Lean A3 Report for Planning Downtime Elimination

1
A3 Report 1B. CLARIFY THE PROBLEM: Eliminate Planning Downtime from 5 Hours per Week to 0 Hours per Week by July 2012. 2. BREAKDOWN THE PROBLEM: 3. SET A TARGET (The challenge): 4. ANALYZE THE ROOT CAUSE: 5 & 6. DEVELOP & IMPLEMENT COUNTERMEASURES: 7. EVALUATE RESULTS: 8. STANDARDIZE: Next challenge: Sharing with others: Lessons Learned: Form #: F-108 - Revision Date: 02/17/201 Waste(s) Identified Transportation: Inventory: Motion: Waiting: X Overproduction: Over processing Defects Skills Unused Means of Standardization: Standard Work Visual Aids /Procedures Training X Process Audits: LPA TPM Checklist 5S Audit X Other Root Causes Selected Countermeasure Who Target Finish There is no standardization at location of packages by size and model. Providing area for packaging in shelves IC Team WK 1229 WK 1229 Separation and standardization of packages location according to the type Thiego Silva WK 1229 WK 1229 Visual identification of each location for packages Rodrigo Marques WK 1229 WK 1229 Data collection – After improvement Nattyer Nunes WK 1229 WK 1229 Key Metric to Impact: Downtime IM / FA Problem Identification: What: High Where: IM/FA When: Wk 25 ~ Wk 28 How much: 15% 1A. Opportunity: Elimination of Planning Downtime Team Member Names: Leader: Thiego Silva Site/Plant: Manaus Date:22/08/2012 Nattyer Nunes Group/Workcell/Site: STB Annual Savings (US$): Rodrigo Marques Mentor: Thiego Silva - 100% of planning Downtime is related to Lack of available package in the process. - 15% of Average Downtime IM/FA is related to Planning. - Average Downtime is 5 hours per week. Loss time Planning Downtime: Lack of available package Method Environme nt - Employees not trained about how organize the place of package - Lack of organization of the location of packages - The location of packages is not standardized - Why planning Downtime? Due lack of available package in the process - Why? Because the packages were not available when the process was requested. - Why? Because operator loses time looking for packages - Why? Due lack of organization of the packages - Why? There is no standardization at location of packages by size and model. - Operator loses time when looking for packages - Eliminate buffer and other wastes that can be solved by Planning Team. - Share this project with production leaders and stock area employees. Visual Management is an important tool. It makes problems visible. Planning Downtime Eliminated Savings MVA – Material Value Added per unit US$ 6 / unit MVA / Hour (MVA x Rate) US$ 1422 / h Plannig Downtime 5 Hours / Week Total Saving/WK US$ 7110/ Week Total Saving/Month US$ 28440 / Month High Downtime: IM / FA US$ 28440/Mon th Before After

description

A3 Report (Lean Manufacturing template for PDCA), Applied to a project to reduce line down  due to lack of returnable boxes. ... Relatório em formato A3 (Template para o PDCA usado no Lean Manufacturing), aplicado a um projeto de redução de paradas de linha devido falta de embalagens vai-e-vem.

Transcript of Lean A3 Report for Planning Downtime Elimination

Page 1: Lean A3 Report for Planning Downtime Elimination

A3 Report1B. CLARIFY THE PROBLEM:

Eliminate Planning Downtime from 5 Hours per Week to 0 Hours per Week by July

2012.

2. BREAKDOWN THE PROBLEM:

3. SET A TARGET (The challenge):

4. ANALYZE THE ROOT CAUSE:

5 & 6. DEVELOP & IMPLEMENT COUNTERMEASURES:

7. EVALUATE RESULTS:

8. STANDARDIZE:

Next challenge:

Sharing with others:

Lessons Learned:

Form #: F-108 - Revision Date: 02/17/2012

Waste(s) Identified

Transportation:

Inventory:

Motion:

Waiting: X

Overproduction:

Over processing

Defects

Skills Unused

Means of Standardization:

Standard Work Visual Aids Global Document /Procedures

Training Other X

Process Audits:

LPA TPM Checklist 5S Audit X Other

Root Causes Selected Countermeasure Who Target Finish

There is no standardization at

location of packages by size and model.

Providing area for packaging in shelves IC Team WK 1229 WK 1229

Separation and standardization of packages location according to the type Thiego Silva WK 1229 WK 1229

Visual identification of each location for packages Rodrigo Marques WK 1229 WK 1229

Data collection – After improvement Nattyer Nunes WK 1229 WK 1229

Key Metric to Impact:

Downtime IM / FA

Problem Identification:

What: High

Where: IM/FA

When: Wk 25 ~ Wk 28

How much: 15%

1A. Opportunity: Elimination of Planning Downtime Team Member Names:

Leader: Thiego Silva

Site/Plant: Manaus Date:22/08/2012 Nattyer Nunes

Group/Workcell/Site: STB Annual Savings (US$): Rodrigo Marques Mentor: Thiego Silva

- 100% of planning Downtime is related to Lack of available package in the process.

- 15% of Average Downtime IM/FA is related to Planning.

- Average Downtime is 5 hours per week.

Loss

time

Planning Downtime:

Lack of available package

Method

Environment

- Employees not trained about how organize the place of package

- Lack of organization of the location of packages

- The location of packages is not standardized

- Why planning Downtime?Due lack of available package in the process- Why?Because the packages were not available when the process was requested.- Why?Because operator loses time looking for packages- Why?Due lack of organization of the packages- Why?There is no standardization at location of packages by size and model.

- Operator loses time when looking for packages

- Eliminate buffer and other wastes that can be solved by Planning Team.

- Share this project with production leaders and stock area employees.

Visual Management is an important tool. It makes problems visible.

Planning Downtime Eliminated

SavingsMVA – Material Value Added per unit

US$ 6 / unit

MVA / Hour (MVA x Rate) US$ 1422 / hPlannig Downtime 5 Hours / Week

Total Saving/WK US$ 7110/ Week

Total Saving/Month US$ 28440 / Month

High Downtime: IM / FA

Before After

US$ 28440/Month