(LEAN) PROCESSPLANNING in the DESIGN PHASE · (LEAN) PROCESSPLANNING in the DESIGN PHASE IGLC 2014...

31
CASE: ACADEMY OF ART AND DESIGN IN BERGEN (KHIB) (LEAN) PROCESSPLANNING in the DESIGN PHASE IGLC 2014 JUNE 23rd

Transcript of (LEAN) PROCESSPLANNING in the DESIGN PHASE · (LEAN) PROCESSPLANNING in the DESIGN PHASE IGLC 2014...

CASE: ACADEMY OF ART AND DESIGN IN BERGEN (KHIB)

(LEAN) PROCESSPLANNING in the DESIGN PHASE

IGLC 2014 – JUNE 23rd

OR: HOW TO HANDLE AN ELEPHANT…

KHIB: SOME FACTS…

Projectstart and designcompetition: Autumn 2005

Granting of final construction work fundings: June 2013

Total budget (pr. July 2013): 1.038 mill. NOK (incl. VAT)

Floor space (pr. July 2013): 14.500 sqm

Schedule:

2014: Detailled design / Demolition / Ground preparations

2015: Foundation works / Framework / Enveloping

2017: Scheduled completion Q2

OWNER - CLIENT: Statsbygg

ARCHITECTS: Snöhetta

DESIGNING ENGINEERS: Ramböll

1) Experiences from Lean Construction (ie. UiO Domus Medica, Oslo)

2) Lean construction seminars (ie. Porsche Consulting)

3) Takt - Train

4) Film-clip: 30 floors in 14 days (China)

And as an objective: A very lean project.

BACKGROUND / LEAN MOTIVATION

• Strategy

- An as lean project as possible in design and construction.

- Lean on all levels and in all phases.

• Tools

- BiM

- dRofus (room functional database)

KHIB PLAN

GENERAL PROJECT PRINCIPALS

Transparency / Overview / Collaboration

Culture for continous improvement

Lean included in all contract documents

Extended lean requirements for contractors

Reduce, minimize or (preferably) eliminate waste

Flow where possible

Maximize frontloading

KHIB LEAN STEP BY STEP

1) Pre-Seminar

Discussing and preparing a lean construction strategy.

Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting)

Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process

«Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors.

- Contract review.

- Contract handover (from design to contractors).

- Frontloading (putting the puzzle together).

- Lean construction.

6) Lessons learned

PLANNING USING

LAMINATED

A0-DRAWINGS

DRAFT 2ND FLOOR

CONSTRUCTION

STRATEGY

1) Pre-Seminar

Discussing and preparing a lean construction strategy.

Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting)

Project top level (1) overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process

«Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors.

- Contract review.

- Contract handover (from design to contractors).

- Frontloading (putting the puzzle together).

- Lean construction.

6) Lessons learned

KHIB LEAN STEP BY STEP

PCP-LEAN-SEMINAR W/ PORSCHE CONSULTING

COMPLETE PROCESSMAP LEVEL 1

DEPENDENCIES & TRANSPARENCY

EVERYONE ON THE SAME PAGE

«LEVEL 2 & 3»

COMPLETE PROCESSMAP LEVEL 1

PROCESSES (7)

STATSBYGG PHASES & MILESTONES (MAINTAINED)

KEYPOINTS (NEW)

Everyone developed the PCP-level-1-map together.

Everyone’s «on the same page».

Everyone has «the same mind».

Everyone has the same objectives.

WITH MINDS FULL OF A LOT OF THEORY AND EXPECTATIONS.

1) Pre-Seminar

Discussing and preparing a lean construction strategy.

Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting)

Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..? From construction to design.

4) Developing and improving the lean design process

«Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors.

- Contract review.

- Contract handover (from design to contractors).

- Frontloading (putting the puzzle together).

- Lean construction.

6) Lessons learned

KHIB LEAN STEP BY STEP

Cutting the elephant into minor manageable pieces.

Continous flow to BiM and physical construction.

Restructure flow according to contracts and milestones.

Issues/topics have appointed owners.

2-week «takt» with one 3-day big-room co-location.

Continous priority 1-2-3 (or: must-should-can).

Iteration-steps: 5 fw and 1 bw (instead of 4-3).

Efficiency: 80% effort & 20% time spent (instead of 100-100).

DESIGN TEAM OBJECTIVES

TOPICS WITH

ISSUSES & OWNERS

CONTINOUS FLOW

TO THE VIRTUAL

BUILDING (BIM) AND

THE PHYSICAL

BUILDING

DESIGN FLOW OVERVIEW

OWNER

TOPIC

ISSUES:

- RESOURCES

- TIME

- INPUT

DEADLINE

«PRODUCT»/OUTPUT

SLICING THE ELEPHANT: MINOR PIECES / TOPICS

2-WEEK «TAKT»

INCL.

3-DAYS BIG-ROOM

CO-LOCATION

«TAKT and TRAIN»

2 WEEK TAKT /

WORK PROCEDURE

1) Pre-Seminar

Discussing and preparing a lean construction strategy.

Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting)

Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process

«Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors.

- Contract review.

- Contract handover (from design to contractors).

- Frontloading (putting the puzzle together).

- Lean construction.

6) Lessons learned

KHIB LEAN STEP BY STEP

COMBINING THE LEVELS

TOPICS /

OWNERS /

PRIORITY /

STATUS

CONNECTED TO:

PROCESSES AND

KEYPOINTS (LEVEL 1)

«LEVELS 2 & 3»

PROCESSES (7)

MILESTONES & KEYPOINTS & BIM-DEVELOPMENT

LEVEL 2 PROJECT

DESIGNPLAN

(TOPIC OVERVIEW)

3-DAYS BIG-ROOM CO-LOCATION

3-DAY MEETING SESSIONS

BOOKING LIST

TOPIC OWNER SHARING

TOPIC

OWNER

BIG ROOM

1) Pre-Seminar

Discussing and preparing a lean construction strategy.

Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting)

Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process

«Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors.

- Contract review.

- Contract handover (from design to contractors).

- Frontloading (putting the puzzle together).

- Lean construction.

6) Lessons learned

KHIB LEAN STEP BY STEP

The lean processes in the project are ongoing.

Lean takt-planning and construction are yet to come.

(From 2015 onwards.)

KHiB goal:

The lessons so far learned in KHiB lean design, have

been visualized in this presentation.

Common mindset for all parties involved in the project

Common objectives and tools and agreed transparency

Lean project strategy (for mindshift, construction and design)

Complete and transparent project processoverview («all in»)

Agreeing on «minor pieces» and continous flow

Assign topics with issues and owners

Agree on work-procedures and managing (decision)levels

Big-room transparency

Putting the pieces together (BiM & construction)

SUMMARY

QUESTIONS…?

(If time…)

Hans Thomas Holm / Statsbygg

• Projectmanager with Statsbygg since 2007. • Projectmanager for KHiB since June 2013. • Email: [email protected] • Cell-phone: +47 - 915 73 626

Sven Wertebach / Terramar

• Projectmanager with Terramar since 2013. • Designmanager for KHiB since September 2013. • Email: [email protected] / [email protected] • Cell-phone: +47 - 415 42 992