    PLANNING ENGINEERING &PROJECT MANAGEMENT

    DEPARTMENT OF ENGINEERINGMANAGEMENT, COLLEGE OF E&ME,

    NUST

    LECTURER:ENGR. AFSHAN NASEEM

    LECTURE NO.5

  • 7/30/2019 Lec.05.PEPM.afshan

    2/14

    QUIZNO.2

    Develop a WBS for designing an aircraft.

    Engr.AfshanNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    3/14

    WORK BREAKDOWNSTRUCTURE (CONTD.)

  • 7/30/2019 Lec.05.PEPM.afshan

    4/14

    FORMATSOFWBS

    Engr.AfshanNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    5/14

    FORMATSOFWBS

    Tree Diagram/Org-Chart Format

    Indented Outline Format

    Bubble Format

    Cycling Format

    Engr.AfshanNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    6/14

    ORG-CHARTFORMAT

    Org-chart format: Often good for a bird view of the

    project (executive summaries,...)

    Less effective for displaying largenumbers of activities

    Engr.AfshanNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    7/14

    PERMITS/INSPECTIONS

    SAMPLE WBS - GARAGE

    GARAGEPROJECT

    GARAGEGROUNDS CONSTR.PLANS

    PROJECTMGT

    WALLSFOUNDATION ROOFUTILITIES

    FRAME DOORS/WINDOWS

    Level 1

    Level 4DOORS/

    WINDOWS

    DRY WALL/

    PANELINGASSEMBLY

    ASSEMBLY

  • 7/30/2019 Lec.05.PEPM.afshan

    8/14

    OUTLINEFORMAT

    Outline format:

    Easier to read and understand if WBScontains many activities

    Engr.Afsha

    nNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    9/14

    INTRANET WBS IN TABULAR FORM

    1.0 Concept

    1.1 Evaluate current systems

    1.2 Define Requirements

    1.2.1 Define user requirements

    1.2.2 Define content requirements

    1.2.3 Define system requirements

    1.2.4 Define server owner requirements

    1.3 Define specific functionality

    1.4 Define risks and risk management approach

    1.5 Develop project plan

    1.6 Brief Web development team2.0 Web Site Design

    3.0 Web Site Development

    4.0 Roll Out

    5.0 Support

    Engr.Afsha

    nNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    10/14

    BUBBLEFORMAT

    Bubble format:

    Effective for supporting the brainstormingprocess

    Not so good for displaying workbreakdown structures to audiences whoare not familiar with the project.

    Use bubble format to develop the WBS,then turn it into Org-Chart or outline

    format.

    Engr.Afsha

    nNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    11/14

    11

    Bubble Format:

    ReviewDraft Report Prepare

    Report

    Review

    Draft Report

    Review

    Final Report

    PrintFinal Report

    Write

    Final Report

  • 7/30/2019 Lec.05.PEPM.afshan

    12/14

    COMBINEDFORMAT

    In large projects:

    Use a combination of org-chart andoutline formats:

    Display activities in org-chart format,

    Display subactivities and tasks in outlineformat.

    Engr.Afsha

    nNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    13/14

    CYCLINGFORMAT

    A cycling format is utilized on researchprojects that are performed in phases.

    Although WBS elements are usually thought

    of as representing unique, one time events,research projects present a differentapproach.

    In this case, a cycling WBS is recommended

    because as tasks are executed, newinformation may create need to repeat tasksat a new level of detail.

    Engr.Afsha

    nNaseem

  • 7/30/2019 Lec.05.PEPM.afshan

    14/14

    DISCUSSION