Current status and plan of the LHCf experiment (LHCf; Large Hadron Collider forward)
LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it...
-
Upload
roland-malone -
Category
Documents
-
view
212 -
download
0
Transcript of LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it...
![Page 1: LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it be delayed? – Present plan below. LHCf to removed at first.](https://reader035.fdocuments.net/reader035/viewer/2022072008/56649d765503460f94a57178/html5/thumbnails/1.jpg)
LHCf 2015
• Questions from LMC:– LHCf run scheduled shortly after initial commissioning
– can it be delayed?– Present plan below. LHCf to removed at first
opportunity after run – i.e. TS1 in present planning
Following discussion with Hiroaki MENJO – 29th August 2014
![Page 2: LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it be delayed? – Present plan below. LHCf to removed at first.](https://reader035.fdocuments.net/reader035/viewer/2022072008/56649d765503460f94a57178/html5/thumbnails/2.jpg)
Requirements
• Pilot run to qualify DAQ sometime before main run (pile-up not an issue)
• 11 m is OK – unsqueeze not needed for LHCf• 1.5e29 cm-2s-1, mu = 0.01, Nb < 40, half
crossing angle 140 microrad• Integrated luminosity: 10 nb-1
• Delivery rate about 0.5 nb-1/hour – need 20 hours Stable Beams – say 2 days plus set-up
![Page 3: LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it be delayed? – Present plan below. LHCf to removed at first.](https://reader035.fdocuments.net/reader035/viewer/2022072008/56649d765503460f94a57178/html5/thumbnails/3.jpg)
Note
• If LHCf is exposed to the high radiation levels in the TAN associated with high luminosity – it will be damaged – 2 weeks maximum at high luminosity
• Installation time:– 1 working week– 1 to 2 days physical installation plus cabling and
electronics tests• Removal time: – 1 to 2 days for both sides
![Page 4: LHCf 2015 Questions from LMC: – LHCf run scheduled shortly after initial commissioning – can it be delayed? – Present plan below. LHCf to removed at first.](https://reader035.fdocuments.net/reader035/viewer/2022072008/56649d765503460f94a57178/html5/thumbnails/4.jpg)
Delay run?
• If the run is not performed initially, the detector will have to be installed and tested during a later technical stop
• The run will have to take place reasonably soon after the technical stop to avoid damage
• 1 – 2 days within 2 weeks of the run will be required to removed the detectors
• Both installation and removal will have to take place in an irradiated area – this will not be the case if the run takes place during the initial period
• ALARA strongly favours doing the run as scheduled.