Linac4 Status
description
Transcript of Linac4 Status
1
Linac4 Status
Project Meeting22.06.2010
2
Schedule
Linac construction - commissioningLinac consolidation - improve reliability 10 months?LHC shut-down for Linac4 connection to PSB 8 monthsPSB to ultimate performance, in ppm 8 monthsPS to ultimate performance, in ppm (in parallel)
Possible time lineShut-downs
2014 20152013 2016
- The schedule defined at Chamonix (connection of Linac4 to PSB during the long shut-down 2014/15) is now official.
- However, some modifications (longer PSB start-up period) could come if it is confirmed that the upgrade of PSB to 2 GeV will be done during the same shut-down (and in general we will have to interface the 2 projects).
3
Budgets- Thanks to all WP Holder for providing the new EVM data, which have
been essential for preparing the new budget that went into the MTP. More information during the EVM presentation.
- But: the MTP was not approved by the Council, which asks for some cuts. A new version of the MTP will be prepared during summer, but it is not expected that it will have an impact on Linac4.
4
Technical highlightsPositive side:- The 1st RFQ module (out of 3) has been successfully brazed on May 3rd.
Negative side:- An arc at 45 kV on the source HV insulation has
damaged the insulation and stopped the source since April 12th . Insulation repaired and improved, but RF power supply broken twice trying to restart… new power supply being cannibalized from the 3 MeV modulator, some hope to restart soon…
5
The Linac4 building
The building is taking shape… and shocks people driving along the Weisskopf Road!
Few key numbers:
- Overall floor surface of Linac4 installations = 3’305 m2 (over 4 levels);- Overall floor surface of Linac2 installations = 1’181 m2 (over 5 levels).
Linac4 makes >3 times the energy and can be extended to full-power SPL using only 2.8 times the surface of Linac2 !
7
9
Project Organization
L4 Integration-Installation Committee (J. Coupard)
LINAC4 MANAGEMENT AND COMMUNICATION STRUCTURE – 03/2010
S. Maury (deputy) - Planning, Safety, Integration PS A. Lombardi (deputy) - Linac Beam Performance ? ? ? – Technical Coordinator (interfaces WPs)F. Gerigk - Accelerating StructuresC. Rossi - System Integration, Test Stand , QualityK. Hanke - PSB CommissioningC. Carli - PSB Beam PerformanceR. Garoby – sLHC and SPL
L4 Beam Coordination Committee (S. Maury)
L4 Core Team -Support to
Project Management & Coordination
2.1 Ion Source, LEBT2.2 RFQ2.3 Chopper Line2.4 Acc. Structures2.5 Linac Beam Dynamics
2.7 Beam Instrumentation2.6 RF Systems
2.8 Transfer Line2.9 Magnets2.10 Power Converters2.11 Vacuum Systems2.12 Control Systems
3.1 Booster Injection3.2 PSB Beam Dynamics4.1 Test Stand Operation
5.1 Civil Engineering5.2 Cooling, Ventilation5.3 Electrical Systems
4.2 Transport, Installation4.3 Survey4.4 Linac Commissioning4.5 PSB Commissioning
2.13 Beam Int. devices
Linac4 Workpackages
Linac Beam Dynamics Working Group
(A. Lombardi)
Accelerating Structures Working Group
(F.Gerigk)
3 MeV Technical
Coordination Committee (C. Rossi)
PSB Beam Dynamics Working Group
(C. Carli)
Support to:Budget, EVMAdministrationQuality AssuranceSafety FileRisk Management
Linac4 Project Management M. Vretenar
A&T Sector S. Myers
PSB Commissioning Working
Group(K. Hanke)
10
Safety Organization
BE Department
Project Leader
EN Department
PSO
Project specific safety coordination
General safety coordination
DSO
Workpackage 1 Workpackage 2
Workpackage N
Workpackage 1 Workpackage 2
Workpackage N
TE Department D
SO
Workpackage 1 Workpackage 2
Workpackage N
A&T
Sect
or
Safety Commission
provides advice and information
verifies that industrial standards are applied
(from SAPOCO)
DSO
Line of responsibility
Safety in case of a Project:
- single line of responsibility, going to the DG via supervisors, Groups and Departments (= each Department is responsible for Safety within its own Workpackages). The PSO supports the DPOs (but does not replace them).
- the Project:a. Verifies that safety
requirements are taken into account by the WPs for the entire duration of the project,
b. identifies and takes action for safety issues at the interface between WPs.
The Project provides the time perspective and the global view.
11
Linac4 TSOsSafety during the installation and commissioning phase is verified and coordinated by the TSOs. They are nominated by the DSOs following proposals from the Project.
For Linac4:Phase 1 (2011), installation of general services : EN responsibility.Phase 2 (2012 onwards), machine installation and commissioning: BE responsibility.
Building Description 2011 2012 - 2013 2014 - 2015installation gen. services
installation machine components
commissioning
410 tunnelS. Grillot
(?)400 equipment
hallJ. Marques Balula
400 1-018 1-011 R-003 R-002
CV rooms (Y. Body)
400 1-010 EL substation
(N. Dos Santos)
12
Linac4 – External Contributions
H-source RFQ DTL
45 keV 3 MeV 50 MeV 90 MeV 160 MeV
chopper line CCDTL PIMS transfer line to PSBLEBT
352 MHz 704 MHz
80 m
Chopper line built in a EU Joint Research Activitycompleted
Participation of ESS-Bilbao in DTL construction, agreed and started
Construction of CCDTL in Russia, via an ISTC Project agreed and started
Collaboration agreement with Soltan Institute (Poland) and FZ Julich (D) for PIMS construction, in preparation.
Transfer line vacuum chambers and supports from Pakistan, agreed
Prototype modulator, RF tuners, couplers, waveguides from India, in progress
RFQ RF design, RF amplifiers, modulator construction from French Special Contribution. agreed and started.
Network of agreements to support Linac4 construction – updated June 2010
Agreement with DESY to access drawings of H- sourcecompleted