Levy Nuclear PlantOverview of Water Issues
Presented by Jamie Hunter
to the
FDEP – Central District’s
13th Annual Power Generation Conference
Lake Buena Vista, FLJuly 2009
Progress Energy Florida Service Area
Counties shown in green are wholly or partially served by PEF
Levy Nuclear Plant Site Location
Levy Aerial
Levy Site Layout(Expanded View)
Levy Aerial View (Looking West)
Artist Conceptual View
AP1000 Standard Plant Configuration
Major State/Local Permits & Approvals
Levy Co. Land Use/ Zoning/ Comp. Plan Obtained Required Approvals in Sept. 2008
Florida PSC Need Determination Affirmative Determination issued August 2008
Florida Power Plant Site Certification Expect Siting Board Approval in August 2009
Major Federal Permits & Approvals
FDEP PSD Air Construction Permit Obtained Final Permit in February 2008
FDEP NPDES Water Permit Expect Final Permit in Late 2009
Army Corps of Engineers 404/10 Permit Expect Final Permit in Late 2010
NRC Combined Operating License Expect Final License in Late 2011
Levy Nuclear Plant – Air Emissions
Particulate Drift from Cooling Towers
Emergency Diesel Generators/Pumps
Avoided CO2 Emissions – Over 14 Million Tons per Year vs. Coal Over 6 Million Tons per Year vs. Natural Gas
CO2 Emission Factors – Various Fuels
Nuclear Life-Cycle CO2 Emissions
Annual Air Emissions Comparison
Cooling Water Needs/Supply
Low Profile Closed-Cycle Cooling Towers will be Used – Reduces Cooling Water needs by ~95%
Over 99% of the Project’s Water Needs are for Steam Condenser Cooling Requirements
Cooling Tower Makeup Water Needs are ~122 MGD
Source:
Cross Florida Barge Canal
CT Blowdown of ~82 MGD
Discharge Location:
Crystal River Energy Complex
CFBC at Inglis Lock – Looking West
CFBC at Inglis Lock – Looking East
Cross Florida Barge Canal (Looking West)
Intake
Levy Cooling Water Intake at CFBC
Levy Make-Up Pipeline Route
Levy Blowdown Pipeline Route
Crystal River Site Discharge Canal
Freshwater Needs/Source
Project Requires Freshwater for: Process Boiler Water/Steam Makeup
Process Equipment Cooling System
Potable Water for Drinking/Sanitary
Fire Suppression Systems
Freshwater Quantity Needed is 1.58 MGD
Freshwater Source is Groundwater from Floridan Aquifer via Onsite Wells
Groundwater Well Locations/Drawdown
Groundwater Wells/ Wetland Overlay
Wetland Impacts/Mitigation
Project Property Contains a Significant Amount of Wetlands
Project Site Design/Layout Planned to Avoid/Minimize Wetland Impacts
Total Project Impacts (Plant/Transmission) Currently >400 UMAM Credits
Much of the Mitigation Proposed to occur Onsite, with additional Offsite as Needed
Wetlands Total/ Wetlands Impacted
Water Summary
>95% Reduction in Overall Water Needs with the Use of Cooling Towers
>99% of Project Water Needs Met by Use of Salt Water for Steam Condenser
Cooling
Minimal Aquifer and Wetland Impacts from Groundwater Withdrawals
Wetland Impacts Minimized and Unavoidable Impacts Fully Mitigated
An Update of What’s Behind the News