Name of work: Construction of a latrine at S.No . Description of work No Measurements. Conten ts L B D 1 Earthwork excavation in all clauses of soils with initial lead and lift as per SS20 for foundation. Wall all-round 1 20.72 0.75 0.75 11.66c um c/s wall 1x2 4.92 0.75 0.75 5.54cu m Septick tank 1 4.46 2.46 1.50 16.46c um 33.66c um 2 Filling with carted sand including all cost and conveyance and all labour charges etc. complete. Basement: w.c.room 1x2 5.33 0.78 0.30 2.44cu m Passa ge 1 5.22 1.78 0.30 2.79cu m 5.23cu m 3 Cement concrete 1`:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc. complete.

Transcript of Latrine Skelten

Page 1: Latrine Skelten

Name of work: Construction of a latrine at

S.No.

Description of workNo Measurements.

Contents

L B D

1 Earthwork excavation in all clauses of soils with initial lead and lift as per SS20 for foundation.Wall all-round 1 20.72 0.75 0.75 11.66c

umc/s wall 1x2 4.92 0.75 0.75 5.54cu

mSeptick tank 1 4.46 2.46 1.50 16.46c

um33.66c

um

2 Filling with carted sand including all cost and conveyance and all labour charges etc. complete.Basement: w.c.room 1x2 5.33 0.78 0.30 2.44cu

m Passage 1 5.22 1.78 0.30 2.79cu

m5.23cu

m

3 Cement concrete 1`:4:8 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges etc. complete.Foundation: Main wall all-round

1 20.72 0.75 0.30 4.66cum

c/s wall 2x1 4.92 0.75 0.30 2.21cum

Basement: w.c.room 1x2 5.22 0.78 0.10 0.81cum

Passage 1x1 5.22 1.78 0.10 0.93cu

Page 2: Latrine Skelten

m Septic tank 1 4.46 2.46 0.10 1.10cu

mDeduct:w.c. portion in floor

2x5 0.40 0.30 0.10 0.12cum

9.59cum

4. Random Rubble Masonry in cement mortar 1:5, mix using required bond stone with simultaneous pointing etc. complete.I st footing: Wall all-round

1 20.72 0.60 0.45 5.59cum

c/s wall 1x2 5.07 0.60 0.45 2.74cum

IInd forint: Wall all-round

1 20.72 0.45 0.50 4.66cum

c/s wall 1x2 5.22 0.45 0.50 2.35cum

15.34cum

S.No.

Description of workNo Measurements.

Contents

L B D

5 Brickwork in cement mortar 1:5, mix using country bricks including all cost and conveyance and all labour charges etc. complete.Plinth core wall: wall all-round

1x2

20.72 0.055

0.11 0.25cum

c/s wall 2x2

5.22 0.055

0.11 0.13cum

Superstructure wall all-round

1x2

20.72 0.23 2.40+2.2

21.92cum

Passage rear wall 1 2.00 0.23 2.40 1.10cu

Page 3: Latrine Skelten

mW.C.room c ros wall 2x

41.00 0.11 1.80 1.58cu

mSeptic tank 1 12.92 0.23 1.50 4.46cu

mWater tub 1 6.92 0.23 1.00 1.59cu

mSteps L.S. 0.63cu

mDeductions:Door 5x

20.75 0.23 2.00 3.45cu

m RCC jolly 5x

20.30 0.23 0.30 0.21cu

m Lintel 1x

25.90 0.23 0.15 0.41cu

m27.59c

um

6 Supplying and fabrication of steel for RCC works including all cost and conveyance and all labour charges etc. complete.As per steel schedule 4.70qtl

.

7. Centering soffits for RCC works including all cost and conveyance and all labour charges etc. complete.Lintel alround 2 sides 2x

212.26 - 0.15 7.36sq

m Bottom of door 2x

50.75 0.23 - 1.7

3sqmRoof slab bottom 1x

25.44 1.00 - 10.88s

qmProjection bottom 2x

25.90 0.20 - 4.72sq

mSide all-round 2x

115.52 - 0.10 3.10sq

mTub beam two sides 1x

22.46 - 0.23 1.13sq

mBottom of tub 1 1.23 2.00 - 2.46sq

Page 4: Latrine Skelten

mTub slab side all-round 1 7.84 - 0.10 0.78sq

m32.16s

qm

S.No.

Description of workNo Measurements.

Contents

L B D

8 R.C.C.1:1 ½:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc. complete.Plinth Beam : al round 1 20.72 0.34 0.11 0.77cu

m Cross wall 1x2 5.33 0.34 0.11 0.40

cumLintel 1x2 5.90 0.23 0.15 0.41

cumRoof slab 1x2 5.90 1.86 0.10 2.19

cumTub beam 1x2 2.46 0.23 0.23 0.26

cumTub bottom slab 1 2.46 1.46 0.10 0.36

cumSeptic tank cover slab 1x9 2.46 0.50 0.075 0.83

cum5.22cu

m

9 Paving the floor with good quality of ceramic tiles including all cost and conveyance etc. complete.W.C.room floorAdd door wayDeduct: w.c. portionPassage floor

Page 5: Latrine Skelten

Add front open door way

10 Daddoring wall with good quality of ceramic tiles including all cost and conveyance and all labour charges etc. complete.

11 Granolithic type floor concrete in cement concrete in 1:2;4 mix using 10-12mm chips including all cost and conveyance etc. complete.W.C. portionDoor wayDeduct w.c.portion.

S.No.

Description of workNo Measurements.

Contents

L B D

12 Plastering with cement mortar 1:5 mix using 12mm thick including all cost and conveyance etc. complete.w.c.rom inner all-round below c/s wall

2x5 4.00 - 1.80 72.00sqm

_d0_above c/s wall 1x2 1.84 - .6+.4/2

13.84sqm

Top of c/s wall 2x5 1.00 0.11 - 1.10sqm

Passage wall 3 sides 1 13.34 - 2.40 32.02sq

Page 6: Latrine Skelten

mWater tub inner 1 6.00 - 1.00 6.00sq

mTop of tub 1 6.92 0.23 - 1.59sq

mTub outer all-round 1 7.84 - 1.00 7.84sq

mBuilding outer all-round 1 21.64 - -2.20 47.61sq

mGable wall 1/2

x2x2

1.46 - 0.2/2 0.29sqm

Passage rear wall portion

1 2.00 - 1.50 3.00sqm

Soffits of door 2x5 4.75 0.23 - 10.93sqm

Front open soffits 1x2 - 0.23 2.40 1.10sqm

Soffits of rcc jolly 2x5 1.20 0.10 - 2.16sqm

Brickondege all-round 1 22.52 0.22 - 4.95sqm

Top roof slab 1x2 5.90 1.86 - 21.95sqm

Ceiling 1x2 5.44 1.00 - 10.88sqm

Two sides projection 2x2 5.90 0.20 - 4.72sqm

Add for steps 1.92sqm

Septic tank inner all-round

1 12.00 - 1.50 18.00sqm

Deductions:Door 2x5 0.75 - 2.00 15.00sq

mRCC jolly 2x5 0.30 - 0.30 0.90sq

mFront open 1 2.00 - 2.00 4.00sq

m242.00s

qm

13 White washing two coats including all cost

Page 7: Latrine Skelten

and conveyance and all labour charges etyc. Complete.w.c.rom inner all-round below c/s wall

2x5 4.00 - 1.80 72.00sqm

_d0_above c/s wall 1x2 1.84 - .6+.4/2

13.84sqm

Top of c/s wall 2x5 1.00 0.11 - 1.10sqm

Passage wall 3 sides 1 13.34 - 2.40 32.02sqm

Water tub inner 1 6.00 - 1.00 6.00sqm

Top of tub 1 6.92 0.23 - 1.59sqm

Soffits of door 2x5 4.75 0.23 - 10.93sqm

137.48sqm

S.No.

Description of workNo Measurements.

Contents

L B D

137.48sqm

Front open soffits 1x2 - 0.23 2.40 1.10sqm

Soffits of rcc jolly 2x5 1.20 0.10 - 2.16sqm

Top roof slab 1x2 5.90 1.86 - 21.95sqm

Ceiling 1x2 5.44 1.00 - 10.88sqm

Two sides projection 2x2 5.90 0.20 - 4.72sqm

Deductions:Door 2x5 0.75 - 2.00 15.00sq

mRCC jolly 1x5 0.30 - 0.30 0.45sq

m 162.8

4sqm

14 Colourwashing two coats including all cost

Page 8: Latrine Skelten

and conveyance and all labour charges etc. complete.Building outer all-round 1 21.64 - -2.20 47.61sq

mGable wall 1/2

x2x2

1.46 - 0.2/2 0.29sqm

Passage rear wall portion

1 2.00 - 1.50 3.00sqm

Brickondege all-round 1 22.52 0.22 - 4.95sqm

Basement alround 1 22.52 - 0.50 11.26sqm

Deductions:RCC jolly 1x5 0.30 - 0.30 0.45sq

mFront open 1 2.00 - 2.00 4.00sq

m62.66sq

m

15. Painting with ready mixed paint two coats including all cost and conveyance etc. complete.W.C.Doors 2x2

x50.75 - 1.80 27.00sq

mFront door 1x2 2.00 - 2.00 8.00sq

m35.00sq

m

16. Towards cost and supply of water closets and stone ware pipes including all cost and conveyance etc. complete.

L.S.

17. Towards cost and supply of steel door of size 0.75m x 1.80m

10Nos.

Page 9: Latrine Skelten

18. Towards cost and supply of steel door of size 2.00m x 2.00m

1No.

S.No.

Description of workNo Measurements.

Contents

L B D

19. Towards cost and supply of RCC jolly including all cost and conveyance of size 0.30m x 0.30m

10Nos.

20. Towards water supply of water arrangements

L.S.

21. Towards Electrification wiring charges

L.S.

22. Towards lettering Name board

L.S.

23. Towards cost supply of lock & key.

L.S.

24. Contigencies and other unforeseen charges.

L.S.

Assistant Engineer (R.D.), Rajapalayam.

Page 10: Latrine Skelten

Name of work: Construction of a latrine at-----------------------------------------------------------------------

S.No.

Quantity

Description of work Rate per Amount

1

cum

Earthwork excavation in all clauses of soils with initial lead and lift etc .complete for foundation as per SS 20 B for foundation

1cum

2

cum

Filling with carted sand including all cost and conveyance and all labour charges etc. complete.

1cum

3

cum

Cement concrete 1:4:8 mix using 40mm ISS HBG metal including all cost and conveyance etc. complete.

1cum

4

cum

Random Rubble Masonry in cement mortar 1:5, mix using country bricks including all cost and conveyance etc. complete.

1cum

5

cum

Brickwork in cement mortar 1:5, mix using country bricks including all cost and conveyance etc. complete.

1cum

6

Qtl.

Supplying and fabrication of steel for RCC works including all cost and conveyance etc. complete.

1qtl.

Page 11: Latrine Skelten

7

sqm

Centering soffits for RCC works including all cost and conveyance and all labour charges etc. complete.

1cum

8

cum

R.C.C.1:1 ½:3 mix using 20mm ISS HBG metal inclluding all cost and conveyance etc. com plete.

1cum

9

sqm

Paving the floor with good quality of ceramic tiles including all cost and conveyance and all labour charges.

1sqm

10

sqm

Dadooring wall with good quality of ceramic tiles including all cost and conveyance and all labour charges.

1sqm

11

cum

Granolithic type concrete in cement concrete 1:2:4 mix using 10 12mm chips including all cost and conveyance etc. complete.

1cum

12

sqm

Plastering with cement mortar 1:5,12mm thick including all cost and conveyance and all labour charges etc. complete.

1sqm

c/o

S.No.

Quantity

Description of work Rate per Amount

B/F

13

sqm

White washing two coats including all cost and conveyance and all labour charges etyc. Complete.

1sqm

14 Colourwashing two coats including all cost and conveyance and all labour

1sqm

Page 12: Latrine Skelten

charges etc. complete.15 Painting with ready mixed

paint two coats including all cost and conveyance etc. complete.

1sqm

16 Towards cost and supply of water closets and stone ware pipes including all cost and conveyance etc. complete.

L.S.

17 Towards cost and supply of steel door of size 0.75m x 1.80m

L.S.

18 Towards cost and supply of steel door of size 2.00m x 2.00m

L.S.

19 Towards cost and supply of RCC jolly including all cost and conveyance of size 0.30m x 0.30m

L.S.

20 Towards water supply of water arrangements

L.S.

21 Towards Electrification wiring charges

L.S.

22 Towards lettering Name board

L.S.

23 Towards cost supply of lock & key.

L.S.

24 Contigencies and other unforeseen charges.

L.S.

Total

Page 13: Latrine Skelten

Assistant Engineer (R.D.), Rajapalayam.

Specification report to accompany the estimate for the work of construction of a latrine at

Estimate Amount Rs.

It is proposed to construct a latrine complex at under As per the District Collector’s proceedings No: datedAdopting current schedule of rates for the year 2008_09.

The building contains 10 sets of toilet with size 1.00m x 1.00mwith a passage of 2.00m width.

The following provisions are made in this estimate,

The foundation earth work will be excavated to a width of 0.75m to a depth of 0.75m. In which cement concrete 1:4:8 mix using 40mm ISS HBG metal to a thick of 0.40m. R R. Masonry will be constructed to section of 0.60 x0.45m and 0.45 x 0.60m respectively. The superstructure wall will be in brickwork using country bricks to a thick of 0.23m and to height of 2.40m in front and 2.20m in rear side.

Necessary reinforcement concrete will be provided for plinth beam, lintel and roof slab. For water facilities a tub in brickwork will be constructed in roof level.

The inner and outer wall will be plastered with cement mortar 1;5, 12mm thick. The inner and outer wall will be whitewashed and colour washed respectively. The door will be painted with good enamel paint two coats.

Page 14: Latrine Skelten

Necessary provisions are made for steel doors, R C C jolly, water facilities, name board, lock, and electrification wiring etc.

On sanction of this estimate, the work will be carried out as per standard specifications and other relevant circular in force.

Assistant Engineer (R.D.), Rajapalayam.