Lifting plan

20
Crane Lifting Plan LIFTING OPERATION METHOD STATEMENT/LIFT PLAN & RISK ASSESSMENT DETAILS FOR THE PROVISION OF A LIFT OPERATION IN COMPLIANCE WITH BS7121 PARTS 1 & 3 AND LOLER REGULATIONS Please tick as appropriate: Completed by appointed person for crane hired by Weston Homes, or Completed by contractor who has hired a crane as part of their work Client Weston Homes Plc Project Site Address Date of Operation Time on Site Client/Site Contact Contact Number Appointed Person Contact Number Appointed Person’s Acceptance of Responsibilities: I confirm that the lifts in the Method Statement have been planned and will be carried out in accordance with current legislation and British Standard 7121 and that I accept responsibility for the preparation of this Method Statement and Risk Assessment. I accept that it is my responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately briefed on the contents of this Method Statement. Signed Date CONTENTS Page Page Introduction 28 Crane Set Up Procedure 37 General Conditions 29 Lift Procedure 37 Weather Conditions 29 Crane De-Rig Procedure 39 Ground Conditions 29 On Site Changes 39 Operation Outline 30 Risk Assessment 40 Site Details 31 Site Register & Toolbox Talk 43 Load & Radius Details 32 Drawings Attached Crane & Lift Information 34
  • date post

    13-Sep-2014
  • Category

    Engineering

  • view

    568
  • download

    29

description

Lifting plan for over 10ton

Transcript of Lifting plan

Page 1: Lifting plan

Crane Lifting Plan

LIFTING OPERATION METHOD STATEMENT/LIFT PLAN & RISK ASSESSMENT

DETAILS FOR THE PROVISION OF A LIFT OPERATION IN

COMPLIANCE WITH BS7121 – PARTS 1 & 3 AND LOLER REGULATIONS

Please tick as appropriate: Completed by appointed person for crane hired by Weston Homes, or Completed by contractor who has hired a crane as part of their work

Client Weston Homes Plc

Project

Site Address

Date of Operation

Time on Site

Client/Site Contact

Contact Number

Appointed Person

Contact Number

Appointed Person’s Acceptance of Responsibilities: I confirm that the lifts in the Method Statement have been planned and will be carried out in accordance with current legislation and British Standard 7121 and that I accept responsibility for the preparation of this Method Statement and Risk Assessment. I accept that it is my responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately briefed on the contents of this Method Statement.

Signed Date

CONTENTS

Page Page

Introduction 28 Crane Set Up Procedure 37

General Conditions 29 Lift Procedure 37

Weather Conditions 29 Crane De-Rig Procedure 39

Ground Conditions 29 On Site Changes 39

Operation Outline 30 Risk Assessment 40

Site Details 31 Site Register & Toolbox Talk

43

Load & Radius Details 32 Drawings Attached

Crane & Lift Information 34

Page 2: Lifting plan

1 INTRODUCTION

1.1 It is the aim of this Method Statement to define and describe the equipment and safety procedures which are to be employed by the crane lifting company to carry out the lifting operation. The operation will be carried out in accordance with the following Legislation & Approved Codes of Practice.

BS7121 Safe Use of Cranes (part 1) 2006 General & (part 3) 2000 Mobile Cranes

Lifting Operations & Lifting Equipment Regulations 1998 (LOLER)

Health & Safety at Work Act 1974 - Provision and Use of Work Equipment Regulations (PUWER) 1998

Manual Handling Operations Regulations 1992 - Noise at Work Regulations 2006

Control of Substances Hazardous to Health Regulations 2002 (COSHH)

Construction Design and Management Regulations 2007 - Working at Height Regulations 2007

1.2 THE LIFT The lift will be carried out in line with the guidance contained in BS7121.

1.3 SITE INSPECTION The Appointed Person shall carry out a detailed site inspection to ascertain the full requirements of the Site Manager and determine the required crane capacity and make an assessment as far as possible/practicable of any other site issues such as access, ground conditions, overhead obstructions, local authority interaction etc.

1.4 THE APPOINTED PERSON The Appointed Person who has prepared the Method Statement carries full responsibility for the safe completion of all works carried out during the operation. It is the responsibility of the Appointed Person to ensure that the Crane Supervisor is adequately briefed on the contents of this Method Statement.

1.5 THE CRANE SUPERVISOR Prior to the commencement of the works, the Crane Supervisor must ensure that all site personnel are adequately briefed on the contents of this Method Statement. This briefing shall take the form of a short ‘Toolbox Talk’. The Crane Supervisor must liaise with the Appointed Person should site circumstances require material change to the methods to be employed during the operation.

1.6 THE CRANE OPERATOR or OPERATORS All lifting operators or any operators working on behalf of the lifting company shall be fully trained and competent on the machines they operate and will have undergone full manufactures induction and training.

1.7 PERSONNEL All lifting personnel or any personnel working on behalf of the lifting company will be fully trained and hold the relevant certification for the role they undertake on the day of operation. Any non lift company personnel or personnel supplied by the client that will be involved in the lifting operation and taking on a specified role will be required to produce the relevant certification to the Appointed Person or Crane Supervisor prior to the commencement of the operation. Failure to produce the required certification will result in the suspension and possible cancellation of the lifting operation.

1.8 PERSONAL PROTECTIVE EQUIPMENT All lifting personnel will be supplied with standard PPE which consists of, Hard Hat, Safety Boots, Overalls, Gloves, Hi-Vis (and Safety Goggles if required). The Site Manager must inform all Personnel of any specific requirements in advance of the operation date.

1.9 CERTIFICATION Copies of statutory test certification and inspection reports will be available for inspection prior to the lifting operation taking place.

Page 3: Lifting plan

2 GENERAL CONDITIONS

2.1 The Site Manager will provide details of all items to be lifted, including weights, dimensions and any specific lifting tackle requirements. The Site Manager is responsible for the structural integrity of all loads to be lifted including any specified lifting points or slinging recommendations.

2.2 The Site Manager must ensure safe access to and egress from site for all lifting personnel and vehicles, and also ensure that the working area is clear of all obstructions to allow the safe assembly and working of the crane. The Site Manager will be responsible for supplying suitable floodlighting where necessary or when required. The Site Manager must carry out any enabling works required prior to crane arrival.

2.3 The Site Manager must ensure that the area where the crane is to stand/operate is firm and level and this it is capable of withstanding the expected loadings that will be imposed upon it.

2.4 The Site Manager must ensure that any Traffic Management (not supplied by the lift company) is in place prior to the positioning of the crane.

2.5 Any personnel not directly concerned with the lift must be kept out of the crane assembly and working area. The working area should be cordoned off with barrier tape, temporary fencing or otherwise secured, to prevent non lift associated personnel or the general public from entering the lifting area.

2.6 The Crane Supervisor shall make himself known to all relevant personnel on site, and conduct a ‘Toolbox Talk’ prior to commencing operations. The Site Manager should arrange for a site specific induction for the lifting personnel prior to the commencement of work. The Site Managers Site Risk Assessment, which identified any site hazards should be made available and brought to the attention of the lifting personnel.

2.7 All cranes to be left unattended for a period, shall be left in safe condition (jib retracted or laid down if possible), with not load on the crane hook. Cranes shall be shut down and isolated as per manufacturer’s instructions, secured and locked. Under no circumstances shall the crane be moved for lifting purposes if not under the instruction of the Crane Supervisor.

2.8 In the event that specified cranes or lifting tackle, cannot be supplied on the day of operation due to operational issues, breakdown or any unforeseen circumstances. The lift company has the discretion to supply cranes or equipment that is of a suitable alternative to that detailed in this Method Statement, (at no extra cost to the client). In the event of this situation arising, the Appointed Person and the Site Manager will be notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors or safety within this method statement.

3 WEATHER CONDITIONS

3.1 In the event of extreme weather conditions the lift company may need to suspend the lifting operation until such time as it is safe to proceed. Although the safe workable wind speed varies from crane to crane, as a guide, the maximum wind speed at which lifting operations can take place is 10 metres per second, (22mph). In the event that man riding duties are required the maximum workable wind speed reduces to 7 metres per second, (16mph).

Please note that local conditions and the safety of personnel may dictate the Crane Supervisor and Crane Operator have to suspend lifting operations at a lower wind speed than specified in this Method Statement. In addition, lifting operations must stop during storms or when there is a risk of lightning strikes.

4 GROUND CONDITIONS

4.1 The lift company will endeavour to advise the client regarding ground conditions, after a visual inspection (or where necessary/provided, perusal of a client ground survey report) and supply suitable plates, mats where required. The Client is required to advise the lifting company of any known underground services, voids or vaults as state in BS7121. Safe Use of Cranes.

Page 4: Lifting plan

5 OPERATION OUTLINE

5.1 LIFT CLASSIFICATION

LIFT CLASSIFICATION

Basic Lift Standard Lift Complex Lift

Full Contract Lift Supervisor Only Contract Lift

Note:

If a “Supervisor Only Contract Lift” is the chosen option, it is imperative that any personnel supplied by the client, be fully trained, competent and experienced in lifting operations and hold current, valid and legislatively required certification, which must be available for our Appointed Person or Crane Supervisor to inspect prior to commencement of the lifting operation.

Any personnel supplied by the Site Manager must work under the instruction of the Appointed Person or Crane Supervisor. Failure to comply with the above will results in the suspension of lifting until the aforementioned is adhered to.

5.2 PERSONNEL

The following numbers of personnel for this lift are needed:

Crane Operator Crane Supervisor

Slinger/Signaller

5.3 COMMUNICATIONS

Communications between the lifting crew and Crane Operator/s shall be maintained by means of

Two-Way Radios Supplied

by the Crane Company

Two-Way Radios

Supplied by Site Manager

Hand Signals

5.4 WEATHER CONDITIONS

Maximum Workable Wind Speed for

the Crane is:

Weather forecast to be obtained on morning of lift, confirming wind direction and strength. Wind speed forecast 15.6mph.

Guide: 10 metres per second (22mph) for load lifting. 7 metres per second (16mph) for man riding duties.

5.5 BRIEF SCOPE OF WORK/NOTABLE FEATURES OF THIS LIFTING OPERATION

Page 5: Lifting plan

6 SITE DETAILS

6.1 ENABLING WORKS Any enabling works discussed and agreed to at the site inspection, should be carried out prior to arrival of the crane.

Are any enabling works required

6.2 ACCESS & EGRESS

The Site Manager shall ensure that the crane and all associated vehicles have safe and unimpeded access and egress to and from site.

Details of site access & egress

6.3 GROUND CONDITIONS – including any underground services, voids or vaults.

Details of ground conditions

6.4 OVERHEAD CABLES, OBSTRUCTIONS OR REGULATIONS & ANY SLEWING RESTRICTIONS

Details of any overhead or slewing restrictions

Page 6: Lifting plan

6.5 TRAFFIC AND PEDESTRIAN MANAGEMENT

Traffic Management Required Pedestrian Management

Required

Arranged by

Details of any Restrictions & Local Authorities Concerned

7 LOAD & RADIUS DETAILS

7.1 LOAD DETAILS (to be provided by The Site Manager) In the event of there being multiple lifts of different weights and dimensions, only the details of the maximum required lifts will be shown.

Description Dimensions Weight

7.2 LIFTING POINTS

It is the Site Managers/Plant Managers responsibility to ensure that any manufactured Lifting Points are certified & tested for lifting purposes. This also applies to specified slinging methods where no lifting points are provided.

Does the load have Manufactured Lifting Points or Manufacturer guidance for the method of lifting that has been approved for use by the Site Manager?

If “No” to the above: Has the Appointed Person assessed and agreed a method of slinging with the Site

Manager?

Has the Centre of Gravity been taken into account for all proposed lifts?

Have the lifting points and/or the lifting method been approved for use by the Appointed Person?

Page 7: Lifting plan

7.3 LIFTING TACKLE

Please Note: In the event that the specified lifting tackle cannot be supplied on the day of operation due to operational changes, breakdown or any unforeseen circumstances. The crane company can supply and use lifting tackle/equipment that is of a suitable alternative to that detailed above. In the event of this situations arising, the Appointed Person and Site Manager should be notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors of safety within this Method Statement.

All Lifting Tackle certification to be available on site. The Crane Supervisor shall inspect all Lifting Tackle prior to each use.

Any Lifting Tackle supplied by the Site Manager to be fit for purpose, fully certified and in good condition. Any damaged tackle shall be marked “Not For Use” and returned to the depot for disposal. Nylon Slings must be protected from sharp edges using sling guards or suitable packaging.

7.4 CALCULATED MAXIMUM LIFT WEIGHTS In the event of there being multiple lifts of different weights, only the details of the maximum required lift/s will be shown.

Weight of Load

Weight of Hook Block

Weight of Lifting Tackle

Weight of Fly/S-Lift on Boom

7.5 CALCULATED MAXIMUM RADIUS

Maximum Required Radius

7.6 MAXIMUM CALCULATED LIFTS

Gross lift weight

In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum loads, see below:

Maximum required radius

Gross Lift Weight

To be lifted to a radius of

Weight to be lifted at max radius

Page 8: Lifting plan

8 CRANE & LIFT INFORMATION

8.1 CRANE/S DETAIL

CRANE

Crane (make & model)

Registration and/or Plant No.

4 Yearly Test and Thorough Examination

12 Month Thorough Examination (6 Months

if Crane is used for Lifting People)

Weekly Crane Inspection

YES NO

Certificate Expiry Date YES NO

8.2 REQUIRED WEIGHT & RADIUS

Gross Lift Weight

Required Radius

SWL of Crane at Required Radius

Safety Margin

In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum loads, see below:

LOAD

Maximum Required Radius

Gross Weight at Max Radius

SWL of Crane

Safety Margin

8.3 OUTRIGGER LOADINGS & MATS

Outrigger Point Load

Mat Size

Mat Area Provided

Please Note that the Site Manager is responsible for ensuring that the ground conditions are suitable to accept the above loadings and pressures.

Page 9: Lifting plan

REGISTER OF LIFTING EQUIPMENT – TO BE COMPLETED BY CRANE SUPERVISOR

Project:

Lifting equipment (e.g. chains or strops)

Description ID No. / Reg.

Supplier: Test Cert. Expiry Date:

12 Monthly Thorough Examination Expiry Date:

Used for lifting persons? Y/N. (If so, 6 Monthly Thorough Exam’n?)

Weekly Inspections carried out by:

Page 10: Lifting plan

THIS PAGE IS INTENTIONALLY BLANK

Page 11: Lifting plan

CRANE & LIFT INFORMATION (Continued)

9 CRANE SET UP PROCEDURE

THE CRANE TEAM

Crane Supervisor: CITB CTA Card Expiry Date:

Appointed Person:

Slinger/Signaller(s): CITB CTA Card Expiry Date:

Crane Driver:

9.1 The crane, together with the associated operating crew will arrive on site at the specified and agreed date and time.

9.2 Crane Supervisor will meet the Site Manager and carry out “Toolbox Talk” with all personnel involved in the lifting operation. Once this has been completed, all involved in the lifting operation must sign the register for this Method Statement. Any site inductions that are required will also be carried out.

9.3 Any traffic management, ancillary pans, mats or temporary roadways etc that are required to be positioned by hi-ab or other means, prior to the crane or cranes manoeuvring into position, will be done under the instruction of the Crane Supervisor.

9.4 The crane will then manoeuvre into position as shown on attached drawing. All manoeuvring to be carried out under the guidance of a member of the lifting crew.

9.5 The crane will then commence set-up procedure and rig to the configuration stated in section 8.1. All

personnel assisting with rigging will be under the guidance of the crane operator, at all times. The set-up procedure will be carried out as per crane manufactures manual.

9.6 Upon completion of the rigging procedure, the crane operator will carry out procedural safety and computer checks, implementing any specific operational requirements, i.e. slewing restrictions, short rig configurations or fly jib configurations.

9.7 The Crane Supervisor will then carry out a radio communications check between the crane operator and the lifting crew.

9.8 Hook block of crane will then be lowered and required lifting tackle placed on the hook, Lift Supervisor will ensure that the correct lifting tackle has been selected.

9.9 The crane operator will then be instructed to hoist lifting tackle clear of any obstructions and position the crane ready for the first required lift. Any delivery/removal vehicles will now be positioned adjacent to the crane as per attached drawings, ready for work to commence.

10 LIFTING PROCEDURE

10.1 Slinger/Signallers will issue instructions via hand signals or two-way radios to the crane operator to position the crane over first required lift, Slinger/Signallers will plumb the boom head, directly over the load or set short to allow for jib deflection where necessary.

Page 12: Lifting plan

10.2 The Slinger/Signallers will instruct crane operator, the lower the hooks with lifting tackle to allow Slinger/Signaller to attach lifting tackle to load.

LIFTING PROCEDURE (Continued) 10.3 All slinging will be carried out by fully trained, certificated and experienced slingers.

Slinging methods adopted will be as specified by load manufacturers, using specified lifting points or, in the event that no manufacturer instruction or lifting points are provided, our Slingers will work to the Appointed Persons recommendations and to Health & Safety executives guidelines for safe slinging for lifting loads, (see section 7.2 & 7.3). The lifting tackle used, will be as stated in section 7.3 and will have current test certification available.

10.4 Upon completion of the attachment of the lifting tackle to the load, the Slinger/Signaller will instruct the operator by hand signals or radios, to hoist up to take the slack out of the lifting tackle. Once the lifting tackle has started to take the weight and has tightened the Slinger/Signaller will instruct operator or operators to stop hoisting. The Slinger/Signaller will then carry out a check around the load to ensure that the lifting tackle is sitting correctly, angled correctly and also check any lifting points for security and correct operation.

10.5 Once lifting tackle check has been carried out the Slinger/Signaller will instruct the crane operator or operators, to hoist the load to a height that allows the lifting tackle to take the full weight of the load and again instruct the operator to stop hoisting when the load is just airborne to allow a final check of the lifting tackle and lifting points and also check the structural integrity of the load.

10.6 Once the Slinger/Signaller is confident that the lifting tackle and the load are secure, any tag lines that may be required will be attached to the load. Instructions will then be given to the crane operator or operators to hoist the load clear of any obstructions, ensuring that any site specific risks are monitored throughout the hoisting procedure.

10.7 Once the load is clear of all obstructions, the Slinger/signaller will give instructions to the crane operator to manoeuvre the load as required for railing, or manoeuvre to the required landing area for single crane lifts.

10.8 In the event that the landing area is at a different level or should access not permit, the Slinger/Signaller will pass control of the crane signalling to a second strategically placed Slinger/Signaller at the landing area.

10.9 The landing area Slinger/Signaller will then commence giving instructions to the crane operator or operators to manoeuvre and lower the load to the required landing point, ensuring that any site specific risks are monitored throughout the landing procedure.

10.10 The Slinger/Signaller will guide the load to the correct orientation as the load becomes contactable by hand or by attached tag lines.

10.11 The Slinger/Signaller will instruct the crane operator to lower the load to just above the landing position and then instruct the operator to stop lowering to allow the Site Manager to confirm position and orientation of load prior to landing.

10.12 Once the position is confirmed by the Site Manager, the Slinger/Signaller will instruct the operator to slowly lower load into position. Once landed, a final position check will be made before the Slinger/Signaller instructs the operator to lower off all load weight.

10.13 Slinger/Signaller will instruct the operator to lower off, to allow lifting tackle to be released from the load. In the event that any load is too large or high for safe access by ladder, powered access equipment or a lifted man basket will be used to remove slings from loads.

10.14 Once lifting tackle is detached from the load, the Slinger/Signaller will instruct the operator to slowly hoist the lifting tackle clear of the load and any site specific risks ensuring that no snagging occurs.

Page 13: Lifting plan

10.15 Once the lifting tackle is clear of all obstructions the Slinger/signaller will instruct the crane operator to manoeuvre the crane ready for any further lifts that may be required and had over to another Slinger/Signaller were required.

10.16 All other required lifts will be carried out as stated in sections 11.1 to 11.5. The Lift Supervisor will

ensure that all lifting and operational procedures are followed as per the Appointed Persons recommendations and that any queries or deviation from this Method Statement are notified immediately to the Site Manager and the Appointed Person.

11 DE-RIG PROCEDURE

11.1 Upon completion of the lifting operation, the Crane Supervisor will instruct the crane operator to load any ancillary equipment or heavy lifting tackle onto relevant transport ready for removal from site.

11.2 The Crane Supervisor will then instruct the crane operator to lower all lifting tackle to the ground to allow removal from hook.

11.3 The crane operator will then instigate the removal of any lifting tackle stored on the crane and then commence the de-rig procedure.

11.4 All personnel assisting with de-rigging will be under the guidance of the crane operator at all times. The de-rig procedure will be carried out as per crane manufacturers manual.

11.5 Once the crane has been de-rigged and all safety checks for road travel have been carried out the crane operator will manoeuvre the crane/s off site, under the guidance of a member of the lifting crew. The crane will then proceed on its way.

11.6 The remaining members of the lifting crew will ensure that any ancillary mats or equipment etc are removed from site or placed in an appropriate position ready for collection prior to them leaving site.

11.7 Any traffic or pedestrian management arranged by the lift company will be unimplemented and removed.

11.8 The Crane Supervisor will inform the Site Manager or site representative of the completion of the operation and address any issues that may be raised and inform of any equipment left on site for later collection.

12 ON SITE CHANGES/ADDITIONAL LIFTS

12.1 Any changes to this Method Statement & Lifting Plan must be notified to and approved by the Appointed Person. Any crane position changes or amendments to drawings must also be notified and approved by the Appointed Person.

Amendment Details

Page 14: Lifting plan

1) 2) 3) 4) 5) 6) 7) 8) 9) 10)

Changed discussed with and approved by the Appointed Person

Crane Supervisor

Date

(Sign & Print)

13 RISK ASSESSMENT The aim of this risk assessment is to highlight any possible hazards that are likely to occur during the lifting operation.

Upon its completion with either a “High, Medium, Low or N/A” in the Risk Rating Box and either a “” or

“N/A” in the Risk Managed box, the document coverts to a site specific assessment.

Identified Hazards

Risk Risk

rating Prevention Measures

Risk Managed

Access to and Egress from

Site

Interaction with public highway and members of the public. Interaction

with other site operations and operatives. Interaction with delivery

vehicles.

Risk to: Public/ Operators/ Site Operatives

High Banksman with hi-vis to control traffic and public while crane manoeuvring into site. Flashing amber lights and audible alarms

when reversing. Site management to be aware of intended

route on site. All other site operatives to be made aware

of crane movement.

Low

Medium

Low

N/A

Ground Conditions

Crane travelling over unprepared or uneven ground possible damage to

ground surface and or crane and property.

Ground collapse beneath outriggers causing possible overturning.

Risk to: Public/ Operators/ Site

Operatives

High Ground to be assessed at time of site

inspection. Ground improvement to be implemented where needed.

Operator/Crane Supervisor to inspect on day of operation.

Outrigger pans to be used with additional heavy duty mats where needed. Client to inform the crane company of any known

risks

Low

Medium

Low

N/A

Underground Services

Damage to sub-surface service lines causing possible flooding, explosion,

High

A full assessment and mapping of the

Page 15: Lifting plan

asphyxiation or electrocution.

Risk to: Public/ Operators/ Site Operatives

Medium travelling and working area of the crane

will be made at the site inspection. The Site Manager to make the crane operator aware of any known risk.

Permit to work in place where applicable. Operator/ Crane Supervisor to check on day

of operation for any new or unseen risks.

Low

Low

N/A

Crane Positioning

- Set up

Procedure -

De-rig Procedure

Crane positioned incorrectly for required lift.

Possible damage to crane or property during set up or de-rig procedure.

Risk to: Public/ Operators/ Site

Operatives

High Crane working position clearly identified in

Method Statement drawings and made known to crane operators and marked out

where required. Crane manufacturer’s instructions for set up and de-rig procedure followed. Only

trained and competent personnel to operate and assist with rigging. No one but lift associated personnel within crane set

up area.

Low

Medium

Low

N/A

Plant Operations

Crane operation, causing damage to

property or injury to personnel. Mechanical breakdown or structural

damage.

Risk to: Public/ Operators/ Site Operatives

High

Trained, certified and competent crane operators.

Cranes fully maintained with full service and testing history.

Manufacturer’s instructions adhered to at all times.

Low

Medium

Low

N/A

Page 16: Lifting plan

Identified Hazards

Risk Risk

rating Prevention Measures

Risk Managed

Manual Handling

- Sling of Loads

- Signalling

- Tailing

Operations -

Multiple Crane

Operations

Incorrect slinging of loads.

Unsuitable lifting equipment used. Failure of lifting equipment.

Incorrect signals give to crane operator causing damage to loads,

property or injury to personnel. Crane operator lifting unseen loads.

Risk to: Public/ Operators/ Site

Operatives

High

Trained, certified and competent Slingers to sling all loads. Only specified lifting tackle

and lifting tackle with current and valid certification to be used. Visual inspection to

be carried out on all lifting tackle prior to use. Qualified Signallers to use recognised

hand signals or radio commands to communicate with crane operators.

Radios used for unsighted lifts.

Low

Medium

Low

N/A

Working at Height

- Ladders

- Scaffolding

- Access

Platforms -

Man Baskets

Personnel falling from height during crane assembly and or lifting

operations. Personnel falling from delivery

vehicles during slinging of loads. Operation of mechanical platforms.

Personnel working from man Baskets.

Risk to: Public/ Operators/ Site Operatives

High

Operators to work from footed ladders for crane assembly.

Slingers to work from footed ladders for slinging loads where reasonably

practicable. Work platforms or lifted man basket to be

used where a height risk is deemed excessive. Access operators to be IPAF

trained. Site to ensure all working areas at height

are safe with suitable guard rails. Harnesses to be worn where required / practicable. All

scaffolds to be certified for working use.

Low

Medium

Low

N/A

Protection of Public & Site Operatives

- Falling

Objects

Injury to public or site personnel from falling objects or materials.

Damage to vehicles or property during lifting operations. Risk from

suspended loads.

Risk to: Public/ Operators/ Site Operatives

High Work area to be cordoned off as an exclusion zone.

Sufficient barrier & signage to be in place to warn non lift associated persons of

overhead & ground level risks. All over-sail to be addressed, monitored and evacuation implemented where practicable. Lift crew

to be aware of all lifting operations.

Low

Medium

Low

N/A

Traffic Pedestrian

Management

Damage to property or plant. Risk of responsibility for collision or injury.

Protection of personnel during works.

Risk to: Public/ Operators/ Site Operatives

High Full assessment of required restrictions on public highways, service roads or private roads to be made at site inspection. Any Traffic Management contractors supplied by site or the crane company will be fully

certified and competent. Traffic Management supplied by the site should be

set up prior to arrival of crane.

Low

Medium

Low

N/A

Adverse Weather

Conditions

Crane operation, load stability and control.

Risk of injury to personnel and damage to property.

Risk of lightning strike. Bad visibility.

Risk to: Public/ Operators/ Site

High Weather reports obtained before and during lifting operations.

Crane operator to monitor wind speed equipment.

Suspension of lifting operation until risk subsides.

Low Medium

Low

Page 17: Lifting plan

Operatives

N/A

Page 18: Lifting plan

Identified Hazards

Risk Risk

rating Prevention Measures

Risk Managed

Overhead or slewing

Obstructions or

Restrictions -

Low Headroom

Damage to crane or property if crane boom or superstructure comes into

contact with any restriction. Infringement of unauthorised air space. Working in restricted work

space.

Risk to: Public/ Operators/ Site Operatives

High Full assessment of any risks made and addressed at site inspection. Safe system of

work adhered to where implemented. Work to zone alarms where implemented.

Implement crane swl computer working restrictions.

All relevant authorities contacted and advised and any restrictions adhered to.

Low

Medium

Low

N/A

ADDITIONAL SITE SPECIFIC RISKS

ADDITIONAL RISKS IDENTIFIED ON DAY OF OPERATIONS ADDITIONAL RISKS DUE TO ON SITE CHANGES

Identified Hazards

Risk Risk Rating

Prevention Measures Risk Managed

Page 19: Lifting plan

14 SITE REGISTER/TOOLBOX TALK All operational staff involved in this lifting operation must read this method Statement or have had the contents of it explained in detail to them prior to commencing work. All persons involved in this lifting operation are to sign below in acceptance that a detailed briefing of this operation has been given and understood. All certification has been checked and verified prior to the lifting operation commencing.

Crane Supervisor’s Acceptance of Responsibilities:

I confirm that I have been fully briefed on the contents of this Method Statement and Risk Assessment and that I accept the duty of ensuring that the lift/s will be carried out in accordance with the Methods and Procedures set

out in this Document.

Signed

Date

Print Name Position Signature Date

Site Manager Acceptance of this Method Statement I confirm that I have read and understood this Method Statement and Risk Assessment and that I

accept the responsibilities of the site management with respect to Safe Use of Cranes (part 1) 2006 General and (part 3) 2000 Mobile Cranes.

Signed Date SUMMARY

Crane Detail Site Manager

Crane

Site

Project

Detail

Req Radius

SWL SES

Point Load

Date Issue No

Page 20: Lifting plan

THIS PAGE IS INTENTIONALLY BLANK