed. There are 22 acres available for development within a quarter‐mile of the proposed site. The parcels at this site are generally not contiguous, making assembly of land for larger developments more difficult. 

Figure 7‐2. Site 3 Amtrak Station Area Half‐Mile Zoning 

 Source: City of South Bend 

 

7.5.1 Development Program and Associated Impacts 

The potential 10 year development program for the Amtrak station area and the associated costs and impacts  are  presented  in Table  7‐4.    The  development  program  includes  a mix  of  residential  types:  dense  single‐family  homes,  duplexes,  townhomes,  and  low‐rise  apartments,  along  with  shopping center  format  retail  and  a  modest  amount  of  employment‐generating  industrial  development compatible with nearby anchor uses.   This redevelopment program represents an ambitious change in land  uses  from  the  current  profile,  but  is  small  in  scale  due  to  depressed  current  values  that  may challenge attraction of  investors.      In addition to private sector  investment, this redevelopment would need to be supported with City development incentives to encourage solvent projects.  The City would also  need  to  make  investment  in  local  infrastructure  (streets,  sidewalks,  streetscaping,  bicycle amenities, water/utilities) to aid  in conversion from the area’s  industrial history, maintain security and community  cohesion,  and  support  administrative  and  planning  actions  (rezoning  and  creating neighborhood plans).   

 

2.3

29.4

0.5 2.5 2.1

27.6

Business Industrial Mixed Use Office Multifamily SF &Duplex

Page 49: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |41 

Figure 7‐3. Site 3 Amtrak Station Area Developable Parcels 

 Source: City of South Bend 

Table 7‐4. Site 3 Amtrak Station Area Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  60%  270 DU  $19,700,000   

Industrial Development  5%  76,000 sf  $1,820,000   

Retail Development  5%  37,000 sf  $1,730,000   

Office Development  0%  ‐  ‐   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    490,000 sf  $23,250,000   

Development Construction Cost (2017)      $38,400,000   

Jobs Generated (FTE:  direct, indirect, induced)      910 FTE   

Economic Output (10 year, year of occurrence)      $139,700,000 

419% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $11,440,000 

34% station cost recovered  

 

 

Page 50: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |42 

8.0 Summary of Alternative Site 4: Downtown South Bend Station This  site  is  at  the  former South Bend Union Station, which  is  located  at  the  south  end of  the  city’s downtown, in a rapidly evolving tech industry area.  

8.1 Physical and Socio‐Economic Site and Station Area Characteristics 

8.1.1 Capacity for Station Facility and Parking 

The proposed station would have the tracks and station running at‐grade on South Street, between the Union Station Technology Center building and the Four Winds Field ballpark. 

Additionally,  there  is  not  enough  space  for  five  acres  of  surface  parking  on  the blocks  immediately adjacent to the proposed station site options, south of South Street and west to Main Street. Additional surface parking might be provided on the block bounded by Lafayette Boulevard, South Street, Main Street,  and  Monroe  Street,  which  is  currently  vacant  although  appears  to  be  well  situated  for redevelopment. Additional underutilized lots and existing surface parking are present in the downtown within a  three  to  ten minute walk of  the  station  site options.   Shared parking with Four Winds Field might also be an option outside of baseball season but not likely year round or for weekday commuters during  baseball  season.  Alternatively,  a  structured  parking  garage  could  be  constructed  nearby  to accommodate the approximately 500 spaces that would be needed to meet the estimated demand of the ridership at the station, consuming a smaller footprint of downtown land than five acres. 

8.1.2 Land Needs 

Parcel  acquisition  would  be  required.  These  parcels  are  owned  by  the  Salvation  Army  of  Illinois, Housing  Authority  of  South  Bend  and  Claey’s  Candy  Factory.  The  Salvation  Army  and  Housing Authority parcels would likely be partial acquisitions. 

8.1.3 Commuter Access 

This  station  is  accessible  by  bike  lanes  and  marked  bike  routes  on  South  Street  and  Lafayette Boulevard. The station area also has a dense network of sidewalks making it accessible to pedestrians. However, personal vehicles will still likely be the primary means of accessing this station. It is assumed that parking would be available adjacent to the station. Nearly all Transpo bus routes run within a half‐mile  of  the  proposed  station.  This  site  is  approximately  five  miles  from  the  airport.    Some  type  of shuttle service to the airport that is timed to coordinate with SSL trains is recommended.  

Two at‐grade crossings would be required, at Meade Street and Olive Street. Crossing protection would need  to  be  configured  to  function  with  the  NS  existing  crossing  systems  at  these  two  locations. Crossing protection for Amtrak passengers crossing the extended SSL line to reach platforms on the NS is included in the estimated costs.   

8.1.4 Rail Infrastructure 

Service  to  this  site would  involve a new SSL main  line  track  from  the SSL Main Line/Airport Branch Junction near Grandview Avenue, a distance of about  three miles. A  segment‐by‐segment  listing of likely improvements is presented in Table 8‐1. 

   

Page 51: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |43 

Table 8‐1. Site 4 Downtown Station Alignment Segment Improvements 

From  To  Dist.  Improvements 

Airport Branch Jct. 

Olive Street  7,600'  This would be the same as for Site 3, building one new track and   extending another  1100' east  from  the Amtrak Station on NICTD or CSSSB‐owned land 

Olive Street  abandoned ROW west of Cherry St. 

3,100'  Acquire a strip of  land from property owners adjacent to the NS, and build one track at grade. Add 2,000’ siding for use by SSL trains serving special events. 

Abandoned ROW west of Cherry St. 

west approach to  Western / Walnut Bridge 

700'  Acquire strip of land and construct ramp (approx. 2.5% grade) to  join elevation of NS to span Western/Walnut  intersection. Build one track. 

Western / Walnut Bridge 450'  A separate bridge would be constructed on the north side of 

the existing NS structure.  

East approach to Western / Walnut Bridge 

West approach to Chapin St. Bridge 

2,300'  Acquire ROW to build one track on embankment that would extend east  to Chapin. Some  retaining wall may be needed.  The Soccer field at the Kroc Complex would be moved to the north, and parking relocated. 

Chapin Bridge 100’  A separate bridge would be constructed on the north side of 

the existing NS structure. 

East approach to Chapin Bridge 

South St. Site  1,300’  Track  would  ramp  down  to  grade  on  land  to  be  acquired.  Scott  Street  viaduct  proposed  for  closure;  the  alignment would follow and replace South Street. The platform and two station  tracks would extend east  to  the north  side of Union Station.   

 

8.1.5 Socio‐Economic and Environmental Impacts 

There  are  approximately  2,400  people  that  live  within  a  half‐mile  of  this  proposed  site.  Of  that population, 62 percent  are minorities,  53 percent of households  are below  the poverty  level  and 62 percent of households do not own a car. Additionally, there are 771 low‐income housing units within a half‐mile of the proposed station. 

The Four Winds Field  is within a half‐mile of  the proposed site and  is  technically a park,  though  it  is privately owned. The Kroc Center  recreational  facility  is  also within  a half‐mile  and  is  also privately owned.  There  are  no  public  parks  within  a  half‐mile  of  the  proposed  site.  There  are  two  day  care facilities within a half‐mile. 

8.1.6 Businesses 

There  are  683  businesses  within  a  half‐mile  of  the  proposed  station.  Approximately  500  of  these businesses have less than 10 employees. The largest businesses are the St. Joseph County of Insurance, U.S. Post Office and the South Bend Police Department. The area just south of Sample Street, east of Prairie Avenue,  is  Ignition Park. This  is  the  site of  the  former Studebaker manufacturing auto plant. Since  2000,  the  state  has  aggressively  reclaimed  this  former  brownfield  site  to  allow  for  the development  of  high‐tech manufacturing,  commercial  and  office buildings  throughout  this business park. Employment at Ignition Park is forecasted to grow, based on conversations with the city. 

8.1.7 Crime  

During the six month period from July‐December 2017, a total of 291 incidents were reported, including 153 Violent, 122 Property and 16 Quality of Life incidents. 

Page 52: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |44 

8.2 Capital Costs The capital costs for Site 4: Downtown are estimated at approximately $102.3 million.  Cost controls for reduced parking and station facilities could lower costs to $98.4 million. Table 8‐2 summarizes the site costs by major category. The detailed estimate of cost components is presented in South Bend Station Alternatives Feasibility Study Tech Memo 1: Construction Feasibility. 

Table 8‐2. Site 4 Downtown Station Estimated Capital Costs by Category 

 

FTA Cost Category 

Cost, thousands 

of 2017 dollars 

10  Guideway & Track Elements  $27,579 20  Stations, Stops, Terminals, Intermodal  $7,040 30  Support Facilities: Yards, Shops, Admin.   $3,785 40  Sitework & Special Conditions  $10,213 50  Systems  $11,928   CONSTRUCTION SUBTOTAL (10‐50)  $60,544 60  ROW, Land, Existing Improvements  $5,400 70  Vehicles  $0 80  Professional Srvs. (Applies to Cat. 10‐50)  $15,898 90  Unallocated Contingency  $20,460   Total   $102,302 

 

8.3 Operating and Maintenance Costs Annual  O&M  costs  for  the  Downtown  station  are  estimated  at  $577,430,  which  would  be  shared between NICTD and the City.   

8.4 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the Downtown  station.   Detailed analysis  is provided  in the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

8.4.1 Travel Times and Schedule 

Table 8‐3 summarizes travel distance and time characteristics to serve the Downtown station. 

Table 8‐3. Site 4 Downtown Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  5.2 miles Travel Time to Pine Road  5.1 min Scheduled Speed to Pine Road  61.1 mph Total Westbound Travel Times to Millennium Station  84 min.‐ 100 min. Total Eastbound Travel Times from Millennium Station  92 min.‐ 99 min. 

 

Figure 8‐1 presents the schedule for Site 4. 

Page 53: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |45 

Figure 8‐1. Site 4 Downtown Station Proposed Schedule 

 

 

8.4.2 Ridership 

Table 8‐4 summarizes forecasted ridership at the Downtown station. 

Table 8‐4. Site 4 Downtown Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 2015  54  69  163  100  386  21,584 

2040  112  122  313  188  735  26,737 

 

8.5 Economic Development This section presents the analysis of development potential  in the Downtown station area, along with an  estimation  of  economic  and  fiscal  impacts.    Detailed  documentation  of  this  task’s  findings  is contained  in  the  South  Shore  Line  Alternative  Stations  Feasibility  Study:    Task  3:    TOD  and Economic Analysis technical presentation. 

8.5.1 Land Available for Development 

There are 83 acres within a half‐mile that are available for development, see Figure 8‐3.  It  is assumed that the  large surface parking and unimproved exempt parcels can be acquired and developed. There are 16 acres available for development within a quarter‐mile of the proposed site.  

WESTBOUND

mp Train 6 8 10 12 18 20 422 424 22 426

-2.4 Downtown* 5:24 AM 6:16 AM 7:05 AM 8:55 AM 11:55 AM 4:05 PM 5:45 PM 6:39 PM 7:47 PM 9:10 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

89.7 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

Elapsed T ime (mins) 87 84 94 100 100 100 42 43 100 40

Number of Stops 8 6 11 15 15 15 2 2 14 2

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

-2.4 Downtown* 5:02 AM 5:57 AM 6:49 AM 8:25 AM 10:21 AM 3:22 PM 5:34 PM 6:22 PM 7:04 PM 8:54 PM

Elapsed T ime (mins) 27 33 33 95 96 97 92 92 99 99

Number of Stops 2 2 2 10 14 15 10 11 15 15

*Eastern Time expressed as Central.

Page 54: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |46 

Figure 8‐2. Site 4 Downtown Station Area Half‐Mile Zoning 

 Source: City of South Bend 

Figure 8‐3. Site 4 Downtown Station Area Developable Parcels 

 Source: City of South Bend 

 

8.5.1 Development Program and Associated Impacts 

The potential 10 year development program  for the Downtown station area and the associated costs and impacts are presented in Table 8‐4.  The development program includes a mix of residential types:  higher density duplexes,  townhomes, and apartments,  retail provided as ground‐floor uses  in mixed‐use multi‐family residential projects, and some office space.  The program also envisions employment‐generating industrial and flex uses south of the railroad tracks building upon the recent transformation of  the high‐tech  incubator and business‐park style  industrial developments.   This program  is  large  in 

4.9 18.0

9.6 0.3 2.4 4.3

36.2

Page 55: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |47 

scale due  to attractive development values and positive current  trends.    In addition  to private sector investment, the City would also need  to continue  its  investments  in greater downtown  infrastructure (streets, sidewalks, streetscaping, bicycle amenities, water/utilities), maintain security and community cohesion, and support administrative and planning actions. 

Table 8‐5. Site 4 Downtown Station Area Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  45%  670 DU  $116,780,000   

Industrial Development  12%  217,000 sf  $12,750,000   

Retail Development  8%  109,000 sf  $12,200,000   

Office Development  5%  52,000 sf  $6,090,000   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    1,280,000 sf  $147,810,000   

Development Construction Cost (2017)      $107,440,000   

Jobs Generated (FTE:  direct, indirect, induced)      2,680 FTE   

Economic Output (10 year, year of occurrence)      $415,300,000 

386% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $45,150,000 

42% station cost recovered  

 

   

Page 56: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |48 

9.0 Summary of Realigned South Bend Airport Station A station  located at  the South Bend Airport but  relocated  to  the west side of  the airport  is currently under study by NICTD and an  independent consultant team  led by DLZ.   This section summarizes the AECOM team’s understanding of designs and service feature for that station alternative.   This section also contains an analysis of development potential in the area around a relocated station in order for all station locations to be compared fully. 

9.1 Physical and Socio‐Economic Site and Station Area Characteristics This analysis assumes implementation of access Alternative G. 

9.2 Capital Costs Estimated capital costs for Alternative G are $29,480,000. 

Table 9‐1. Realigned Airport Station (Alternative G) Estimated Capital Costs by Category 

 

FTA Cost Category 

Cost, thousands of 2017 dollars 

10  Guideway & Track Elements  $4,424 20  Stations, Stops, Terminals, Intermodal  $2,640 30  Support Facilities: Yards, Shops, Admin.   $0 40  Sitework & Special Conditions  $3,854 50  Systems  $7,949   CONSTRUCTION SUBTOTAL (10‐50)  $18,866 60  ROW, Land, Existing Improvements  $3,000 70  Vehicles  $3,769 80  Professional Srvs.  

(Applies to Cat. 10‐50) $25,635 

  SUBTOTAL  $25,635 90  Unallocated Contingency  $3,845 

15%   TOTAL   $29,480 

 

No variations in capital costs were identified because the station platform is minimal and parking is not separate from general airport facilities. 

9.3 Operating and Maintenance Costs Annual O&M costs for a Realigned Airport Station are estimated at $247,430, which would be shared between NICTD and the South Bend Airport.   

9.4 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the  realigned  Airport  station.  Detailed analysis  is provided  in  the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

9.4.1 Travel Times and Schedule 

Table 9‐1 summarizes travel distance and time characteristics to serve the realigned Airport station. 

Page 57: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |49 

Table 9‐2. Realigned Airport Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  2.8 miles Travel Time to Pine Road  5.4 min Scheduled Speed to Pine Road  31.2 mph Total Westbound Travel Times to Millennium Station  84 to 100 minutes Total Eastbound Travel Times from Millennium Station  92 to 99 minutes 

 

Figure 9‐1 presents the schedule for the realigned Airport station. 

Figure 9‐1. SSL Proposed Future Schedule w/Double Track, West Lake and Airport Re‐route 

 

 

9.4.2 Ridership 

Table 9‐2 summarizes forecasted ridership at the realigned Airport station. 

Table 9‐3. Realigned Airport Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 2015  24  60  151  148  383  21,583 

2040  47  108  295  277  727  26,733 

 

   

WESTBOUND

mp Train 6 8 10 12 18 20 422 424 22 426

89.7 So. Bend Airport (west terminal)* 5:24 AM 6:16 AM 7:05 AM 8:55 AM 11:55 AM 4:05 PM 5:45 PM 6:39 PM 7:47 PM 9:10 PM

32.2 Carroll Av (M.City) 6:27 PM 7:22 PM 9:50 PM

0.0 Millennium 6:51 AM 7:40 AM 8:39 AM 10:35 AM 1:35 PM 5:45 PM 9:27 PM

Elapsed T ime (mins) 87 84 94 100 100 100 42 43 100 40

Number of Stops 8 6 11 15 15 15 2 2 14 2

EASTBOUND

mp Train 401 403 405 5 7 9 11 13 15 19

89.7 Millennium 6:50 AM 8:45 AM 1:45 PM 4:02 PM 4:50 PM 5:25 PM 7:15 PM

32.2 Carroll Av (M.City) 4:35 AM 5:24 AM 6:16 AM

0.0 So. Bend Airport (west terminal)* 5:04 AM 5:59 AM 6:51 AM 8:25 AM 10:21 AM 3:22 PM 5:34 PM 6:22 PM 7:04 PM 8:54 PM

Elapsed T ime (mins) 29 35 35 95 96 97 92 92 99 99

Number of Stops 2 2 2 10 14 15 10 11 15 15

*Eastern Time expressed as Central.

Page 58: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |50 

9.5 Economic Development This section presents the analysis of development potential in the realigned Airport station area, along with an estimation of economic and  fiscal  impacts.   Detailed documentation of  this  task’s  findings  is contained  in  the  South  Shore  Line  Alternative  Stations  Feasibility  Study:    Task  3:    TOD  and Economic Analysis technical presentation. 

9.5.1 Land Available for Development 

There are 34 acres within a half‐mile that are available for development, as shown in Figures 9‐2 and 9‐3.  It  is  assumed  that unimproved  exempt  land  can be developed  consistent with  airport operations.  Parcels slated for the new rail alignment are excluded, as is land identified in airport runway protection zone  and/or designated  for  airport operations  in  2010  land use plan. There  are  7  acres  available  for development within a quarter‐mile of the proposed station.   

Figure 9‐2.  Realigned Airport Station Area Half‐Mile Area Zoning 

 Source: City of South Bend 

 

9.5.1 Development Program and Associated Impacts 

The potential 10 year development program for the realigned Airport station area and the associated costs  and  impacts  are  presented  in Table  9‐3.   The development  program  for  the  realigned Airport station  area  is  small  due  to  limited  amounts  of  developable  land  due  to  constraints  from  Airport operations and protection.  Industrial uses reflect a mixture of flex and production facilities capitalizing on airport and highway access.  Some shopping center format retail could be situated on Lincolnway.  

 

1.4

5.3

15.5

12.2

Business Commercial Industrial SF & Duplex

Page 59: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |51 

Figure 9‐3. Realigned Airport Station Area Developable Parcels 

 Source: City of South Bend 

 

Table 9‐4. Realigned Airport Station Area Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  0%  ‐  ‐   

Industrial Development  50%  271,000 sf  $13,200,000   

Retail Development  20%  56,000 sf  $4,620,000   

Office Development  0%  ‐  ‐   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    330,000 sf  $17,820,000   

Development Construction Cost (2017)      $15,040,000   

Jobs Generated (FTE:  direct, indirect, induced)      540 FTE   

Economic Output (10 year, year of occurrence)      $83,800,000 

271% of station capital cost 

Fiscal Impacts  (10 year, year of occurrence)      $8,800,000 

28% station cost recovered  

 

Page 60: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |52 

10.0 Summary of Current South Bend Airport Station The South Bend South Shore Line station is currently located at the South Bend Airport on the east side of  the  terminal.    This  section  also  contains  an  analysis  of  ridership,  travel  times,  and  development potential in the area around the current station in order for all station locations to be compared fully. 

10.1 Physical and Socio‐Economic Site and Station Area Characteristics This  analysis  assumes  the  station  remains  at  the  existing  location,  with  no  improvements  (the  “No Build” alternative). 

10.2 Capital Costs No capital costs are planned for the “No Build” alternative. 

10.3 Rail Operations This  section  summarizes  the  operational  characteristics  of  serving  the  realigned  Airport  station.  Detailed analysis  is provided  in  the South Shore Line Alternative Stations Feasibility Study:   Tech Memo 2: Potential Rail Operations Impacts technical memorandum. 

10.3.1 Travel Times and Schedule 

Table 10‐1 summarizes travel distance and time characteristics to serve the current Airport station. 

Table 10‐1. Current Airport Station Operations Characteristics 

Attribute  Metric Route Length to Pine Road  5.2 miles Travel Time to Pine Road  15.1 min Scheduled Speed to Pine Road  20.7 mph Total Westbound Travel Times to Millennium Station  115 to 160 minutes Total Eastbound Travel Times from Millennium Station  118 to 155 minutes 

 

Figure 10‐1 presents the current 2017 schedule for the present South Bend Airport station.  A schedule for  service  to  the  current  South  Bend  Airport  station  that  does  include  other  South  Shore  Line improvements (e.g., Double‐Track NWI) is not available. 

Page 61: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |53 

Figure 10‐1. Current SSL Schedule (Effective July 2017) 

 

 

10.3.2 Ridership 

Table 10‐2 summarizes current estimated ridership at the present Airport station.  Forecast ridership for 2040  including other planned South Shore Line  improvements and  implementation of the West Lake Extension service, but excluding the South Bend station realignment, is not available. 

Table 10‐2. Current Airport Station Weekday Boardings 

Model Year  Walk Kiss‐n‐Ride 

Park‐n‐Ride  Transfer  Total 

All SSL Station 

Boardings 2015  38  101  146  2  287  12,291 

2040  Not available 

 

10.4 Economic Development This section presents the analysis of development potential  in the current Airport station area, along with an estimation of economic and  fiscal  impacts.   Detailed documentation of  this  task’s  findings  is contained  in  the  South  Shore  Line  Alternative  Stations  Feasibility  Study:    Task  3:    TOD  and Economic Analysis technical presentation. 

10.4.1 Land Available for Development 

There are 63 acres within a half‐mile that are available for development, as shown in Figures 10‐2 and 10‐3. It is assumed that unimproved exempt land can be developed consistent with airport operations.  Land identified in airport runway protection zone and/or designated for airport operations in 2010 land use plan has been excluded from consideration. There are 15 acres available for development within a quarter‐mile of the proposed station.   

WESTBOUND

mp Train 6 14 18 20 22 422 424

0.0 South Bend Airport* 5:00 AM 7:48 AM 11:49 AM 3:45 PM 7:05 PM 8:40 PM 10:30 PM

32.6 Carroll Av (M.City) 8:37 AM 12:33 PM 4:27 PM 7:57 PM 9:35 PM 11:11 PM

90.1 Millennium 6:55 AM 10:28 AM 2:14 PM 6:13 PM 9:36 PM

Elapsed T ime (mins) 115 160 145 148 151 55 41

Number of Stops 6 17 17 17 17 3 3

EASTBOUND

mp Train 401 403 7 9 11 17 19

90.1 Millennium 8:45 AM 12:35 PM 3:57 PM 5:28 PM 7:10 PM

32.6 Carroll Av (M.City) 3:30 AM 6:30 AM 10:27 AM 2:22 PM 7:15 AM 9:04 AM

0.0 South Bend Airport* 4:11 AM 7:11 AM 11:08 AM 3:03 PM 5:55 PM 8:03 PM 9:45 PM

Elapsed T ime (mins) 41 41 143 148 118 155 155

Number of Stops 3 3 17 17 7 16 17

*Eastern Time expressed as Central.

Page 62: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |54 

Figure 10‐2. Current Airport Station Area Half‐Mile Area Zoning 

 Source: City of South Bend 

 

Figure 10‐3. Current Airport Station Area Developable Parcels 

 Source: City of South Bend 

 

10.4.2 Development Program and Associated Impacts 

The potential 10 year development program for the Airport station area and the associated costs and impacts are presented in Table 10‐3.  The development program for the realigned Airport station area is small  due  to  limited  amounts  of  developable  land  due  to  constraints  from  Airport  operations  and 

3.1

10.3

24.7

12.2

Business Commercial Industrial SF & Duplex

Page 63: Line Station Alternatives Feasibility Study Executive Summary

SOUTH BEND SOUTH SHORE LINE STATION ALTERNATIVES FEASIBILITY STUDY   

 Final Draft Executive Summary | April 2018 |55 

protection.   Industrial uses reflect a mixture of flex and production facilities capitalizing on airport and highway access.  Some shopping center format retail could be situated on Lincolnway. 

 

Table 10‐3. Current Airport Station Area Development Program and Associated Impacts 

  Program  Units  Value  Return 

Residential Development  0%  ‐  ‐   

Industrial Development  50%  394,000 sf  $19,150,000   

Retail Development  20%  66,000 sf  $5,440,000   

Office Development  0%  ‐  ‐   

Open Space  30%  ‐  ‐   

Total Value (Assessed Value, 2017)    460,000 sf  $24,590,000   

Development Construction Cost (2017)      $20,710,000   

Jobs Generated (FTE:  direct, indirect, induced)      290 FTE   

Economic Output (10 year, year of occurrence)      $39,000,000  N/A 

Fiscal Impacts  (10 year, year of occurrence)      $7,210,000  N/A