Linac4 connectionWork to be done and draft planning
JBL-12/09/2013
![Page 2: Lina c4 connection Work to be done and draft planning](https://reader035.fdocuments.net/reader035/viewer/2022062516/56812c00550346895d907240/html5/thumbnails/2.jpg)
JBL - 12/09/2013
2 different areas.
• LBE line upgrade
• Linac2/Linac4 interface
![Page 3: Lina c4 connection Work to be done and draft planning](https://reader035.fdocuments.net/reader035/viewer/2022062516/56812c00550346895d907240/html5/thumbnails/3.jpg)
JBL - 12/09/2013
Linac4/Linac2 interfaceWhat to be done?
1. Shielding wall2. Emergency exit3. Château4. Chicane
![Page 4: Lina c4 connection Work to be done and draft planning](https://reader035.fdocuments.net/reader035/viewer/2022062516/56812c00550346895d907240/html5/thumbnails/4.jpg)
JBL - 12/09/2013
Linac4/Linac2 interface
ID Tasks Estimated time1 Removal of beam line between Linac2 and BHZ.20 1 week
2 Drill an emergency exit door in Linac2 wall 2 weeks
3 Construction of the Château 1 week
4 Build the chicane in L2 tunnel 1 week
5 Shielding wall –bdg 363 3 weeks
6 Installation of remaining TL (vertical step to BHZ.20) (after 3) 3 weeks
7 Modification of L2 access door (after 4) 1 week
![Page 5: Lina c4 connection Work to be done and draft planning](https://reader035.fdocuments.net/reader035/viewer/2022062516/56812c00550346895d907240/html5/thumbnails/5.jpg)
JBL - 12/09/2013
LBE upgradeID Tasks Estimated time1 Cool down--- Is it needed? 2 weeks
2 Removal of Linac2 LBE 1 week
3 Installation of Linac4 LBE line, dump and shielding 3 weeks
![Page 6: Lina c4 connection Work to be done and draft planning](https://reader035.fdocuments.net/reader035/viewer/2022062516/56812c00550346895d907240/html5/thumbnails/6.jpg)
JBL - 12/09/2013
Draft Planning• 4 weeks for hardware and beam commissioning (very conservative considering the TL will have been
already commissioned up to the debuncher (H- stripping test stand). Week 1 2 3 4 5 6 7 8 9 10 11 12
Linac2/Linac4 interfaceLine removal up to BHZ.20Emergency exit doorChâteauChicaneShielding wallInstallation of TL and BHZ.20L2 access doorLBECool down?Removal of L2 LBEInstallation of L4 LBEBeam commissioning
Beam OK to PSB
• Time needed for the L2/L4 : 7 weeks• Time needed for LBE : 4 weeks (cool down not taken into account!).• Beam could be delivered to PSB 11 weeks after the Linac2 shut down.• Work in the LBE area cannot be done if ions in the PS.• If an ion run right after Linac2 shutdown, no cool down time necessary for the LBE work.