Linac4 Risk Assessment Criteria and Methodology. Linac4 General Meeting – C. Rossi 11.06.2009...
-
Upload
gavin-jones -
Category
Documents
-
view
214 -
download
2
Transcript of Linac4 Risk Assessment Criteria and Methodology. Linac4 General Meeting – C. Rossi 11.06.2009...
Linac4 Risk Assessment
Criteria and Methodology
Linac4 General Meeting – C. Rossi 11.06.2009
Definitions
• A risk is any event that could produce a change in the project management plan:
• A threat has negative impact• An opportunity has positive impact
• A risk is defined by its probability to occur and by its impact on project objectives.
• Project objectives are:Cost, Time, Scope and Quality
• Scope Availability of the injector• Quality Beam Brightness for LHC
Linac4 General Meeting – C. Rossi 11.06.2009
Objective
• Decide actions and develop strategies to minimize threats (and enhance opportunities).
• Define clear responsibilities for each risk response, which should be accepted by all parties involved.
• Link the risk management activity to all other management processes.
Linac4 General Meeting – C. Rossi 11.06.2009
ToolsThe Risk Management Plan:Provides definitions for roles & responsibilities, for probability and impact of a risk, defines criteria for risk evaluation and possible responses. It defines the processes involved in the risk management activity.
The Risk Response Plan
The Risk Register:Lists the prioritized risks by their “scores”, highlights the risk owners, summarizes risk responses and contingency plans.
OUTPUT
Risk Monitoring and Control
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Management Plan methodology
The risk owner for the RMP is the Linac4 project management, which supervises the implementation of the Risk Response Plan.Work package holders have already minimized risks within their work packages.
First risk identification is performed in a brainstorming session of the Core Team.
The risk analysis will be initially qualitative.Quantitative risk analysis is left to cases with high impact if more information is required to prioritize the response.
The draft of the Risk Register will be submitted to work package holders for feedback.
The Risk Response Plan is revised at least once per year and after that significant project milestones are obtained.
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Management Plan criteria
The project objectives have been benchmarked as follows:
• COST: project overall cost estimate (baseline 2009)
• TIME: project total duration (baseline 2009)
• SCOPE: injector availability (reference to Linac2)
• QUALITY: beam brightness for LHC as compared to Linac2
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Management Plan criteria
Criteria for impact on project objectives:• Impact on Cost: Ic = cost / overall cost• Impact on Time: It = time / total duration• Impact on Scope: Is = Injector Beam uptime after 1 year of operation• Impact on Quality: Iq = enhancing factor to L2 beam brightness.Impact on project objectives:
IMPACT / Project objectives
Cost(%)
Time(yr)
Scope(%)
Quality(L2)
CATASTROPHIC 30 < Ic 2 ≤ It Is< 70 Iq< 0.5
CRITICAL 20 < Ic < 30 It = 1 70 < Is< 90 0.5 < Iq < 1
MARGINAL 5 < Ic < 20 It = 0.3 90 < Is< 98 1 < Iq< 1.5
NEGLIGIBLE Ic < 5 It < 0.1 98 ≤ Is 1.5 < Iq< 2
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Management Plan criteria
The probability for a risk to occur is summarized by four levels:
• HIGH: 50% < P. Several evidences already present.
• MEDIUM: 20% < P < 50%. A few evidences already present.
• LOW: 5% < P < 20%. One simple indication exists.
• VERY LOW: P < 5%. No indications, but still some probability.
The “score” associated to a risk is given by:
S = P x Impact (Ic, It, Is, Iq)
Linac4 General Meeting – C. Rossi 11.06.2009
The Probability and Impact Matrix
CATASTROPHIC CRITICAL MARGINAL NEGLIGIBLE
HIGH MAX MAX IMPORTANT MINOR
MEDIUM MAX IMPORTANT MINOR MIN
LOW IMPORTANT MINOR MINOR MIN
VERY LOW MINOR MIN MIN MIN
Numerical values could be associated to Probability and Impact:• PROBABILITY: HIGH = 4, MEDIUM = 3, LOW = 2, VERY LOW = 1
• IMPACT: CATASTROPHIC = 5, CRITICAL = 3, MARGINAL = 2, NEGLIGIBLE = 1
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Register
RISKREGISTER
Risk ID Risk Label Cat. P Ic It Is Iq S Current response Management decision S’
BE-RF-01 Failure of LEP klystrons to provide 1.3 MW P 3 3 2 2 5 15Acceptance with contingency plan
Include additional klystrons as an option in the contract with the klystron supplier
9
LINAC4 PROJECT
Excel file summarizing information on identified risks:
It may contain also:• Indication of common risk causes;• Triggers for contingency plans;• Responsibilities for risk responses.
Linac4 General Meeting – C. Rossi 11.06.2009
The Risk Response PlanThe activity of Risk Response Planning concerns:• planning interventions to reduce the risk to a project• developing and enlisting a series of options in hopes of reducing any
threats that may exist to the predefined project objectives.
Possible responses to a risk:• AVOIDANCE: change the project plan to avoid the threat or reduce the scope of the
project• ACCEPTANCE:
• Active Acceptance: a contingency plan is developed should the risk occur• Passive Acceptance: no action required
• MITIGATION: reduce the consequences of a threat. Reduce the probability of the event• TRANSFER: transfer the risk to a third party that has more suitable means to face it.
Linac4 General Meeting – C. Rossi 11.06.2009
Risk Monitoring and ControlThe activity of Risk Monitoring and Control concerns:• Updating the Risk Register;• Reviewing the risk responses and evaluating their effectiveness;• Integrating the risk management activities into the management process.
RiskMonitoring
&Control
Qualitative / Quantitative
Risk Analysis
Risk Register
RiskIdentification
RiskResponsePlanning