LHC - LS2 2018-2021 Coordination meeting #63 1 LHC coordination meeting, 18th February 2020 18th February 2020, week 8 Marzia Bernardini, María Baberán, Julie Coupard, Michela Pirozzi, Estrella Vergara

Transcript of LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901...

Page 1: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC - LS2 2018-2021Coordination meeting #63

1LHC coordination meeting, 18th February 2020

18th February 2020, week 8

Marzia Bernardini, María Baberán, Julie Coupard, Michela Pirozzi, Estrella Vergara

Page 2: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 Coordination

2

• Piquet’s phone number: 161669

• INDICO: https://indico.cern.ch/category/7200/ (LHC-LS2)

• OSS website (planning, constraints, useful links…):

https://lhc-coordination.web.cern.ch/

• LS2 Plannings (all accelerators)

• LS2 Access constraints

• LS2 Baseline EDMS 1817804

LHC coordination meeting, 18th February 2020

Page 3: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

3

EL tests & maintenance(EDMS 2058996) NO ACCESS

400 kV maintenance 22 July – 27 Sept 2019 (W30-39)

4 July – 27 Sept 2019 (W27-39)

4 July- 4 October (W27-40)

Auto-

transfert

No autotransfert from

16th September 2019 to May 2020

Test: 27-29 April 2020

Maintenance NO ACCESS* AUG NO ACCESS*

Point Day Point Day

LHC1 + ATLAS6 -7- 8 -13 January 2020 – NO access (W2)

9 - 10 January 2020 - Limited access (W2)LHC1 + ATLAS 13 January 2020 (W3)

LHC18 + SM18 23-25 April 2019 (W17) LHC18 + SM18

26 April 2019 (W17)

15 April 2020 (TBC)

Under discussion September 2020

(Exact date TBC from EN-EL)

LHC2 + ALICE

11-14 June 2019 (W24) – Access OK

LHC2 + ALICE 27 January 2020 (W5)20-21-22-27 January 2020 – NO access (W4)

23-24 January 2020 - Limited access (W4)

LHC3 + PM32 9-12 March 2020 (W11) LHC3 + PM3230 April 2019 (W18)

13 March 2020 (W11)

LHC417-20 June 2019 (W25) – Access OK

LHC47 Oct. 2019 (W41)

24-28 February 2020 (W9) 2 March 2020 (W10)

LHC5 + CMS 20-24 May 2019 (W21)

LHC5 + CMS 27 May 2019 (W22)

24-27 June 2019 (W26) – Access OK 5 May 2020 (W19)

LHC63-6 June 2019 (W23) TBC – Access OK

LHC6 20 Sept. 2019 (W38)17-19 Sept. 2019 (W38)

LHC7 23-27 Sept. 2019 (W39) LHC7 30 Sept. 2019 (W40)

LHC8

15-19 April 2019 (W16) – Access OK

LHC8 16 Dec. 2019 (W51)9-10 Dec. 2019 – NO access (W50)

11-12-13 Dec. 2019- Limited access (W50)

TEST SECOURS 2020 Mardi 26 Mai 2020 Prevessin4 April 2020 (W14)

under discussion 27 June 2020 (W26)

Meyrin (Administrative)

Meyrin (PS complex)

6 June 2020

16+17 May 2020

NEXT WEEK

Page 4: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

4

EL tests & maintenance P4 NO ACCESS

LHC coordination meeting, 14th January 2020

From 24th February to 2nd March 2020

EDMS:

• LHC-L-PRD-0002

Page 5: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 28th January 2020 5

SM18 informed that the shutdown will be performed on September 2020 and in order to reduce

perturbations on June they request if the CV maintenance and the AUG test at SM18 can be shifted on

September (w36 and forwards).

• AUG test on w36 or 37 EN-EL confirmed that is ok

• CV maintenance from w36-w37

• From CV point of view there is no problem to postponed the maintenance, but instead of 2w they

will need 3 weeks.

• This maintenance affect the cryo in the sector 12 in which the COOL-DOWN is scheduled from

w38.

• TE-CRG if the CV maintenance is finished before week 38, the cryo won’t be affected.

• CV maintenance could start on week 35 to 37.

• ELQA test on w36-37 if in the tunnel the ventilation and the humidity remains normal, the test

can be performed in parallel with the CV maintenance.

SM18 could start the test on week 35 instead of 36 as requested in view of the EN-CV and TE-CRG

constraint.

SM18 Shutdown on September

W35-39 (24th August 28th September)

Page 6: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 EN-CV Maintenance

6

Point Activity Week Start Start Date End Date Duration Status

LHC5

SF - CV Maintenance W50 10-Dec-18 01-Feb-19 6 wks Completed

SU - AC Maintenance W50 10-Dec-18 14-Dec-18 1 wk Completed

USC55 - CV Maintenance W50 10-Dec-18 08-Mar-19 11 wks Completed

SU - Ventilation Maintenance W10 04-Mar-19 29-Mar-19 4 wks Completed

Ventilation Maintenance in RRW14W15

01-Apr-1908-Apr-19

30-Apr-19 4 wks Completed

SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started

USC55 reduced - CV Maintenance W3 11-Jan-21 29-Jan-21 3 wks Not Started

Point Activity Week Start Start Date End Date Duration Status

LHC6

UW, UA, RE - CV MaintenanceW40W39

30-Sep-1923-Sep-19

25-Oct-19 4 wks Started

SF - CV Maintenance W44 28-Oct-19 10-Jan-20 9 wks Not Started

SU - CV Maintenance W3 13-Jan-20 07-Feb-20 4 wks Not Started

UW reduced - CV Maintenance (TBC) W28 06-Jul-20 24-Jul-20 3 wks Not Started

SF+SU reduced - CV Maintenance (TBC) W46 09-Nov-20 27-Nov-20 3 wks Not Started

Point Activity Week Start Start Date End Date Duration Status

LHC8

SF - CV Maintenance W7 10-Feb-20 08-Apr-20 8.5 wks Not Started

SU - CV Maintenance W16 14-Apr-20 19-May-20 5 wks Not Started

UW, UA , RE - CV Maintenance W21 20-May-20 18-Jun-20 4 wks Not Started

SF+SU reduced - CV MaintenanceW42 12-Oct-20 30-Oct-20 3 wks Not Started

W41 5-Oct-20 23-Oct-20 3wks

UW reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC1

SU1 - Ventilation Maintenance (RR, RE) W51 17-Dec-18 21-Dec-18 1 wk Completed

SU1 - Cooling Maintenance W2 07-Jan-19 01-Feb-19 4 wks Completed

SF - CV Maintenance - Dependant from SPS tests in BA6

W4 21-Jan-19 29-Mar-19 10 wks Completed

USA15 + US15 cooling + ventilation maintenance - Impact on LHC Tunnel

VentilationW6 04-Feb-19 01-Mar-19 4 wks Completed

USA15 EM W10 04-Mar-19 29-Mar-19 4 wks Completed

SF+SU reduced - CV Maintenance W50 07-Dec-20 08-Jan-21 3 wks Not Started

USA reduced - CV Maintenance + ventilation RR, RE

W3 11-Jan-21 29-Jan-21 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC2

UW - CV Maintenance -Cooling, UA, RE W40 30-Sep-19 01-Nov-19 5 wks Not Started

SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

SU - CV Maintenance W16 15-Apr-20 20-May-20 5 wks Not Started

UW reduced - CV Maintenance -EG Only W34 17-Aug-20 14-Sep-20 4 wks Not Started

SF+SU + Ventilation UA- CV reduced Maintenance

W45 02-Nov-20 20-Nov-20 3 wks Not Started

Point ActivityWeek Start

Start Date End Date Duration Status

LHC4

SF - CV Maintenance W4 20-Jan-20 13-Mar-20 8 wks Not Started

SU - CV Maintenance W12 16-Mar-20 14-Apr-20 4 wks Not Started

UW - CV Maintenance - Cooling, UA, RE W21 22-May-20 19-Jun-20 4 wks Not Started

UW reduced - Cooling Maintenance -Ventilation reduced

W37 07-Sep-20 28-Sep-20 3 wks Not Started

SF+SU reduced - CV Maintenance W42 12-Oct-20 30-Oct-20 3 wks Not Started

UW25 off

(Transfo replacement)

Week 10

from 02-Mar-20

to 06-Mar-20

UW45 off

(Transfo replacement)

Week 8

from 17 to 21 Febr. 20

UW65 off

(Transfo replacement)

Week 48

from 25-Nov-19

to 29-Nov-19

UW85 off

(Transfo replacement)

Week 51

from 17-Dec-19

to 20-Dec-19

In progress

Next to start

Maintenance tableau Hazemeyer EN/CV dates under definition

LHC coordination meeting, 18th February 2020

Page 7: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 EN-CV Maintenance

7

Point Activity Week Start Start Date End Date Duration Status

LHC 18

LHC 3.2

LHC3.3

LHC 7

LHC 18- CV Maintenance W35 24-Aug-20 14-Sept-20 3 wks Not Started

LHC 3.2UW PM32

W27W31

30-Jun-2027-July-20

6-July-2031-July-20

1 wk1 wk

Not Started

LHC 3 W26 22-Jun-20 24-July-20 5 wks Not Started

LHC 7 W26 22-Jun-20 24-July-20 5 wks Not Started

In progress

Next to start

LHC coordination meeting, 18th February 2020

Page 8: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

8

LS2 cryogenics milestonesCryogenics unlockout surface Date

P18

25-Feb-20

18-Feb-20

P2 25-May-20

P4 (S.3-4) 23-Mar-20

P4 (S.4-5) 20-Apr-20

P6 (S.5-6) 21-Apr-20

P6 (S.6-7) 21-Apr-20

P8 (S.7-8) 06-Apr-20

P8 (S.8-1)

10-Feb-20

06-Jan-20

Cryogenics unlockout

undergroundDate

s. 1-2 06-Apr-20

s. 2-3 16-Apr-20

S.3-4 01-Jun-20

S.4-5 04-May-20

S.5-6 15-Jun-20

S.6-7 29-Jun-20

S.7-8 18-May-20

S.8-1 06-Apr-20

Cryo ok for ELQA@warm

and cool-downDate

S. 1-2 04-Jun-20

S. 2-3 07-Aug-20

S. 3-4 17-Jul-20

S. 4-5 19-Jun-20

S. 5-6 31-Jul-20

S. 6-7 14-Aug-20

S. 7-8 06-Jul-20

S. 8-1 26-May-20

Cryo Unlock Surface and Underground

Cryo Ready for ELQA & Cool Down

LHC coordination meeting, 18th February 2020

NEXT

Page 9: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 9

Page 10: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 10

Thursday 16th April 2020

Page 11: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Open Points

LHC coordination meeting, 28th January 2020 11

• BE-BI

• BPMWI @ A5L8.R News? Draft presented at LMC on 5th February

• BGC modifications??? HL-LHC integration

• Major changes with respect to the original ECR on the increased footprint, orientation, volume, blackening coating, reuse of the BGI

system and racks.

• ECR update under preparation

• Ready to install 3rd February 2020 ??? date change

• PM56 Lift Replacement

• New dates Start from 30th March until 17th June (1st April – 6th June)

• Procedure for mitigation measures on going

• BE-ICS Installation of UL16 /UL14 access point

• Check magnet transport

• UL14 2nd - 3rd March

• UL16 4th – 5th March

Page 12: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Open Points

LHC coordination meeting, 28th January 2020 12

• Kicker pulse test (MKBV) TE-VSC News• TE-VSC :

• The MKB in RA63 (vacuum sector BTD62.DR) is ready for TE-ABT test.

• Issue with one ion pump on the MKB located in RA67 (vacuum sector BTD68.DB) Need to be changed (around 2

days of mechanic and between 1 and 2 weeks to recondition the sector)

TB discuss if postponed after the Kicker pulse test

• TE-ABT:

• Preparatory works on generators at UA starting on 17th February

• W10-13 validation test on MKBH & MKBV (Beam1) (LSS6L & UA67)

• W14-18 validation test on MKBH & MKBV (Beam2) (LSS6R & UA63)

Page 13: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Magnet Exchange Campaign

LHC coordination meeting, 18th February 202013

Next

ma

in a

ctivities-

On

go

ing–

Co

mp

leted

• 26/28 removed (takes into account WP11 HL-LHC + C16L2 + Q16L2)

• 30/36 reinstalled (takes into account 3 parts per 11T and cryo assemblies)

Q16L2:

• Disconnection starting from 20/09/2019

• Transport new magnet: 19/11/2019

C16L2:

• Disconnection starting from 24/09/19

• Transport new magnet: 11/11/2019

CC-C11L2:

• Disconnection starting from 26/09/2019

• Installation 2 LEP: 4 and 5/11/2019

• Installation LEN: 8/11/2019

CC-C11R2:

• Disconnection starting from 02/10/2019

• Transport 1st LEP: 29/11/2019

Due to a NC, this LEP has been removed from

the tunnel but already re-installed (03/02/20).

Currently it is being connected

• Transport 2nd LEP: 13/12/19

• Transport LEN: 17/12/19

11T LSS7L:

• Disconnection starting from 19/03/2019 (tbc)

• Transport old magnet starting: 26/03/2019 (tbc)

• Transport 11T & LEN starting: 17/04/2020 (tbc)

11T LSS7R:

• Disconnection starting from mid March (tbc)

• Transport old magnet starting: (tbc)

• Transport 11T & LEN starting: (tbc)

Page 14: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

TCLD arc 12 installation

LHC coordination meeting, 18th February 2020 14

TBC if pre-series is going to be installed on 27th February vs series

Page 15: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

TDIS crane status vs weight of TDIS

LHC coordination meeting, 28th January 2020 15

New crane will be installed in both point LSS2L and LSS8R

LSS2L EN-HE not before mid-March 2020 W13 Confirmed

Installation date postponed to 6th April 2020

LSS8R EN-HE W14 Confirmed

NO IMPACT on the installation dates (13th July 2020)

Page 16: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

16

UPR 13 SAS installation w12 EN-EL will confirn on w9 or

10 if the cable pulling is finished to give the green light to SMB

Opening from w13 to w16

SAS dismantling and Metallic plate installation w17

UPR 53 SAS installation 6th April / Smoke test w14

Opening from w15 to w19

SAS dismantling and Metallic plate installation w 20

HL-LHC UPRs 13 & 53 Request new dates for Opening

LHC coordination meeting, 28th January 2020

Page 17: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 28th January 2020

LSS5 Realignment Planning consolidated

17

Phase I – Realignment from Q7 to Q5 14th Sep to 10th Oct 2019

Phase II – Realignment between Q5 to Q5 in progress (From January 2020 to May 2020)

• Q5-D1 (6 MBWX, 1 Q4, 1 D2, 1 TAN, 4 pick-ups and 4 Collimators)

• Q1L-Q1R (2 TAS, VAS and 2 BPMWK)

LSS5L

Relative Vertical alignment (3 tours) Q5-D1, Q1L-Q1R W3-4

Radial measurement of the principal (with duct) components Q5-D1, Q1L-Q1R W10-11

Calculations W12-13

Radial alignment principal components (2-3 last days with duct) Q5-D1, Q1L-Q1R W16-17

Alignment secundary components W20-21

LSS5R

Relative Vertical alignment (3 tours) Q5-D1, Q1L-Q1R W5-6-7

Radial measurement of the principal (with duct) components Q5-D1, Q1L-Q1R W8-9

Calculations W12-13

Radial alignment principal components (2-3 last days with duct) Q5-D1, Q1L-Q1R W14-15

Alignment secundary components W18-19

Q1 – DFBX Alignment on the Inner Triplet area project (V Parma)

LSS5L W5

Endoscopy TE-VSC on Wednesday 29 January

X-Ray 4th February

LSS5R w11

Endoscopy TE-VSC on Wednesday 11th March

X-Ray 12th March

TAS (Right side) (F Sanchez Galan) w11 in // with the DFBX LSS5R

Page 18: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

EN-STI: Beam Dump ReplacementLink to schedule (in work) / IMPACT 149959

LHC coordination meeting, 18th February 2020 18

Opening of the shielding and storage of the activated

dumps in the UDs week 9 (UD62 and UD68) + scans

Work in UX65 till end of

May 2020 Installation of

the spare dumps from June

Page 19: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Collimators installation dates

LHC coordination meeting, 28th January 2020 19

Asset number Collimator LocationDelivery date at CERN

(On 20/09/2019)Delivery date at CERN

(On 14/02/2020)Ready to install(Baseline 2.2)

Ready to Install(Foreseen dates)

Removal old collimator

Installation date (Baseline 2.2)

Installation date (Foreseen dates)

HCTCPPM001-CZ000001 TCPP #1 TCP.C6R7.B2 10/2019 28/12/2019 20/12/2019 20/01/2020 06/02/2020 17/01/2020 12/02/2020 +4wks

HCTCPPM001-CZ000002 TCPP #2 TCP.D6L7.B1 11/2019 28/12/2019 20/12/2019 20/01/2020 30/09/2020 10/02/2020 05/10/2020 +33wks

HCTCPPM001-CZ000003 TCPP #3 TCPP.C6L7.B1 11/2019 ???? 03/02/2020 ?????? - 14/02/2020 - -

HCTCPPM001-CZ000004 TCPP #4 TCP.D6R7.B2 10/2019 19/12/2019 03/02/2020 04/02/2020 06/02/2020 17/01/2020 12/02/2020 +4wks

HCTCLDA001-CZ000001/2 TCLD #2 TCLD.A11L2.B2 12/2019 19/02/2020 05/02/2020 27/03/2020 - 21/02/202027/02/2020 (pre-series)

03/04/2020 (series)+1wk (pre-series)

+6wks (series)

HCTCLDA001-CZ000002/3 TCLD #3 TCLD.A11R2.B1 12/2019 19/02/2020 05/02/2020 27/03/2020 - 30/03/2020 06/05/2020 +5wks

HCTCLDA001-CZ000003/4 TCLD #4 TCLD.A9L7.B2 01/2020 11/03/2020 05/03/2020 20/04/2020 - 27/07/2020 TBC -

HCTCLDA001-CZ000004/5 TCLD #5 TCLD.A9R7.B1 01/2020 11/03/2020 05/03/2020 20/04/2020 - 11/06/2020 TBC -

HCTCSPM001-CZ000001 TCSPM #1 TCSPM.B4L7.B1 02/2020 15/04/2020 28/02/2020 25/05/2020 - 05/06/2020 26/05/2020 -2wks

HCTCSPM001-CZ000002 TCSPM #2 TCSPM.B4R7.B2 02/2020 15/04/2020 28/02/2020 25/05/2020 - 13/03/2020 27/05/2020 +10wks

HCTCSPM001-CZ000003 TCSPM #3 TCGS.D4R7.B2

(TCSPM)03/2020 12/05/2020 04/05/2020 20/06/2020 17/06/2020 10/03/2020 22/06/2020 +10wks

HCTCSPM001-CZ000004 TCSPM #4 TCSPM.6R7.B1 03/2020 12/05/2020 04/05/2020 20/06/2020 - 15/05/2020 23/06/2020 +5wks

HCTCSPM001-CZ000005 TCSPM #5 TCSPM.E5L7.B2 04/2020 09/06/2020 02/06/2020 17/07/2020 - 16/07/2020 20/07/2020 +1wks

HCTCSPM001-CZ000006 TCSPM #6 TCSPM.E5R7.B1 04/2020 09/06/2020 02/06/2020 17/07/2020 - 11/05/2020 21/07/2020 +10wks

HCTCSPM001-CZ000007 TCSPM #7 TCSPM.6L7.B2 05/2020 07/07/2020 01/07/2020 20/08/2020 - 08/07/2020 24/08/2020 +6wks

HCTCSPM001-CZ000008 TCSPM #8 TCGS.D4L7.B1

(TCSPM)05/2020 07/07/2020 01/07/2020 20/08/2020 12/08/2020 09/06/2020 25/08/2020 +11wks

TCAPM #1 TCAPM.A5L7.B1 - - 29/06/2020 02/03/2020 - 15/07/2020 19/03/2020 -16wks

TCAPM #2 TCAPM.A5R7.B2 - - 27/04/2020 02/03/2020 - 15/05/2020 25/03/2020 -7wksTCPP #5 TCPP.C6L7.B1 07/2020 04/08/2020 03/02/2020 15/09/2020 30/09/2020 - 06/10/2020 -

Page 20: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

20

Collimators

LS2 Baseline 2.2

Collimators

LS2 Foreseen dates

NEG activation after Cool-Down

Sector 67:

- W40/41 Survey measurement at cold

- W43/45 Survey V and R smoothing at cold

Sector 78:

- W37/38 Survey measurement at cold

- W41/43 Survey V and R smoothing at cold

Updated Collimators schedule after new reception dates

Page 21: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

21LHC coordination meeting, 18th February 2020

LHC P7 RR73 / RR77

Page 22: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

11T installation in Sector 78

22

New dates presented in the LMC on the 20th of November are obsoleted:

• 9R7 removal postponed to March 2020

LHC coordination meeting, 18th February 2020

Page 23: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Reminder

LHC coordination meeting, 18th February 2020 23

Page 24: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC Access Constraint overview

W8-W9, 2020

24LHC coordination meeting, 18th February 2020

Page 25: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

25

Week 8/9 2020 - P1 + Sector 1-2 + P2 + Sector 2-3

LHC coordination meeting, 18th February 2020

Page 26: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

26

Week 8/9 2020 - P3 + Sector 3-4 + P4 + Sector 4-5

LHC coordination meeting, 18th February 2020

Page 27: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

27

Week 8/9 2020 - P5 + Sector 5-6 + P6 + Sector 6-7

LHC coordination meeting, 18th February 2020

Page 28: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

28

Week 8/9 2020 - P7 + Sector 7-8 + P8 + Sector 8-1

LHC coordination meeting, 18th February 2020

Page 29: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Next meetings

29

W9: 25th February LS2 coordination meeting #64

W11: 10th March LS2 coordination meeting #65

https://indico.cern.ch/category/7200/

LHC coordination meeting, 18th February 2020

Page 30: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

Back-up Slides

30LHC coordination meeting, 18th February 2020

Page 31: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 31

Friday 8th May 2020

Page 32: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 32

Friday 26th

June 2020

(tbc with CMS)

Page 33: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 33

Monday 3rd August 2020

Page 34: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

BE-ICS: Access System Commissioning

LHC coordination meeting, 18th February 2020 34

Friday 21st August 2020

Page 35: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

35LHC coordination meeting, 18th February 2020

LHC General

Page 36: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

36LHC coordination meeting, 18th February 2020

LHC P1

Page 37: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

37LHC coordination meeting, 18th February 2020

LHC P1.8

No Access

Page 38: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

38LHC coordination meeting, 18th February 2020

LSS1L/R

Page 39: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

39LHC coordination meeting, 18th February 2020

LHC P1 RR13 / RR17

Page 40: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

40

LHC P1 RR13 / RR17

LHC coordination meeting, 18th February 2020

Page 41: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 41

Arc

1-2

: D

ISM

AC

Page 42: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

42

Arc 1-2: 16L2 & CC-C11L2

LHC coordination meeting, 18th February 2020

Page 43: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

43LHC coordination meeting, 18th February 2020

TI2

Page 44: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

44LHC coordination meeting, 18th February 2020

LHC P2

Page 45: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

45LHC coordination meeting, 18th February 2020

LHC P2 UA23

Page 46: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

46LHC coordination meeting, 18th February 2020

LHC P2 UA27

No

Acce

ss

Page 47: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

47LHC coordination meeting, 18th February 2020

LSS2L/R

Page 48: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 48

Arc

2-3

: D

ISM

AC

LHC coordination meeting, 10th December 2019

Page 49: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

49

Arc 2-3: CC-C11R2

LHC coordination meeting, 18th February 2020

Page 50: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

50LHC coordination meeting, 18th February 2020

LHC P3.2 + P3.3

No

Acce

ss

No

Acce

ss

LHC-L-PRD-0002https://edms.cern.ch/document/2138732/

Page 51: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

51LHC coordination meeting, 18th February 2020

LSS3L/R

EN

-EL

Main

tenance P

4

Page 52: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 52

Arc

3-4

: D

ISM

AC

Page 53: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

53LHC coordination meeting, 18th February 2020

LSS4L/R

EN

-EL M

Ain

ten

an

ce

Page 54: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

54LHC coordination meeting, 18th February 2020

LHC P4

No

Acce

ss

LHC-L-PRD-0002https://edms.cern.ch/document/2138732/

Page 55: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

55LHC coordination meeting, 18th February 2020

LHC P4

No

Acce

ss

No

Acce

ss

Page 56: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 56

Arc

4-5

: D

ISM

AC

Page 57: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

57

LHC P5

LHC coordination meeting, 18th February 2020

Page 58: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

58LHC coordination meeting, 18th February 2020

LHC P5 RR53 / RR57

Page 59: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 59

LSS5L/R

EN

-EL M

ain

ten

ance P

4

Page 60: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 60

Arc 5-6: DISMAC

Page 61: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

61

LHC P6

LHC coordination meeting, 18th February 2020

Page 62: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

62

LHC P6 UA63 UA67

LHC coordination meeting, 18th February 2020

Page 63: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 63

LSS6L/R

TE-VSC vacuum control section will be finished week 8 (left side)

Page 64: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 64

Arc 6-7: DISMAC

Page 65: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

65

LHC P7

LHC coordination meeting, 18th February 2020

Page 66: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

66LHC coordination meeting, 18th February 2020

LSS7L/R

Page 67: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

67LHC coordination meeting, 18th February 2020

LHC P7 RR73 / RR77

Page 68: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 68

Arc 7-8: DISMAC

Page 69: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 69

Arc

7-8

: 11

T &

SIT

Page 70: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

70LHC coordination meeting, 18th February 2020

LSS8L/R

Page 71: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 71

LHC P8

Page 72: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 72

LHC P8 UA83 UA87

Page 73: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

73LHC coordination meeting, 18th February 2020

Ti8

Under definition

Page 74: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC coordination meeting, 18th February 2020 74

Arc 8-1

Page 75: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC LSS1 Co-Activities in March 2020

W10W14, 2020

75LHC coordination meeting, 18th February 2020

Page 76: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

RL

P1 Week 10 (from 2 to 6 March)

LHC coordination meeting, 18th February 2020 76

Pulling cable campaign

From US15 to 6R including ITs

Scaffolding needed (DFBX MBXW.4R1)

Pulling cable campaign

From US15 to 6L including ITs

Scaffolding needed (DFBX MBXW.4L1)

Page 77: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

RL

P1 Week 11 (from 9 to 13 March)

LHC coordination meeting, 18th February 2020 77

Optical Fibre Campaign

US15cell 14L1

9-12 Mar

EN-SMM alignment

Q8R1Q1R1

9 - 13 March

Connection&Test cable campaign

From US15 to 6L including ITs

Scaffolding needed (DFBX MBXW.4L1)

Connection&Test cable campaign

From US15 to 6R including ITs

Scaffolding needed (DFBX MBXW.4R1)

Canalis reinstallation

RR13

10-16 March

Page 78: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

RL

P1 Week 12 (from 16 to 20 March)

LHC coordination meeting, 18th February 2020 78

Optical Fibre Campaign

US15cell 14R1

16-17 Mar

EN-SMM alignment

Q8L1Q1L1

16- 20 March

Connection&Test cable campaign

From US15 to 6L including ITs

Scaffolding needed (DFBX MBXW.4L1)

Scaffolding removal:19 March

Connection&Test cable campaign

From US15 to 6R including ITs

Scaffolding needed (DFBX MBXW.4R1)

Scaffolding removal:19 March

Page 79: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

RL

P1 Week 13-14 (from 23 to 27 March)

LHC coordination meeting, 18th February 2020 79

EN-SMM alignment

Q8L-Q8R

Until 27 March

Page 80: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC LS2 OSS Organisation

80LHC coordination meeting, 18th February 2020

Page 81: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

General Information

LHC coordination meeting, 18th February 2020 81

Page 82: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 Coordination

82LHC coordination meeting, 18th February 2020

LIU-TCDIL in Ti2&Ti8F.X.-Nuiry

Connexion cryostat full assembly in LSS2

D. Schoerling

11T Dipole Full Assembly in LHC P7

D. Schoerling

DISMAC (Dipole diodes consolidation

& Magnets replacement)

J.-Ph. Tock

Water cooled cablesreplacementB. Gutierrez

Facility Coordinators

Frame & ArcsMarzia Bernardini

EROS

LHC 4 & 5Emmanuel Paulat

Integration

Frederic Galleazzi

Jean Pierre Corso

Configuration / Layout DB

Anne-Laure PerrotCollimators

(TCLIA in LSS2, TCSPM in LSS7)

I. Lamas

Installation of generalservices in the UPR

L. Tavian

Consolidation of the LHC access system

T. Hakulinen

New TANB in LSS8F. Sanchez

LSSsMichela Pirozzi

Maria Barberàn

Support for projects:

- DISMACEstrella Vergara

- HL-LHC UPRMarta Alcaide

New TDIS in L2 and R8A. Perillo

Activity Technical

Coordinator

TDE consolidationD. Grenier

Service areasJulie Coupard

LHC 2 & 3 & 6Michel Bonnet

LHC 1John Etheridge

LHC 7 & 8Cyrille Bedel

LHC Piquet phone 161669

INDICO LHC-LS2 Coordination

LHC LS2 coordination website

Page 83: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

83

LHC-LS2: cryogenics FULL lock out completed

LHC coordination meeting, 18th February 2020

Page 84: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 MsProject Planning Breakdown Structure

84

LHC MASTER Schedule

• LHC_LS2_GENERAL

• LHC LS2 Main Frame

• Service Areas + RRs planning

• Arcs planning

• LHC_LS2_LSS

• LHC LSS planning

• WCC Project detailed planning

• Collimators

• Cabling campaign

• HL-LHC

• LHC_LS2_TI2-TI8

• LHC TI2-TI8 planning

• LIU-LHC: TCDIL installation planning

• LHC_LS2_DISMAC

• DISMAC detailed planning

• Magnet exchange campaing detailed planning

• HL-LHC: WP11 11T

LHC_LS2_GENERAL

LHC_LS2_LSS LHC_LS2_TI2-TI8 LHC_LS2_DISMAC

• Main Constraints

• Main activities summary tasks

LHC MASTER SCHEDULE

_EDMS1817804

_EDMS2000365

_EDMS2030625

_EDMS2020179

Planning Baseline in EDMS on week 48 (end November 2018) LHC coordination meeting, 18th February 2020

Page 85: LHC - LS2 2018-2021 Coordination meeting #63...UW -CV Maintenance Cooling, UA, RE W40 30 Sep 1901 Nov 5 wks Not Started SF - CV Maintenance W45 04-Nov-19 17-Jan-20 9 wks Not Started

LHC-LS2 Linear & Constraint Planning

85LHC coordination meeting, 18th February 2020

LHC_LS2_GENERAL LHC_LS2_DISMACLHC_LS2_LSS LHC_LS2_TI2-TI8