LCG LHC Computing Grid Project - LCG
The LHC Computing Grid
First steps towards a
Global Computing Facility for Physics18 September 2003
Les Robertson – LCG Project LeaderCERN – European Organization for Nuclear Research
Geneva, Switzerland
LCG
les robertson - cern-it-2last update 18/04/23 19:51
LCG LHC Computing Grid Project
The LCG Project is a collaboration of – The LHC experiments The Regional Computing Centres Physics institutes
.. working together to prepare and deploy the computing environment that will be used by the experiments to analyse the LHC data
This includes support for applications provision of common tools, frameworks, environment, data
persistency .. and the development and operation of a computing service
exploiting the resources available to LHC experiments in computing centres, physics institutes and universities around the world
presenting this as a reliable, coherent environment for the experiments
les robertson - cern-it-3last update 18/04/23 19:51
LCG
Joint with EGEE
Applications Area
Development environmentJoint projects
Data managementDistributed analysis
Middleware Area
Provision of a base set of gridmiddleware – acquisition,development, integration,
testing, support
CERN Fabric Area
Large cluster managementData recording
Cluster technologyNetworking
Computing service at CERN
Grid Deployment Area
Establishing and managing theGrid Service - Middleware
certification, security, operations,registration, authorisation,
accounting
Operational Management of the Project
les robertson - cern-it-4last update 18/04/23 19:51
LCG Applications Area Projects Software Process and Infrastructure (SPI) (A.Aimar)
Librarian, QA, testing, developer tools, documentation, training, … Persistency Framework (POOL) (D.Duellmann)
POOL hybrid ROOT/relational data store Core Tools and Services (SEAL) (P.Mato)
Foundation and utility libraries, basic framework services, object dictionary and whiteboard, math libraries, (grid enabled services)
Physicist Interface (PI) (V.Innocente) Interfaces and tools by which physicists directly use the software. Interactive analysis,
visualization, (distributed analysis & grid portals) Simulation (T.Wenaus et al)
Generic framework, Geant4, FLUKA integration, physics validation, generator services
Close relationship with -- ROOT (R.Brun) ROOT I/O event store; Analysis package
Group currently working on distributed analysis requirements
LHC data
• 40 million collisions per second
• After filtering, 100-200 collisions of interest per second
• 1-10 Megabytes of data digitised for each collision = recording rate of 0.1-1 Gigabytes/sec
• 1010 collisions recorded each year = ~15 Petabytes/year of data
CMS LHCb ATLAS ALICE
1 Megabyte (1MB)A digital photo
1 Gigabyte (1GB) = 1000MBA DVD movie
1 Terabyte (1TB)= 1000GBWorld annual book production
1 Petabyte (1PB)= 1000TBAnnual production of one LHC experiment
1 Exabyte (1EB)= 1000 PBWorld annual information production
LHC data
~15 PetaBytes – about 20 million CDs each year!
Concorde(15 Km)
Balloon(30 Km)
CD stack with1 year LHC data!(~ 20 Km)
Mt. Blanc(4.8 Km)
Its analysis will need the computing power of ~ 100,000 of today's fastest PC processors!
Where will the experiments store all of this data?
and where will they find this computing power?
The CERN Computing Centre
~2,000 processors~100 TBytes of disk~1 PB of magnetic tape
Even with technology-driven improvementsin performance and costs – CERN can provide nowhere near enough capacity for LHC!
Computing for LHC
Solution: Computing centres, which were isolated in the past, will be connected into a computing grid
Europe: 267 institutes4603 users
Elsewhere: 208 institutes1632 users
-- uniting the computing resources of particle physicists in the world!
les robertson - cern-it-9last update 18/04/23 19:51
LCG LCG Regional Centres
First wave centres CERN Academica Sinica Taiwan Brookhaven National Lab PIC Barcelona CNAF Bologna Fermilab FZK Karlsruhe IN2P3 Lyon KFKI Budapest Moscow State University University of Prague Rutherford Appleton Lab (UK) University of Tokyo
Other Centres Caltech GSI Darmstadt Italian Tier 2s(Torino, Milano,
Legnaro) JINR Dubna Manno (Switzerland) NIKHEF Amsterdam Ohio Supercomputing Centre Sweden (NorduGrid) Tata Institute (India) Triumf (Canada) UCSD UK Tier 2s University of Florida–
Gainesville ……
Pilot production service : 2003 – 2005 Pilot production service : 2003 – 2005
les robertson - cern-it-10last update 18/04/23 19:51
LCG
Some of the Sources for Middleware & Tools used by
LCG
The Virtual Data Toolkit - VDT
les robertson - cern-it-11last update 18/04/23 19:51
LCGGoals for LCG-1 – 2003-04
The Pilot Grid Service for LHC Experiments
Be the principal service for Data Challenges in 2004 Initially focused on batch production work And later also interactive analysis
Get experience in close collaboration between the Regional Centres
Learn how to maintain and operate a global grid
Focus on a production-quality Robustness, fault-tolerance, predictability, and supportability
take precedence; additional functionality gets prioritized
LCG should be integrated into the sites’ mainline physics computing services – it should not be something apart This requires coordination between participating sites in:
Policies and collaborative agreements Resource planning and scheduling Operations and Support
les robertson - cern-it-12last update 18/04/23 19:51
LCGElements of a Production LCG
Service Middleware:
Integration, testing and certification Packaging, configuration, distribution and site validation Support – problem determination and resolution; feedback to
middleware developers Operations:
Grid infrastructure services Site fabrics run as production services Operations centres – trouble and performance monitoring, problem
resolution – 24x7 globally Support:
Experiment integration – ensure optimal use of system User support – call centres/helpdesk – global coverage; documentation;
training
les robertson - cern-it-13last update 18/04/23 19:51
LCG
Certification and distribution process established Middleware package – components from –
European DataGrid (EDG) US (Globus, Condor, PPDG, GriPhyN) the Virtual Data Toolkit
Agreement reached on principles for registration and security Rutherford Lab (UK) to provide the initial Grid Operations Centre FZK (Karlsruhe) to operate the Call Centre
Pre-release middleware deployed in July to the initial 10 centres The “certified” release was made available to 13 centres on 1
September – Academia Sinica Taipei, BNL, CERN, CNAF, FNAL, FZK, IN2P3 Lyon, KFKI Budapest, Moscow State Univ., Prague, PIC Barcelona, RAL, Univ. Tokyo
Next steps – - Get the experiments going - Expand to other centres
LCG LCG Service Status
les robertson - cern-it-14last update 18/04/23 19:51
LCGPreliminary full simulation and reconstruction tests with ALICE
ALIEN submitting work to the LCG service
Aliroot 3.09.06 - fully reconstructed events
CPU-intensive, RAM-demanding (up to 600MB), long lasting jobs ( average 14 hours )
Outcome: > 95 % successful job submission, execution and
output retrieval
les robertson - cern-it-15last update 18/04/23 19:51
LCGLCG 1 at the Time of First
Release
Impressive improvement on Stability w.r.t. old 1.x EDG releases and corresponding testbeds
Lots of room for further improvements
Additional features to be added before the end of the year, in preparation for the data challenges of 2004
As more centres join, Scalability will surely become a major issue
les robertson - cern-it-16last update 18/04/23 19:51
LCG
Resources committed for 1Q04
Resources in Regional Centres
Resources planned for the period of the data challenges in 2004
CERN ~12% of the total capacity
Numbers have to be refined – different standards used by different countries
Efficiency of use is a major question mark
Reliability Efficient scheduling Sharing between Virtual
Organisations (user groups)
CPU (kSI2K)
Disk TB
Support FTE
Tape TB
CERN 700 160 10.0 1000
Czech Repub 60 5 2.5 5
France 420 81 10.2 540
Germany 207 40 9.0 62
Holland 124 3 4.0 12
Italy 507 60 16.0 100
Japan 220 45 5.0 100
Poland 86 9 5.0 28
Russia 120 30 10.0 40
Taiwan 220 30 4.0 120
Spain 150 30 4.0 100
Sweden 179 40 2.0 40
Switzerland 26 5 2.0 40
UK 1656 226 17.3 295
USA 801 176 15.5 1741
Total 5600 1169 120.0 4223
les robertson - cern-it-17last update 18/04/23 19:51
LCG
From LCG-1 to LHC Startup
les robertson - cern-it-18last update 18/04/23 19:51
LCGWhere are we now with Grid
Technology? For LHC –
- we now understand the basic requirements for batch processing
And we have a prototype solution developed by Globus and Condor in the US and the DataGrid and related projects in Europe
It is more difficult than was expected – - reliability, scalability, monitoring, operation, ..And we are not yet seeing useful industrial products
But we are ready to start re-engineering the components part of the large EGEE project proposal submitted to the EU re-write of Globus using a web-services architecture is now
available
Many more practical problems will be discovered now that we start running a grid as a sustained round-the-clock service
and the LHC experiments begin to use it for doing real work
les robertson - cern-it-19last update 18/04/23 19:51
LCGGrid Middleware for LCG in the
Longer Term
Requirements – A second round of specification of the basic grid
requirements is being completed now - HEPCAL II A team has started to specify the higher level
requirements for distributed analysis – batch and interactive – and define the HEP-specific tools that will be needed
For basic middleware the current strategy is to assume that the US DoE/NSF will provide a well supported Virtual
Data Toolkit based on Globus Toolkit 3 that the EGEE project, approved for EU 6th framework
funding, will develop the additional tools needed by LCG
And the LCG Applications Area will develop higher-level HEP-specific functionality
LCG
ARDA – An Architectural RoadmapTowards Distributed Analysis
Information Service
Authentication
Authorisation
Audi ting
Grid Monitoring
Workload Management
Metadata Catalogue
File Catalogue
Data Management
Computing Element
Storage Element
Job Monitor
Job Provenance
Package Manager
DB Proxy
User Interface
API
Accounting
7:
12:
5:
13:
8:
15: 11:
9: 10:
1:
4:
2:
3:
6:
14:
Work inProgress
!
les robertson - cern-it-21last update 18/04/23 19:51
LCGHow close are we to LHC startup?
agree spec. of initial service (LCG-1)open LCG-1
used for simulated event productions
* TDR – technical design report
stabilise, expand the service develop operations centre, etc.
2003
2004
2005
2006
2007
first data
physicscomputing service
Starter toolkit – componentsfrom VDT and EDG
les robertson - cern-it-22last update 18/04/23 19:51
LCGTimeline for the LCG computing service
agree spec. of initial service (LCG-1)open LCG-1
used for simulated event productions
principal service for LHC data challenges – batch analysis and simulation
LCG-2 upgraded middleware, mgt. s/w
* TDR – technical design report
stabilise, expand the service develop operations centre, etc.
2003
2004
2005
2006
2007
first data
physicscomputing service
This is the full complement of thefirst generation middleware fromVDT/EDG - hardened to provide a
stable, reliable service
Computing model TDRs*
les robertson - cern-it-23last update 18/04/23 19:51
LCGTimeline for the LCG computing service
agree spec. of initial service (LCG-1)open LCG-1
used for simulated event productions
principal service for LHC data challenges – batch analysis and simulation
validation of computing models
LCG-2 upgraded middleware, mgt. s/w
LCG-3 full multi-tier prototype service – batch and interactive
* TDR – technical design report
stabilise, expand the service develop operations centre, etc.
2003
2004
2005
2006
2007
first data
physicscomputing service
Computing model TDRs*
testing, hardening of 2nd generation middleware
TDR for the Phase 2 gridAt this point we expect to startdeploying second generation
middleware components- building this up during the year
to attain the full base functionalityrequired for LHC startup
les robertson - cern-it-24last update 18/04/23 19:51
LCGTimeline for the LCG computing service
agree spec. of initial service (LCG-1)open LCG-1
used for simulated event productions
principal service for LHC data challenges – batch analysis and simulation
validation of computing models
LCG-2 upgraded middleware, mgt. s/w
LCG-3 full multi-tier prototype service – batch and interactive
TDR for the Phase 2 grid
acquisition, installation, commissioning of Phase 2 service (for LHC startup)
Phase 2 service in production
* TDR – technical design report
stabilise, expand the service develop operations centre, etc.
testing, hardening of 2nd generation middleware
2003
2004
2005
2006
2007
first data
experiment setup & preparation
physicscomputing service
Computing model TDRs*
At CERN the acquisitionprocess will have startedalready during 2004 with
a market survey
les robertson - cern-it-25last update 18/04/23 19:51
LCGTimeline for the LCG computing service
agree spec. of initial service (LCG-1)open LCG-1
used for simulated event productions
principal service for LHC data challenges – batch analysis and simulation
validation of computing models
LCG-2 upgraded middleware, mgt. s/w
LCG-3 full multi-tier prototype service – batch and interactive
TDR for the Phase 2 grid
acquisition, installation, commissioning of Phase 2 service (for LHC startup)
Phase 2 service in production
* TDR – technical design report
stabilise, expand the service develop operations centre, etc.
testing, hardening of 2nd generation middleware
2003
2004
2005
2006
2007
first data
experiment setup & preparation
physicscomputing service
Computing model TDRs*
les robertson - cern-it-26last update 18/04/23 19:51
LCGEvolution of the Base
Technology
These are still very early days – with very few grids providing a reliable, round-the-clock “production” service
And few applications that are managing gigantic distributed databases
Although the basic ideas and tools have been around for a long time, we are only now seeing these applied to large scale services
Developing the grid concept continues to attract substantial interest and public funding
There are major changes taking place in architecture and frameworks –
E.g. the Open Grid Services Architecture and Infrastructure (OGSA, OGSI)
and there will be more to come as experience grows
There is a lot of commercial interest from potential software suppliers (IBM, HP, Microsoft, ..) – but no clear sight of useful products
les robertson - cern-it-27last update 18/04/23 19:51
LCGAdapting to the changing
landscape In the short-term there will many grids and several middleware
implementations -- for LCG - inter-operability will be a major headache
Will be all agree on a common set of tools? - unlikely! Or will we have to operate a grid of grids – some sort of federation? Or will computing centres be part of several grids?
The Global Grid Forum – promises to provide a mechanism for evolving architecture and agreeing on standards – but this is a long-term process
In the medium-term, until there is substantial practical experience with different architectures and different implementations,de facto standards will emerge
How quickly will we recognise the winners? Will we have become too attached to our own developments to
change?
les robertson - cern-it-28last update 18/04/23 19:51
LCG
-- this is probably the greatest risk that we take by adopting the grid model for LHC computing
Access Rights and Security
The grid idea assumes global authentication, and authorisation based on the user’s role in his virtual organisation
-- one set of credentials for everything you do
The agreement for LHC is that all members of a physics collaboration will have access to all of its resources
-- the political implications of this have still to be tested!
Could be an attractive target for hackers
les robertson - cern-it-29last update 18/04/23 19:51
LCGKey LCG goals for next 12
months
Take-up by the experiments of the first versions of common applications – starts NOW
Evolve the LCG-1 service into a production facility for LHC experiments – validated in data challenges
Establish the requirements and a credible implementation plan for baseline distributed grid analysis for 2007-08
the model hep-specific tools base grid technology - middleware
to support the computing models of the experiments – Technical Design Reports due end 2004
LCG
les robertson - cern-it-30last update 18/04/23 19:51
LCG Summary
The LCG Project has a clear goal of providing the environment and services for recording and analysing the LHC data when the accelerator starts operation in 2007
The computational requirements of LHC dictate a geographically distributed solution, taking maximum advantage of the facilities available to LHC around the world --- a computational GRID
A pilot service – LCG-1 – has been opened to learn how to use this technology to provide a reliable, efficient service encompassing many independent computing centres
It is already clear that the current middleware will have to re-engineered or replaced to achieve the goals of reliability and scalability
In the medium term we expect to get this new middleware from EU and US funded projects
But the technology is evolving rapidly – and LCG will have to adapt to a changing environment
While we keep a strong focus on providing a continuing service for the LHC Collaborations