LiberTrace - Establishing and Operating a Timber Legality Verification Department (LVD) within Liberia’s Forestry Development Authority (FDA) and Building Capacity within FDA
Inception presentation12/12/2013Clinton Bambridge – LiberTrace Project Manager
2
Table of contents
From LiberFor to LiberTrace
Outputs of LiberTrace Project
Liberia Legality Assurance System
IT Solution - LegalTrace
Project Initiated
© SGS 2013 – All rights reserved
3
From LiberFor to LiberTrace
© SGS 2013 – All rights reserved
LiberFor LiberTrace
Project initiated
12/2007 (60 months initially) 10/2013 (60 months)
FundingUSAID / GOL/ PROFOR (WB/EU/DFID) / Autofinancing
EU / DFID
Context
2006:Forest concessions cancelledNew Forestry Law enactedUN sanctions on timber export lifted
2011: VPA signed between EU and GOL2013: VPA ratified by GOL
Main mandates
• Development / monitoring of computerized COCIS
• Timber export permits emission• Forest taxes collection• Capacity building
• Continuity of LiberFor mandates• Building LVD• Development of a CoC + legality web
based application• Auditing companies’ legality
compliance• Licensing system (FLEGT Licenses)
4
Project Objective
Objective: Establish and Operate a Timber Legality Verification
Department (LVD) within Liberia’s Forestry Development Authority (FDA) and Build Capacity within FDA
Beneficiaries: FDA Ministry of Finance Stakeholders
Partners: Forest sector operators VPA Support Unit FLEGT Coordinator
5
LiberTrace Project – 5 Outputs
Output 0: Project managed
Output 1: LVD established
Output 2: LVD capacities established
Output 3 - Design and development of the LVS
Output 4 - Design and development of the new COCIS
Output 4/3 - Roll out of the new COCIS/LVS
Output 5: LVD transferred to FDA
© SGS 2013 – All rights reserved
6
Output 0 – Project Managed (60 months)
Methodology PRINCE2 Project Management Team Management by quarterly
stages Quality management M&E system based on KPIs
Work Packages Project Initiation Stage control Project closure
LVDTechnical Managers
FDA Managing Director
SGSManaging Director
FDA Board of DirectorsMOA., MOC, MOF, MOCIT, MOPEA,
Central Bank, FDA MD, etc.
SGSCorporate Direction
Project Board / Project Evaluation Committee
Project Manager
EFIQuality
Assurance
Project Management Team
Technical Advisory
Committee
SGS Liberia/Geneva
Project Support
Capacity-buildingTeam Leader
LASTeam Leader
LVD Technical Manager
MOF Represent-
atives
DFID Represen-
tative
Senior Users Senior SupplierExecutive
DFID
© SGS 2013 – All rights reserved
7
Output 1 – LVD to be established
Strategy Vision of the LVD: values,
responsibilities, organisation
© SGS 2013 – All rights reserved
LVD Technical Manager
Project Manager
Trainee Operations Manager
Operations Manager
LASTeam Leader
Capacity Building
Team LeaderIT Expert
Quality Manager
Administrative Officer
Invoice processing Coordinator
Trainee Database Information Manager
Database Information Manager
Work Packages LVD institutional design Installation in FDA HQ Key positions staffed Administrative management system / Initial QMS
8
Output 2 – Capacity built within the FDA
Capacity-building Implementation Plan (CBIP) Capacity needs assessment, Deployment plan, staff management plan, training plan,
procurement plan, communication plan
Training sessions Management: Leadership, Integrity, HSE, QMS IT: Basic IT, use of the COCIS & LVS, support and
maintenance Forestry: Regulation/FLEGT, Verification procedures,
timber grading & scaling
Capacity-building approach Change management, “System builders”, Trainee/Graduate
© SGS 2013 – All rights reserved
9
Output 3 – Design and Development of the Legality Verification System
The Legality Verification System is a key element of the Liberia Legality Assurance System (LLAS)
Design of Legality Verification Standard Operating Procedures (SOPs). Consultation of stakeholders and field testing
Based on EU/GOL VPA Legality Matrix
Verification of compliance with the Legality Standard
© SGS 2013 – All rights reserved
10
Output 4 - Design and development of the new COCIS
Standard Operating Procedures (SOPs) Review of existing SOPs Design of new SOPs Stakeholders consultation and field testing
Current COCIS used by LiberFor is LiberTrack
LiberTrack will be progressively replaced by the new COCIS based on SGS solution: LegalTraceTM
11
SGS web application: LegalTraceTM
LegalTraceTM is:
The timber traceability and legality software developed by SGS in compliance with VPA requirements.
Built on the SGS “.Net” Framework already used worldwide by SGS Group.
A single software solution that manages traceability and legality verification as well as the functionality enabling the issuance of FLEGT licences.
Based on the recommendations of SGS forestry and IT experts, LegalTraceTM has been developed as a generic system covering 80% of the requirements of any VPA.
The remaining 20% will be developed specifically for Liberia into an application called LiberTrace.
© SGS 2013 – All rights reserved
12
Outputs 3 & 4 - LVS & COCIS operated
© SGS 2013 – All rights reserved
Operational team structure
COC Inspection teams
LV Inspection teams
COC / LV Rangers
COC/LV Data Management
Internal Auditing
LVD Headquarters in Monrovia
03 permanent field offices
Intermittent presence in other sites
13
Output 5 – LVD transferred to the FDA
Recruitment and deployment
Transfer Plan approved by DFID and GOL
Pilot handover in one selected regional office
Scaling up the handover in remaining regional offices based on lessons learned from the pilot.
Handover of complete LVD headquarters functions, but with a continuing backstopping and coaching/mentoring programme;
LVD certified against ISO9001 standards
Post-handover support provided by SGS
Month
25
60
2
24
43
49
51
12
© SGS 2013 – All rights reserved
14
Project Initiated: activities up to date
© SGS 2013 – All rights reserved
Outputs Activities
Output 0: Project managed
Meetings with key stakeholders Key resources mobilized Procurement initiated Reporting structures implemented
Output 1: LVD established Job Descriptions of SGS/FDA Counterparts drafted
Output 2: LVD capacities established In progress
Output 3 - Design and development of the LVS Deployment of Legality Expert – Dr. M. Brink in progress
Output 4 - Design /development of the new COCIS LiberTrace IT solution under development
Output 4/3 - Roll out of the new COCIS/LVS Delivered project month 18
Output 5: LVD transferred to FDA Transfer plan month 12 , implementation to follow
15
Clinton BAMBRIDGE, Project Manager
Email: [email protected]
Francis K. ODOOM, Project coordinator – Capacity building
Email: [email protected]
Jerome LAPORTE, Project coordinator – LAS
Email: [email protected]
Thank you