Legal hurdles to deployment of SMRs in the UK SMR 2016 · SMR 2016 Funded Decommissioning Programme...
Transcript of Legal hurdles to deployment of SMRs in the UK SMR 2016 · SMR 2016 Funded Decommissioning Programme...
Legal hurdles to deployment of SMRs in
the UK
SMR 2016
Ian Truman
Burges Salmon LLP
9th June 2016
SMR 2016
Overview
Regulatory approach
Lifecycle, Phases and Key Issues of a nuclear new
build project in the current UK regulatory regime
Current government policy and its applicability to
SMRs
What is required to facilitate deployment of SMRs
in the UK
SMR 2016
Regulatory approach
Economics of SMRs reliant on regulators accepting claims of
developers e.g. EPZs, number of control rooms per unit etc
Claims largely untested by Western regulatory bodies - ONR/EA have
not been formally engaged and/or funded
Starting point for any ONR/EA assessment?
Goal based regulatory approach requires safety case to persuade
regulators that risks are ALARP – evidence to support claims and
arguments ?
Compatibility of UK approach with international efforts to standardise
generic design acceptance for SMRs – CORDEL, MDEP, ERDA?
SMR 2016
Lifecycle, Phases and Key Issues
Predevelopment Phase
Final Investment decision
Construction
Decommissioning
Commissioning
Operation
Design Complete
Key Consents
Key Agreements
Finance
Project Company
Engagement Finance Site Technology
and contracting
Licensing and
consents
Develop Design
Budget Schedule Dispute
Resolution Contract
Management Managing change
Key Regulatory Hold Point
LC 21
Refinancing Outages Change in
Law / Guidance
Safety CFD Site Licence Life
extension
FDP Site Licence Supply Chain Decommissioning Contracts
Spent Fuel and Waste Disposal
FDP Waste
Transfer Contract
GDF Development
Government Policy on
Spent Fuel
Technological advances
SMR 2016
Current policy
Government White Paper “Meeting the Energy Challenge”
in 2008:
“The Government believes new nuclear power stations should have a role to
play in this country’s future energy mix alongside other low carbon sources;
that it would be in the public interest to allow energy companies the option of
investing in new nuclear power stations; and that the Government should take
active steps to facilitate this.”
Facilitative actions were aimed at large nuclear and some
are not appropriate to SMRs e.g. SSA, planning reform,
funded decommissioning guidance
SMR 2016
Sites
Theoretically less siting restrictions for SMRs
SSA and the Nuclear NPS
Non-listed sites can come forward - s105 Planning
Act 2008 but not optimal
New NPS would have to approved by Parliament
Took 38 months to develop current Nuclear NPS
Competitive auction of land e.g. Magnox sites?
SMR 2016
Streamlined planning process
s15 of the Planning Act 2008 a generating station is an
NSIP if its capacity is 50MW or more when constructed or
extended
NSIP applications for nuclear reactors to be decided in
accordance with Nuclear NPS – which doesn’t currently
cover SMRs
DCO process currently takes ~15 months (assuming no
judicial review)
SMR 2016
Licensing a nuclear installation in the UK
Justification
Generic Design Assessment
Nuclear Site Licensing
SMR 2016
Justification
A decision from the Secretary of
State that the economic social or
other benefits derived from any new
class or type of practice involving
ionising radiation outweigh any
health detriment that may be caused
Application submitted to SoS
Judicial review risk
Potential timescales - 28 months
(without challenge)
SMR 2016
Generic Design Assessment
Not mandatory but widely
regarded as necessary
Lack of evidence to support safety
cases
Advantage for developers of
smaller versions of larger
reactors?
Lack of regulatory expertise in the
UK and abroad
Typically 4 years plus for larger
reactors – SMRs?
SMR 2016
Licensing
Applicant must persuade ONR
risks are ALARP
Inspection of manufacturing
facilities
Separate companies
manufacturing and constructing?
Separate operators on a site?
Typically takes about 2 years
SMR 2016
Funded Decommissioning Programme
s47 of the Energy Act 2008 - it is a criminal offence to ‘use’ a
nuclear site without having an FDP approved by the SoS
Decommissioning Waste Management Plan (DWMP) and a
Funding Arrangements Plan (FAP)
Developing DWMP involves comparison against a Base Case
i.e. a generic lifecycle plan for a new nuclear power station
DECC’s current base case is not suitable for SMRs e.g. it is
based on a large reactor and assumes on-site interim storage
facilities for ILW and spent fuel
Timescales?
SMR 2016
Nuclear liability / Insurance
Current requirement for operators is to
provide insurance or other financial security
to a limit of £140 million
The Nuclear Installations (Liability for
Damage) Order 2016 implements the 2004
Paris Protocol into UK Law
Increases limits phased in over 5 years from
€700 million to €1200 million
Low hazard installations €70 million
Not clear how government will approach
SMRs
SMR 2016
Nuclear Liability – cont.
The IAEA’s CSC – USA and (more recently) Canada have now
signed this convention and it offers a platform for a global regime.
Now in force following Japan joining.
UK has no treaty relations with USA, China, Russia, Canada, Korea
Supply chain joined into TEPCO case in California
UK Indemnity pressures building
Indemnities for SMR developers / supply chain?
SMR 2016
SMR 2016
Finance
Certain historic finance difficulties
eased by promise of SMRs including:
- shorter construction phase
- enhanced safety
- simple design
- lower capital costs per unit
Other traditional financing difficulties
remain:
- political risk
- foak (at least initially)
- no take over of the asset
SMR 2016
Government support mechanisms
Revenue stabilisation
– long term CFD
Sovereign credit
guarantee – lowers
cost of borrowing
SMR 2016
Revenue Stabilisation
Impact of response to
the HPC strike price
Will government
accept more risk in
future?
Current uncertainty for
large nuclear and
SMRs
SMR 2016
Debt Guarantee
Infrastructure Guarantee allows
operator to make use of the
Government’s credit rating
Can lower the cost of borrowing
and create liquidity for the Bank
market
State Aid approval required (if UK
remains in the EU)
SMR 2016
Other Finance
Project financing
Sovereign model
Utility balance sheet
Government-to-Government
ECAs
Vendor credit or equity
Investor financing
SMR 2016
Remaining Challenges for deployment of
SMRs in the UK
Develop and resource ONR/EA to develop a regulatory model:
- risk characterization and mitigation – are SMR promises viable?
- review current codes and standards
- publish regulatory guidance
Implement facilitative package for SMRs with roadmap:
- CFDs
- commence siting strategy to pre-approve sites and update the Nuclear NPS
- Commence land auction programme if applicable
- FDP guidance
Engagement on nuclear liability
SMR 2016
Questions
SMR 2016 This presentation gives general information only and is not intended to be an exhaustive statement of the law. Although we have taken care
over the information, you should not rely on it as legal advice. We do not accept any liability to anyone who does rely on its content.