Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

26
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009

Transcript of Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

Page 1: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

Large Generator Interconnection Procedures

Reform

Stakeholder Meeting

February 19, 2009

Page 2: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

2

Agenda

• Goals and Expectations

• Background

• Recap of Recent Changes

• LGIP Reform

• Next Steps

Page 3: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

3

Goals and Expectations

• Goal: Develop a process that allows competitive generators to deliver their energy to load on a reliable transmission system.

• Expectations of this stakeholder process:– An iterative process that examines Tri-State’s

interconnection procedures;

– Constructive dialog with stakeholders on specific improvements to Tri-State’s concept paper;

– Final procedures that meet the goal.

Page 4: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

4

Background• In 2007 and 2008, 57 requests were added to

Tri-State’s queue– Process became unmanageable

• Recently several ISOs implemented queue reforms.

• Tri-State reviewed these reform efforts and initiated its own.

Page 5: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

5

2008 LGIP Process

• Nov. 5, 2008: Tri-State stopped accepting applications.

• Nov. 20, 2008: Interconnection Customer meeting on proposed LGIP modifications.

• Nov.20-Dec.15, 2008 accepted comments.• Jan. 9, 2009: Posted modified LGIP with

revisions based on comments.• Jan. 12, 2009: Modified LGIP effective• Jan. 12, 2009: Began accepting applications

Page 6: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

6

LGIP Changes Effective 1/12/09

• Application deposit:– $125,000 for projects 75 MW or less, – $250,000 for larger projects. – $25,000 is non-refundable if project drops out

of queue.

• Site Control: – No additional Deposit in lieu of Site Control – Require 50% of necessary land at application– 100% prior to interconnection agreement.

Page 7: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

7

LGIP Changes Effective 1/12/09

• Projects designated as a network resource or with a power purchase agreement receive priority for study work—FIRST READY-FIRST SERVED.

• Prior to Facilities Study, network interconnection requestors must have power customer.

• Suspension of construction for Force Majuere events only.

• Only accept “immediately available funds” in advance.

• Several changes to streamline study process.

Page 8: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

8

LGIP Reform

• Tri-State’s LGIP Reform concept paper is the second step in a two step process

• Changes in January were designed to improve queue management and the interconnection study process.

• Tri-State’s LGIP Reform concept paper presents ideas that will simplify and expedite the generation interconnection process.

Page 9: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

9

LGIP Reform

• Most of the changes adopted in January 2009 will be retained.

• New Concepts:– Interconnection process based on Load and

Resource Transmission Study.– New options for determining Network Upgrades.– Biannual Interconnection Request Windows.

Page 10: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

10

LGIP Reform

• New Concepts (continued):– Multiple Customer options for proceeding to

Facilities Study– Queue Management:

• First Come-First Served through the System Impact Study, subject to priority for projects with designation as Network Resource;

• First Ready-First Served after the System Impact Study.

Page 11: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

11

Load and Resource Plan

• Load and Resource Plan– Submitted by all Network Customers.– Identify resource amounts and anticipated

geographic areas.– Up to 4 resource distribution scenarios will be

accepted with each plan.

Page 12: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

12

Draft Definition• Load and Resource Plan shall have the

meaning set forth in Section 31.6 of the Tariff and shall identify projected load growth and projected amounts of generating capacity from each Resource Zone to meet the network integration transmission customers’ network load requirements.

Page 13: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

13

Load and Resource Transmission Study

• Performed once annually

• Will include transmission upgrades in Tri-State’s most recent 10 year transmission plan.

• Will determine and estimate the cost of additional upgrades required to accommodate the needs presented in the Load and Resource Plans.

Page 14: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

14

Draft Definition• Load and Resource Transmission Study

means a transmission planning study that models the Transmission System and identifies Network Upgrades and projected amounts of generation from each Resource Zone to accommodate the combined Load and Resource Plan.

Page 15: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

15

Draft Definition• Resource Zone means a geographic area that is a

projected location for interconnection of new Network Resources to the Transmission System. Transmission Provider shall evaluate each Resource Zone on the basis of the combined Load and Resource Plan of all Network Integration Transmission Service customers as required by Section 31.6 of the Tariff, and in coordination with Transmission Provider’s applicable Tariff and regional transmission planning responsibilities.

Page 16: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

16

Interconnection Service

• Pro Forma LGIP: – Energy Resource Interconnection Service– Network Resource Interconnection Service

• Tri-State concept:– Single Interconnection Service– Focuses on Interconnection Facilities– Network Upgrades handled either in Load and

Resource Study or subsequent to Transmission Service Request (TSR)

Page 17: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

17

Interconnection Service—Draft• Interconnection Service. For the purpose of

Interconnection Service, Transmission Provider shall make no distinction among types of transmission service or delivery capabilities from physically similar Interconnection Facilities, except that Network Upgrades shall be identified either through a Load and Resource Transmission Study or through studies to be provided as part of a Transmission Service Request.

Page 18: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

18

Interconnection Service—Draft

• The Product. Transmission Provider shall conduct the necessary Studies to construct the Interconnection Facilities and Network Upgrades needed to integrate the Large Generating Facility (1) in a manner comparable to that in which Transmission Provider integrates its generating facilities to serve native load customers based upon a Load and Resource Transmission Study that includes Network Upgrades; or (2) with Interconnection Facilities provided and Network Upgrades added pursuant to a Transmission Service Request; or (3) with Interconnection Facilities provided and Network Upgrades deferred at the Interconnection Customer’s own risk of operating limits for the purpose of future Transmission Service.

Page 19: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

Review Published Load & Resource

Transmission Study

Attend Information Session at beginning

of IR Application Window

Customer may perform Optional Feasibility Studies and have access to Base

Case Data

Customer

A

Page 20: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

$250,000 Study Deposit for >75 MW ProjectsOR,

$125,000 Study Deposit for ≤ 75 MW Projects

(Includes $25,000 non-refundable for both generation levels)

IR Applications reviewed on semi-annual basis. Two-month windows to submit application

Submit IR

B

Proof of 50% site control at time of application

Page 21: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

SIS

After power flow portion of SIS, customer is asked to select one

generation level

SIS Scoping Meeting

Three levels of generation allowed and specified for study at time of meeting

IC Facilities Only

C

Page 22: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

Customer shows designation as

Network Resource

LGIA

SIS Review (with cost

estimates) and FS Scoping Meeting

100% of Site Control required at this point

Facilities Study

Customer deposits IC Facilities money and

submits TSR or proceeds at own risk

EXIT

Network Upgrade Studies

TSR Path

At Risk Path

D

Page 23: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

23

Alternatives for Advancement to Facilities Study

• Interconnection Customer has five options:– Show designation as Network Resource; or– Advance funds for facility construction and

submit Transmission Service Request (TSR); or– Advance funds for facility construction without

TSR and proceed at own risk; or– Suspend work for up to one year; return to queue

behind any project ready for Facilities Study; or– Withdraw project from the queue.

Page 24: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

Customer Shows

Designation as Network Resource

Review Published

Load & Resource

Trans-mission Study

LGIA

IR Applications reviewed on semi-annual basis. Two

month windows to submit

application

IC Facilities

Only

Attend Information Session at Beginning

of IR Application

Window

Customer may perform

Optional Feasibility

Studies and have access to Base Case

Data

Facilities Study

Customer deposits IC Facilities money and submits TSR

or proceeds at own risk

EXIT

Submit IR

Network Upgrade Studies

Customer

TSR Path

At Risk Path

$250,000 Study Deposit for >75 MW ProjectsOR,

$125,000 Study Deposit for ≤ 75 MW Projects (Includes $25,000 non-refundable for both

generation levels)

Proof of 50% site control at time of application

SIS Scoping Meeting

Three levels of generation

allowed and specified for study at time of meeting

SIS After power flow portion

of SIS, customer is

asked to select one generation

level

SIS Review

(with cost estimates)

and FS

Scoping Meeting 100% of

Site Control

required at this point

A B C D

Page 25: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

25

Next Steps• March 19th—Comments due on concept.

• April 21st—Tri-State will post comments and responses, and formal proposal.

• May 5th—Second Stakeholder meeting.

• June 5th—Second round of comments due.

• Balance of timeline will be determined after second stakeholder meeting.

Page 26: Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.

February 19, 2009

26

Comments• Submit your comments today or by March 19th to:

• Ron SteinbachTransmission Policy AdministratorTri-State Generation and Transmission

Association, Inc.P.O. Box 33695Denver, CO 80233

• OR to

[email protected] • Questions—call Ron at

– 303-254-3355