Light Rail Transit
description
Transcript of Light Rail Transit
Light Rail Transit
Central Corridor
DBE&
Workforce InclusionReports
CCLRT DBE/AA Joint Oversight Committee MeetingFebruary 21, 2013
DBE AchievementProfessional ServicesLight Rail
Transit
Central Corridor
Contractor Contract Description
Amended Contract
$ DBE Goal Contract Payments to
Date
$ DBE to Date % DBE of Contract
Payments to Date
Cumulative work done
thru
AECOMPE, APE and
FD (17% goal)
$112,175,175 $19,069,780 $102,185,520 $18,253,155 17.86% 10/26/12
MnDOTProperty
Services (15% goal)
$1,314,592 $197,189 $694,239 $81,278 11.71% 5/8/2012
2
DBE AchievementConstruction (15% goal)
Contractor Bid Pack Amended Contract $ DBE Goal
Contract Billings to
Date
$ DBE Payments to
Date
% DBE of Contract
Payments to Date
Cumulative work done thru
Ames/McCrossan Civil West $120,505,689 $18,075,853 $118,876,161 $18,692,696 15.72% 12/15/2012
Walsh Civil East $220,795,717 $33,119,358 $212,959,563 $36,898,001 17.33% 11/25/2012
Aldridge/Collisys Systems $89,060,808 $13,359,121 $44,531,321 $4,554,562 10.23% 11/31/2012
PCL OMF $47,520,795 $7,128,119 $37,710,454 $3,163,426 8.39% 11/25/2012
Carl Bolander AUR $13,768,232 $2,065,235 $13,768,202 $1,631,238 11.85% 10/21/2011
Graham ATI $4,246,305 $636,946 $4,246,312 $686,532 16.17% 11/3/2011
3
Workforce Inclusion
TOTAL HOURS AS OF 1/31/2013
(-/+) indicates change from previous month
Contractor Total hours Minority hours Minority % Women hours Women %
Walsh 1,092,037.13 206,056.99 18.87(+.02) 66,822.25 6.12 (-.01)
AMJV 486,842 103,262 21.2% (+.1) 39,579 8.1% (+.1)
PCL 200,101.55 36,537.35 18.26%(-.52) 16,340.60 8.17% (+.02)
ACJV 68,456.25 9,497.75 13.87%(+.18) 44,558.75 6.66% -.25)