LEB 30 VII 09 C. Garion Aluminum bellows for experiments C. Garion & R. Veness, TE/VSC.
-
Upload
shanon-norton -
Category
Documents
-
view
214 -
download
0
Transcript of LEB 30 VII 09 C. Garion Aluminum bellows for experiments C. Garion & R. Veness, TE/VSC.
LEB 30 VII 09C. Garion
Aluminum bellows for experiments
C. Garion & R. Veness, TE/VSC
LEB 30 VII 09
Outline
• Development history
• 2 ways of procurement Japanese company CERN
• Development at CERN Material Bellows parameters Bellows manufacturing Present situation and further actions
• Conlusions
C. Garion
LEB 30 VII 09C. Garion
Development History• Formed Bellows
– European industry R&D project (1999-2001)• Thick-walled aluminium bellows are
made for cryogenic applications, but no standard production of thin-walled bellows in Europe
• 2 development projects were followed with European manufacturers, but neither successful results nor much interest
• Machined Bellows– CERN Workshops (2001-2006)
• Good results obtained for 0.3 mm thick bellows
• Pieces installed in LHCb (small stroke)• Leaks during production and test linked
to material form and quality
R.Veness LEB 30 VII 09
LEB 30 VII 09C. Garion
Japanese Industry• Background
– Both Titanium and Aluminium bellows have been used in accelerator vacuum systems in Japan (TRISTAN and J-PARC)
– They were produced by Japanese industry in large numbers following joint development projects with the labs
– With help from KEK, a potential supplier was identified, and CERN issued a specification
R.Veness
LEB 30 VII 09C. Garion
Development Contract• Prototype series
– Order placed in June ‘09 for a series of 3 bellows, as per the drawing opposite
– Delivery expected end Oct ’09
• Full series– An offer has been made for a
series of 30 bellows– Unit Price ~ 1800 CHF/piece– 3 months delivery
R.Veness
LEB 30 VII 09C. Garion
CERN development for formed bellows Material
Requirements:
Formability (high ductility)
Weldability (also with 2219)
Low Heat affected zone
Available in thin foils
Good mechanical properties
2 materials: series 5000 (Magnesium):
Well weldable
Good corrosion resistance
Mechanical properties acceptable
Non heat treatable
5754 H22:
0.3mm thick
5083 H111, 0.2 and 0.3mm thick (available beginning of September)
0.2 and 0.3 mm thick
LEB 30 VII 09C. Garion
DesignAlgorithm of optimization of bellows expansion joints
(Based on EJMA)
•Minimise the objective function:
•inequality constraints: bellows convoluted lengthinner diameterouter diameterbellows maxi compression
membrane stressmembrane stress membrane & bending stress
fatigue life
column buckling in-plane squirm
c
p3
pmT
fblax n
n
w
tdE
C)x(F
0LL blmax 0DD minin
0DD outmax 0minbl
0SS 1ad 0SS 2ad
0)SS(S 4334
0N)S(N 0ftf
0PP 1col 0PP 2inp
Atlas constraints (technical specification EDMS 429891):
Lbmax = 100 mm
Dmin ~ 60 mm
Dmax = 80 mm
Stroke = -24/+8mm
Nf > 500 cycles
LEB 30 VII 09C. Garion
DesignBellows parameters
Thickness 0.3 mm Thickness 0.2 mm
Other wish: if possible use the same tooling:
0.3mm thick: 13 convolutions, bellows length: ~96mm, Inner diameter: 60 mm, outer diameter: 78.8mm
0.2mm thick: 8 convolutions, bellows length: ~59mm, Inner diameter: 60 mm, outer diameter: 78.8mm
Design has to be compatible with formability capacity
LEB 30 VII 09C. Garion
Bellows manufacturing(courtesy of L. Prever Loiri, EN/MME)
Aluminum foil Rolled tube & longitudinal weld (EB) Welds of the end fittings (EB)
Forming @150°C combining pressure and displacement loading
Cut of the end fittings
LEB 30 VII 09C. Garion
Present situation2 materials have been chosen:
•5754 has been received, metallurgical and mechanical tests have been done (EN/MME)
•5083 has been ordered. Delivery is expected beginning of September
Bellows parameters have been defined and optimized
Welding procedure has been determined
Metallurgical observations (grain size, inclusions) Tensile test at room temperature
Micrograph of longitudinal weld
LEB 30 VII 09C. Garion
Present situationTooling (forming and welding) have been designed and manufactured (EN/MME)
First tube equipped with the end fittings is ready for forming
Tubes are equipped with the end fittings
Analysis is being done to optimize the forming process (pressure-displacement function)
LEB 30 VII 09C. Garion
Forming simulation
Plastic strain after forming
Mesh Deformed shapesMesh
Pressure
Displacement
Further detailed FE analysis will be done (A. Sarrio Martinez)
LEB 30 VII 09C. Garion
Next steps
Forming tests on 5754 tube:
-As assembled
-After heat treatment (annealing)?
Qualification tests:
-Leak tightness
-Fatigue life a room temperature
-Stability?
Reception of 5083 and metallurgical tests
Welding tests
Forming
Qualification:
-Leak tightness
-Fatigue life a room temperature
-Stability?
LEB 30 VII 09C. Garion
Tentative schedule(Alba Sarrio)
Task Name Duration Start
Order material (Al-5083) 16 wks Mon 5/18/09
Crack propagation test 50 days Thu 5/28/09
Define test 2 mons Thu 5/28/09
Calibration of the test 2 wks Thu 7/23/09
Characterize material Al-5083 2 mons Mon 9/7/09
Tooling for the forming and welding 2 wks Thu 5/28/09
Circular weld and edges 112 days Thu 6/11/09
Al-5754 6 wks Thu 6/11/09
Al-5083 2 wks Mon 11/2/09
Forming 110 days Mon 7/6/09
Numerical simulations 3 wks Mon 7/6/09
Al-5754 6 wks Thu 7/23/09
Al-5083 3 wks Mon 11/16/09
Qualification tests 123 days Wed 7/15/09
Testing tooling production 1 mon Wed 7/15/09
Prototype test 1 mon Mon 12/7/09
Series production 3 mons Mon 1/4/10
19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
First bellows by August 2009
End of prototyping: 12/09
Series
LEB 30 VII 09C. Garion
Conclusions
An order has been placed to a Japanese company for aluminum bellows prototypes
Development of aluminum bellows at CERN is well advanced:
-2 Material chosen: 1 delivered and 1 available beginning of September
-Forming process at “high” temperature will be used
-Bellows parameters are defined
-Welding process are defined
-Tooling for forming are ready
Forming process will probably not be straight forward. Iterations might be necessary.