Linac4 Status

12
Linac4 Status 1 Project Meeting 22.06.2010

description

Linac4 Status. Project Meeting 22.06.2010. Schedule. - The schedule defined at Chamonix (connection of Linac4 to PSB during the long shut-down 2014/15 ) is now official. - PowerPoint PPT Presentation

Transcript of Linac4 Status

Page 1: Linac4 Status

1

Linac4 Status

Project Meeting22.06.2010

Page 2: Linac4 Status

2

Schedule

Linac construction - commissioningLinac consolidation - improve reliability 10 months?LHC shut-down for Linac4 connection to PSB 8 monthsPSB to ultimate performance, in ppm 8 monthsPS to ultimate performance, in ppm (in parallel)

Possible time lineShut-downs

2014 20152013 2016

- The schedule defined at Chamonix (connection of Linac4 to PSB during the long shut-down 2014/15) is now official.

- However, some modifications (longer PSB start-up period) could come if it is confirmed that the upgrade of PSB to 2 GeV will be done during the same shut-down (and in general we will have to interface the 2 projects).

Page 3: Linac4 Status

3

Budgets- Thanks to all WP Holder for providing the new EVM data, which have

been essential for preparing the new budget that went into the MTP. More information during the EVM presentation.

- But: the MTP was not approved by the Council, which asks for some cuts. A new version of the MTP will be prepared during summer, but it is not expected that it will have an impact on Linac4.

Page 4: Linac4 Status

4

Technical highlightsPositive side:- The 1st RFQ module (out of 3) has been successfully brazed on May 3rd.

Negative side:- An arc at 45 kV on the source HV insulation has

damaged the insulation and stopped the source since April 12th . Insulation repaired and improved, but RF power supply broken twice trying to restart… new power supply being cannibalized from the 3 MeV modulator, some hope to restart soon…

Page 5: Linac4 Status

5

The Linac4 building

The building is taking shape… and shocks people driving along the Weisskopf Road!

Few key numbers:

- Overall floor surface of Linac4 installations = 3’305 m2 (over 4 levels);- Overall floor surface of Linac2 installations = 1’181 m2 (over 5 levels).

Linac4 makes >3 times the energy and can be extended to full-power SPL using only 2.8 times the surface of Linac2 !

Page 6: Linac4 Status
Page 7: Linac4 Status

7

Page 8: Linac4 Status
Page 9: Linac4 Status

9

Project Organization

L4 Integration-Installation Committee (J. Coupard)

LINAC4 MANAGEMENT AND COMMUNICATION STRUCTURE – 03/2010

S. Maury (deputy) - Planning, Safety, Integration PS A. Lombardi (deputy) - Linac Beam Performance ? ? ? – Technical Coordinator (interfaces WPs)F. Gerigk - Accelerating StructuresC. Rossi - System Integration, Test Stand , QualityK. Hanke - PSB CommissioningC. Carli - PSB Beam PerformanceR. Garoby – sLHC and SPL

L4 Beam Coordination Committee (S. Maury)

L4 Core Team -Support to

Project Management & Coordination

2.1 Ion Source, LEBT2.2 RFQ2.3 Chopper Line2.4 Acc. Structures2.5 Linac Beam Dynamics

2.7 Beam Instrumentation2.6 RF Systems

2.8 Transfer Line2.9 Magnets2.10 Power Converters2.11 Vacuum Systems2.12 Control Systems

3.1 Booster Injection3.2 PSB Beam Dynamics4.1 Test Stand Operation

5.1 Civil Engineering5.2 Cooling, Ventilation5.3 Electrical Systems

4.2 Transport, Installation4.3 Survey4.4 Linac Commissioning4.5 PSB Commissioning

2.13 Beam Int. devices

Linac4 Workpackages

Linac Beam Dynamics Working Group

(A. Lombardi)

Accelerating Structures Working Group

(F.Gerigk)

3 MeV Technical

Coordination Committee (C. Rossi)

PSB Beam Dynamics Working Group

(C. Carli)

Support to:Budget, EVMAdministrationQuality AssuranceSafety FileRisk Management

Linac4 Project Management M. Vretenar

A&T Sector S. Myers

PSB Commissioning Working

Group(K. Hanke)

Page 10: Linac4 Status

10

Safety Organization

BE Department

Project Leader

EN Department

PSO

Project specific safety coordination

General safety coordination

DSO

Workpackage 1 Workpackage 2

Workpackage N

Workpackage 1 Workpackage 2

Workpackage N

TE Department D

SO

Workpackage 1 Workpackage 2

Workpackage N

A&T

Sect

or

Safety Commission

provides advice and information

verifies that industrial standards are applied

(from SAPOCO)

DSO

Line of responsibility

Safety in case of a Project:

- single line of responsibility, going to the DG via supervisors, Groups and Departments (= each Department is responsible for Safety within its own Workpackages). The PSO supports the DPOs (but does not replace them).

- the Project:a. Verifies that safety

requirements are taken into account by the WPs for the entire duration of the project,

b. identifies and takes action for safety issues at the interface between WPs.

The Project provides the time perspective and the global view.

Page 11: Linac4 Status

11

Linac4 TSOsSafety during the installation and commissioning phase is verified and coordinated by the TSOs. They are nominated by the DSOs following proposals from the Project.

For Linac4:Phase 1 (2011), installation of general services : EN responsibility.Phase 2 (2012 onwards), machine installation and commissioning: BE responsibility.

Building Description 2011 2012 - 2013 2014 - 2015installation gen. services

installation machine components

commissioning

410 tunnelS. Grillot

(?)400 equipment

hallJ. Marques Balula

400 1-018 1-011 R-003 R-002

CV rooms (Y. Body)

400 1-010 EL substation

(N. Dos Santos)

Page 12: Linac4 Status

12

Linac4 – External Contributions

H-source RFQ DTL

45 keV 3 MeV 50 MeV 90 MeV 160 MeV

chopper line CCDTL PIMS transfer line to PSBLEBT

352 MHz 704 MHz

80 m

Chopper line built in a EU Joint Research Activitycompleted

Participation of ESS-Bilbao in DTL construction, agreed and started

Construction of CCDTL in Russia, via an ISTC Project agreed and started

Collaboration agreement with Soltan Institute (Poland) and FZ Julich (D) for PIMS construction, in preparation.

Transfer line vacuum chambers and supports from Pakistan, agreed

Prototype modulator, RF tuners, couplers, waveguides from India, in progress

RFQ RF design, RF amplifiers, modulator construction from French Special Contribution. agreed and started.

Network of agreements to support Linac4 construction – updated June 2010

Agreement with DESY to access drawings of H- sourcecompleted