PLANNING ENGINEERING &PROJECT MANAGEMENT
DEPARTMENT OF ENGINEERINGMANAGEMENT, COLLEGE OF E&ME,
NUST
LECTURER:ENGR. AFSHAN NASEEM
LECTURE NO.5
-
7/30/2019 Lec.05.PEPM.afshan
2/14
QUIZNO.2
Develop a WBS for designing an aircraft.
Engr.AfshanNaseem
-
7/30/2019 Lec.05.PEPM.afshan
3/14
WORK BREAKDOWNSTRUCTURE (CONTD.)
-
7/30/2019 Lec.05.PEPM.afshan
4/14
FORMATSOFWBS
Engr.AfshanNaseem
-
7/30/2019 Lec.05.PEPM.afshan
5/14
FORMATSOFWBS
Tree Diagram/Org-Chart Format
Indented Outline Format
Bubble Format
Cycling Format
Engr.AfshanNaseem
-
7/30/2019 Lec.05.PEPM.afshan
6/14
ORG-CHARTFORMAT
Org-chart format: Often good for a bird view of the
project (executive summaries,...)
Less effective for displaying largenumbers of activities
Engr.AfshanNaseem
-
7/30/2019 Lec.05.PEPM.afshan
7/14
PERMITS/INSPECTIONS
SAMPLE WBS - GARAGE
GARAGEPROJECT
GARAGEGROUNDS CONSTR.PLANS
PROJECTMGT
WALLSFOUNDATION ROOFUTILITIES
FRAME DOORS/WINDOWS
Level 1
Level 4DOORS/
WINDOWS
DRY WALL/
PANELINGASSEMBLY
ASSEMBLY
-
7/30/2019 Lec.05.PEPM.afshan
8/14
OUTLINEFORMAT
Outline format:
Easier to read and understand if WBScontains many activities
Engr.Afsha
nNaseem
-
7/30/2019 Lec.05.PEPM.afshan
9/14
INTRANET WBS IN TABULAR FORM
1.0 Concept
1.1 Evaluate current systems
1.2 Define Requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements
1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief Web development team2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support
Engr.Afsha
nNaseem
-
7/30/2019 Lec.05.PEPM.afshan
10/14
BUBBLEFORMAT
Bubble format:
Effective for supporting the brainstormingprocess
Not so good for displaying workbreakdown structures to audiences whoare not familiar with the project.
Use bubble format to develop the WBS,then turn it into Org-Chart or outline
format.
Engr.Afsha
nNaseem
-
7/30/2019 Lec.05.PEPM.afshan
11/14
11
Bubble Format:
ReviewDraft Report Prepare
Report
Review
Draft Report
Review
Final Report
PrintFinal Report
Write
Final Report
-
7/30/2019 Lec.05.PEPM.afshan
12/14
COMBINEDFORMAT
In large projects:
Use a combination of org-chart andoutline formats:
Display activities in org-chart format,
Display subactivities and tasks in outlineformat.
Engr.Afsha
nNaseem
-
7/30/2019 Lec.05.PEPM.afshan
13/14
CYCLINGFORMAT
A cycling format is utilized on researchprojects that are performed in phases.
Although WBS elements are usually thought
of as representing unique, one time events,research projects present a differentapproach.
In this case, a cycling WBS is recommended
because as tasks are executed, newinformation may create need to repeat tasksat a new level of detail.
Engr.Afsha
nNaseem
-
7/30/2019 Lec.05.PEPM.afshan
14/14
DISCUSSION