LEBT Beam neutralization, H-injection for space charge compensation, magnets
description
Transcript of LEBT Beam neutralization, H-injection for space charge compensation, magnets
1
LEBTBeam neutralization, H-injection forspace charge compensation, magnets
LEBT=Low Energy Beam Transport
R. Scrivens, JB Lallement, T Zickler, T Fowler.
Linac4 Source External Review, 7 June 2011
2
LEBT
Transfers and matches the beam from the source to the RFQ.Allows placement for diagnostics.Position for the Beam-Stoppers and Pre-chopper.
3
Layout of the first 3MeV Building 152 LEBT
LEBT contains:
2 Solenoids2 H+V Steerers2 Beam stopper1 Faraday Cup1 Harp Profile MonitorPump / GaugeSector valveGas InjectionPre-ChopperBeam Current TransformerIon Trapping Electrode
4
Almost fully assembled “3MeV Test Stand” LEBT
5
Optics - computing
LEBT beam dynamics are modelled with the multi-particle PATH code.CERN code, maintained in BE/ABPSpace charge (radial mesh or point to point)Magnetic field maps (3D or R-Z)It is fast (1 minute per simulation)Batch processing of runs (scan solenoid settings automatically)IBSimu code now has a PATH Manager output file option.
6
Solenoid
SourceEmittance meter
Comparison of the simulation and measurement through 1 solenoidMeasurements made before and after the solenoid.
Optics - computing
7
Shown is a phase space plot of measured protons, H2+ H3+ beam, superimposed with a simulation.Shows good agreement of the main features of the beam -> Confidence in PATH.
Optics - computing
-0.150
-0.100
-0.050
0.000
0.050
0.100
0.150
-3.5 -3.0 -2.5 -2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5
X'(r
ad)
X(cm)
Single Solenoid 1000A -H+ H2+ H3+
10mA
X’ (mrad)
X (mm)
Protons
H2+
H3+
H0
8
Optics
Based on the common two solenoids approach, as used at Linac2, and many other LEBTs.Original starting point was a measurement of the emittance from DESY (at 35keV).100mm aperture has been maintained (with the new solenoids).With significant changes to the extraction, LEBT input conditions change.Modifications to extraction will have to be iterated through the LEBT layout to assure consistency (aim is to not redesign the LEBT for each source modification).
-0.015
-0.010
-0.005
0.000
0.005
0.010
0.015
0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0
x rm
s (m
)
Distance (m)
Example beam profile along the LEBT
9
The decision has been made to use large aperture solenoids (more flexibility, better field quality in the usable aperture). Max 140mm aperture, 340mm total length.DC powering (estimates are than the DC option is cheaper overall).MedAustron (a CERN collaboration partner) is ordering these solenoids now. Linac4 can piggy back on the order.LEBT was designed to allow 320mm long solenoids. New length and final positioning need to be checked.Magnet follow up by TE/MSC (Magnets).Power Convertors from TE/EPC (Power Convertors)
Solenoids
0
0.5
1
1.5
2
2.5
3
3.5
0 10 20 30 40 50 60
Bz (k
G)
Position (cm)
Bz field plot
10
Steerers
2 sets of window steerer corrector magnets. Up to 50 mrad steering if required.Positioning made into “free space” in the LEBT.Laminated cores. Will allow shot-to-shot variation for testing.Ambient air cooled. DC power convertors.Magnets for the 3MeV test stand / Linac4 are operational (with power convertors)Spare unused magnets from the 3MeV line could be reused. Situation to be followed up.
Power Convertors by TE/EPC
11
Pre-Chopper
The pre-chopper is an electrostatic kicker, deflecting the beam away from the RFQ input.Shortens the rise time of the beam, limiting the unwanted beam into the RFQ.Limits the fall time, reducing the beam sent to the tail dump.Acts as part of the beam interlock system, inhibit accelerated beam in Linac4, but allow the source to pulse. It is not considered to have a high safety “rating”.An initial, 10kV deflector was designed (request to increase voltage to 20kV came after production was launched).
Can be tested with protons, and DC powering in 2011.Driver will be produced by TE/ABT group.Driver specification is being written. Delivery is for mid 2012, to test with H- and the RFQ at the test stand.
12
Space Charge Compensation
Space charge of the low energy beam is compensated by ions/electrons, created by projectile/rest gas collisions.Independent injection of gas into the LEBT is foreseen. Hydrogen and Xenon should be tested.Higher pressure means faster compensation, but more gas stripping of H-. ~3% stripping loss at 45keV at 1x10-5 mbar pressure.Optimisation of the two processes of this will be in the range 10-7 to 5x10-5 mbar.
13
2 LEBT Installations
3MeV Test Stand – Future Linac4For June 2012• New Solenoids• Diagnostic tank modification• Pre-Chopper -> 20kV
Source Test Stand – Building 152Critical Items for September 2012• New Installation of all equipment.
14
3MeV Test Stand LEBT modificationsObjective is to be ready to modifications in a 3 month period in 2012, when the proton source is stopped. Design office needs to start in August 2011 to meet this schedule.Full planning in progress.
General Schedule
15
Items completed and installed
Solenoids 3MeV versions recovered from Linac1 and Linac2.
To be replaced by larger aperture DC solenoids.
Steerers
Faraday Cup
SEMGrid
Pumping 1 x 600 l/s turbo pump + group
Pressure Penning + Pirani Gauge set
Beam Current Transformer
Heavily shielded design
16
Still to be completed
Beam Stoppers Under construction
Gas Injection Gas delivery to be made and tested with beam
Ion Trapping electrode
Produced, but not yet installed
In design Phase
Solenoids To be replaced by larger aperture DC solenoids.
Pre-Chopper Pre-chopper to be redesigned for higher voltages.Driver for specification starting.
Layout modification
Reorder diagnostics box to allow beam measurement in access conditions.
17
Cost (kchf)
Original LEBT cost 650
Still to do for existing LEBT. 250
Extra pair of solenoids and steerers 110
Diagnostics See presentation U Raich
Pre chopper (Driver plus modifications to the design)
Power Convertors See presentation D Nisbet
LEBT modifications for new source prototypes 100
Additional b357 source test stand costs 200
Manpower (FTEy)
Finalising 3MeV TS LEBT – Co-ord Source TS LEBT 1.0
Pre Chopper Driver
Commissioning LEBT 1.0
Optics Simulations (for different source variants) 0.5
Commissioning (with different source variants) 0.75
18
• Planning for modifications for the 3MeV test stand LEBT are very tight. • Time for beam testing will be VERY limited.• For the source test stand, prioritisation will need to be given after feedback from the workshop.
Feasibility
19
The test stand version of the LEBT is running (with some missing parts).Several updates are needed to 3MeV Test Stand LEBT.A new Source Test Stand LEBT is needed. Planning very tight and prioritisation needed.
Summary