Lift planning and Supervision
Sam Evans EPS Plant & Safety Ltd
-
Update on BS 7121 2016 & IS 361
� The language used in Part 1 is “Intermediate Lifts”(standard)
� “Lift Plan” is an inclusive term for risk assessments, method statements and supporting information, such as a schedule of lifts, drawings and photographs.
� Leans towards a more definitive requirement for Appointed Person attendance on Complex Lifts.
� Increase to derating tandem lifting operations from 25% to at least 30%
-
Ground bearing
� Hirer to supply information on GBC (same in
contract lift scenario)
� CBR test to determine potential capacity of the
ground
� Determine the jack load of the crane
� Calculate the pad size required under the
outrigger foot
-
Employing Organisation
-
EMPLOYING ORGANISATION
EMPLOYING ORGANISATION
- BUILDING COMPANY -
REQUIRE LOAD LIFTED
HIRE CRANE
PLAN AND MANAGE
-
CPA Crane Hire
� Loss of, or damage to crane on hire to you
� Continuing hire charges
� Injury to operator
� Injury to other parties including damage to property
� Loss or damage to goods lifted
� Driver to report to Appointed Person on site
� Hire company to supply competent driver &
Crane that is tested, inspected, with documents etc.
-
EMPLOYING AND USER ORGANISATION
USER ORGANISATION
- CRANE HIRE COMPANY -
PLAN AND MANAGE
CONTRACT THE LIFT
Q1, 9
EMPLOYING ORGANISATION PROVIDE WRITTEN
DETAILS OF WORK TO BE DONE
S5-P3S1-P24 S4-P3,4
-
Contract Hire
� Crane Co. supplies Appointed person etc.
� Loss of or damage to plant caused solely by owners negligence.
� Loss of or damage to other property caused by owners negligence
� (a) Liability Goods,25,000.00 Stg.
� (b) Liability loss/damage 5,000,000.00
� Hirer (you) to pay for insurance
-
F O B B
�Falls of rope
�Outrigger configuration
�Boom Configuration
�Ballast Configuration� All information available from the duties chart!
-
Falls of Rope
�Maximum permissible line pull
�Weight to be lifted
�Calculate falls required
�Identify correct hook block
-
Outrigger Configuration
�Full extension
�Half extension
�Pick and carry
�Free on wheels
-
Boom Configuration
� Identify length of boom required
� Identify type of Boom (telematik or telescopic)
� Identify correct individual section extension telematik (0, 46, 92, 100)
�Telescopic boom identify correct percentage of extensions.
-
STRUCTURAL STRENGTH
STRUCTURAL
STRENGTH
STABILITY
-
Ballast (counterweight)
� Identify correct amount of ballast (from duty chart)
�Many cranes have at least 6 different ballast combinations
-
Wind speed
�Wind speed for crane configuration
�VmaxTab
�Wind speed for operational Vmax
�Calculate the working wind speed
-
Tower crane collapse in Poland
� https://youtu.be/x4OW4WtVsPE
� https://youtu.be/VEIEO4jj1Z4
-
Greenwich London
-
Summary
�Falls of rope
�Outrigger configuration
�Boom configuration
�Ballast configuration
�Wind speed rigged and operational
�All info from duties charts
-
Thank you