Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ...

33
Lesson 1- Contract Documents & BQ Copy Right. ES. 2015. 1

Transcript of Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ...

Page 1: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Copy Right. ES. 2015.

1

Page 2: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Copy Right. ES. 2015.

2

OUTLINE

Standard Form of Contract

Standard Method of Measurement

3 essentials elements for contract documents

Bill of Quantities & it’s Benefits

Contents of BQ

Page 3: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Copy Right. ES. 2015.

3

Standard Form of Contract

1. To set up the client’s requirements and the condition of the project and;

2. To guide the contractual parties and all consultants through the construction process (can be modify to suit the needs or situation);

3. E.g. general description & drawings, quality of work, contractual condition for administration, construction programs, etc.

Standard Method of Measurement

1. To provide a common basis for measuring the component parts and scale for the project which is uniformly used and understood by the construction industry.

Page 4: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

There are 3 essential elements of Contract Documentation:

1. The form of Contract

The wisely contract documents practiced locally shall be the latest SIA Articles and Conditions of Building Contract (Private) and Public Sector Standard Conditions of Contract (Public), etc.

These conditions lay down the legal agreement which will be formalized between client and contractor as a legal framework.

4

Copy Right. ES. 2015.

Page 5: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

There are 3 essential elements of Contract Documentation:

2. The Contract Drawings

To provide the essential locational information, along with the overall design and details of the building (plan, sections, elevation & details)

Architectural, Structural and M&E Design Drawings (discrepancies?)

It is good that comprehensive contract drawing are providing sufficient information, precise and clearer understanding of the project. This will leads to accurate, genuine and realistic price (less dispute & VO)

5

Copy Right. ES. 2015.

Page 6: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

There are 3 essential elements of Contract Documentation:

2. The Contract Drawings (Cont’d)

6

Copy Right. ES. 2015.

Tender Drawings

Contract Drawings

Construction Drawings

Detailed / Shop

Drawings

As-Built Drawings

Page 7: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Copy Right. ES. 2015.

7

Title block

Page 8: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

There are 3 essential elements of Contract Documentation:

3. The Specifications

Exact statement of the particular needs to be satisfied, or essential characteristics that a client requires (in a good, material, method, process, service, system or work) and which a Contractor must deliver.

The Specifications provide the necessary qualitative information and should explicitly define the quality of all work indicated on the contract drawings.

Need to be expressed in writing as drawings alone cannot define.

(1) Performance Specifications: conform to known customer requirement;

(2) Technical Specifications: express the level of performance of the building.

8

Copy Right. ES. 2015.

Page 9: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Bill of Quantities (BQ)

What is BQ?

9

Copy Right. ES. 2015.

Page 10: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Bill of Quantities (BQ)

What is BQ?

A list of the items with detailed identifying descriptions and quantities, which make up the component parts of the building.

BQ translate the drawings, schedules and specification notes produced by designer into documents.

It’s provide a uniform and common basis for pricing a competitive tender in any project. And it establishes an accurate account of quality and quantity of the work set out in a logical system for pricing by contractors.

BQ needs to be fully described and accurately represented the quantity and quality of work to be carried out, as accordance to SMM7 0r NRM2

10

Copy Right. ES. 2015.

Page 11: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Bill of Quantities (BQ) – Cont’d Functions

1. To sets out a systematic manner indicating the quantities and descriptions of the items of labour ,materials, and plant required to erect and complete a building. This may later offer assistance to the contractor in ordering materials and labourarrangement.

2. To provide a basis for valuation of variation to the contract, which are common occurrences during the construction period.

3. To provide a basis for the valuation of work executed for the purpose of making interim payments to the Contractor.

4. To facilitates budget control for both the Employer and the Contractor.

5. Good basis for a cost analysis for use on future projects in cost planning.

11

Copy Right. ES. 2015.

Page 12: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Form of Bill of Quantities

1. Preliminaries

2. Prime Cost (PC) & Provisional Sum incl Profit & Attendance

3. Contingency Sum

4. Preambles

5. Measured Works

6. Day Works

7. Appendices

12

Copy Right. ES. 2015.

Page 13: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(1) Preliminaries

It contains the general clauses and recommendation pertaining to the Works and the Site. It gives directives on what should be allowed for besides the normal items appearing in BQ. E.g. plant, site staff, site facilities, protection works to surrounding neighbors, safety protection for public, noise & vector control.

The nature and the size of the project will determine the value of the preliminaries in the total contract sum.

The contents of preliminaries bill are usually based on the particulars listed in section 2 – Preliminaries of SMM7 . These particulars include details on preliminary particulars, contract particulars, general matters and obligations and Works by NSC; good and Materials by NS, and Works by Local Authorities.

13

Copy Right. ES. 2015.

Page 14: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(1) Preliminaries (Cont’d)

14

Copy Right. ES. 2015.

Page 15: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(2) Prime Cost Sum (PC) & Provisional Sums

PC Sum: Works which is to be carried out by a nominated sub-contractor or for materials to be supplied by a nominated supplier for fixing by the Contractor.

The firms are to be selected by the Architect who will instruct the Contractor to enter a contractual relationship with them & to coordinate the work.

Contractor is entitle with pre-determined Profit & Attendance for the coordination works.

Provisional Sum: Works which is cannot be entirely foreseen or design/drawings has not been finalized at the time or preparing the BQ, and are not subject to Contractor’s profit and attendance normally.

15

Copy Right. ES. 2015.

Page 16: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(2.1) Profit (%)

It represents a management fee for arranging and taking responsibility for sub-contract work or for arranging, checking and accepting the supply of material and goods.

Usually in the forms of percentage % of the indicative prime cost or as a lump sum which is inserted by the tenderers (less practice). The final Contractor’s profit will be finalized and adjusted on a pro-rata basis only at the time of actual final invoices obtained.

16

Copy Right. ES. 2015.

Page 17: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(2.2) Attendance (sum)

The main contractor is responsible for the satisfactory integration of NSC work within the main contract works; with providing general site facilities without work interruption. E.g. site access, standing scaffolding, electricity & water supply, rubbish disposal, space for sub-con site office, etc.

Besides, it aims to enable proper provision to be made for significant costs beyond those visualized in the general attendance.

The sums inserted is not adjustable, as the amount and type of attendance works or services is unlikely to vary significantly with variations in the actual cost of the sub-contract.

17

Copy Right. ES. 2015.

Page 18: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(3) Contingency Sum

Is allowed in the contract to cover the cost of work or expenses not contemplated or implied in the contract sum e.g. underground structural and services diversion works, variation cost arise from late design confirmation or changes.

It will be a substantial saving to the client where such unforeseen circumstances did not occur.

The process for implementing and using contingency amounts should be contractual, as spelled out as part of the agreement for accountability purposes.

18

Copy Right. ES. 2015.

Page 19: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles

It contains descriptions relating to the quality and performance of materials, the standard of workmanship, testing of materials and workmanships, and taking samples of materials, and any other ancillary works which to be included in price.

Thus, it always bring attention of estimators they will affect the price/rates that he inserts against billed items of measured works.

It reduces significantly the length of the item descriptions and assists considerably in correct pricing for all.

19

Copy Right. ES. 2015.

Page 20: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles - Examples

20

Copy Right. ES. 2015.

Page 21: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles - Examples

21

Copy Right. ES. 2015.

Page 22: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles - Examples

22

Copy Right. ES. 2015.

Page 23: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles - Examples

23

Copy Right. ES. 2015.

Page 24: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(4) Preambles - Examples

24

Copy Right. ES. 2015.

Page 25: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(5) Measured Works

This is the main part of the bill of quantities, which listed all the items of work to be undertaken directly by the Contractor.

The quantities and descriptions of items should be determined in accordance with the tabulated rules of measurement of SMM7 or NRM2.

Trade Method: Items in the bill are grouped under their respective trades clearly. This will minimize the possibility of repetition and useful for subletting process.

Elemental Method: Items of work are group according to their position in the building, on the basis of a recognized elemental subdivision of the project.

(to be discussed in detail in later)

25

Copy Right. ES. 2015.

Page 26: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ26

Trade Method Elemental Method

Brickwork Block 1181

Half Brick Solid Brick Sub-Structural Works

- 1st Storey Pile-Cap

- Typical Storey - Excavation

- Roof Storey - Lean Concrete

Full Brick Solid Brick - Formwork

- Internal Wall - Rebar

- External Wall - Concrete

Copy Right. ES. 2015.

Page 27: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(6) Dayworks

It covers those works which cannot be properly measured and valued at the rates in BQ due to abnormal work sequencing, different in work conditions, etc.

It is a method of payment for work based on the prime cost of all labour, materials and plant used in carrying out the work, and overhead and profit are deemed to have been included in the daywork rates in respect of labour and plant.

“Timesheet Card”, detailing the time spent daily of the workmen’s names and the plant and materials used, shall be submitted for verification to Architect’s site representative.

The rates and prices used in the valuation of daywork shall be based on the inserted in the schedule during tender, without any adjustment of actual wages or market condition.

27

Copy Right. ES. 2015.

Page 28: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ28

Copy Right. ES. 2015.

Page 29: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ29

Copy Right. ES. 2015.

Page 30: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ30

Copy Right. ES. 2015.

Page 31: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

(7) Appendices

Schedule of Rate (SOR)

Material Price List for fluctuation claim, if any

Particular specifications

Copies of quotation

Copies of correspondences,

List of Warranties & Indemnities,

Letter of Undertaking,

Special safety conditions & green mark requirements, etc

31

Copy Right. ES. 2015.

Page 32: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ

Recap: Form of Bill of Quantities

1. Preliminaries

2. Prime Cost (PC) & Provisional Sum incl Profit & Attendance

3. Contingency Sum

4. Preambles

5. Measured Works

6. Day Works

7. Appendices

32

Copy Right. ES. 2015.

Page 33: Lesson 1- Contract Documents & BQ - Trent Global – The ... · Lesson 1- Contract Documents & BQ ... - 1st Storey Pile-Cap - Typical Storey - Excavation - Roof Storey ... Schedule

Lesson 1- Contract Documents & BQ33

Copy Right. ES. 2015.