deliver projects better, faster, together
LEAN CONSTRUCTION IRELANDDELIVER PROJECTS BETTER, FASTER, TOGETHER
LCI WEBINAR NO.11 (07 SEPTEMBER 2017)
“THE 5 LEVELS OF THE LAST PLANNER® SYSTEM: SHOULD, CAN, WILL, DID AND LEARN”
PRESENTED BY PAUL EBBS, SPECIAL GUEST DAVE UMSTOT
deliver projects better, faster, together
LCI Ireland COP WebinarDate : 7th Sept 2017
Presenter : Paul Ebbs, with special guest David Umstot of Umstot Project and Facility Solutions, LLC.
Moderated by : Eleanor Parker (LCI Leadership Group Representative)Opening Introduction by: Richard Fitzpatrick – Chair, Lean Construction Ireland
Topic : The 5 Levels of the Last Planner® System: Should, Can, Will, Did and Learn
deliver projects better, faster, together
Today’s Presentation
deliver projects better, faster, together
Personal Planning
What % of your personal promises are completed every day?
deliver projects better, faster, together
Who are the Last Planners®?The Last Planners are those who are closest to the work at the
lowest level of responsibility who can commit resources or have the
authority to make decisions during planning meetings.
deliver projects better, faster, together
1. Those closest to the work know the work best and plan the
work - the “Last Planners”
2. Leverage the collective experience of the team to plan
3. It delivers bad news…
Why use the Last Planner® System?
deliver projects better, faster, together
1.Better project outcomes
2.“Articulates and activates” a routine of conversations that lead to
commitments
3.Produces reliable work plans and reduces variability which leads to
greater trust and facilitates efficient execution of work
What are some of the benefits of the Last Planner® System?
deliver projects better, faster, together
Early 1990s and continues to be developed today
Ballard & Howell surveyed
7 construction companies
450 foremen’s weekly work plans
Q: What % of the time did foremen deliver on their promises?
Ranged between 33% and 70%
Average …
Development of the Last Planner® System
deliver projects better, faster, together
What Happens when Commitments are Missed?
“Promising”, particularly the ability to make and elicit reliable promises, is the primary skill needed for working in the LPS and is key to coordination… (Hal Macomber and
Greg Howell, 2003)
deliver projects better, faster, together
A social system used for production planning & control to improve workflow,
plan reliability, coordination and the predictability of work on projects.
The basic premise is those who do the work, plan the work, and make
commitments to complete work (reliable promises) to other members of the
team.
What is the Last Planner® System?
deliver projects better, faster, together
What role does the Last Planner® System play within a Lean Project
Delivery System?1. Social system and backbone of Lean Project Delivery.
2. Stabilises workflow variation towards continuous flow for Last Planners.
3. Dictates the pace of production by making work ready so what SHOULD be done CAN be
done. Once it CAN be done promises are elicited for work that WILL be done. Promises are
tracked daily (DOING & DID) to ensure the team LEARN from any plan failures and prevent
reoccurrence.
deliver projects better, faster, together
What is the Last Planner®System?
deliver projects better, faster, together
According to the Lean Construction Institute (2015, p. 149):The LCI holds a registered trademark (®) on Last Planner®. The purpose of trademarking the term is to take care of the use and meaning of Last Planner and the Last Planner System of Production Control®. There is no intent to prevent people and companies from using LPS® to deliver their projects. All LCI asks is for people to include the registered trademark ® once in any document, to note that the Lean Construction Institute is the owner of the trademark and to include LCI’s website with the attribution. (www.leanconstruction.org)
Trademark of the Last Planner® System
deliver projects better, faster, together
According to the Lean Construction Institute (2015, p. 149):The LCI holds a registered trademark (®) on Last Planner®. The purpose of trademarking the term is to take care of the use and meaning of Last Planner and the Last Planner System of Production Control®. There is no intent to prevent people and companies from using LPS® to deliver their projects. All LCI asks is for people to include the registered trademark ® once in any document, to note that the Lean Construction Institute is the owner of the trademark and to include LCI’s website with the attribution. (www.leanconstruction.org)
Trademark of the Last Planner® System
deliver projects better, faster, together
Should: Milestone & Phase Planning
deliver projects better, faster, together
Should: Milestone Planning (30,000’)
Image courtesy of David Umstot
©2017PaulEbbs
deliver projects better, faster, together
Should: Phase Planning (10,000’)
©2017PaulEbbs
Image courtesy of David Umstot
deliver projects better, faster, together
Why use Pull Planning?• Can you say the alphabet?• Can you say it backwards?•Why is it so difficult?
• Flush out predecessors and constraints that release work• Gain a better understanding of each actors work and the
project as a whole• Helps deliver bad news at the wall and not in the field
©2017PaulEbbs
deliver projects better, faster, together
CAN: Make Ready Planning (1,000’)
©2017PaulEbbs
deliver projects better, faster, together
CAN: 6 – 8 Week Make Ready Plan
©2017PaulEbbs
deliver projects better, faster, together
CAN: Flow Walk - Screening for Constraints
©2017PaulEbbs
deliver projects better, faster, together
WILL: Commitment Planning (100’)
©2017PaulEbbs
deliver projects better, faster, together
WILL: Reliable Promising
The Conversations for Action Cycle (after Flores, 2013 and Macomber and Howell, 2003)
©2017PaulEbbs
deliver projects better, faster, together
WILL: Weekly Work Coordination
©2017PaulEbbs
deliver projects better, faster, together
DID: Daily Huddle
©2017PaulEbbs
deliver projects better, faster, together ©2017PaulEbbs
DID: Daily Huddle
deliver projects better, faster, together
LEARN: Improve the System
©2017PaulEbbs
deliver projects better, faster, together
The person?
The system?
Both?
LEARN: Who is Blamed when Projects Slip?
©2017PaulEbbs
deliver projects better, faster, together
LEARN: Reasons for Missed Commitments
deliver projects better, faster, together
Which Team was Successful???
©2017PaulEbbs
deliver projects better, faster, together
Where to find out more?
©2017PaulEbbs
deliver projects better, faster, together
Thank You
©2017PaulEbbs
For more information contact
deliver projects better, faster, together
Q&A
deliver projects better, faster, together
LEAN CONSTRUCTION IRELANDDELIVER PROJECTS BETTER, FASTER, TOGETHER
WWW.LEANCONSTRUCTIONIRELAND.IE
WWW.LINKEDIN.COM/GROUPS/4332330
WWW.FACEBOOK.COM/LEANCONSTRUCTIONIRELAND
TWITTER.COM/LCI_IRELAND