Lift planning and Supervision - iosh.com · Update on BS 7121 2016 & IS 361 The language used in...

39
Lift planning and Supervision Sam Evans EPS Plant & Safety Ltd

Transcript of Lift planning and Supervision - iosh.com · Update on BS 7121 2016 & IS 361 The language used in...

  • Lift planning and Supervision

    Sam Evans EPS Plant & Safety Ltd

  • Update on BS 7121 2016 & IS 361

    � The language used in Part 1 is “Intermediate Lifts”(standard)

    � “Lift Plan” is an inclusive term for risk assessments, method statements and supporting information, such as a schedule of lifts, drawings and photographs.

    � Leans towards a more definitive requirement for Appointed Person attendance on Complex Lifts.

    � Increase to derating tandem lifting operations from 25% to at least 30%

  • Ground bearing

    � Hirer to supply information on GBC (same in

    contract lift scenario)

    � CBR test to determine potential capacity of the

    ground

    � Determine the jack load of the crane

    � Calculate the pad size required under the

    outrigger foot

  • Employing Organisation

  • EMPLOYING ORGANISATION

    EMPLOYING ORGANISATION

    - BUILDING COMPANY -

    REQUIRE LOAD LIFTED

    HIRE CRANE

    PLAN AND MANAGE

  • CPA Crane Hire

    � Loss of, or damage to crane on hire to you

    � Continuing hire charges

    � Injury to operator

    � Injury to other parties including damage to property

    � Loss or damage to goods lifted

    � Driver to report to Appointed Person on site

    � Hire company to supply competent driver &

    Crane that is tested, inspected, with documents etc.

  • EMPLOYING AND USER ORGANISATION

    USER ORGANISATION

    - CRANE HIRE COMPANY -

    PLAN AND MANAGE

    CONTRACT THE LIFT

    Q1, 9

    EMPLOYING ORGANISATION PROVIDE WRITTEN

    DETAILS OF WORK TO BE DONE

    S5-P3S1-P24 S4-P3,4

  • Contract Hire

    � Crane Co. supplies Appointed person etc.

    � Loss of or damage to plant caused solely by owners negligence.

    � Loss of or damage to other property caused by owners negligence

    � (a) Liability Goods,25,000.00 Stg.

    � (b) Liability loss/damage 5,000,000.00

    � Hirer (you) to pay for insurance

  • F O B B

    �Falls of rope

    �Outrigger configuration

    �Boom Configuration

    �Ballast Configuration� All information available from the duties chart!

  • Falls of Rope

    �Maximum permissible line pull

    �Weight to be lifted

    �Calculate falls required

    �Identify correct hook block

  • Outrigger Configuration

    �Full extension

    �Half extension

    �Pick and carry

    �Free on wheels

  • Boom Configuration

    � Identify length of boom required

    � Identify type of Boom (telematik or telescopic)

    � Identify correct individual section extension telematik (0, 46, 92, 100)

    �Telescopic boom identify correct percentage of extensions.

  • STRUCTURAL STRENGTH

    STRUCTURAL

    STRENGTH

    STABILITY

  • Ballast (counterweight)

    � Identify correct amount of ballast (from duty chart)

    �Many cranes have at least 6 different ballast combinations

  • Wind speed

    �Wind speed for crane configuration

    �VmaxTab

    �Wind speed for operational Vmax

    �Calculate the working wind speed

  • Tower crane collapse in Poland

    � https://youtu.be/x4OW4WtVsPE

    � https://youtu.be/VEIEO4jj1Z4

  • Greenwich London

  • Summary

    �Falls of rope

    �Outrigger configuration

    �Boom configuration

    �Ballast configuration

    �Wind speed rigged and operational

    �All info from duties charts

  • Thank you

    �Sam Evans EPS Plant & Safety Ltd.